NavigatingICUCosts.pdf
Handle: Version-105560
Owner: O'Dell, Vivian (User-2054, vodell:LDAP)DS
Tuesday, May 10, 2022 02:40:13 PM CDT
Wednesday, May 25, 2022 04:04:07 PM CDT
Modified By:
- How to relate the IceCube Upgrade Basis of Estimates to the Cost Workbook The basis of estimates are all of the same template. - The WBS and Activity Columns can be found in the Cost Workbook. - These hours are then recorded in the cost workbook and costs are calculated according to the labor rate, fringe, and indirect at the respective institution. - These can be found either in the body of the BOE or in the directory that the BOE is found. - In addition, stand alone 1030’s have been made that remove the reference to the cost workbook pivot tables for convenience.
1
Appears In: NavigatingICUCosts.pdf