DRAFT Exhibit 3: Statement of Work – IceCube Neutrino Observatory Upgrade Rheinisch-Westfälische Technische Hochschule (RWTH) Aachen 1 October 2018 through 30 September 2023 Scientific and Technical Contributions This Memorandum of Understanding (MoU) describes the equipment that will be designed and built as part of the IceCube Upgrade.
  • RWTH Aachen will make every effort to carry out their responsibilities consistent with the project
schedule and contribute the following items for the IceCube Upgrade project: WBS L3 Quantity Item 1.5.2 12 Acoustic subsystem modules 1.5.2 41 Mini Mainboard layout and first batch pro...
Allowed
Adobe Portable Document Format (.pdf) - application/pdf
MoU - IceCube Upgrade - Exhibit 3 - Aachen.pdf
No
10000
77855
No
Appears In: IceCube Upgrade MOUs
Preferred Version: MoU - IceCube Upgrade - Exhibit 3 - Aachen.pdf