- 1 IceCube Upgrade Project Review March 17, 2020 Recommendation: COVID-19 Emergency Response Plan: We recommend that you provide a document that describes the risks and projected impact (on the cost, schedule, and budget) on the ICNO M&O & Upgrade/Construction activities due to the COVID-19 outbreak; this should include any respective/potential delays of the procured equipment deliveries, various productions of parts and units (DOMs, etc.), and potential losses or delays of labor and people/positions. - 2 Risk Severity Risk Probability 1. - Drill Control System Risk severity: High Risk probability: Moderate to high Descrip...