BOE-1-2-2.pdf | |
Handle: | Version-105542 |
Owner: | O'Dell, Vivian (User-2054, vodell:LDAP)DS |
Tuesday, May 10, 2022 01:41:31 PM CDT | |
Wednesday, May 25, 2022 02:39:42 PM CDT | |
Modified By: | |
- Last revision: 10 May 2022 1 Basis of Estimate 1. - WBS ID 1.2.2 $95,123 total cost for this BOE 2. - WBS Name Thermal Plant – Off-Ice 3. - Estimated by Terry Benson (University of Wisconsin) 4. - WBS Dictionary Description Includes the design, procurement, resurrection, construction, integration, and testing of subsystems associated with the drill system’s hot water thermal plant: Preheat System, Main Heating Plants, a new Seasonal Equipment Site fuel day tank and fuel distribution system. - These reflect the estimated uncertainty in the estimate. Review, specify... | |
1 | |
Appears In: | BOE-1-2-2.pdf |
DocuShare is now read-only. Use Google Drive.