BOE-1-4-4.pdf | |
Handle: | v_Document-90462 |
Owner: | O'Dell, Vivian (User-2054, vodell:LDAP)DS |
Tuesday, May 10, 2022 02:03:57 PM CDT | |
Tuesday, May 10, 2022 02:03:57 PM CDT | |
Modified By: | |
- Last revision: 10 May 2022 1 Basis of Estimate 1. - WBS ID 1.4.4 $210,429 total cost for this WBS 2. - WBS Name CPT Central Infrastructure 3. - Estimated by John Kelley (University of Wisconsin) 4. - WBS Dictionary Description This element includes design, production and testing of the electronics infrastructure required to distribute timing signals from the IceCube master clock to the FieldHubs in the IceCube Laboratory (ICL). - This element also includes the power supplies which will supply power to in-ice devices through the FieldHubs. The communications and timi... | |
1 | |
Appears In: | BOE-1-4-4.pdf |
DocuShare is now read-only. Use Google Drive.