IceCubeUpgrade_Review_Detailed_Questions_Answers.pdf
Handle: v_Document-89811
Owner: Madsen, Jim (User-61, madsen:LDAP)DS
Thursday, November 4, 2021 10:07:05 AM CDT
Thursday, November 4, 2021 10:07:05 AM CDT
Modified By:
- Ice Cube Review – Detailed Questions from the Panel. - Components that are in the cargo list are not at the South Pole. - At surface the in-ice cable is connected to a surface junction box. - Is this available? Labor hour estimates for drilling, which are the majority of on ice work, are in the project schedule (file provided). - Labor hour estimates for installation are not in the schedule now. - i. Possible to shift tasks to Season 2, winterover or a Season 4? Shifting any deep drilling/installation tasks will require 45 people, even in another season.