  • Ice Cube Review – Detailed Questions from the Panel.
  • Components that are
in the cargo list are not at the South Pole.
  • At surface the in-ice cable is connected to a surface
junction box.
  • Is this available?
Labor hour estimates for drilling, which are the majority of on ice work, are in the project schedule (file provided).
  • Labor hour estimates for installation are not in the
schedule now.
  • i. Possible to shift tasks to Season 2, winterover or a Season 4?
Shifting any deep drilling/installation tasks will require 45 people, even in another season.
Allowed
Adobe Portable Document Format (.pdf) - application/pdf
IceCubeUpgrade_Review_Detailed_Questions_Answers.pdf
No
10000
409277
No
Appears In: Answers to Questions
Preferred Version: IceCubeUpgrade_Review_Detailed_Questions_Answers.pdf