IceCube Upgrade: Field Seasons Plan & ResultsF.
  • Feyzi and IceCube Upgrade Team
ICNO/Upgrade Project - NSF Site Visit ReviewMarch 18, 2020Define 1.21Upgrade Implementation– 22/23 Season Site PlanGen1 EHWD – Seasonal Equipment Site (SES)3Upgrade Drill to be very similar.
  • ICL
Tight configuration.
  • GPR will influence final locations.
  • 20/21 Field Season detail (1)
13List of Items We Need to Transport to South Pole 20/21Gen2 and Gen3Need to be moved to flatrack with ISO2-conversion or ISO3SPOT-1Day Tank and Gen HoodsNeed to be moved to flatrack with ISO2-conversion or ISO3SPOT-1Gen1 – Put this on a Herc.
Allowed
Microsoft PowerPoint 2007 (.pptx) - application/vnd.openxmlformats-officedocument.presentationml.presentation
Upgrade Field Seasons Plan.pptx
No
10000
5966353
No
Appears In: NSF Field Work FY21 - FY25 Discussion
Preferred Version: Upgrade Field Seasons Plan.pptx