- Last revision: 10 May 2022 1 Basis of Estimate 1. - WBS ID 1.4.6 $136,629 total cost for this WBS 2. - WBS Name CPT Management 3. - Estimated by Tyce DeYoung (Michigan State University) 4. - WBS Dictionary Description This element includes management and oversight of all activities within WBS 1.4. - 5. Assumptions and Related Documents The estimates described in this document rely on the following assumptions, which are consistent with the Project’s “Key Assumptions” document” (1) and the “Cost Estimating Plan” (2). ... | |