PreviousReviewRecommendations rev1.xlsx
Review recommendations from November 2021 Logistics Review
Handle: Document-90246
Owner: O'Dell, Vivian (User-2054, vodell:LDAP)DS
Monday, April 11, 2022 07:46:07 PM CDT
Monday, April 11, 2022 07:46:07 PM CDT
Modified By:
Locked By:
  • Last update 4/07/2022
ID Recommendation Responsible Status Estimated Date for closing Notes LR1 Project team should perform their own schedule analysis using the 10 Best Practices for a high-quality and reliable schedule discussed in the GAO Schedule Assessment Guide (GAO-16-89G) for guidance and deliver their self-assessment to NSF at their next project review Vivian O'Dell / Jim Lowe closed 03/01/22 Schedule cleanup performed to implement GAO best practice.
  • (in principle year 2 in a 3 FS project
LR4 Research potential advantages of heating the cables in the area where they enter the ICL towers to make snaking them from the snow trench into ICL easier.
  • Add a float column with co...
Allowed
Microsoft Excel 2007 (.xlsx) - application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
PreviousReviewRecommendations rev1.xlsx
No
10000
25525
No
Appears In: 5. IC Upgrade Prior Review Docs
Preferred Version: PreviousReviewRecommendations rev1.xlsx