Modified By:
- Risk Management Plan 2019-004.6 Approval Date Project Director Vivian O’Dell Project Manager F. - Feyzi Quality & Safety Manager M. - Zernick Project Science Coordinator Michael DuVernois Change Log Revision Description: Author Date 0 Original document: M. - Zernick 1/31/19 1 Added Monte Carlo reference: M. - Zernick 4/09/19 2 Added cost tracking, contingency, and scope planning: F. - Feyzi 10/1/2019 3 Updated per comments received from NSF: F. Feyzi 02/0...