A | B | C | D | E | F | G | H | I |
---|---|---|---|---|
1 | L2 | WBS | P/C | Task Name | Duration | Start Date | End Date | Predecessor WBS | Target |
2 | 1 | 1 | P | IceCube Phase 1 Upgrade Project | 949d | 10/03/22 | 06/03/26 |
3 | P | Project Milestones | 949d | 10/03/22 | 06/03/26 |
4 | P | External Project Milestones | 809d | 10/03/22 | 11/15/25 |
5 | C | Project Start | 0 | 10/03/22 | 10/03/22 |
6 | P | Filed Season Milestones | 778d | 11/15/22 | 11/15/25 |
7 | C | FS0 Start | 0 | 11/15/22 | 11/15/22 |
8 | C | FS1 Start | 0 | 11/15/23 | 11/15/23 |
9 | C | FS2 Start | 0 | 11/15/24 | 11/15/24 |
10 | C | FS3 Start | 0 | 11/15/25 | 11/15/25 |
11 | P | Internal High Level Project Milestones | 388d | 12/02/24 | 06/03/26 |
12 | C | Project End | 0 | 06/03/26 | 06/03/26 | 14 |
13 | C | Field Hub ROS | 0 | 12/02/24 | 12/02/24 | 8FS +10d |
14 | 1.1 | P | Project Office | 41d | 04/08/26 | 06/03/26 |
15 | C | Project Closeout | 41d | 04/08/26 | 06/03/26 | 69 |
16 | 1.2 | P | Implementation | 863d | 10/03/22 | 02/03/26 |
17 | P | Off-Ice Work | 453d | 10/03/22 | 07/01/24 |
18 | P | Drill Control System | 453d | 10/03/22 | 07/01/24 |
19 | C | MHP Design, procure, develop | 140d | 10/03/22 | 04/14/23 | 4 |
20 | C | PHS & WT2 | 78d | 10/03/22 | 01/18/23 | 4 |
21 | C | TOS & Reels | 203d | 10/03/22 | 07/12/23 | 4 |
22 | C | Drillheads | 110d | 01/30/24 | 07/01/24 | 6FS +119d, 29 |
23 | C | DCC, WT1, and Fuel Daytank | 195d | 01/02/23 | 09/29/23 | 4, 6SS +34d |
24 | C | Gensets | 76d | 03/18/24 | 07/01/24 | 7FS +85d, 29 |
25 | C | HPP | 213d | 10/03/22 | 07/26/23 | 4 |
26 | C | ARA Rodwell System | 121d | 10/03/22 | 03/20/23 | 4 |
27 | C | DCS Set 1 Ready to Ship | 0 | 07/12/23 | 07/12/23 | 18, 19, 20, 25 |
28 | C | DCS Set 2 Ready to Ship | 0 | 07/01/24 | 07/01/24 | 21, 22, 23, 24 |
29 | P | On-Ice Work | 571d | 11/15/23 | 02/03/26 |
30 | C | Field Season 1 | 51d | 11/15/23 | 01/29/24 | 7 |
31 | C | Field Season 2 | 55d | 11/15/24 | 02/04/25 | 8 |
32 | P | Field Season 3 | 55d | 11/15/25 | 02/03/26 | 9 |
33 | C | SES Setup | 0 | 11/15/25 | 11/15/25 | 9 |
34 | C | Tower 1 / Tower 2 ready | 3d | 11/17/25 | 11/19/25 | 32 |
35 | C | Drill Preparation | 19d | 11/17/25 | 12/12/25 | 32 |
36 | C | Drill 5 holes | 15d | 12/15/25 | 01/06/26 | 34 |
37 | C | Drill 7 holes | 5d | 01/07/26 | 01/13/26 | 35 |
38 | C | Decommissioning tasks | 15d | 01/14/26 | 02/03/26 | 36 |
39 | 1.3 | P | Sensors | 255d | 10/03/22 | 09/22/23 |
40 | P | D-Eggs | 226d | 10/03/22 | 08/14/23 |
41 | C | D-Egg FAT Testing of all 19 batches | 216d | 10/03/22 | 07/31/23 | 4 |
42 | C | D-Eggs Crated for shipping | 10d | 08/01/23 | 08/14/23 | 40 |
43 | C | D-Eggs Ready to Ship | 0 | 08/14/23 | 08/14/23 | 41 |
44 | P | M-Doms | 216d | 11/25/22 | 09/22/23 |
45 | C | All M-DOM mainboard parts available | 0 | 11/25/22 | 11/25/22 |
46 | C | Integration of M-DOM mainboards on M-DOMS and Final Acceptance Testing | 206d | 11/25/22 | 09/08/23 | 44 |
47 | C | M-DOMS crated for shipping | 10d | 09/11/23 | 09/22/23 | 45 |
48 | C | M-DOMs Ready to Ship | 0 | 09/22/23 | 09/22/23 | 46 |
49 | P | Ship Sensors | 126d | 03/31/23 | 09/22/23 |
50 | C | Shipment 1 of Sensors | 0 | 03/31/23 | 03/31/23 | 40SS +90d, 45SS +90d |
51 | C | Shipment 2 of Sensors | 0 | 09/22/23 | 09/22/23 | 42, 47 | |||
---|---|---|---|---|---|---|---|---|---|
52 | 1.4 | P | Coms/Power/Timing | 320d | 10/03/22 | 12/26/23 | |||
53 | P | Main Cable | 265d | 10/03/22 | 10/06/23 | ||||
54 | C | Main Cable Assembly Production | 249d | 10/03/22 | 09/14/23 | 4 | |||
55 | C | Main Cable Assembly Ready to Ship | 0 | 09/14/23 | 09/14/23 | 53 | |||
56 | P | Breakout Cable Assembly | 265d | 10/03/22 | 10/06/23 | ||||
57 | C | BCA Design | 55d | 10/03/22 | 12/16/22 | 4 | |||
58 | C | BCA procurement, manufacturing (1st 2 strings) | 141d | 12/19/22 | 07/03/23 | 56 | |||
59 | C | BCA manufacturing (final 5 strings) | 69d | 07/04/23 | 10/06/23 | 57 | |||
60 | C | BCA 2 strings ready to ship | 0 | 07/03/23 | 07/03/23 | 57 | |||
61 | C | BCA 5 strings ready to ship | 0 | 10/06/23 | 10/06/23 | 58 | |||
62 | P | Field Hub | 320d | 10/03/22 | 12/26/23 | ||||
63 | C | Field Hub Desgin | 176d | 10/03/22 | 06/05/23 | 4 | |||
64 | C | Field Hub Production, Assembly, Testing | 144d | 06/06/23 | 12/26/23 | 62 | |||
65 | C | Field Hub ready to ship | 0 | 12/26/23 | 12/26/23 | 63 | |||
66 | 1.5 | P | Calibration | 480d | 10/03/22 | 08/07/24 | |||
67 | C | Standalone Calibration Devices Complete | 480d | 10/03/22 | 08/07/24 | 4 | |||
68 | 1.6 | P | Data Systems | 45d | 02/04/26 | 04/07/26 | |||
69 | C | Commission devices following deployment | 45d | 02/04/26 | 04/07/26 | 31 | |||
70 | C | Project Handoff to M&O | 0 | 04/07/26 | 04/07/26 | 68 | |||
71 | |||||||||
72 | P | Logistics | 858d | 08/01/22 | 11/20/25 | ||||
73 | P | Vessel | 858d | 08/01/22 | 11/20/25 | ||||
74 | C | Vessel FY22 (FS1 delivery) | 263d | 11/15/22 | 11/16/23 | ||||
75 | C | Vessel FY23 (FS2 delivery) | 260d | 11/15/23 | 11/15/24 | ||||
76 | C | Vessel FY24 (FS3 delivery) | 260d | 11/15/24 | 11/18/25 | ||||
77 | P | ComSur | 858d | 08/01/22 | 11/20/25 | ||||
78 | C | ComSur FY22 (FS0 delivery) | 80d | 08/01/22 | 11/18/22 | ||||
79 | C | ComSur FY23 (FS1 delivery) | 80d | 08/01/23 | 11/20/23 | ||||
80 | C | ComSur FY24 (FS2 delivery) | 80d | 08/01/24 | 11/20/24 | ||||
81 | C | ComSur FY25 (FS3 delivery) | 80d | 08/01/25 | 11/20/25 |