D_02_IC_Upgrade_Cost_Estimating_Plan.pdf
Handle: Version-105618
Owner: Madsen, Jim (User-61, madsen:LDAP)DS
Monday, April 11, 2022 04:59:22 PM CDT
Saturday, July 2, 2022 10:21:04 AM CDT
Modified By:
- Cost Estimating Plan for the IceCube Upgrade Project 2022-004.5 Approvals Role Name Date Signature Principal Investigator K. - Hanson Project Director V. - O’Dell Project Manager F. - Feyzi Mar 10, 2022 Mar 16, 2022 Vivian O'Dell (Mar 17, 2022 19:20 CDT) Vivian O'Dell Mar 17, 2022 Cost Estimating Plan, IceCube Upgrade Version 5.0 Page 2 of 13 Change Log Version Date Author Summary of changes 1.0 2021-07-27 V. - O’Dell 1st version 2.0 2021-07-29 V. - O’Dell 2st version 3.0 2021-08-12 M. Rogal Full version for IceCube Upgrade 4.0 ...