BOE-1-3-3_V2.pdf | |
Handle: | v_Document-90457 |
Owner: | O'Dell, Vivian (User-2054, vodell:LDAP)DS |
Tuesday, May 10, 2022 01:49:33 PM CDT | |
Tuesday, May 10, 2022 01:49:33 PM CDT | |
Modified By: | |
- Last revision: 6 May 2022 1 Basis of Estimate 1. - WBS ID 1.3.3 $150,870.05 total burdened cost for this WBS 2. - WBS Name PDOM 3. - Estimated by Perry Sandstrom (WIPAC) 4. - WBS Dictionary Description This element is responsible for upgrading 20 spare IceCube Gen1 DOMs with PDOM readout electronics, HV systems, calibration devices, and penetrators. - These are summarized in the Project’s Key Assumptions document (1). The techniques are: A=Analogy; C=Engineering build-up; D=Expert opinion; E=Extrapolation from actuals; F=Parametric; L=Learning Curves. Last revision: 6 Ma... | |
1 | |
Appears In: | BOE-1-3-3_V2.pdf |