1 Basis of Estimate 1.
  • WBS ID 1.1
Total cost for this BOE: $3,889,990.98 2.
  • WBS Name
Project Office 3.
  • Estimated by Farshid Feyzi (University of Wisconsin)
4.
  • WBS Dictionary Description
Provide oversight and direction in managing and facilitating the IceCube Upgrade Project.
  • Oversees the quotation
process on serially produced parts. 1.1.4 Polar Operations This element includes the planning and execution of all of the activities needed at South Pole to successfully install sensor instrumentation into 7 deep drill...