Mid-Term Review Q&A | |
Handle: | v_Document-93182 |
Owner: | Kelley, John (User-174, jkelley:LDAP)DS |
Tuesday, April 30, 2024 09:21:09 AM CDT | |
Tuesday, April 30, 2024 09:21:09 AM CDT | |
Modified By: | |
- IceCube Mid-Term Review Q&A John Kelley IceCube Director of Operations NSF Mid-Term Review 30 April 2024 M&O Mid-Term Review Q&A 1 M&O Mid-Term Review Q&A 2 Questions • Is the additional required power for the Upgrade of 11–13 kW an issue given the current power usage at South Pole? • Has there been or will there be coordination with the other major South Pole science groups on power usage? 1–2 kW • Coarse estimate: ICL environmental is an additional 8–10 kW Upgrade Power Estimated Breakdown M&O Mid-Term Review Q&A ... | |
1 | |
Appears In: | Mid-Term Review Q&A |