1. Rebaseline Schedule PY5-PY8
  2. Comments

  A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH AI AJ AK AL AM AN AO AP AQ
1 H # L2 WBS Task Name Started P/C O-L NSF Critical Path L1 Milestone L2 Milestone Internal Milestone Duration Start Date End Date SD+Time ED+Time Early End Date Float Predecessor WBS Target % Complete Status Status Note Plan TBC Sum-Plan Sum-TBC Target EV(%) 1.1 1.2 1.3 1.4 1.5 1.6 Assign To Personnel Notes Baseline Notes WBS# Count RowID TN#
2 x WBS EV % NSF Upgrade Funding Monthly EV Actuals Should have Started C 1 1 Red $0.00 $0.00 $0.00 $0.00 1 1
3 x 1 15.57% $574,364.76 Should have Started C 1 1 Red $0.00 $0.00 $0.00 $0.00 1 2
4 x 1.1 13.63% $87,066.08 Should have Started C 1 1 Red $0.00 $0.00 $0.00 $0.00 1 3
5 x 1.2 18.33% $329,794.06 Should have Started C 1 1 Red $0.00 $0.00 $0.00 $0.00 1 4
6 x 1.3 6.55% $11,028.66 Should have Started C 1 1 Red $0.00 $0.00 $0.00 $0.00 1 5
7 x 1.4 11.48% $83,547.86 Should have Started C 1 1 Red $0.00 $0.00 $0.00 $0.00 1 6
8 x 1.5 0.00% $0.00 Should have Started C 1 1 Red $0.00 $0.00 $0.00 $0.00 1 7
9 x 1.6 19.97% $62,928.10 Should have Started C 1 1 Red $0.00 $0.00 $0.00 $0.00 1 8
10 1 1 IceCube Phase 1 Upgrade Project Started P 1 2078d 06/01/18 06/01/26 06/01/18 8:00 AM 06/01/26 4:59 PM 14.98% 32.00% Green $0.00 $0.00 $552,586.21 $3,688,103.63 15% PM 1 1 9 IceCube Phase 1 Upgrade Project
11 1.1 1.1 Project Office Started P 2 1992d 10/01/18 06/01/26 10/01/18 8:00 AM 06/01/26 4:59 PM 15.71% 20.0% Green $0.00 $0.00 $100,361.68 $638,698.89 16% PM 1.1 1 10 Project Office
12 1.1 1.1.1 Project Management Started P 3 1 1992d 10/01/18 06/01/26 10/01/18 8:00 AM 06/01/26 4:59 PM 16% 4.00% Yellow $0.00 $0.00 $53,260.70 $327,293.00 16% PM 1.1.1 1 11 Project Management
13 1.1 1.1.1.1 Project Administration (B) Started C 4 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 16% 16% Green $53,260.70 $327,293.00 $53,260.70 $327,293.00 16% $52,366.88 PM 1.1.1.1 1 12 Project Administration (B)
14 1.1 1.1.1.2 Annual Report Should have Started P 4 1 1558d 10/01/19 09/29/25 10/01/19 8:00 AM 09/29/25 8:00 AM 43% 0% Red $0.00 $0.00 $0.00 $0.00 PM 1.1.1.2 1 13 Annual Report
15 1.1 1.1.1.2.1 Annual Report 1 Complete C 5 1 1 0 10/01/19 10/01/19 10/01/19 8:00 AM 10/01/19 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.2.1 1 14 Annual Report 1
16 1.1 1.1.1.2.2 Annual Report 2 Complete C 5 1 1 0 10/01/20 10/01/20 10/01/20 8:00 AM 10/01/20 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.2.2 1 15 Annual Report 2
17 1.1 1.1.1.2.3 Annual Report 3 Complete C 5 1 1 0 10/01/21 10/01/21 10/01/21 8:00 AM 10/01/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.2.3 1 16 Annual Report 3
18 1.1 1.1.1.2.4 Annual Report 4 Not Started C 5 1 1 0 10/01/22 10/01/22 10/01/22 8:00 AM 10/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.2.4 1 17 Annual Report 4
19 1.1 1.1.1.2.5 Annual Report 5 Not Started C 5 1 1 0 09/29/23 09/29/23 09/29/23 8:00 AM 09/29/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.2.5 1 18 Annual Report 5
20 1.1 1.1.1.2.6 Annual Report 6 Not Started C 5 1 1 0 09/29/24 09/29/24 09/29/24 8:00 AM 09/29/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.2.6 1 19 Annual Report 6
21 1.1 1.1.1.2.7 Annual Report 7 Not Started C 5 1 1 0 09/29/25 09/29/25 09/29/25 8:00 AM 09/29/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.2.7 1 20 Annual Report 7
22 1.1 1.1.1.3 Partnership Agreements (MoUs) Signed Complete C 4 1 1 0 03/01/19 03/01/19 03/01/19 8:00 AM 03/01/19 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.3 1 21 Partnership Agreements (MoUs) Signed
23 1.1 1.1.1.4 Project Execution Plan (PEP) Should have Started P 4 1 1559d 10/01/18 09/25/24 10/01/18 8:00 AM 09/25/24 8:00 AM 57% 0% Red $0.00 $0.00 $0.00 $0.00 PM 1.1.1.4 1 22 Project Execution Plan (PEP)
24 1.1 1.1.1.4.1 Project Execution Plan (PEP) 1 Complete C 5 1 1 0 10/01/18 10/01/18 10/01/18 8:00 AM 10/01/18 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.4.1 1 23 Project Execution Plan (PEP) 1
25 1.1 1.1.1.4.2 Project Execution Plan (PEP) 2 Complete C 5 1 1 0 09/25/19 09/25/19 09/25/19 8:00 AM 09/25/19 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.4.2 1 24 Project Execution Plan (PEP) 2
26 1.1 1.1.1.4.3 Project Execution Plan (PEP) 3 Complete C 5 1 1 0 09/25/20 09/25/20 09/25/20 8:00 AM 09/25/20 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.4.3 1 25 Project Execution Plan (PEP) 3
27 1.1 1.1.1.4.4 Project Execution Plan (PEP) 4 Complete C 5 1 1 0 09/25/21 09/25/21 09/25/21 8:00 AM 09/25/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.4.4 1 26 Project Execution Plan (PEP) 4
28 1.1 1.1.1.4.5 Project Execution Plan (PEP) 5 Not Started C 5 1 1 0 09/25/22 09/25/22 09/25/22 8:00 AM 09/25/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.4.5 1 27 Project Execution Plan (PEP) 5
29 1.1 1.1.1.4.6 Project Execution Plan (PEP) 6 Not Started C 5 1 1 0 09/25/23 09/25/23 09/25/23 8:00 AM 09/25/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.4.6 1 28 Project Execution Plan (PEP) 6
30 1.1 1.1.1.4.7 Project Execution Plan (PEP) 7 Not Started C 5 1 1 0 09/25/24 09/25/24 09/25/24 8:00 AM 09/25/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.4.7 1 29 Project Execution Plan (PEP) 7
31 1.1 1.1.1.5 Project Reviews Should have Started P 4 1 1809d 03/13/19 03/01/26 03/13/19 8:00 AM 03/01/26 8:00 AM 46% 0% Red $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5 1 30 Project Reviews
32 1.1 1.1.1.5.1 Annual NSF Review Should have Started P 5 1 1809d 03/13/19 03/01/26 03/13/19 8:00 AM 03/01/26 8:00 AM 38% 0% Red $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5.1 1 31 Annual NSF Review
33 1.1 1.1.1.5.1.1 Annual NSF Review 1 Complete C 6 1 1 0 03/13/19 03/13/19 03/13/19 8:00 AM 03/13/19 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5.1.1 1 32 Annual NSF Review 1
34 1.1 1.1.1.5.1.2 Annual NSF Review 2 Complete C 6 1 1 0 03/10/20 03/10/20 03/10/20 8:00 AM 03/10/20 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5.1.2 1 33 Annual NSF Review 2
35 1.1 1.1.1.5.1.3 Annual NSF Review 3 Complete C 6 1 1 0 03/10/21 03/10/21 03/10/21 8:00 AM 03/10/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5.1.3 1 34 Annual NSF Review 3
36 1.1 1.1.1.5.1.4 Annual NSF Review 4 Not Started C 6 1 1 0 03/10/22 03/10/22 03/10/22 8:00 AM 03/10/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5.1.4 1 35 Annual NSF Review 4
37 1.1 1.1.1.5.1.5 Annual NSF Review 5 Not Started C 6 1 1 0 03/10/23 03/10/23 03/10/23 8:00 AM 03/10/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5.1.5 1 36 Annual NSF Review 5
38 1.1 1.1.1.5.1.6 Annual NSF Review 6 Not Started C 6 1 1 0 03/10/24 03/10/24 03/10/24 8:00 AM 03/10/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5.1.6 1 37 Annual NSF Review 6
39 1.1 1.1.1.5.1.7 Annual NSF Review 7 Not Started C 6 1 1 0 03/10/25 03/10/25 03/10/25 8:00 AM 03/10/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5.1.7 1 38 Annual NSF Review 7
40 1.1 1.1.1.5.1.8 Annual NSF Review 8 Not Started C 6 1 1 0 03/01/26 03/01/26 03/01/26 8:00 AM 03/01/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5.1.8 1 39 Annual NSF Review 8
41 1.1 1.1.1.5.2 Instrumentation Pre-Shipment Review Complete C 5 1 1 0 10/15/21 10/15/21 10/15/21 8:00 AM 10/15/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5.2 1 40 Instrumentation Pre-Shipment Review
42 1.1 1.1.1.5.3 Instrumentation Deployment Readiness Review Not Started C 5 1 1 0 10/28/22 10/28/22 10/28/22 8:00 AM 10/28/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.1.5.3 1 41 Instrumentation Deployment Readiness Review
43 1.1 1.1.2 Project Controls Started P 3 1 1992d 10/01/18 06/01/26 10/01/18 8:00 AM 06/01/26 4:59 PM 48% 49.00% Green $0.00 $0.00 $0.00 $0.00 PM 1.1.2 1 42 Project Controls
44 1.1 1.1.2.1 Project Controls and Finance (B) Started C 4 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 38% 43.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.1 1 43 Project Controls and Finance (B)
45 1.1 1.1.2.2 EVMS Started P 4 1 1988d 10/05/18 06/01/26 10/05/18 8:00 AM 06/01/26 4:59 PM 41% 10.0% Red $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2 1 44 EVMS
46 1.1 1.1.2.2.1 EVMS Operational Started C 5 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 38% 20.0% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.1 1 45 EVMS Operational
47 1.1 1.1.2.2.2 Project Financial and EV Monthly Report Should have Started P 5 1 1968d 10/05/18 05/05/26 10/05/18 8:00 AM 05/05/26 8:00 AM 43% 0% Red $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2 1 46 Project Financial and EV Monthly Report
48 1.1 1.1.2.2.2.1 Project Financial and EV Monthly Report 1 Started C 6 1 1 0 10/05/18 10/05/18 10/05/18 8:00 AM 10/05/18 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.1 1 47 Project Financial and EV Monthly Report 1
49 1.1 1.1.2.2.2.2 Project Financial and EV Monthly Report 2 Started C 6 1 1 0 11/05/18 11/05/18 11/05/18 8:00 AM 11/05/18 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.2 1 48 Project Financial and EV Monthly Report 2
50 1.1 1.1.2.2.2.3 Project Financial and EV Monthly Report 3 Started C 6 1 1 0 12/05/18 12/05/18 12/05/18 8:00 AM 12/05/18 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.3 1 49 Project Financial and EV Monthly Report 3
51 1.1 1.1.2.2.2.4 Project Financial and EV Monthly Report 4 Started C 6 1 1 0 01/05/19 01/05/19 01/05/19 8:00 AM 01/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.4 1 50 Project Financial and EV Monthly Report 4
52 1.1 1.1.2.2.2.5 Project Financial and EV Monthly Report 5 Started C 6 1 1 0 02/05/19 02/05/19 02/05/19 8:00 AM 02/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.5 1 51 Project Financial and EV Monthly Report 5
53 1.1 1.1.2.2.2.6 Project Financial and EV Monthly Report 6 Started C 6 1 1 0 03/05/19 03/05/19 03/05/19 8:00 AM 03/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.6 1 52 Project Financial and EV Monthly Report 6
54 1.1 1.1.2.2.2.7 Project Financial and EV Monthly Report 7 Started C 6 1 1 0 04/05/19 04/05/19 04/05/19 8:00 AM 04/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.7 1 53 Project Financial and EV Monthly Report 7
55 1.1 1.1.2.2.2.8 Project Financial and EV Monthly Report 8 Started C 6 1 1 0 05/05/19 05/05/19 05/05/19 8:00 AM 05/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.8 1 54 Project Financial and EV Monthly Report 8
56 1.1 1.1.2.2.2.9 Project Financial and EV Monthly Report 9 Started C 6 1 1 0 06/05/19 06/05/19 06/05/19 8:00 AM 06/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.9 1 55 Project Financial and EV Monthly Report 9
57 1.1 1.1.2.2.2.10 Project Financial and EV Monthly Report 10 Started C 6 1 1 0 07/05/19 07/05/19 07/05/19 8:00 AM 07/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.10 1 56 Project Financial and EV Monthly Report 10
58 1.1 1.1.2.2.2.11 Project Financial and EV Monthly Report 11 Started C 6 1 1 0 08/05/19 08/05/19 08/05/19 8:00 AM 08/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.11 1 57 Project Financial and EV Monthly Report 11
59 1.1 1.1.2.2.2.12 Project Financial and EV Monthly Report 12 Started C 6 1 1 0 09/05/19 09/05/19 09/05/19 8:00 AM 09/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.12 1 58 Project Financial and EV Monthly Report 12
60 1.1 1.1.2.2.2.13 Project Financial and EV Monthly Report 13 Started C 6 1 1 0 10/05/19 10/05/19 10/05/19 8:00 AM 10/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.13 1 59 Project Financial and EV Monthly Report 13
61 1.1 1.1.2.2.2.14 Project Financial and EV Monthly Report 14 Started C 6 1 1 0 11/05/19 11/05/19 11/05/19 8:00 AM 11/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.14 1 60 Project Financial and EV Monthly Report 14
62 1.1 1.1.2.2.2.15 Project Financial and EV Monthly Report 15 Started C 6 1 1 0 12/05/19 12/05/19 12/05/19 8:00 AM 12/05/19 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.15 1 61 Project Financial and EV Monthly Report 15
63 1.1 1.1.2.2.2.16 Project Financial and EV Monthly Report 16 Started C 6 1 1 0 01/05/20 01/05/20 01/05/20 8:00 AM 01/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.16 1 62 Project Financial and EV Monthly Report 16
64 1.1 1.1.2.2.2.17 Project Financial and EV Monthly Report 17 Started C 6 1 1 0 02/05/20 02/05/20 02/05/20 8:00 AM 02/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.17 1 63 Project Financial and EV Monthly Report 17
65 1.1 1.1.2.2.2.18 Project Financial and EV Monthly Report 18 Started C 6 1 1 0 03/05/20 03/05/20 03/05/20 8:00 AM 03/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.18 1 64 Project Financial and EV Monthly Report 18
66 1.1 1.1.2.2.2.19 Project Financial and EV Monthly Report 19 Started C 6 1 1 0 04/05/20 04/05/20 04/05/20 8:00 AM 04/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.19 1 65 Project Financial and EV Monthly Report 19
67 1.1 1.1.2.2.2.20 Project Financial and EV Monthly Report 20 Started C 6 1 1 0 05/05/20 05/05/20 05/05/20 8:00 AM 05/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.20 1 66 Project Financial and EV Monthly Report 20
68 1.1 1.1.2.2.2.21 Project Financial and EV Monthly Report 21 Started C 6 1 1 0 06/05/20 06/05/20 06/05/20 8:00 AM 06/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.21 1 67 Project Financial and EV Monthly Report 21
69 1.1 1.1.2.2.2.22 Project Financial and EV Monthly Report 22 Started C 6 1 1 0 07/05/20 07/05/20 07/05/20 8:00 AM 07/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.22 1 68 Project Financial and EV Monthly Report 22
70 1.1 1.1.2.2.2.23 Project Financial and EV Monthly Report 23 Started C 6 1 1 0 08/05/20 08/05/20 08/05/20 8:00 AM 08/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.23 1 69 Project Financial and EV Monthly Report 23
71 1.1 1.1.2.2.2.24 Project Financial and EV Monthly Report 24 Started C 6 1 1 0 09/05/20 09/05/20 09/05/20 8:00 AM 09/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.24 1 70 Project Financial and EV Monthly Report 24
72 1.1 1.1.2.2.2.25 Project Financial and EV Monthly Report 25 Started C 6 1 1 0 10/05/20 10/05/20 10/05/20 8:00 AM 10/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.25 1 71 Project Financial and EV Monthly Report 25
73 1.1 1.1.2.2.2.26 Project Financial and EV Monthly Report 26 Started C 6 1 1 0 11/05/20 11/05/20 11/05/20 8:00 AM 11/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.26 1 72 Project Financial and EV Monthly Report 26
74 1.1 1.1.2.2.2.27 Project Financial and EV Monthly Report 27 Started C 6 1 1 0 12/05/20 12/05/20 12/05/20 8:00 AM 12/05/20 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.27 1 73 Project Financial and EV Monthly Report 27
75 1.1 1.1.2.2.2.28 Project Financial and EV Monthly Report 28 Started C 6 1 1 0 01/05/21 01/05/21 01/05/21 8:00 AM 01/05/21 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.28 1 74 Project Financial and EV Monthly Report 28
76 1.1 1.1.2.2.2.29 Project Financial and EV Monthly Report 29 Started C 6 1 1 0 02/05/21 02/05/21 02/05/21 8:00 AM 02/05/21 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.29 1 75 Project Financial and EV Monthly Report 29
77 1.1 1.1.2.2.2.30 Project Financial and EV Monthly Report 30 Started C 6 1 1 0 03/05/21 03/05/21 03/05/21 8:00 AM 03/05/21 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.30 1 76 Project Financial and EV Monthly Report 30
78 1.1 1.1.2.2.2.31 Project Financial and EV Monthly Report 31 Started C 6 1 1 0 04/05/21 04/05/21 04/05/21 8:00 AM 04/05/21 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.31 1 77 Project Financial and EV Monthly Report 31
79 1.1 1.1.2.2.2.32 Project Financial and EV Monthly Report 32 Started C 6 1 1 0 05/05/21 05/05/21 05/05/21 8:00 AM 05/05/21 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.32 1 78 Project Financial and EV Monthly Report 32
80 1.1 1.1.2.2.2.33 Project Financial and EV Monthly Report 33 Started C 6 1 1 0 06/05/21 06/05/21 06/05/21 8:00 AM 06/05/21 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.33 1 79 Project Financial and EV Monthly Report 33
81 1.1 1.1.2.2.2.34 Project Financial and EV Monthly Report 34 Started C 6 1 1 0 07/05/21 07/05/21 07/05/21 8:00 AM 07/05/21 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.34 1 80 Project Financial and EV Monthly Report 34
82 1.1 1.1.2.2.2.35 Project Financial and EV Monthly Report 35 Started C 6 1 1 0 08/05/21 08/05/21 08/05/21 8:00 AM 08/05/21 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.35 1 81 Project Financial and EV Monthly Report 35
83 1.1 1.1.2.2.2.36 Project Financial and EV Monthly Report 36 Started C 6 1 1 0 09/05/21 09/05/21 09/05/21 8:00 AM 09/05/21 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.36 1 82 Project Financial and EV Monthly Report 36
84 1.1 1.1.2.2.2.37 Project Financial and EV Monthly Report 37 Started C 6 1 1 0 10/05/21 10/05/21 10/05/21 8:00 AM 10/05/21 8:00 AM 100% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.37 1 83 Project Financial and EV Monthly Report 37
85 1.1 1.1.2.2.2.38 Project Financial and EV Monthly Report 38 Should have Started C 6 1 1 0 11/05/21 11/05/21 11/05/21 8:00 AM 11/05/21 8:00 AM 100% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.38 1 84 Project Financial and EV Monthly Report 38
86 1.1 1.1.2.2.2.39 Project Financial and EV Monthly Report 39 Should have Started C 6 1 1 0 12/05/21 12/05/21 12/05/21 8:00 AM 12/05/21 8:00 AM 100% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.39 1 85 Project Financial and EV Monthly Report 39
87 1.1 1.1.2.2.2.40 Project Financial and EV Monthly Report 40 Should have Started C 6 1 1 0 01/05/22 01/05/22 01/05/22 8:00 AM 01/05/22 8:00 AM 100% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.40 1 86 Project Financial and EV Monthly Report 40
88 1.1 1.1.2.2.2.41 Project Financial and EV Monthly Report 41 Not Started C 6 1 1 0 02/05/22 02/05/22 02/05/22 8:00 AM 02/05/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.41 1 87 Project Financial and EV Monthly Report 41
89 1.1 1.1.2.2.2.42 Project Financial and EV Monthly Report 42 Not Started C 6 1 1 0 03/05/22 03/05/22 03/05/22 8:00 AM 03/05/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.42 1 88 Project Financial and EV Monthly Report 42
90 1.1 1.1.2.2.2.43 Project Financial and EV Monthly Report 43 Not Started C 6 1 1 0 04/05/22 04/05/22 04/05/22 8:00 AM 04/05/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.43 1 89 Project Financial and EV Monthly Report 43
91 1.1 1.1.2.2.2.44 Project Financial and EV Monthly Report 44 Not Started C 6 1 1 0 05/05/22 05/05/22 05/05/22 8:00 AM 05/05/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.44 1 90 Project Financial and EV Monthly Report 44
92 1.1 1.1.2.2.2.45 Project Financial and EV Monthly Report 45 Not Started C 6 1 1 0 06/05/22 06/05/22 06/05/22 8:00 AM 06/05/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.45 1 91 Project Financial and EV Monthly Report 45
93 1.1 1.1.2.2.2.46 Project Financial and EV Monthly Report 46 Not Started C 6 1 1 0 07/05/22 07/05/22 07/05/22 8:00 AM 07/05/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.46 1 92 Project Financial and EV Monthly Report 46
94 1.1 1.1.2.2.2.47 Project Financial and EV Monthly Report 47 Not Started C 6 1 1 0 08/05/22 08/05/22 08/05/22 8:00 AM 08/05/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.47 1 93 Project Financial and EV Monthly Report 47
95 1.1 1.1.2.2.2.48 Project Financial and EV Monthly Report 48 Not Started C 6 1 1 0 09/05/22 09/05/22 09/05/22 8:00 AM 09/05/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.48 1 94 Project Financial and EV Monthly Report 48
96 1.1 1.1.2.2.2.49 Project Financial and EV Monthly Report 49 Not Started C 6 1 1 0 10/05/22 10/05/22 10/05/22 8:00 AM 10/05/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.49 1 95 Project Financial and EV Monthly Report 49
97 1.1 1.1.2.2.2.50 Project Financial and EV Monthly Report 50 Not Started C 6 1 1 0 11/05/22 11/05/22 11/05/22 8:00 AM 11/05/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.50 1 96 Project Financial and EV Monthly Report 50
98 1.1 1.1.2.2.2.51 Project Financial and EV Monthly Report 51 Not Started C 6 1 1 0 12/05/22 12/05/22 12/05/22 8:00 AM 12/05/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.51 1 97 Project Financial and EV Monthly Report 51
99 1.1 1.1.2.2.2.52 Project Financial and EV Monthly Report 52 Not Started C 6 1 1 0 01/05/23 01/05/23 01/05/23 8:00 AM 01/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.52 1 98 Project Financial and EV Monthly Report 52
100 1.1 1.1.2.2.2.53 Project Financial and EV Monthly Report 53 Not Started C 6 1 1 0 02/05/23 02/05/23 02/05/23 8:00 AM 02/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.53 1 99 Project Financial and EV Monthly Report 53
101 1.1 1.1.2.2.2.54 Project Financial and EV Monthly Report 54 Not Started C 6 1 1 0 03/05/23 03/05/23 03/05/23 8:00 AM 03/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.54 1 100 Project Financial and EV Monthly Report 54
102 1.1 1.1.2.2.2.55 Project Financial and EV Monthly Report 55 Not Started C 6 1 1 0 04/05/23 04/05/23 04/05/23 8:00 AM 04/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.55 1 101 Project Financial and EV Monthly Report 55
103 1.1 1.1.2.2.2.56 Project Financial and EV Monthly Report 56 Not Started C 6 1 1 0 05/05/23 05/05/23 05/05/23 8:00 AM 05/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.56 1 102 Project Financial and EV Monthly Report 56
104 1.1 1.1.2.2.2.57 Project Financial and EV Monthly Report 57 Not Started C 6 1 1 0 06/05/23 06/05/23 06/05/23 8:00 AM 06/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.57 1 103 Project Financial and EV Monthly Report 57
105 1.1 1.1.2.2.2.58 Project Financial and EV Monthly Report 58 Not Started C 6 1 1 0 07/05/23 07/05/23 07/05/23 8:00 AM 07/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.58 1 104 Project Financial and EV Monthly Report 58
106 1.1 1.1.2.2.2.59 Project Financial and EV Monthly Report 59 Not Started C 6 1 1 0 08/05/23 08/05/23 08/05/23 8:00 AM 08/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.59 1 105 Project Financial and EV Monthly Report 59
107 1.1 1.1.2.2.2.60 Project Financial and EV Monthly Report 60 Not Started C 6 1 1 0 09/05/23 09/05/23 09/05/23 8:00 AM 09/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.60 1 106 Project Financial and EV Monthly Report 60
108 1.1 1.1.2.2.2.61 Project Financial and EV Monthly Report 61 Not Started C 6 1 1 0 10/05/23 10/05/23 10/05/23 8:00 AM 10/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.61 1 107 Project Financial and EV Monthly Report 61
109 1.1 1.1.2.2.2.62 Project Financial and EV Monthly Report 62 Not Started C 6 1 1 0 11/05/23 11/05/23 11/05/23 8:00 AM 11/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.62 1 108 Project Financial and EV Monthly Report 62
110 1.1 1.1.2.2.2.63 Project Financial and EV Monthly Report 63 Not Started C 6 1 1 0 12/05/23 12/05/23 12/05/23 8:00 AM 12/05/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.63 1 109 Project Financial and EV Monthly Report 63
111 1.1 1.1.2.2.2.64 Project Financial and EV Monthly Report 64 Not Started C 6 1 1 0 01/05/24 01/05/24 01/05/24 8:00 AM 01/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.64 1 110 Project Financial and EV Monthly Report 64
112 1.1 1.1.2.2.2.65 Project Financial and EV Monthly Report 65 Not Started C 6 1 1 0 02/05/24 02/05/24 02/05/24 8:00 AM 02/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.65 1 111 Project Financial and EV Monthly Report 65
113 1.1 1.1.2.2.2.66 Project Financial and EV Monthly Report 66 Not Started C 6 1 1 0 03/05/24 03/05/24 03/05/24 8:00 AM 03/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.66 1 112 Project Financial and EV Monthly Report 66
114 1.1 1.1.2.2.2.67 Project Financial and EV Monthly Report 67 Not Started C 6 1 1 0 04/05/24 04/05/24 04/05/24 8:00 AM 04/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.67 1 113 Project Financial and EV Monthly Report 67
115 1.1 1.1.2.2.2.68 Project Financial and EV Monthly Report 68 Not Started C 6 1 1 0 05/05/24 05/05/24 05/05/24 8:00 AM 05/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.68 1 114 Project Financial and EV Monthly Report 68
116 1.1 1.1.2.2.2.69 Project Financial and EV Monthly Report 69 Not Started C 6 1 1 0 06/05/24 06/05/24 06/05/24 8:00 AM 06/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.69 1 115 Project Financial and EV Monthly Report 69
117 1.1 1.1.2.2.2.70 Project Financial and EV Monthly Report 70 Not Started C 6 1 1 0 07/05/24 07/05/24 07/05/24 8:00 AM 07/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.70 1 116 Project Financial and EV Monthly Report 70
118 1.1 1.1.2.2.2.71 Project Financial and EV Monthly Report 71 Not Started C 6 1 1 0 08/05/24 08/05/24 08/05/24 8:00 AM 08/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.71 1 117 Project Financial and EV Monthly Report 71
119 1.1 1.1.2.2.2.72 Project Financial and EV Monthly Report 72 Not Started C 6 1 1 0 09/05/24 09/05/24 09/05/24 8:00 AM 09/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.72 1 118 Project Financial and EV Monthly Report 72
120 1.1 1.1.2.2.2.73 Project Financial and EV Monthly Report 73 Not Started C 6 1 1 0 10/05/24 10/05/24 10/05/24 8:00 AM 10/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.73 1 119 Project Financial and EV Monthly Report 73
121 1.1 1.1.2.2.2.74 Project Financial and EV Monthly Report 74 Not Started C 6 1 1 0 11/05/24 11/05/24 11/05/24 8:00 AM 11/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.74 1 120 Project Financial and EV Monthly Report 74
122 1.1 1.1.2.2.2.75 Project Financial and EV Monthly Report 75 Not Started C 6 1 1 0 12/05/24 12/05/24 12/05/24 8:00 AM 12/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.75 1 121 Project Financial and EV Monthly Report 75
123 1.1 1.1.2.2.2.76 Project Financial and EV Monthly Report 76 Not Started C 6 1 1 0 01/05/25 01/05/25 01/05/25 8:00 AM 01/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.76 1 122 Project Financial and EV Monthly Report 76
124 1.1 1.1.2.2.2.77 Project Financial and EV Monthly Report 77 Not Started C 6 1 1 0 02/05/25 02/05/25 02/05/25 8:00 AM 02/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.77 1 123 Project Financial and EV Monthly Report 77
125 1.1 1.1.2.2.2.78 Project Financial and EV Monthly Report 78 Not Started C 6 1 1 0 03/05/25 03/05/25 03/05/25 8:00 AM 03/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.78 1 124 Project Financial and EV Monthly Report 78
126 1.1 1.1.2.2.2.79 Project Financial and EV Monthly Report 79 Not Started C 6 1 1 0 04/05/25 04/05/25 04/05/25 8:00 AM 04/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.79 1 125 Project Financial and EV Monthly Report 79
127 1.1 1.1.2.2.2.80 Project Financial and EV Monthly Report 80 Not Started C 6 1 1 0 05/05/25 05/05/25 05/05/25 8:00 AM 05/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.80 1 126 Project Financial and EV Monthly Report 80
128 1.1 1.1.2.2.2.81 Project Financial and EV Monthly Report 81 Not Started C 6 1 1 0 06/05/25 06/05/25 06/05/25 8:00 AM 06/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.81 1 127 Project Financial and EV Monthly Report 81
129 1.1 1.1.2.2.2.82 Project Financial and EV Monthly Report 82 Not Started C 6 1 1 0 07/05/25 07/05/25 07/05/25 8:00 AM 07/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.82 1 128 Project Financial and EV Monthly Report 82
130 1.1 1.1.2.2.2.83 Project Financial and EV Monthly Report 83 Not Started C 6 1 1 0 08/05/25 08/05/25 08/05/25 8:00 AM 08/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.83 1 129 Project Financial and EV Monthly Report 83
131 1.1 1.1.2.2.2.84 Project Financial and EV Monthly Report 84 Not Started C 6 1 1 0 09/05/25 09/05/25 09/05/25 8:00 AM 09/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.84 1 130 Project Financial and EV Monthly Report 84
132 1.1 1.1.2.2.2.85 Project Financial and EV Monthly Report 85 Not Started C 6 1 1 0 10/05/25 10/05/25 10/05/25 8:00 AM 10/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.85 1 131 Project Financial and EV Monthly Report 85
133 1.1 1.1.2.2.2.86 Project Financial and EV Monthly Report 86 Not Started C 6 1 1 0 11/05/25 11/05/25 11/05/25 8:00 AM 11/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.86 1 132 Project Financial and EV Monthly Report 86
134 1.1 1.1.2.2.2.87 Project Financial and EV Monthly Report 87 Not Started C 6 1 1 0 12/05/25 12/05/25 12/05/25 8:00 AM 12/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.87 1 133 Project Financial and EV Monthly Report 87
135 1.1 1.1.2.2.2.88 Project Financial and EV Monthly Report 88 Not Started C 6 1 1 0 01/05/26 01/05/26 01/05/26 8:00 AM 01/05/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.88 1 134 Project Financial and EV Monthly Report 88
136 1.1 1.1.2.2.2.89 Project Financial and EV Monthly Report 89 Not Started C 6 1 1 0 02/05/26 02/05/26 02/05/26 8:00 AM 02/05/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.89 1 135 Project Financial and EV Monthly Report 89
137 1.1 1.1.2.2.2.90 Project Financial and EV Monthly Report 90 Not Started C 6 1 1 0 03/05/26 03/05/26 03/05/26 8:00 AM 03/05/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.90 1 136 Project Financial and EV Monthly Report 90
138 1.1 1.1.2.2.2.91 Project Financial and EV Monthly Report 91 Not Started C 6 1 1 0 04/05/26 04/05/26 04/05/26 8:00 AM 04/05/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.91 1 137 Project Financial and EV Monthly Report 91
139 1.1 1.1.2.2.2.92 Project Financial and EV Monthly Report 92 Not Started C 6 1 1 0 05/05/26 05/05/26 05/05/26 8:00 AM 05/05/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.2.2.92 1 138 Project Financial and EV Monthly Report 92
140 1.1 1.1.2.3 Subaward Management Started P 4 1 1821d 10/01/18 10/01/25 10/01/18 8:00 AM 10/01/25 8:00 AM 75% 99.00% Green $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3 1 139 Subaward Management
141 1.1 1.1.2.3.1 Setup subagreements w US institutions Complete C 5 1 1 1d 01/30/19 01/30/19 01/30/19 8:00 AM 01/30/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.1 1 140 Setup subagreements w US institutions
142 1.1 1.1.2.3.2 Distributed Funding to Sub-Awardees Started P 5 1 1821d 10/01/18 10/01/25 10/01/18 8:00 AM 10/01/25 8:00 AM 50% 99.00% Green $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.2 1 141 Distributed Funding to Sub-Awardees
143 1.1 1.1.2.3.2.1 Distributed Funding to Sub-Awardees 1 Complete C 6 1 1 1d 10/01/18 10/01/18 10/01/18 8:00 AM 10/01/18 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.2.1 1 142 Distributed Funding to Sub-Awardees 1
144 1.1 1.1.2.3.2.2 Distributed Funding to Sub-Awardees 2 Complete C 6 1 1 1d 10/01/19 10/01/19 10/01/19 8:00 AM 10/01/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.2.2 1 143 Distributed Funding to Sub-Awardees 2
145 1.1 1.1.2.3.2.3 Distributed Funding to Sub-Awardees 3 Complete C 6 1 1 1d 10/01/20 10/01/20 10/01/20 8:00 AM 10/01/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.2.3 1 144 Distributed Funding to Sub-Awardees 3
146 1.1 1.1.2.3.2.4 Distributed Funding to Sub-Awardees 4 Complete C 6 1 1 1d 10/01/21 10/01/21 10/01/21 8:00 AM 10/01/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.2.4 1 145 Distributed Funding to Sub-Awardees 4
147 1.1 1.1.2.3.2.5 Distributed Funding to Sub-Awardees 5 Not Started C 6 1 1 0 10/01/22 10/01/22 10/01/22 8:00 AM 10/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.2.5 1 146 Distributed Funding to Sub-Awardees 5
148 1.1 1.1.2.3.2.6 Distributed Funding to Sub-Awardees 6 Not Started C 6 1 1 0 10/01/23 10/01/23 10/01/23 8:00 AM 10/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.2.6 1 147 Distributed Funding to Sub-Awardees 6
149 1.1 1.1.2.3.2.7 Distributed Funding to Sub-Awardees 7 Not Started C 6 1 1 0 10/01/24 10/01/24 10/01/24 8:00 AM 10/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.2.7 1 148 Distributed Funding to Sub-Awardees 7
150 1.1 1.1.2.3.2.8 Distributed Funding to Sub-Awardees 8 Not Started C 6 1 1 0 10/01/25 10/01/25 10/01/25 8:00 AM 10/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.2.8 1 149 Distributed Funding to Sub-Awardees 8
151 1.1 1.1.2.3.3 Monthly Tracking Started P 6 1 1777d 11/03/18 09/03/25 11/03/18 8:00 AM 09/03/25 8:00 AM 46% 99.00% Green $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3 1 150 Monthly Tracking
152 1.1 1.1.2.3.3.1 Monthly Tracking 1 Complete C 7 1 1 1d 11/03/18 11/03/18 11/03/18 8:00 AM 11/03/18 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.1 1 151 Monthly Tracking 1
153 1.1 1.1.2.3.3.2 Monthly Tracking 2 Complete C 7 1 1 1d 12/03/18 12/03/18 12/03/18 8:00 AM 12/03/18 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.2 1 152 Monthly Tracking 2
154 1.1 1.1.2.3.3.3 Monthly Tracking 3 Complete C 7 1 1 1d 01/03/19 01/03/19 01/03/19 8:00 AM 01/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.3 1 153 Monthly Tracking 3
155 1.1 1.1.2.3.3.4 Monthly Tracking 4 Complete C 7 1 1 1d 02/03/19 02/03/19 02/03/19 8:00 AM 02/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.4 1 154 Monthly Tracking 4
156 1.1 1.1.2.3.3.5 Monthly Tracking 5 Complete C 7 1 1 1d 03/03/19 03/03/19 03/03/19 8:00 AM 03/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.5 1 155 Monthly Tracking 5
157 1.1 1.1.2.3.3.6 Monthly Tracking 6 Complete C 7 1 1 1d 04/03/19 04/03/19 04/03/19 8:00 AM 04/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.6 1 156 Monthly Tracking 6
158 1.1 1.1.2.3.3.7 Monthly Tracking 7 Complete C 7 1 1 1d 05/03/19 05/03/19 05/03/19 8:00 AM 05/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.7 1 157 Monthly Tracking 7
159 1.1 1.1.2.3.3.8 Monthly Tracking 8 Complete C 7 1 1 1d 06/03/19 06/03/19 06/03/19 8:00 AM 06/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.8 1 158 Monthly Tracking 8
160 1.1 1.1.2.3.3.9 Monthly Tracking 9 Complete C 7 1 1 1d 07/03/19 07/03/19 07/03/19 8:00 AM 07/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.9 1 159 Monthly Tracking 9
161 1.1 1.1.2.3.3.10 Monthly Tracking 10 Complete C 7 1 1 1d 08/03/19 08/03/19 08/03/19 8:00 AM 08/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.10 1 160 Monthly Tracking 10
162 1.1 1.1.2.3.3.11 Monthly Tracking 11 Complete C 7 1 1 1d 09/03/19 09/03/19 09/03/19 8:00 AM 09/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.11 1 161 Monthly Tracking 11
163 1.1 1.1.2.3.3.12 Monthly Tracking 12 Complete C 7 1 1 1d 10/03/19 10/03/19 10/03/19 8:00 AM 10/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.12 1 162 Monthly Tracking 12
164 1.1 1.1.2.3.3.13 Monthly Tracking 13 Complete C 7 1 1 1d 11/03/19 11/03/19 11/03/19 8:00 AM 11/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.13 1 163 Monthly Tracking 13
165 1.1 1.1.2.3.3.14 Monthly Tracking 14 Complete C 7 1 1 1d 12/03/19 12/03/19 12/03/19 8:00 AM 12/03/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.14 1 164 Monthly Tracking 14
166 1.1 1.1.2.3.3.15 Monthly Tracking 15 Complete C 7 1 1 1d 01/03/20 01/03/20 01/03/20 8:00 AM 01/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.15 1 165 Monthly Tracking 15
167 1.1 1.1.2.3.3.16 Monthly Tracking 16 Complete C 7 1 1 1d 02/03/20 02/03/20 02/03/20 8:00 AM 02/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.16 1 166 Monthly Tracking 16
168 1.1 1.1.2.3.3.17 Monthly Tracking 17 Complete C 7 1 1 1d 03/03/20 03/03/20 03/03/20 8:00 AM 03/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.17 1 167 Monthly Tracking 17
169 1.1 1.1.2.3.3.18 Monthly Tracking 18 Complete C 7 1 1 1d 04/03/20 04/03/20 04/03/20 8:00 AM 04/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.18 1 168 Monthly Tracking 18
170 1.1 1.1.2.3.3.19 Monthly Tracking 19 Complete C 7 1 1 1d 05/03/20 05/03/20 05/03/20 8:00 AM 05/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.19 1 169 Monthly Tracking 19
171 1.1 1.1.2.3.3.20 Monthly Tracking 20 Complete C 7 1 1 1d 06/03/20 06/03/20 06/03/20 8:00 AM 06/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.20 1 170 Monthly Tracking 20
172 1.1 1.1.2.3.3.21 Monthly Tracking 21 Complete C 7 1 1 1d 07/03/20 07/03/20 07/03/20 8:00 AM 07/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.21 1 171 Monthly Tracking 21
173 1.1 1.1.2.3.3.22 Monthly Tracking 22 Complete C 7 1 1 1d 08/03/20 08/03/20 08/03/20 8:00 AM 08/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.22 1 172 Monthly Tracking 22
174 1.1 1.1.2.3.3.23 Monthly Tracking 23 Complete C 7 1 1 1d 09/03/20 09/03/20 09/03/20 8:00 AM 09/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.23 1 173 Monthly Tracking 23
175 1.1 1.1.2.3.3.24 Monthly Tracking 24 Complete C 7 1 1 1d 10/03/20 10/03/20 10/03/20 8:00 AM 10/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.24 1 174 Monthly Tracking 24
176 1.1 1.1.2.3.3.25 Monthly Tracking 25 Complete C 7 1 1 1d 11/03/20 11/03/20 11/03/20 8:00 AM 11/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.25 1 175 Monthly Tracking 25
177 1.1 1.1.2.3.3.26 Monthly Tracking 26 Complete C 7 1 1 1d 12/03/20 12/03/20 12/03/20 8:00 AM 12/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.26 1 176 Monthly Tracking 26
178 1.1 1.1.2.3.3.27 Monthly Tracking 27 Complete C 7 1 1 1d 01/03/21 01/03/21 01/03/21 8:00 AM 01/03/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.27 1 177 Monthly Tracking 27
179 1.1 1.1.2.3.3.28 Monthly Tracking 28 Complete C 7 1 1 1d 02/03/21 02/03/21 02/03/21 8:00 AM 02/03/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.28 1 178 Monthly Tracking 28
180 1.1 1.1.2.3.3.29 Monthly Tracking 29 Complete C 7 1 1 1d 03/03/21 03/03/21 03/03/21 8:00 AM 03/03/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.29 1 179 Monthly Tracking 29
181 1.1 1.1.2.3.3.30 Monthly Tracking 30 Complete C 7 1 1 1d 04/03/21 04/03/21 04/03/21 8:00 AM 04/03/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.30 1 180 Monthly Tracking 30
182 1.1 1.1.2.3.3.31 Monthly Tracking 31 Complete C 7 1 1 1d 05/03/21 05/03/21 05/03/21 8:00 AM 05/03/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.31 1 181 Monthly Tracking 31
183 1.1 1.1.2.3.3.32 Monthly Tracking 32 Complete C 7 1 1 1d 06/03/21 06/03/21 06/03/21 8:00 AM 06/03/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.32 1 182 Monthly Tracking 32
184 1.1 1.1.2.3.3.33 Monthly Tracking 33 Complete C 7 1 1 1d 07/03/21 07/03/21 07/03/21 8:00 AM 07/03/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.33 1 183 Monthly Tracking 33
185 1.1 1.1.2.3.3.34 Monthly Tracking 34 Complete C 7 1 1 1d 08/03/21 08/03/21 08/03/21 8:00 AM 08/03/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.34 1 184 Monthly Tracking 34
186 1.1 1.1.2.3.3.35 Monthly Tracking 35 Complete C 7 1 1 1d 09/03/21 09/03/21 09/03/21 8:00 AM 09/03/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.35 1 185 Monthly Tracking 35
187 1.1 1.1.2.3.3.36 Monthly Tracking 36 Started C 7 1 1 0 10/03/21 10/03/21 10/03/21 8:00 AM 10/03/21 8:00 AM 100% 50.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.36 1 186 Monthly Tracking 36
188 1.1 1.1.2.3.3.37 Monthly Tracking 37 Should have Started C 7 1 1 0 11/03/21 11/03/21 11/03/21 8:00 AM 11/03/21 8:00 AM 100% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.37 1 187 Monthly Tracking 37
189 1.1 1.1.2.3.3.38 Monthly Tracking 38 Should have Started C 7 1 1 0 12/03/21 12/03/21 12/03/21 8:00 AM 12/03/21 8:00 AM 100% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.38 1 188 Monthly Tracking 38
190 1.1 1.1.2.3.3.39 Monthly Tracking 39 Should have Started C 7 1 1 0 01/03/22 01/03/22 01/03/22 8:00 AM 01/03/22 8:00 AM 100% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.39 1 189 Monthly Tracking 39
191 1.1 1.1.2.3.3.40 Monthly Tracking 40 Not Started C 7 1 1 0 02/03/22 02/03/22 02/03/22 8:00 AM 02/03/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.40 1 190 Monthly Tracking 40
192 1.1 1.1.2.3.3.41 Monthly Tracking 41 Not Started C 7 1 1 0 03/03/22 03/03/22 03/03/22 8:00 AM 03/03/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.41 1 191 Monthly Tracking 41
193 1.1 1.1.2.3.3.42 Monthly Tracking 42 Not Started C 7 1 1 0 04/03/22 04/03/22 04/03/22 8:00 AM 04/03/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.42 1 192 Monthly Tracking 42
194 1.1 1.1.2.3.3.43 Monthly Tracking 43 Not Started C 7 1 1 0 05/03/22 05/03/22 05/03/22 8:00 AM 05/03/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.43 1 193 Monthly Tracking 43
195 1.1 1.1.2.3.3.44 Monthly Tracking 44 Not Started C 7 1 1 0 06/03/22 06/03/22 06/03/22 8:00 AM 06/03/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.44 1 194 Monthly Tracking 44
196 1.1 1.1.2.3.3.45 Monthly Tracking 45 Not Started C 7 1 1 0 07/03/22 07/03/22 07/03/22 8:00 AM 07/03/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.45 1 195 Monthly Tracking 45
197 1.1 1.1.2.3.3.46 Monthly Tracking 46 Not Started C 7 1 1 0 08/03/22 08/03/22 08/03/22 8:00 AM 08/03/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.46 1 196 Monthly Tracking 46
198 1.1 1.1.2.3.3.47 Monthly Tracking 47 Not Started C 7 1 1 0 09/03/22 09/03/22 09/03/22 8:00 AM 09/03/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.47 1 197 Monthly Tracking 47
199 1.1 1.1.2.3.3.48 Monthly Tracking 48 Not Started C 7 1 1 0 10/03/22 10/03/22 10/03/22 8:00 AM 10/03/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.48 1 198 Monthly Tracking 48
200 1.1 1.1.2.3.3.49 Monthly Tracking 49 Not Started C 7 1 1 0 11/03/22 11/03/22 11/03/22 8:00 AM 11/03/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.49 1 199 Monthly Tracking 49
201 1.1 1.1.2.3.3.50 Monthly Tracking 50 Not Started C 7 1 1 0 12/03/22 12/03/22 12/03/22 8:00 AM 12/03/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.50 1 200 Monthly Tracking 50
202 1.1 1.1.2.3.3.51 Monthly Tracking 51 Not Started C 7 1 1 0 01/03/23 01/03/23 01/03/23 8:00 AM 01/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.51 1 201 Monthly Tracking 51
203 1.1 1.1.2.3.3.52 Monthly Tracking 52 Not Started C 7 1 1 0 02/03/23 02/03/23 02/03/23 8:00 AM 02/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.52 1 202 Monthly Tracking 52
204 1.1 1.1.2.3.3.53 Monthly Tracking 53 Not Started C 7 1 1 0 03/03/23 03/03/23 03/03/23 8:00 AM 03/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.53 1 203 Monthly Tracking 53
205 1.1 1.1.2.3.3.54 Monthly Tracking 54 Not Started C 7 1 1 0 04/03/23 04/03/23 04/03/23 8:00 AM 04/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.54 1 204 Monthly Tracking 54
206 1.1 1.1.2.3.3.55 Monthly Tracking 55 Not Started C 7 1 1 0 05/03/23 05/03/23 05/03/23 8:00 AM 05/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.55 1 205 Monthly Tracking 55
207 1.1 1.1.2.3.3.56 Monthly Tracking 56 Not Started C 7 1 1 0 06/03/23 06/03/23 06/03/23 8:00 AM 06/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.56 1 206 Monthly Tracking 56
208 1.1 1.1.2.3.3.57 Monthly Tracking 57 Not Started C 7 1 1 0 07/03/23 07/03/23 07/03/23 8:00 AM 07/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.57 1 207 Monthly Tracking 57
209 1.1 1.1.2.3.3.58 Monthly Tracking 58 Not Started C 7 1 1 0 08/03/23 08/03/23 08/03/23 8:00 AM 08/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.58 1 208 Monthly Tracking 58
210 1.1 1.1.2.3.3.59 Monthly Tracking 59 Not Started C 7 1 1 0 09/03/23 09/03/23 09/03/23 8:00 AM 09/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.59 1 209 Monthly Tracking 59
211 1.1 1.1.2.3.3.60 Monthly Tracking 60 Not Started C 7 1 1 0 09/29/23 09/29/23 09/29/23 8:00 AM 09/29/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.60 1 210 Monthly Tracking 60
212 1.1 1.1.2.3.3.61 Monthly Tracking 61 Not Started C 7 1 1 0 10/03/23 10/03/23 10/03/23 8:00 AM 10/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.61 1 211 Monthly Tracking 61
213 1.1 1.1.2.3.3.62 Monthly Tracking 62 Not Started C 7 1 1 0 11/03/23 11/03/23 11/03/23 8:00 AM 11/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.62 1 212 Monthly Tracking 62
214 1.1 1.1.2.3.3.63 Monthly Tracking 63 Not Started C 7 1 1 0 12/03/23 12/03/23 12/03/23 8:00 AM 12/03/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.63 1 213 Monthly Tracking 63
215 1.1 1.1.2.3.3.64 Monthly Tracking 64 Not Started C 7 1 1 0 01/03/24 01/03/24 01/03/24 8:00 AM 01/03/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.64 1 214 Monthly Tracking 64
216 1.1 1.1.2.3.3.65 Monthly Tracking 65 Not Started C 7 1 1 0 02/03/24 02/03/24 02/03/24 8:00 AM 02/03/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.65 1 215 Monthly Tracking 65
217 1.1 1.1.2.3.3.66 Monthly Tracking 66 Not Started C 7 1 1 0 03/03/24 03/03/24 03/03/24 8:00 AM 03/03/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.66 1 216 Monthly Tracking 66
218 1.1 1.1.2.3.3.67 Monthly Tracking 67 Not Started C 7 1 1 0 04/03/24 04/03/24 04/03/24 8:00 AM 04/03/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.67 1 217 Monthly Tracking 67
219 1.1 1.1.2.3.3.68 Monthly Tracking 68 Not Started C 7 1 1 0 05/03/24 05/03/24 05/03/24 8:00 AM 05/03/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.68 1 218 Monthly Tracking 68
220 1.1 1.1.2.3.3.69 Monthly Tracking 69 Not Started C 7 1 1 0 06/03/24 06/03/24 06/03/24 8:00 AM 06/03/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.69 1 219 Monthly Tracking 69
221 1.1 1.1.2.3.3.70 Monthly Tracking 70 Not Started C 7 1 1 0 07/03/24 07/03/24 07/03/24 8:00 AM 07/03/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.70 1 220 Monthly Tracking 70
222 1.1 1.1.2.3.3.71 Monthly Tracking 71 Not Started C 7 1 1 0 08/03/24 08/03/24 08/03/24 8:00 AM 08/03/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.71 1 221 Monthly Tracking 71
223 1.1 1.1.2.3.3.72 Monthly Tracking 72 Not Started C 7 1 1 0 09/03/24 09/03/24 09/03/24 8:00 AM 09/03/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.72 1 222 Monthly Tracking 72
224 1.1 1.1.2.3.3.73 Monthly Tracking 73 Not Started C 7 1 1 0 10/29/24 10/29/24 10/29/24 8:00 AM 10/29/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.73 1 223 Monthly Tracking 73
225 1.1 1.1.2.3.3.74 Monthly Tracking 74 Not Started C 7 1 1 0 11/03/24 11/03/24 11/03/24 8:00 AM 11/03/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.74 1 224 Monthly Tracking 74
226 1.1 1.1.2.3.3.75 Monthly Tracking 75 Not Started C 7 1 1 0 12/03/24 12/03/24 12/03/24 8:00 AM 12/03/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.75 1 225 Monthly Tracking 75
227 1.1 1.1.2.3.3.76 Monthly Tracking 76 Not Started C 7 1 1 0 01/03/25 01/03/25 01/03/25 8:00 AM 01/03/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.76 1 226 Monthly Tracking 76
228 1.1 1.1.2.3.3.77 Monthly Tracking 77 Not Started C 7 1 1 0 02/03/25 02/03/25 02/03/25 8:00 AM 02/03/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.77 1 227 Monthly Tracking 77
229 1.1 1.1.2.3.3.78 Monthly Tracking 78 Not Started C 7 1 1 0 03/03/25 03/03/25 03/03/25 8:00 AM 03/03/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.78 1 228 Monthly Tracking 78
230 1.1 1.1.2.3.3.79 Monthly Tracking 79 Not Started C 7 1 1 0 04/03/25 04/03/25 04/03/25 8:00 AM 04/03/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.79 1 229 Monthly Tracking 79
231 1.1 1.1.2.3.3.80 Monthly Tracking 80 Not Started C 7 1 1 0 05/03/25 05/03/25 05/03/25 8:00 AM 05/03/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.80 1 230 Monthly Tracking 80
232 1.1 1.1.2.3.3.81 Monthly Tracking 81 Not Started C 7 1 1 0 06/03/25 06/03/25 06/03/25 8:00 AM 06/03/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.81 1 231 Monthly Tracking 81
233 1.1 1.1.2.3.3.82 Monthly Tracking 82 Not Started C 7 1 1 0 07/03/25 07/03/25 07/03/25 8:00 AM 07/03/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.82 1 232 Monthly Tracking 82
234 1.1 1.1.2.3.3.83 Monthly Tracking 83 Not Started C 7 1 1 0 08/03/25 08/03/25 08/03/25 8:00 AM 08/03/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.83 1 233 Monthly Tracking 83
235 1.1 1.1.2.3.3.84 Monthly Tracking 84 Not Started C 7 1 1 0 09/03/25 09/03/25 09/03/25 8:00 AM 09/03/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.3.3.84 1 234 Monthly Tracking 84
236 1.1 1.1.2.4 Financial Reporting Started C 4 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 38% 48.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.2.4 1 235 Financial Reporting
237 1.1 1.1.3 Quality and Safety Started P 3 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 16% 16.00% Green $0.00 $0.00 $17,946.51 $110,879.04 16% PM 1.1.3 1 236 Quality and Safety
238 162 1.1 1.1.3.1 Quality, Safety Management, Document Control Systems (B) Started C 4 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 16% 16% Green $17,946.51 $110,879.04 $17,946.51 $110,879.04 16% $17,740.65 PM 1.1.3.1 1 237 Quality, Safety Management, Document Control Systems (B)
239 1.1 1.1.4 Polar Operations Started P 3 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 14% 17% Green $0.00 $0.00 $24,530.93 $169,585.57 14% PM 1.1.4 1 238 Polar Operations
240 1.1 1.1.4.1 Logistics (B) Started C 4 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 14% 10% Green $24,530.93 $169,585.57 $24,530.93 $169,585.57 14% $16,958.56 PM 1.1.4.1 1 239 Logistics (B)
241 1.1 1.1.4.2 Antarctic Support Contractor Started C 4 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 38% 20% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.4.2 1 240 Antarctic Support Contractor
242 1.1 1.1.4.3 Environment, Health, and Safety Started C 4 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 38% 20% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.4.3 1 241 Environment, Health, and Safety
243 1.1 1.1.4.4 ICL Readied by ASC for Upgrade String Comissioning Not Started C 4 1 0 12/01/22 12/01/22 12/01/22 8:00 AM 12/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.4.4 1 242 ICL Readied by ASC for Upgrade String Comissioning
244 1.1 1.1.5 Project Engineering Started P 3 1 1904d 01/31/19 06/01/26 01/31/19 8:00 AM 06/01/26 4:59 PM 15% 12.00% Green $0.00 $0.00 $4,623.55 $30,941.28 15% PM 1.1.5 1 243 Project Engineering
245 1.1 1.1.5.1 Systems Engineering (B) Should have Started C 4 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 15% Yellow $4,623.55 $30,941.28 $4,623.55 $30,941.28 15% $0.00 PM 1.1.5.1 1 244 Systems Engineering (B)
246 1.1 1.1.5.2 System Engineering Started P 4 1 1904d 01/31/19 06/01/26 01/31/19 8:00 AM 06/01/26 4:59 PM 85% 22.00% Red $0.00 $0.00 $0.00 $0.00 PM 1.1.5.2 1 245 System Engineering
247 1.1 1.1.5.2.1 System Engineering Support Started C 5 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 38% 22% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.5.2.1 1 246 System Engineering Support
248 1.1 1.1.5.2.2 Upgrade String Design Complete Complete C 5 1 1 1 1d 04/03/20 04/03/20 04/03/20 8:00 AM 04/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.5.2.2 1 247 Upgrade String Design Complete
249 1.1 1.1.5.2.3 Configuration Management Plan Complete C 5 1 1d 01/31/19 01/31/19 01/31/19 8:00 AM 01/31/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.5.2.3 1 248 Configuration Management Plan
250 1.1 1.1.5.2.4 Configuration Management Process Implemented Complete C 5 1 1d 02/15/19 02/15/19 02/15/19 8:00 AM 02/15/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.5.2.4 1 249 Configuration Management Process Implemented
251 1.1 1.1.5.3 Production Management Started C 4 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 38% 12% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.5.3 1 250 Production Management
252 1.1 1.1.5.4 Risk Management Started C 4 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 38% 12% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.5.4 1 251 Risk Management
253 1.1 1.1.5.5 Reliability and Quality Assurance Started C 4 1 1825d 05/22/19 06/01/26 05/22/19 8:00 AM 06/01/26 4:59 PM 253FF, 255SS 38% 12% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.5.5 1 252 Reliability and Quality Assurance
254 1.1 1.1.6 Upgrade Project Closeout Not Started C 3 1 1 40d 04/07/26 06/01/26 04/07/26 8:00 AM 06/01/26 4:59 PM 254 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.6 1 253 Upgrade Project Closeout
255 1.1 1.1.7 Detector complete and handed off to M&O Not Started C 3 1 1 1 1 0 04/06/26 04/06/26 04/06/26 4:59 PM 04/06/26 4:59 PM 3571, 3565 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.7 1 254 Detector complete and handed off to M&O
256 1.1 1.1.8 RF Project Start Should have Started C 3 1 0 10/01/18 10/01/18 10/01/18 8:00 AM 10/01/18 8:00 AM 100% Red $0.00 $0.00 $0.00 $0.00 $0.00 PM 1.1.8 1 255 RF Project Start
257 1.2 1.2 Upgrade Implementation Started P 2 1 1973d 10/01/18 05/05/26 10/01/18 8:00 AM 05/05/26 4:59 PM 16.39% 39.00% Green $0.00 $0.00 $294,859.70 $1,799,466.46 16% Ian McEwen 1.2 1 256 Upgrade Implementation
258 1.2 1.2.1 Implementation Management & Systems Engineering Started P 3 1 1973d 10/01/18 05/05/26 10/01/18 8:00 AM 05/05/26 4:59 PM 16.63% 30.0% Green $0.00 $0.00 $68,769.38 $413,456.36 17% Ian McEwen 1.2.1 1 257 Implementation Management & Systems Engineering
259 1.2 1.2.1.1 Implementation Management and Controls Started C 4 1 1951d 10/01/18 04/03/26 10/01/18 8:00 AM 04/03/26 4:59 PM 16.55% 17% Green $24,370.06 $147,220.37 $24,370.06 $147,220.37 17% $25,027.46 Ian McEwen PSL_Drill_Manager M&S - $3000/year: Supplies, Computer replacement, licenses, software upgrades, etc. 1.2.1.1 1 258 Implementation Management and Controls
260 1.2 1.2.1.2 Drill Management & Systems Engineering Started P 4 1 1973d 10/01/18 05/05/26 10/01/18 8:00 AM 05/05/26 4:59 PM 16.14% 45.00% Green $0.00 $0.00 $39,599.39 $245,396.23 16% Ian McEwen 1.2.1.2 1 259 Drill Management & Systems Engineering
261 1.2 1.2.1.2.1 2018-19 Drill Management & Systems Engineering Complete C 5 1 261d 10/01/18 09/30/19 10/01/18 8:00 AM 09/30/19 4:59 PM 100% 100% Gray Late start/funding $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson Includes: Review/Study Hole Drilling, Freeze-Back Rates, Algorythms 1.2.1.2.1 1 260 2018-19 Drill Management & Systems Engineering
262 1.2 1.2.1.2.2 2019-20 Drill Management & Systems Engineering Complete C 5 1 262d 10/01/19 09/30/20 10/01/19 8:00 AM 09/30/20 4:59 PM 260 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.2 1 261 2019-20 Drill Management & Systems Engineering
263 1.2 1.2.1.2.3 2020-21 Drill Management & Systems Engineering Complete C 5 1 261d 10/01/20 09/30/21 10/01/20 8:00 AM 09/30/21 4:59 PM 261 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.3 1 262 2020-21 Drill Management & Systems Engineering
264 1.2 1.2.1.2.4 2021-22 Drill Management & Systems Engineering Started P 5 1 260d 10/01/21 09/29/22 10/01/21 8:00 AM 09/29/22 4:59 PM 16% 41.00% Green $0.00 $0.00 $39,599.39 $245,396.23 16% Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.4 1 263 2021-22 Drill Management & Systems Engineering
265 1.2 1.2.1.2.4.1 2021-22 Systems Engineering Started P 6 260d 10/01/21 09/29/22 10/01/21 8:00 AM 09/29/22 4:59 PM 16% 41.00% Green $39,599.39 $245,396.23 $39,599.39 $245,396.23 16% $100,612.46 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.4.1 1 264 2021-22 Systems Engineering
266 1.2 1.2.1.2.4.1.1 P&ID and Instrumentation List Development Started C 7 1 250d 10/15/21 09/29/22 10/15/21 8:00 AM 09/29/22 4:59 PM 31% 42.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.4.1.1 1 265 P&ID and Instrumentation List Development
267 1.2 1.2.1.2.4.1.2 Parameters Documentation Compiled Started C 7 1 1 0 07/15/22 07/15/22 07/15/22 8:00 AM 07/15/22 8:00 AM 0% 32.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.4.1.2 1 266 Parameters Documentation Compiled
268 1.2 1.2.1.2.4.1.3 IV&T Closed out Started C 7 1 1 0 04/15/22 04/15/22 04/15/22 8:00 AM 04/15/22 8:00 AM 0% 50.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.4.1.3 1 267 IV&T Closed out
269 1.2 1.2.1.2.4.1.4 Drill Procedures Reviewed Started C 7 1 1 0 08/15/22 08/15/22 08/15/22 8:00 AM 08/15/22 8:00 AM 0% 16.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.4.1.4 1 268 Drill Procedures Reviewed
270 1.2 1.2.1.2.4.1.5 Process Control Narrative Development Started C 7 1 250d 10/01/21 09/15/22 10/01/21 8:00 AM 09/15/22 4:59 PM 35% 40.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.4.1.5 1 269 Process Control Narrative Development
271 1.2 1.2.1.2.5 2022-23 Drill Management & Systems Engineering Not Started P 5 1 261d 10/01/22 09/29/23 10/01/22 8:00 AM 09/29/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.5 1 270 2022-23 Drill Management & Systems Engineering
272 1.2 1.2.1.2.5.1 2022-23 Management & Systems Engineering Not Started C 6 261d 10/01/22 09/29/23 10/01/22 8:00 AM 09/29/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.5.1 1 271 2022-23 Management & Systems Engineering
273 1.2 1.2.1.2.5.2 Drill Procedure Review Not Started C 6 1 120d 04/15/23 09/28/23 04/15/23 8:00 AM 09/28/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.5.2 1 272 Drill Procedure Review
274 1.2 1.2.1.2.5.3 Drill Hole Modeling Not Started C 6 1 21d 06/15/23 07/13/23 06/15/23 8:00 AM 07/13/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.5.3 1 273 Drill Hole Modeling
275 1.2 1.2.1.2.5.4 Drill Documentation Support Not Started C 6 1 120d 02/15/23 08/01/23 02/15/23 8:00 AM 08/01/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.5.4 1 274 Drill Documentation Support
276 1.2 1.2.1.2.6 2023-24 Drill Management & Systems Engineering Not Started P 5 1 262d 10/01/23 10/03/24 10/01/23 8:00 AM 10/03/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.6 1 275 2023-24 Drill Management & Systems Engineering
277 1.2 1.2.1.2.6.1 2023-24 Management & Systems Engineering Not Started C 6 262d 10/01/23 10/03/24 10/01/23 8:00 AM 10/03/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.6.1 1 276 2023-24 Management & Systems Engineering
278 1.2 1.2.1.2.6.2 PY6 Season Debrief Not Started C 6 1 1d 03/15/24 03/15/24 03/15/24 8:00 AM 03/15/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.6.2 1 277 PY6 Season Debrief
279 1.2 1.2.1.2.6.3 Drill Procedure Review Not Started C 6 1 120d 04/15/24 09/27/24 04/15/24 8:00 AM 09/27/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.6.3 1 278 Drill Procedure Review
280 1.2 1.2.1.2.6.4 PY6 Drill Advisory Panel Not Started C 6 1 2d 05/01/24 05/02/24 05/01/24 8:00 AM 05/02/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.6.4 1 279 PY6 Drill Advisory Panel
281 1.2 1.2.1.2.6.5 Drill Hole Modeling Not Started C 6 1 21d 06/15/24 07/12/24 06/15/24 8:00 AM 07/12/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.6.5 1 280 Drill Hole Modeling
282 1.2 1.2.1.2.6.6 Drill Documentation Support Not Started C 6 1 120d 02/15/24 07/31/24 02/15/24 8:00 AM 07/31/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.6.6 1 281 Drill Documentation Support
283 1.2 1.2.1.2.7 2024-25 Drill Management & Systems Engineering Not Started P 5 1 261d 10/01/24 10/03/25 10/01/24 8:00 AM 10/03/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.7 1 282 2024-25 Drill Management & Systems Engineering
284 1.2 1.2.1.2.7.1 2024-25 Management & Systems Engineering Not Started C 6 261d 10/01/24 10/03/25 10/01/24 8:00 AM 10/03/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.7.1 1 283 2024-25 Management & Systems Engineering
285 1.2 1.2.1.2.7.2 PY7 Season Debrief Not Started C 6 1 1d 03/15/25 03/15/25 03/15/25 8:00 AM 03/15/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.7.2 1 284 PY7 Season Debrief
286 1.2 1.2.1.2.7.3 Drill Procedure Review Not Started C 6 1 100d 03/15/25 07/31/25 03/15/25 8:00 AM 07/31/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.7.3 1 285 Drill Procedure Review
287 1.2 1.2.1.2.7.4 PY7 Drill Advisory Panel Not Started C 6 1 2d 05/01/25 05/02/25 05/01/25 8:00 AM 05/02/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.7.4 1 286 PY7 Drill Advisory Panel
288 1.2 1.2.1.2.7.5 Drill Hole Modeling Not Started C 6 1 21d 06/15/25 07/11/25 06/15/25 8:00 AM 07/11/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.7.5 1 287 Drill Hole Modeling
289 1.2 1.2.1.2.7.6 Drill Readiness Review (PSL) Not Started C 6 1 1 1 1 2d 07/01/25 07/02/25 07/01/25 8:00 AM 07/02/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.7.6 1 288 Drill Readiness Review (PSL)
290 1.2 1.2.1.2.7.7 Drill Documentation Support Not Started C 6 1 120d 02/15/25 07/31/25 02/15/25 8:00 AM 07/31/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.7.7 1 289 Drill Documentation Support
291 1.2 1.2.1.2.8 2025-26 Drill Management & Systems Engineering Not Started P 5 1 153d 09/30/25 05/05/26 09/30/25 8:00 AM 05/05/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.8 1 290 2025-26 Drill Management & Systems Engineering
292 1.2 1.2.1.2.8.1 2025-26 Management & Systems Engineering Not Started C 6 1 153d 09/30/25 05/05/26 09/30/25 8:00 AM 05/05/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.2.8.1 1 291 2025-26 Management & Systems Engineering
293 1.2 1.2.1.2.8.2 PY8 Season Debrief Not Started C 6 1 1d 03/15/26 03/15/26 03/15/26 8:00 AM 03/15/26 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.8.2 1 292 PY8 Season Debrief
294 1.2 1.2.1.2.8.3 Final Drill Completion Report Not Started C 6 1 1 1 0 04/30/26 04/30/26 04/30/26 8:00 AM 04/30/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.2.8.3 1 293 Final Drill Completion Report
295 1.2 1.2.1.3 Installation Management & Systems Engineering Should have Started P 4 1 1189d 10/01/21 05/05/26 10/01/21 8:00 AM 05/05/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $5,000.00 0% Ian McEwen 1.2.1.3 1 294 Installation Management & Systems Engineering
296 1.2 1.2.1.3.1 2021-22 Management & Systems Engineering Should have Started P 5 261d 10/01/21 09/30/22 10/01/21 8:00 AM 09/30/22 4:59 PM 34% 0% Red $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.3.1 1 295 2021-22 Management & Systems Engineering
297 1.2 1.2.1.3.1.1 String Management and Controls (2021-2022) Should have Started C 6 261d 10/01/21 09/30/22 10/01/21 8:00 AM 09/30/22 4:59 PM 34% 0% Red Tosi - 15% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Tosi 1.2.1.3.1.1 1 296 String Management and Controls (2021-2022)
298 1.2 1.2.1.3.1.2 Installation Engineering (2021-2022) Should have Started C 6 261d 10/01/21 09/30/22 10/01/21 8:00 AM 09/30/22 4:59 PM 34% 0% Red Tosi - 25% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Tosi 1.2.1.3.1.2 1 297 Installation Engineering (2021-2022)
299 1.2 1.2.1.3.1.3 Installation Engineering Support (2021-2022) Should have Started C 6 261d 10/01/21 09/30/22 10/01/21 8:00 AM 09/30/22 4:59 PM 34% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.3.1.3 1 298 Installation Engineering Support (2021-2022)
300 1.2 1.2.1.3.2 2022-23 Management & Systems Engineering Not Started P 5 261d 10/01/22 09/29/23 10/01/22 8:00 AM 09/29/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.3.2 1 299 2022-23 Management & Systems Engineering
301 1.2 1.2.1.3.2.1 String Management and Controls (2022-2023) Not Started C 6 261d 10/01/22 09/29/23 10/01/22 8:00 AM 09/29/23 4:59 PM 0% 0% Green Tosi - 15% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Tosi 1.2.1.3.2.1 1 300 String Management and Controls (2022-2023)
302 1.2 1.2.1.3.2.2 Installation Engineering (2022-2023) Not Started C 6 261d 10/01/22 09/29/23 10/01/22 8:00 AM 09/29/23 4:59 PM 0% 0% Green Tosi - 25% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Tosi 1.2.1.3.2.2 1 301 Installation Engineering (2022-2023)
303 1.2 1.2.1.3.2.3 Installation Engineering Support (2022-2023) Not Started C 6 261d 10/01/22 09/29/23 10/01/22 8:00 AM 09/29/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.3.2.3 1 302 Installation Engineering Support (2022-2023)
304 1.2 1.2.1.3.3 2023-24 Management & Systems Engineering Not Started P 5 262d 10/01/23 10/03/24 10/01/23 8:00 AM 10/03/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.3.3 1 303 2023-24 Management & Systems Engineering
305 1.2 1.2.1.3.3.1 String Management and Controls (2023-2024) Not Started C 6 262d 10/01/23 10/03/24 10/01/23 8:00 AM 10/03/24 4:59 PM 0% 0% Green Tosi - 10% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Tosi 1.2.1.3.3.1 1 304 String Management and Controls (2023-2024)
306 1.2 1.2.1.3.3.2 Installation Engineering (2023-2024) Not Started C 6 262d 10/01/23 10/03/24 10/01/23 8:00 AM 10/03/24 4:59 PM 0% 0% Green Tosi - 30% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Tosi 1.2.1.3.3.2 1 305 Installation Engineering (2023-2024)
307 1.2 1.2.1.3.3.3 Installation Engineering Support (2023-2024) Not Started C 6 262d 10/01/23 10/03/24 10/01/23 8:00 AM 10/03/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.3.3.3 1 306 Installation Engineering Support (2023-2024)
308 1.2 1.2.1.3.4 2024-25 Management & Systems Engineering Not Started P 5 261d 10/01/24 10/03/25 10/01/24 8:00 AM 10/03/25 4:59 PM 0% 0% Green $0.00 $5,000.00 $0.00 $5,000.00 0% $0.00 Ian McEwen 1.2.1.3.4 1 307 2024-25 Management & Systems Engineering
309 1.2 1.2.1.3.4.1 String Management and Controls (2024-2025) Not Started C 6 261d 10/01/24 10/03/25 10/01/24 8:00 AM 10/03/25 4:59 PM 0% 0% Green Tosi - 5% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Tosi 1.2.1.3.4.1 1 308 String Management and Controls (2024-2025)
310 1.2 1.2.1.3.4.2 Installation Engineering (2024-2025) Not Started C 6 261d 10/01/24 10/03/25 10/01/24 8:00 AM 10/03/25 4:59 PM 0% 0% Green Tosi - 25% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Tosi 1.2.1.3.4.2 1 309 Installation Engineering (2024-2025)
311 1.2 1.2.1.3.4.3 Installation Engineering Support (2024-2025) Not Started C 6 261d 10/01/24 10/03/25 10/01/24 8:00 AM 10/03/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.3.4.3 1 310 Installation Engineering Support (2024-2025)
312 1.2 1.2.1.3.5 2025-26 Management & Systems Engineering Not Started P 5 152d 10/01/25 05/05/26 10/01/25 8:00 AM 05/05/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.3.5 1 311 2025-26 Management & Systems Engineering
313 1.2 1.2.1.3.5.1 String Management and Controls (2025-2026) Not Started C 6 152d 10/01/25 05/05/26 10/01/25 8:00 AM 05/05/26 4:59 PM 0% 0% Green Tosi - 5% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Tosi 1.2.1.3.5.1 1 312 String Management and Controls (2025-2026)
314 1.2 1.2.1.3.5.2 Installation Engineering (2025-2026) Not Started C 6 152d 10/01/25 05/05/26 10/01/25 8:00 AM 05/05/26 4:59 PM 0% 0% Green Tosi - 20% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Tosi 1.2.1.3.5.2 1 313 Installation Engineering (2025-2026)
315 1.2 1.2.1.3.5.3 Installation Engineering Support (2025-2026) Not Started C 6 152d 10/01/25 05/05/26 10/01/25 8:00 AM 05/05/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Jeff Cherwinka, Terry Benson 1.2.1.3.5.3 1 314 Installation Engineering Support (2025-2026)
316 1.2 1.2.1.3.5.4 Final String Installation Completion Report Not Started C 6 1 1 1 0 04/30/26 04/30/26 04/30/26 8:00 AM 04/30/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.3.5.4 1 315 Final String Installation Completion Report
317 1.2 1.2.1.4 Implementation Quality and Safety Started P 4 1 1955d 10/01/18 04/09/26 10/01/18 8:00 AM 04/09/26 4:59 PM 41.67% 40.0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.4 1 316 Implementation Quality and Safety
318 1.2 1.2.1.4.1 2018-19 Quality & Safety Complete C 5 261d 10/01/18 09/30/19 10/01/18 8:00 AM 09/30/19 4:59 PM 100% 100% Gray This should have a target PC of 75% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Safety_Mgr M&S within Q&S includes:
- On-Ice team equipment (helmits, harnesses, fall protection, FA kits, etc)
- Off-Ice: Test bed (same)
- Training: In-house and paid courses (Safe Start or similar, etc.)
· SafeStart Certified Trainer Certificate: $2,000
· Safety Equipment for Test Bed at PSL: Hard Hats, First Aid Kit, Spill Kits, Fall Protection Harnesses: $500
· Safety Equipment for Drill Camp: 12 Climber Helmets,2 First Aid Kits, Spill Kits, 4 Fire Extinguishers, 3 Fall Protection Harnesses, Work Gloves, Hand Warmers: $2,000
· Driller/Scientist Safety Training: $500
1.2.1.4.1 1 317 2018-19 Quality & Safety
319 1.2 1.2.1.4.2 2019-20 Quality & Safety Complete C 5 262d 10/01/19 09/30/20 10/01/19 8:00 AM 09/30/20 4:59 PM 317 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Safety_Mgr M&S within Q&S includes:
- On-Ice team equipment (helmits, harnesses, fall protection, FA kits, etc)
- Off-Ice: Test bed (same)
- Training: In-house and paid courses (Safe Start or similar, etc.)
· SafeTrack Certified Trainer Certificate: $2,000
· Safety Equipment for Test Bed at PSL: LOTO, AED, Safety Cabinet: $1,700
· Safety Equipment for Drill Camp: Hand/Foot Warmers, Work Gloves, Safety Glasses: $1,000
· 4 more Fire extinguishers for Drill Camp: $800
· Driller/Scientist Safety Training: $500
1.2.1.4.2 1 318 2019-20 Quality & Safety
320 1.2 1.2.1.4.3 2020-21 Quality & Safety Complete C 5 261d 10/01/20 09/30/21 10/01/20 8:00 AM 09/30/21 4:59 PM 318 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Safety_Mgr M&S within Q&S includes:
- On-Ice team equipment (helmits, harnesses, fall protection, FA kits, etc)
- Off-Ice: Test bed (same)
- Training: In-house and paid courses (Safe Start or similar, etc.)
· Safety Equipment for Test Bed at PSL: LOTO refills, First Aid Kit refills. GFCI replacements: $1,000
· Driller/Scientist Safety Training: $500
· 4 more Fire extinguishers for Drill Camp: $800
· Safety Equipment for Drill Camp: 12 Climber Helmets,2 First Aid Kits, Hand/Foot Warmers, GFCI replacements, Work Gloves, Spill Kits: $2,000
· CO/O2 Monitors, 2 ea.: $2,700
1.2.1.4.3 1 319 2020-21 Quality & Safety
321 1.2 1.2.1.4.4 2021-22 Quality & Safety Should have Started C 5 261d 10/01/21 09/30/22 10/01/21 8:00 AM 09/30/22 4:59 PM 319 34% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Safety_Mgr M&S within Q&S includes:
- On-Ice team equipment (helmits, harnesses, fall protection, FA kits, etc)
- Off-Ice: Test bed (same)
- Training: In-house and paid courses (Safe Start or similar, etc.)
· (8) Balance of Fire Extinguishers for Drill Camp: $1,600
· Driller/Scientist Safety Training( Expanded): $3,000
· Safety Equipment for Drill Camp: 12 Climber Helmets,2 First Aid Kits, Hand/Foot Warmers, Work Gloves, Spill Kits: $2,000
· Safety Equipment for Test Bed at PSL: LOTO refills, First Aid Kit refills. GFCI replacements: $1,000
· CO/O2 Monitors, 1 ea.: $1,400
1.2.1.4.4 1 320 2021-22 Quality & Safety
322 1.2 1.2.1.4.5 2022-23 Quality & Safety Not Started C 5 261d 10/03/22 10/02/23 10/03/22 8:00 AM 10/02/23 4:59 PM 320 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Safety_Mgr M&S within Q&S includes:
- On-Ice team equipment (helmits, harnesses, fall protection, FA kits, etc)
- Off-Ice: Test bed (same)
- Training: In-house and paid courses (Safe Start or similar, etc.)
· Driller/Scientist Safety Training( Expanded): $3,000
1.2.1.4.5 1 321 2022-23 Quality & Safety
323 1.2 1.2.1.4.6 2023-24 Quality & Safety Not Started C 5 261d 10/03/23 10/04/24 10/03/23 8:00 AM 10/04/24 4:59 PM 321 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Safety_Mgr M&S within Q&S includes:
- On-Ice team equipment (helmits, harnesses, fall protection, FA kits, etc)
- Off-Ice: Test bed (same)
- Training: In-house and paid courses (Safe Start or similar, etc.)
· Driller/Scientist Safety Training( Expanded): $3,000
1.2.1.4.6 1 322 2023-24 Quality & Safety
324 1.2 1.2.1.4.7 2024-25 Quality & Safety Not Started C 5 260d 10/07/24 10/08/25 10/07/24 8:00 AM 10/08/25 4:59 PM 322 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Safety_Mgr M&S within Q&S includes:
- On-Ice team equipment (helmits, harnesses, fall protection, FA kits, etc)
- Off-Ice: Test bed (same)
- Training: In-house and paid courses (Safe Start or similar, etc.)
· Driller/Scientist Safety Training( Expanded): $3,000
1.2.1.4.7 1 323 2024-25 Quality & Safety
325 1.2 1.2.1.4.8 2025-26 Quality & Safety Not Started C 5 130d 10/07/25 04/09/26 10/07/25 8:00 AM 04/09/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Safety_Mgr M&S within Q&S includes:
- On-Ice team equipment (helmits, harnesses, fall protection, FA kits, etc)
- Off-Ice: Test bed (same)
- Training: In-house and paid courses (Safe Start or similar, etc.)
· Driller/Scientist Safety Training( Expanded): $3,000
1.2.1.4.8 1 324 2025-26 Quality & Safety
326 1.2 1.2.1.5 Implementation Travel Started P 4 1 1827d 10/01/18 10/08/25 10/01/18 8:00 AM 10/08/25 4:59 PM 47.62% 47.00% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Travel for Vendor Visits, ASC Meetings, Collaboration Mtgs

3 - Manager - Tom Hutchings (1-Denver ASC Support Mtg, 2-Collaboration)
3 - Systems Engineer - Terry Benson (1-Microturbines, 1-ASC Support Mtg, 1-Collaboration)
3 - Systems Engineer - Jeff Cherwinka (1-Microturbines, 1-ASC Support Mtg, 1-Collaboration)
3 - Safety Manager - Mike Zernick (1-Denver ASC Support Mtg, 2-Collaboration)

$1,200 per trip
1.2.1.5 1 325 Implementation Travel
327 1.2 1.2.1.5.1 2018-19 Travel Complete C 5 261d 10/01/18 09/30/19 10/01/18 8:00 AM 09/30/19 4:59 PM 100% 100% Gray Travel planned for later in the PY, will hit soon $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 5 - Drill Manager, Terry Benson, Jeff Cherwinka, Engineer, Quality Manager

Each across 5-year project:
3 - Domestic Trips @ $2,200 x 5 x 3= $33,000
1 - International Trips @ $4,000 x 5 x 1 = $20,000
-------------------------------------
$53,000 ($10,600/year)

Collaboration meetings, Reviews, ASC Support Meetings, Vendor Meetings
1.2.1.5.1 1 326 2018-19 Travel
328 1.2 1.2.1.5.2 2019-20 Travel Complete C 5 262d 10/01/19 09/30/20 10/01/19 8:00 AM 09/30/20 4:59 PM 326 100% 100% Gray Limited travel (COVID) $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 5 - Drill Manager, Terry Benson, Jeff Cherwinka, Engineer, Quality Manager

Each across 5-year project:
4 - Domestic Trips @ $2,200 = $44,000
2 - International Trips @ $4,000 = $40,000
-------------------------------------
$88,000 ($16,800/year)

Collaboration meetings, Reviews, ASC Support Meetings, Vendor Meetings
1.2.1.5.2 1 327 2019-20 Travel
329 1.2 1.2.1.5.3 2020-21 Travel Complete C 5 261d 10/01/20 09/30/21 10/01/20 8:00 AM 09/30/21 4:59 PM 327 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 5 - Drill Manager, Terry Benson, Jeff Cherwinka, Engineer, Quality Manager

Each across 5-year project:
4 - Domestic Trips @ $2,200 = $44,000
2 - International Trips @ $4,000 = $40,000
-------------------------------------
$88,000 ($16,800/year)

Collaboration meetings, Reviews, ASC Support Meetings, Vendor Meetings
1.2.1.5.3 1 328 2020-21 Travel
330 1.2 1.2.1.5.4 2021-22 Travel (non-deployment) Started C 5 261d 10/01/21 09/30/22 10/01/21 8:00 AM 09/30/22 4:59 PM 328 34% 8.00% Red $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 5 - Drill Manager, Terry Benson, Jeff Cherwinka, Engineer, Quality Manager

Each across 5-year project:
4 - Domestic Trips @ $2,200 = $44,000
2 - International Trips @ $4,000 = $40,000
-------------------------------------
$88,000 ($16,800/year)

Collaboration meetings, Reviews, ASC Support Meetings, Vendor Meetings
1.2.1.5.4 1 329 2021-22 Travel (non-deployment)
331 1.2 1.2.1.5.5 2022-23 Travel (non-deployment) Not Started C 5 260d 10/03/22 09/29/23 10/03/22 8:00 AM 09/29/23 4:59 PM 329 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 5 - Drill Manager, Terry Benson, Jeff Cherwinka, Engineer, Quality Manager

Each across 5-year project:
4 - Domestic Trips @ $2,200 = $44,000
2 - International Trips @ $4,000 = $40,000
-------------------------------------
$88,000 ($16,800/year)

Collaboration meetings, Reviews, ASC Support Meetings, Vendor Meetings
1.2.1.5.5 1 330 2022-23 Travel (non-deployment)
332 1.2 1.2.1.5.6 2023-24 Travel (non-deployment) Not Started C 5 195d 01/05/24 10/03/24 01/05/24 8:00 AM 10/03/24 4:59 PM 330FS +66d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 5 - Drill Manager, Terry Benson, Jeff Cherwinka, Engineer, Quality Manager

Each across 5-year project:
4 - Domestic Trips @ $2,200 = $44,000
2 - International Trips @ $4,000 = $40,000
-------------------------------------
$88,000 ($16,800/year)

Collaboration meetings, Reviews, ASC Support Meetings, Vendor Meetings
1.2.1.5.6 1 331 2023-24 Travel (non-deployment)
333 1.2 1.2.1.5.7 2024-25 Travel (non-deployment) Not Started C 5 195d 01/09/25 10/08/25 01/09/25 8:00 AM 10/08/25 4:59 PM 331FS +66d 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 5 - Drill Manager, Terry Benson, Jeff Cherwinka, Engineer, Quality Manager

Each across 5-year project:
4 - Domestic Trips @ $2,200 = $44,000
2 - International Trips @ $4,000 = $40,000
-------------------------------------
$88,000 ($16,800/year)

Collaboration meetings, Reviews, ASC Support Meetings, Vendor Meetings
1.2.1.5.7 1 332 2024-25 Travel (non-deployment)
334 1.2 1.2.1.6 Transportation and Logistics Started P 4 1 1229d 11/06/20 08/01/25 11/06/20 8:00 AM 08/01/25 8:00 AM 30.30% 18.00% Yellow $4,799.93 $15,839.76 $4,799.93 $15,839.76 30% $2,851.16 Ian McEwen 1.2.1.6 1 333 Transportation and Logistics
335 1.2 1.2.1.6.1 Shipment Milestones Not Started P 5 724d 10/15/22 08/01/25 10/15/22 8:00 AM 08/01/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.1 1 334 Shipment Milestones
336 1.2 1.2.1.6.1.1 FY23 USAP Vessel Shipment Departs PSL Not Started C 6 0 10/15/22 10/15/22 10/15/22 8:00 AM 10/15/22 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.1.1 1 335 FY23 USAP Vessel Shipment Departs PSL
337 1.2 1.2.1.6.1.2 FY24 ComSur Shipment Departs PSL Not Started C 6 0 08/01/23 08/01/23 08/01/23 8:00 AM 08/01/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.1.2 1 336 FY24 ComSur Shipment Departs PSL
338 1.2 1.2.1.6.1.2 FY24 USAP Vessel Shipment Departs PSL Not Started C 6 0 10/15/23 10/15/23 10/15/23 8:00 AM 10/15/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.1.2 1 337 FY24 USAP Vessel Shipment Departs PSL
339 1.2 1.2.1.6.1.2 FY25 ComSur Shipment Departs PSL Not Started C 6 0 08/01/24 08/01/24 08/01/24 8:00 AM 08/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.1.2 1 338 FY25 ComSur Shipment Departs PSL
340 1.2 1.2.1.6.1.3 FY25 USAP Vessel Shipment Departs PSL Not Started C 6 0 10/15/24 10/15/24 10/15/24 8:00 AM 10/15/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.1.3 1 339 FY25 USAP Vessel Shipment Departs PSL
341 1.2 1.2.1.6.1.4 FY26 ComSur Shipment Departs PSL Not Started C 6 0 08/01/25 08/01/25 08/01/25 8:00 AM 08/01/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.1.4 1 340 FY26 ComSur Shipment Departs PSL
342 1.2 1.2.1.6.2 Drill Shipment Prep Started P 5 1223d 11/06/20 07/23/25 11/06/20 8:00 AM 07/23/25 4:59 PM 19% 61.00% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2 1 341 Drill Shipment Prep
343 1.2 1.2.1.6.2.1 Crate Shop Parts - Hose Crimper (Vessel) Complete C 6 15d 10/17/21 11/04/21 10/17/21 8:00 AM 11/04/21 4:59 PM 0.98064516 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.1 1 342 Crate Shop Parts - Hose Crimper (Vessel)
344 1.2 1.2.1.6.2.2 Crate GEN-2, 3, PDM - Ship Components, Repair Parts (Vessel) Complete C 6 15d 01/07/21 01/27/21 01/07/21 8:00 AM 01/27/21 4:59 PM 869SS +70d 98% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.2 1 343 Crate GEN-2, 3, PDM - Ship Components, Repair Parts (Vessel)
345 1.2 1.2.1.6.2.3 Prepare: Cable Reels Main and RWCR (Vessel) Complete C 6 21d 10/15/21 11/12/21 10/15/21 8:00 AM 11/12/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.3 1 344 Prepare: Cable Reels Main and RWCR (Vessel)
346 1.2 1.2.1.6.2.4 Crate WT Repair Parts, Replacements (Vessel) Complete C 6 15d 09/07/22 09/27/22 09/07/22 8:00 AM 09/27/22 4:59 PM 897FS +70d 0% 100% Gray delayed until 20/21 season shipment $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

2 - crates
1.2.1.6.2.4 1 345 Crate WT Repair Parts, Replacements (Vessel)
347 1.2 1.2.1.6.2.5 Prepare GEN-2, 3, PDM - Skis (2021-22) (Vessel) Complete C 6 24d 12/06/20 01/06/21 12/06/20 8:00 AM 01/06/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.5 1 346 Prepare GEN-2, 3, PDM - Skis (2021-22) (Vessel)
348 1.2 1.2.1.6.2.6 Crate Generator Hoods (2021-22) (Vessel) Complete C 6 7d 11/06/20 11/16/20 11/06/20 8:00 AM 11/16/20 4:59 PM 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

2 - crates
1.2.1.6.2.6 1 347 Crate Generator Hoods (2021-22) (Vessel)
349 1.2 1.2.1.6.2.7 Prepare Surface Hose to PTH (2021-22) Outdoor Storage MCM (Vessel) Complete C 6 7d 11/06/20 11/16/20 11/06/20 8:00 AM 11/16/20 4:59 PM 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.7 1 348 Prepare Surface Hose to PTH (2021-22) Outdoor Storage MCM (Vessel)
350 1.2 1.2.1.6.2.8 Crate MHP/PHS Replacements & Spares (FY23 Shipment) (Container C - Vessel) Started C 6 6d 05/31/22 06/07/22 05/31/22 8:00 AM 06/07/22 4:59 PM 395 0% 80.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.8 1 349 Crate MHP/PHS Replacements & Spares (FY23 Shipment) (Container C - Vessel)
351 1.2 1.2.1.6.2.9 Crate Fuel Systems & Tower Components (Container C - Vessel) Not Started C 6 7d 05/02/22 05/10/22 05/02/22 8:00 AM 05/10/22 4:59 PM 414 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.9 1 350 Crate Fuel Systems & Tower Components (Container C - Vessel)
352 1.2 1.2.1.6.2.10 Crate TOS Components & Spares (Container C - Vessel) Not Started C 6 4d 06/29/22 07/04/22 06/29/22 8:00 AM 07/04/22 4:59 PM 424 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

2 - crates
1.2.1.6.2.10 1 351 Crate TOS Components & Spares (Container C - Vessel)
353 1.2 1.2.1.6.2.11 Crate Control Systems Components Shipment 1 - DNF (Vessel) Started C 6 5d 10/03/22 10/07/22 10/03/22 8:00 AM 10/07/22 4:59 PM 522, 525, 534, 631, 639 0% 96.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.11 1 352 Crate Control Systems Components Shipment 1 - DNF (Vessel)
354 1.2 1.2.1.6.2.12 Crate ARA Drill Subsystem Parts - Crate 1 (Container C - Vessel) Started C 6 7d 09/15/22 09/23/22 09/15/22 8:00 AM 09/23/22 4:59 PM 955 0 25.00% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

1- crate
1.2.1.6.2.12 1 353 Crate ARA Drill Subsystem Parts - Crate 1 (Container C - Vessel)
355 1.2 1.2.1.6.2.13 Crate ARA Drill Subsystem Parts DNF - Crate 2 (Vessel) Started C 6 7d 09/15/22 09/23/22 09/15/22 8:00 AM 09/23/22 4:59 PM 955 0% 25.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

1- crate
1.2.1.6.2.13 1 354 Crate ARA Drill Subsystem Parts DNF - Crate 2 (Vessel)
356 1.2 1.2.1.6.2.14 Crate Spare Main Drill & Combo Cables (Container C - Vessel) Not Started C 6 6d 05/01/22 05/06/22 05/01/22 8:00 AM 05/06/22 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.14 1 355 Crate Spare Main Drill & Combo Cables (Container C - Vessel)
357 1.2 1.2.1.6.2.15 Prepare Bull Wheel for Shipment (Container C - Vessel) Not Started C 6 2d 07/01/22 07/04/22 07/01/22 8:00 AM 07/04/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.15 1 356 Prepare Bull Wheel for Shipment (Container C - Vessel)
358 1.2 1.2.1.6.2.16 Crate Shop Parts - Consumables & Spares, etc. (Container C - Vessel) Started C 6 5d 09/17/22 09/22/22 09/17/22 8:00 AM 09/22/22 4:59 PM 0% 25.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.16 1 357 Crate Shop Parts - Consumables & Spares, etc. (Container C - Vessel)
359 1.2 1.2.1.6.2.17 Crate Condensate Management Components (Container C - Vessel) Started C 6 4d 05/30/22 06/02/22 05/30/22 8:00 AM 06/02/22 4:59 PM 912 0% 80.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

1 - crate
1.2.1.6.2.17 1 358 Crate Condensate Management Components (Container C - Vessel)
360 1.2 1.2.1.6.2.18 Crate Pump Repair/Replace Components (Container C - Vessel) Started C 6 2d 04/07/22 04/08/22 04/07/22 8:00 AM 04/08/22 4:59 PM 902 0% 80.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

1 - crate
1.2.1.6.2.18 1 359 Crate Pump Repair/Replace Components (Container C - Vessel)
361 1.2 1.2.1.6.2.19 Crate Hose Reel Heating System (Container C - Vessel) Not Started C 6 5d 09/07/22 09/13/22 09/07/22 8:00 AM 09/13/22 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.19 1 360 Crate Hose Reel Heating System (Container C - Vessel)
362 1.2 1.2.1.6.2.20 Load Container C (Main/Combo Cables, Bull Wheel, Hose Heating Components, ARA Drill Components - Crate 2) (Vessel) Not Started C 6 6d 10/01/22 10/07/22 10/01/22 8:00 AM 10/07/22 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.20 1 361 Load Container C (Main/Combo Cables, Bull Wheel, Hose Heating Components, ARA Drill Components - Crate 2) (Vessel)
363 1.2 1.2.1.6.2.21 Crate Drill Heads, Spare Parts to PTH (Vessel) Store in ICL - DNF Not Started C 6 6d 09/23/22 09/30/22 09/23/22 8:00 AM 09/30/22 4:59 PM 445 0% 0% Green Confirm McMurdo/Pole multi-year DNF storage space $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.21 1 362 Crate Drill Heads, Spare Parts to PTH (Vessel) Store in ICL - DNF
364 1.2 1.2.1.6.2.22 Crate Control Systems Components Shipment 2 - DNF (Comsur) Started C 6 7d 06/20/23 06/28/23 06/20/23 8:00 AM 06/28/23 4:59 PM 0 96.00% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.22 1 363 Crate Control Systems Components Shipment 2 - DNF (Comsur)
365 1.2 1.2.1.6.2.30 Crate Control Systems Components Shipment 3 - DNF (Comsur) Started C 6 7d 07/15/25 07/23/25 07/15/25 8:00 AM 07/23/25 4:59 PM 0 96.00% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.30 1 364 Crate Control Systems Components Shipment 3 - DNF (Comsur)
366 1.2 1.2.1.6.2.31 Load FS3 Resupply Container (Comsur) Not Started C 6 7d 07/15/25 07/23/25 07/15/25 8:00 AM 07/23/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.31 1 365 Load FS3 Resupply Container (Comsur)
367 1.2 1.2.1.6.2.28 Load FS2 Resupply Container (FS2 Comsur) Not Started C 6 7d 07/15/24 07/23/24 07/15/24 8:00 AM 07/23/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.28 1 366 Load FS2 Resupply Container (FS2 Comsur)
368 1.2 1.2.1.6.2.29 Crate Repair/Replacement Components Resupply (FS2 Resupply Container - Comsur) Not Started C 6 6d 07/03/24 07/10/24 07/03/24 8:00 AM 07/10/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

1 - crate
1.2.1.6.2.29 1 367 Crate Repair/Replacement Components Resupply (FS2 Resupply Container - Comsur)
369 1.2 1.2.1.6.2.24 Crate MDS Internal Hoses & Spares Resupply (FS2 Resupply Container - Comsur) Started C 6 15d 06/13/24 07/03/24 06/13/24 8:00 AM 07/03/24 4:59 PM 0% 50.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

2 - crates
1.2.1.6.2.24 1 368 Crate MDS Internal Hoses & Spares Resupply (FS2 Resupply Container - Comsur)
370 1.2 1.2.1.6.2.25 Crate Drill Filtration Resupply (FS2 Resupply Container - Comsur) Started C 6 7d 06/15/24 06/24/24 06/15/24 8:00 AM 06/24/24 4:59 PM 0% 80.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.25 1 369 Crate Drill Filtration Resupply (FS2 Resupply Container - Comsur)
371 1.2 1.2.1.6.2.26 Crate FS2 SES Interconnect Resupply (FS2 Resupply Container - Comsur) Not Started C 6 10d 06/15/24 06/27/24 06/15/24 8:00 AM 06/27/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

2 - crates
1.2.1.6.2.26 1 370 Crate FS2 SES Interconnect Resupply (FS2 Resupply Container - Comsur)
372 1.2 1.2.1.6.2.27 Crate MHP/PHS Replacements & Spares (FS2 Resupply Container - Comsur) Started C 6 8d 05/13/24 05/22/24 05/13/24 8:00 AM 05/22/24 4:59 PM 407 0% 50.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.27 1 371 Crate MHP/PHS Replacements & Spares (FS2 Resupply Container - Comsur)
373 1.2 1.2.1.6.2.23 Crate Elect. Distribution System Components (ComSur) Not Started C 6 3d 07/28/23 08/01/23 07/28/23 8:00 AM 08/01/23 4:59 PM 649 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.2.23 1 372 Crate Elect. Distribution System Components (ComSur)
374 1.2 1.2.1.6.3 Drill Shipping Not Started P 5 724d 10/15/22 08/01/25 10/15/22 8:00 AM 08/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.3 1 373 Drill Shipping
375 1.2 1.2.1.6.3.1 FS0 - Ship Control Systems Components Shipment 1, ARA System DNF, Drill Heads, & Container C (Vessel) Started C 6 1 0 10/15/22 10/15/22 10/15/22 8:00 AM 10/15/22 8:00 AM 352, 354, 362, 361, 335SS 0 96.00% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.3.1 1 374 FS0 - Ship Control Systems Components Shipment 1, ARA System DNF, Drill Heads, & Container C (Vessel)
376 1.2 1.2.1.6.3.2 FS1 - Ship Control Systems Components Shipment 2 - DNF (Comsur) Started C 6 1 0 08/01/23 08/01/23 08/01/23 4:59 PM 08/01/23 4:59 PM 372, 336 0 96.00% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.3.2 1 375 FS1 - Ship Control Systems Components Shipment 2 - DNF (Comsur)
377 1.2 1.2.1.6.3.3 FS2 - Ship Control Systems Components Shipment 3, Refit Resupply Container (Comsur) Not Started C 6 1 0 08/01/24 08/01/24 08/01/24 8:00 AM 08/01/24 8:00 AM 650, 338 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.3.3 1 376 FS2 - Ship Control Systems Components Shipment 3, Refit Resupply Container (Comsur)
378 1.2 1.2.1.6.3.4 FS3 - Ship Resupply Container (Comsur) Not Started C 6 1 0 08/01/25 08/01/25 08/01/25 8:00 AM 08/01/25 8:00 AM 651, 340 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.1.6.3.4 1 377 FS3 - Ship Resupply Container (Comsur)
379 1.2 1.2.1.6.4 Installation Shipment Prep Not Started P 5 1 733d 09/07/22 07/07/25 09/07/22 8:00 AM 07/07/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.4 1 378 Installation Shipment Prep
380 1.2 1.2.1.6.4.1 Crate Sensor Handling Structure Not Started C 6 1 18d 09/07/22 09/30/22 09/07/22 8:00 AM 09/30/22 4:59 PM 1899 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.4.1 1 379 Crate Sensor Handling Structure
381 1.2 1.2.1.6.4.2 Crate Installation Kits Not Started C 6 1 14d 06/21/23 07/10/23 06/21/23 8:00 AM 07/10/23 4:59 PM 1916 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.4.2 1 380 Crate Installation Kits
382 1.2 1.2.1.6.4.3 Crate String Weights Not Started C 6 1 5d 06/21/23 06/27/23 06/21/23 8:00 AM 06/27/23 4:59 PM 1916 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.4.3 1 381 Crate String Weights
383 1.2 1.2.1.6.4.4 Crate Science Equipment FS2 (SPAT, IME, Pressure Sensors, Laser Rangers) Not Started C 6 1 5d 06/06/24 06/12/24 06/06/24 8:00 AM 06/12/24 4:59 PM 1934, 1945 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.4.4 1 382 Crate Science Equipment FS2 (SPAT, IME, Pressure Sensors, Laser Rangers)
384 1.2 1.2.1.6.4.5 Crate Science Equipment FS3 Not Started C 6 1 5d 07/01/25 07/07/25 07/01/25 8:00 AM 07/07/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.4.5 1 383 Crate Science Equipment FS3
385 1.2 1.2.1.6.5 Installation Shipping Not Started P 5 1 724d 10/15/22 08/01/25 10/15/22 8:00 AM 08/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.5 1 384 Installation Shipping
386 1.2 1.2.1.6.5.1 Ship Sensor Handling Structure Not Started C 6 1 0 10/15/22 10/15/22 10/15/22 8:00 AM 10/15/22 8:00 AM 379, 335SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.5.1 1 385 Ship Sensor Handling Structure
387 1.2 1.2.1.6.5.2 Ship Installation Kits Not Started C 6 1 0 10/15/23 10/15/23 10/15/23 8:00 AM 10/15/23 8:00 AM 380, 337SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.5.2 1 386 Ship Installation Kits
388 1.2 1.2.1.6.5.3 Ship String Weights Not Started C 6 1 0 10/15/23 10/15/23 10/15/23 8:00 AM 10/15/23 8:00 AM 381, 337SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.5.3 1 387 Ship String Weights
389 1.2 1.2.1.6.5.4 Ship Science Crate FS2 (SPAT, IME, Pressure Sensors, Laser Rangers) Not Started C 6 1 0 08/01/24 08/01/24 08/01/24 8:00 AM 08/01/24 8:00 AM 382, 338SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.5.4 1 388 Ship Science Crate FS2 (SPAT, IME, Pressure Sensors, Laser Rangers)
390 1.2 1.2.1.6.5.5 Ship Science Crate FS3 Not Started C 6 1 0 08/01/25 08/01/25 08/01/25 8:00 AM 08/01/25 8:00 AM 383, 340SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Deployment Lead 1.2.1.6.5.5 1 389 Ship Science Crate FS3
391 1.2 1.2.2 Thermal Plant - Off-ice Started P 3 1 991d 10/01/20 07/23/24 10/01/20 8:00 AM 07/23/24 4:59 PM 0.00% 54.00% Green $0.00 $0.00 $0.00 $120,420.66 0% Ian McEwen 1.2.2 1 390 Thermal Plant - Off-ice
392 1.2 1.2.2.1 Main Heating Plants Started P 4 1 901d 02/04/21 07/23/24 02/04/21 8:00 AM 07/23/24 4:59 PM 0% 69.00% Green $0.00 $0.00 $0.00 $81,792.77 0% Ian McEwen 1.2.2.1 1 391 Main Heating Plants
393 1.2 1.2.2.1.1 Identify Upgrade-Replacements, Spares Complete C 5 1 401d 02/04/21 08/18/22 02/04/21 8:00 AM 08/18/22 4:59 PM 64% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.2.1.1 1 392 Identify Upgrade-Replacements, Spares
394 1.2 1.2.2.1.2 Assemble and Test Components (Flowmeters, PRV & Control boxes ) Started C 5 1 37d 04/01/22 05/23/22 04/01/22 8:00 AM 05/23/22 4:59 PM 0% 85.00% Green $0.00 $55,871.61 $0.00 $55,871.61 0% $47,490.87 Ian McEwen 1.2.2.1.2 1 393 Assemble and Test Components (Flowmeters, PRV & Control boxes )
395 1.2 1.2.2.1.3 Procure MHP Chimney Stacks (PY4) Not Started C 5 1 30d 04/12/22 05/23/22 04/12/22 8:00 AM 05/23/22 4:59 PM 0% 0% Green $0.00 $14,622.95 $0.00 $14,622.95 0% $0.00 Ian McEwen Vessel FY23. Deliverable supports FS1 tasking. 1.2.2.1.3 1 394 Procure MHP Chimney Stacks (PY4)
396 1.2 1.2.2.1.4 Design and Construct MHP Flush & Pressure Test Kit Not Started C 5 1 32d 04/15/22 05/30/22 04/15/22 8:00 AM 05/30/22 4:59 PM 0% 0% Green $0.00 $6,498.29 $0.00 $6,498.29 0% $0.00 Ian McEwen 1.2.2.1.4 1 395 Design and Construct MHP Flush & Pressure Test Kit
397 1.2 1.2.2.1.5 Build Electronics Kit for MHP1, Heater 7 Not Started C 5 1 21d 05/18/22 06/15/22 05/18/22 8:00 AM 06/15/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen ComSur for FY25 season.
Deliverable supports FS2 tasking.
1.2.2.1.5 1 396 Build Electronics Kit for MHP1, Heater 7
398 1.2 1.2.2.1.6 Procure MHP Upgrade, Sub-Components, Spares (PY5) Not Started C 5 1 30d 04/12/23 05/23/23 04/12/23 8:00 AM 05/23/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Comsur for FY23 season.
Deliverable supports FS1 tasking.
1.2.2.1.6 1 397 Procure MHP Upgrade, Sub-Components, Spares (PY5)
399 1.2 1.2.2.1.7 Develop HPU2 Integrate Plan Not Started C 5 1 30d 05/01/24 06/11/24 05/01/24 8:00 AM 06/11/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen After FS1 eval 1.2.2.1.7 1 398 Develop HPU2 Integrate Plan
400 1.2 1.2.2.1.8 Procure and Assemble HPU2 Integration Components Not Started C 5 1 30d 06/12/24 07/23/24 06/12/24 8:00 AM 07/23/24 4:59 PM 398 0 0% Green $0.00 $4,799.93 $0.00 $4,799.93 0% Ian McEwen Comsur 2024 1.2.2.1.8 1 399 Procure and Assemble HPU2 Integration Components
401 1.2 1.2.2.1.9 Combustion Analyzers, 3x, Spec-Procure-Validate Not Started C 5 1 15d 05/02/22 05/20/22 05/02/22 8:00 AM 05/20/22 4:59 PM 0% 0% Green existing equip stopped working, would like to address this in PY4 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Vessel FY23. Deliverable supports FS1 tasking. 1.2.2.1.9 1 400 Combustion Analyzers, 3x, Spec-Procure-Validate
402 1.2 1.2.2.1.10 Procure MHP Upgrade, Sub-Components, Spares (PY6) Not Started C 5 1 5d 04/15/24 04/19/24 04/15/24 8:00 AM 04/19/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Vessel FY23. Deliverable supports FS1 tasking. 1.2.2.1.10 1 401 Procure MHP Upgrade, Sub-Components, Spares (PY6)
403 1.2 1.2.2.2 Pre-Heat System Started P 4 1 554d 03/24/22 05/10/24 03/24/22 8:00 AM 05/10/24 4:59 PM 0% 66.00% Green $0.00 $0.00 $0.00 $15,228.24 0% Ian McEwen 1.2.2.2 1 402 Pre-Heat System
404 1.2 1.2.2.2.1 Refine PHS Plumbing Upgrade Design Started C 5 1 20d 06/02/22 06/29/22 06/02/22 8:00 AM 06/29/22 4:59 PM 0% 69.00% Green $0.00 $3,459.99 $0.00 $3,459.99 0% $2,387.39 Ian McEwen Vessel FY23. Deliverable supports FS1 tasking. 1.2.2.2.1 1 403 Refine PHS Plumbing Upgrade Design
405 1.2 1.2.2.2.2 Identify Upgrade, Replacements & Spares Components Not Started C 5 1 30d 06/02/22 07/13/22 06/02/22 8:00 AM 07/13/22 4:59 PM 0% 0% Green $0.00 $959.99 $0.00 $959.99 0% $0.00 Ian McEwen Driller_PSL_Lead Vessel FY23. Deliverable supports FS1 tasking. 1.2.2.2.2 1 404 Identify Upgrade, Replacements & Spares Components
406 1.2 1.2.2.2.3 Procure and Upgrade Control Boxes (PY4) Started C 5 1 45d 03/24/22 05/25/22 03/24/22 8:00 AM 05/25/22 4:59 PM 0 85.00% Green $0.00 $10,808.27 $0.00 $10,808.27 0% Ian McEwen Driller_PSL_Lead Comsur for FY25 season. Deliverable supports FS2 tasking. 1.2.2.2.3 1 405 Procure and Upgrade Control Boxes (PY4)
407 1.2 1.2.2.2.4 Procure and Upgrade Control Boxes (PY6) Started C 5 1 30d 03/01/24 04/11/24 03/01/24 8:00 AM 04/11/24 4:59 PM 0 85.00% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead Comsur for FY25 season. Deliverable supports FS2 tasking. 1.2.2.2.4 1 406 Procure and Upgrade Control Boxes (PY6)
408 1.2 1.2.2.2.5 Procure Upgrade, Sub-Components, Spares (PY6) Started C 5 1 30d 04/01/24 05/10/24 04/01/24 8:00 AM 05/10/24 4:59 PM 0% 85.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead Comsur for FY25 season. Deliverable supports FS2 tasking. 1.2.2.2.5 1 407 Procure Upgrade, Sub-Components, Spares (PY6)
409 1.2 1.2.2.3 Fuel Storage and Delivery Started P 4 1 919d 10/01/20 04/12/24 10/01/20 8:00 AM 04/12/24 4:59 PM 0% 33.00% Green $0.00 $0.00 $0.00 $23,399.64 0% Ian McEwen Fuel Storage & Delivery is based on the following assumptions:
5,000 fuel tank fleet - is still at NPX, and will be available to the project, minimally, in FY25 and intensively in FY26
The Fuel Tower - currently in use by WISSARD will be available. Logistics need to be planned to traverse this equipment to NPX in FY23 season.
1.2.2.3 1 408 Fuel Storage and Delivery
410 1.2 1.2.2.3.1 Fuel Systems: Review & Redesign (5k Tank-Tower) Complete C 5 1 80d 10/01/20 01/20/21 10/01/20 8:00 AM 01/20/21 4:59 PM 100% 100% Gray Started early during Recon Season 19/20 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.2.3.1 1 409 Fuel Systems: Review & Redesign (5k Tank-Tower)
411 1.2 1.2.2.3.2 Procurement (Hose, Valves, Sensors, Controls Etc.) Started C 5 1 229d 10/04/21 08/18/22 10/04/21 8:00 AM 08/18/22 4:59 PM 413FS +210d 38% 10.0% Red delayed (COVID) $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer $6317 system components
$7480 internal fuel hose
Quote- and catalog- based
See 1.2.2.3 BOE
1.2.2.3.2 1 410 Procurement (Hose, Valves, Sensors, Controls Etc.)
412 1.2 1.2.2.3.3 Fuel Tower: Review Design & Specs, Field Inputs - Develop Plan Complete C 5 1 30d 11/02/20 12/11/20 11/02/20 8:00 AM 12/11/20 4:59 PM 409SS +22d 99% 100% Gray fuel tower staged for delivery to pole in 20/21 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.2.3.3 1 411 Fuel Tower: Review Design & Specs, Field Inputs - Develop Plan
413 1.2 1.2.2.3.4 Fuel Tower: Redesign Components Complete C 5 1 30d 11/02/20 12/11/20 11/02/20 8:00 AM 12/11/20 4:59 PM 411SS 99% 100% Gray controls identified for redesign, need additional as-built info on-site $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.2.3.4 1 412 Fuel Tower: Redesign Components
414 1.2 1.2.2.3.5 Fuel Tower: Final Design Review Complete C 5 1 1 1 0 12/11/20 12/11/20 12/11/20 4:59 PM 12/11/20 4:59 PM 412 100% 100% Gray delayed (COVID) $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.2.3.5 1 413 Fuel Tower: Final Design Review
415 1.2 1.2.2.3.6 Fuel Tower: Procure Upgrade-Replacements, Spares Started C 5 1 60d 02/07/22 04/29/22 02/07/22 8:00 AM 04/29/22 4:59 PM 413FS +300d 0% 33.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer $5927 components
$14241 external fuel hose
Quote- and Catalog- based
see 1.2.2.3 BOE
1.2.2.3.6 1 414 Fuel Tower: Procure Upgrade-Replacements, Spares
416 1.2 1.2.2.3.7 Fuel Sled Panel Updates - Interface Integration Not Started C 5 1 83d 05/30/22 09/21/22 05/30/22 8:00 AM 09/21/22 4:59 PM 413FS +380d 0% 0% Green $0.00 $23,399.64 $0.00 $23,399.64 0% $0.00 Ian McEwen 1.2.2.3.7 1 415 Fuel Sled Panel Updates - Interface Integration
417 1.2 1.2.2.3.8 Procure ARA Fueling Hose & Nozzle (PY5) Not Started C 5 1 10d 02/28/23 03/13/23 02/28/23 8:00 AM 03/13/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.2.3.8 1 416 Procure ARA Fueling Hose & Nozzle (PY5)
418 1.2 1.2.2.3.9 Procure Racor Fuel Filter Elements and Gauges Replacements (PY5) Not Started C 5 1 10d 02/28/23 03/13/23 02/28/23 8:00 AM 03/13/23 4:59 PM 416SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.2.3.9 1 417 Procure Racor Fuel Filter Elements and Gauges Replacements (PY5)
419 1.2 1.2.2.3.10 Procure Fuel system Upgrade/Maintenance Subcomponents (PY6) Not Started C 5 1 10d 03/30/24 04/11/24 03/30/24 8:00 AM 04/11/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.2.3.10 1 418 Procure Fuel system Upgrade/Maintenance Subcomponents (PY6)
420 1.2 1.2.2.3.11 Procure MHP Fuel Heat Exchangers Replacements (PY6) Not Started C 5 1 10d 04/01/24 04/12/24 04/01/24 8:00 AM 04/12/24 4:59 PM 418SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.2.3.11 1 419 Procure MHP Fuel Heat Exchangers Replacements (PY6)
421 1.2 1.2.3 Tower Operations Site (TOS) - Off-ice Started P 3 1 1756d 10/01/18 07/01/25 10/01/18 8:00 AM 07/01/25 4:59 PM 0.83% 68.00% Green $0.00 $0.00 $1,919.97 $231,229.25 1% Ian McEwen 1.2.3 1 420 Tower Operations Site (TOS) - Off-ice
422 1.2 1.2.3.1 TOS and Tower Started P 4 1 1647d 03/01/19 07/01/25 03/01/19 8:00 AM 07/01/25 4:59 PM 0% 46.00% Green $0.00 $0.00 $0.00 $13,128.72 0% Ian McEwen 1.2.3.1 1 421 TOS and Tower
423 1.2 1.2.3.1.1 Reassess Down Hole Loads - String/DOM Configurations Complete C 5 1 306d 03/01/19 05/01/20 03/01/19 8:00 AM 05/01/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.3.1.1 1 422 Reassess Down Hole Loads - String/DOM Configurations
424 1.2 1.2.3.1.2 Perform Structural Review of Tower & Components Complete C 5 1 1 30d 05/03/21 06/11/21 05/03/21 8:00 AM 06/11/21 4:59 PM 367 422FS +260d 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Drafter, PSL_Engineer 1.2.3.1.2 1 423 Perform Structural Review of Tower & Components
425 1.2 1.2.3.1.3 Crescent & Belt Refurbishment (4 ea) Not Started C 5 1 20d 06/01/22 06/28/22 06/01/22 8:00 AM 06/28/22 4:59 PM 355 0% 0% Green $0.00 $5,928.84 $0.00 $5,928.84 0% $0.00 Ian McEwen PSL_Shop, PSL_Technician Budgetary Estimate: Engineering Professional Estimate (From Gen1)
4 Crescents (Est each)
Cam followers - $4080
AL Plates - $1700
UHMW Blocks - $ 672
Large Guide Wheels - $ 300
Belt - $ 600
Hardware - $ 550
TOTAL - $31,608 (all 4)

*Also, may have service contracts - water jet cutting
1.2.3.1.3 1 424 Crescent & Belt Refurbishment (4 ea)
426 1.2 1.2.3.1.4 Procure Replacement Tower Hoist Complete C 5 1 40d 06/14/21 08/06/21 06/14/21 8:00 AM 08/06/21 4:59 PM -379 423 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead Budgetary Estimate from Phase-1 (10% added for inflation):

CE:
$5,500
1.2.3.1.4 1 425 Procure Replacement Tower Hoist
427 1.2 1.2.3.1.5 Crescent Emergency Repair Kit Assembly (PY6) Not Started C 5 1 35d 02/01/24 03/20/24 02/01/24 8:00 AM 03/20/24 4:59 PM 909 0% 0% Green $0.00 $7,199.89 $0.00 $7,199.89 0% $0.00 Ian McEwen PSL_Shop, PSL_Technician Budgetary Estimate: Engineering Professional Estimate (From Gen1)
4 Crescents (Est each)
Cam followers - $4080
AL Plates - $1700
UHMW Blocks - $ 672
Large Guide Wheels - $ 300
Belt - $ 600
Hardware - $ 550
TOTAL - $31,608 (all 4)

*Also, may have service contracts - water jet cutting
1.2.3.1.5 1 426 Crescent Emergency Repair Kit Assembly (PY6)
428 1.2 1.2.3.1.6 Examine Interface between Dust Logger and Tower & Address as Needed Not Started C 5 1 30d 07/01/23 08/10/23 07/01/23 8:00 AM 08/10/23 4:59 PM 694 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Shop, PSL_Technician Budgetary Estimate: Engineering Professional Estimate (From Gen1)
4 Crescents (Est each)
Cam followers - $4080
AL Plates - $1700
UHMW Blocks - $ 672
Large Guide Wheels - $ 300
Belt - $ 600
Hardware - $ 550
TOTAL - $31,608 (all 4)

*Also, may have service contracts - water jet cutting
1.2.3.1.6 1 427 Examine Interface between Dust Logger and Tower & Address as Needed
429 1.2 1.2.3.1.7 TOS Load Cells Not Started P 5 1 261d 03/15/22 03/14/23 03/15/22 8:00 AM 03/14/23 4:59 PM 221 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Quote- and catalog-based
See 1.2.3.1.5 BOE
1.2.3.1.7 1 428 TOS Load Cells
430 1.2 1.2.3.1.7.1 Load Cells Procured Not Started C 6 1 1 0 03/15/22 03/15/22 03/15/22 8:00 AM 03/15/22 8:00 AM -364 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Quote- and catalog-based
See 1.2.3.1.5 BOE
1.2.3.1.7.1 1 429 Load Cells Procured
431 1.2 1.2.3.1.7.2 Calibration Load Cell Not Started C 6 1 20d 02/01/23 02/28/23 02/01/23 8:00 AM 02/28/23 4:59 PM -41 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Quote- and catalog-based
See 1.2.3.1.5 BOE
1.2.3.1.7.2 1 430 Calibration Load Cell
432 1.2 1.2.3.1.7.3 Calibration Load Cell Rigging Not Started C 6 1 10d 03/01/23 03/14/23 03/01/23 8:00 AM 03/14/23 4:59 PM -13 430 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Quote- and catalog-based
See 1.2.3.1.5 BOE
1.2.3.1.7.3 1 431 Calibration Load Cell Rigging
433 1.2 1.2.3.1.8 Identify/Procure: TOS & Tower Hardware, Repair Parts (PY5) Started C 5 1 35d 06/14/23 08/01/23 06/14/23 8:00 AM 08/01/23 4:59 PM 92 0% 4.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead From PY09 Gen1 Budget:
M&S - but changed to CE for Upgrade
$3,084 - MDS Hardware
$15,420 - Misc Parts & Tools
$ 7,710 - Safety gear, harnesses, misc
-----------------------------------------
$26,214
1.2.3.1.8 1 432 Identify/Procure: TOS & Tower Hardware, Repair Parts (PY5)
434 1.2 1.2.3.1.9 Identify/Procure: TOS & Tower Hardware, Repair Parts (PY6) Started C 5 1 35d 06/12/24 07/30/24 06/12/24 8:00 AM 07/30/24 4:59 PM 456 0% 4.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead From PY09 Gen1 Budget:
M&S - but changed to CE for Upgrade
$3,084 - MDS Hardware
$15,420 - Misc Parts & Tools
$ 7,710 - Safety gear, harnesses, misc
-----------------------------------------
$26,214
1.2.3.1.9 1 433 Identify/Procure: TOS & Tower Hardware, Repair Parts (PY6)
435 1.2 1.2.3.1.10 Identify/Procure: TOS & Tower Hardware, Repair Parts (PY7) Started C 5 1 35d 05/14/25 07/01/25 05/14/25 8:00 AM 07/01/25 4:59 PM 792 0% 4.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead From PY09 Gen1 Budget:
M&S - but changed to CE for Upgrade
$3,084 - MDS Hardware
$15,420 - Misc Parts & Tools
$ 7,710 - Safety gear, harnesses, misc
-----------------------------------------
$26,214
1.2.3.1.10 1 434 Identify/Procure: TOS & Tower Hardware, Repair Parts (PY7)
436 1.2 1.2.3.2 Drillheads Started P 4 1 909d 04/01/19 09/22/22 04/01/19 8:00 AM 09/22/22 4:59 PM -2283 60% 91.00% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.2 1 435 Drillheads
437 1.2 1.2.3.2.1 Initial assessment of 3 drillheads Complete C 5 1 120d 04/01/19 09/13/19 04/01/19 8:00 AM 09/13/19 4:59 PM -1270 100% 100% Gray Initial assessment good, some re-anodizing required $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.3.2.1 1 436 Initial assessment of 3 drillheads
438 1.2 1.2.3.2.2 Drillhead and software subsystem testing Complete C 5 1 20d 04/16/21 05/13/21 04/16/21 8:00 AM 05/13/21 4:59 PM 581 99% 100% Gray Activity restarted 11/19. Qiang is lead engineer. Some progress in May. $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician Test equipment, cabling, computer. 1.2.3.2.2 1 437 Drillhead and software subsystem testing
439 1.2 1.2.3.2.3 Rework/rewrite drillhead software Complete C 5 1 45d 03/12/21 05/13/21 03/12/21 8:00 AM 05/13/21 4:59 PM -62 437FF 99% 100% Gray Major achievements accomplished in May, still working on data processing $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.3.2.3 1 438 Rework/rewrite drillhead software
440 1.2 1.2.3.2.4 Recondition and calibrate Drillhead 1 Complete C 5 1 311d 05/25/20 08/02/21 05/25/20 8:00 AM 08/02/21 4:59 PM -353 436FS +180d, 438FF -30d 100% 100% Gray remaining: pressure and caliper tests $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Shop, PSL_Technician From PY09 Gen1 Budget:

CE:
$16,500 - PM Parts & Upgrades, Incl Caliper Replacement, 4" Collars, Etc
-----------------------------------------
M&S:
$ 4,000 - Shop labor (PSL)
1.2.3.2.4 1 439 Recondition and calibrate Drillhead 1
441 1.2 1.2.3.2.5 Recondition and calibrate Drillhead 2 Complete C 5 1 271d 07/20/20 08/02/21 07/20/20 8:00 AM 08/02/21 4:59 PM -378 439FF 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Shop, PSL_Technician 1.2.3.2.5 1 440 Recondition and calibrate Drillhead 2
442 1.2 1.2.3.2.6 Recondition and calibrate Drillhead 3 Complete C 5 1 231d 09/14/20 08/02/21 09/14/20 8:00 AM 08/02/21 4:59 PM -322 440FF 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Shop, PSL_Technician 1.2.3.2.6 1 441 Recondition and calibrate Drillhead 3
443 1.2 1.2.3.2.7 Update Drillheads for Cable Not Started C 5 1 45d 03/16/22 05/17/22 03/16/22 8:00 AM 05/17/22 4:59 PM 226 441FS +161d 0% 0% Green Major achievements accomplished in May, still working on data processing $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.3.2.7 1 442 Update Drillheads for Cable
444 1.2 1.2.3.2.8 Pressure Test Drillhead Hanger & Spare Hose Not Started C 5 1 45d 03/16/22 05/17/22 03/16/22 8:00 AM 05/17/22 4:59 PM -62 442FF 0% 0% Green Major achievements accomplished in May, still working on data processing $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.3.2.8 1 443 Pressure Test Drillhead Hanger & Spare Hose
445 1.2 1.2.3.2.9 Drillheads: Drillheads Updated and Hose Pressure Tested Not Started C 5 1 1 0 05/31/22 05/31/22 05/31/22 4:59 PM 05/31/22 4:59 PM 14 443FS +10d 0 0% Green Major achievements accomplished in May, still working on data processing $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.3.2.9 1 444 Drillheads: Drillheads Updated and Hose Pressure Tested
446 1.2 1.2.3.2.10 Drillheads: Prepare Crates, Spares, Tools, & Docs x3 Not Started C 5 1 6d 09/15/22 09/22/22 09/15/22 8:00 AM 09/22/22 4:59 PM 0% 0% Green Major achievements accomplished in May, still working on data processing $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.3.2.10 1 445 Drillheads: Prepare Crates, Spares, Tools, & Docs x3
447 1.2 1.2.3.3 Reels & Winches Started P 4 1 919d 11/02/20 05/14/24 11/02/20 8:00 AM 05/14/24 4:59 PM -689 1% 61.00% Green $0.00 $0.00 $1,919.97 $202,460.71 1% Ian McEwen 1.2.3.3 1 446 Reels & Winches
448 1.2 1.2.3.3.1 Main Drill Cable Reel (at PSL): Rebuild, Upgrade, Test Complete C 5 1 80d 11/02/20 02/19/21 11/02/20 8:00 AM 02/19/21 4:59 PM -1289 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead, PSL_Engineer, PSL_Shop Level wind & Control Bearings - $ ??
Gearbox - $850
Ball Screw - $680
Linear Rail - $1,620
Rail Guides - $314 (x2)
Elec Motor - $1625 (x2)
Motors & gear box $3,000
Slip Ring - $ ??
Brake System $17,500

Quotes received from: McMaster-Carr, MSC, BBS
1.2.3.3.1 1 447 Main Drill Cable Reel (at PSL): Rebuild, Upgrade, Test
449 1.2 1.2.3.3.2 Return Water Cable Reel (at PSL): Rebuild, Upgrade, Test Complete C 5 1 68d 10/02/21 01/04/22 10/02/21 8:00 AM 01/04/22 4:59 PM 100% 100% Gray $1,919.97 $1,919.97 $1,919.97 $1,919.97 100% $1,919.97 Ian McEwen Driller_PSL_Lead, PSL_Engineer Slip ring
Brake System
1.2.3.3.2 1 448 Return Water Cable Reel (at PSL): Rebuild, Upgrade, Test
450 1.2 1.2.3.3.3 Main Supply Hose Reel (Big Red at NPX) - Procure Replacement Parts Started C 5 1 582d 01/05/22 04/02/24 01/05/22 8:00 AM 04/02/24 4:59 PM 448 3% 75.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer Rotary Union ~$5,000
Limit Switches ~$2,000
Brake Components ~$2,000
Plumbing Refurb ~$2,000
Heating Blanket System?

FailSafe Disc Brake - $22,986
Gearbox - $ 850
Ball Screw - $1,700
Linear Rail - $4,050 (x2)
Rail Guides - $ 314 (x4)
Elec Motor - $2,900
Main Bearing - $5,050 (x2)
-----------------------------
Total Cost $47,892 (25% factor = $11,973)
1.2.3.3.3 1 449 Main Supply Hose Reel (Big Red at NPX) - Procure Replacement Parts
451 1.2 1.2.3.3.4 Return Water Hose Reel (at NPX) - Procure Replacement Parts Started C 5 1 612d 01/05/22 05/14/24 01/05/22 8:00 AM 05/14/24 4:59 PM 449SS 3% 75.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer Rotary union
Large Ball Valve
Motor
Manifold
1.2.3.3.4 1 450 Return Water Hose Reel (at NPX) - Procure Replacement Parts
452 1.2 1.2.3.3.5 TU-20 Winches (at NPX) - Plan/Procure Replacement Parts. Design/Fabricate New Axles Complete C 5 1 60d 02/01/21 04/23/21 02/01/21 8:00 AM 04/23/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer, PSL_Shop Recondition slip rings
2 new steel axles from Tulsa Power
Electric Brake Replacement
Hydraulic lift replacements
1.2.3.3.5 1 451 TU-20 Winches (at NPX) - Plan/Procure Replacement Parts. Design/Fabricate New Axles
453 1.2 1.2.3.3.6 Cable Tensioner (at PSL) - Procure Repair Parts Complete C 5 1 90d 02/01/21 06/04/21 02/01/21 8:00 AM 06/04/21 4:59 PM 451SS 100% 100% Gray a few parts still needed $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, PSL_Engineer New Tread 1.2.3.3.6 1 452 Cable Tensioner (at PSL) - Procure Repair Parts
454 1.2 1.2.3.3.7 Main Drill Cable Reel/Main Hose Reel Load Sharing (PY4) Should have Started P 5 1 390d 12/20/21 06/16/23 12/20/21 8:00 AM 06/16/23 4:59 PM 0 0% Green $0.00 $200,540.74 $0.00 $200,540.74 0% Ian McEwen Driller_PSL_Lead, PSL_Engineer, PSL_Shop Recondition slip rings
2 new steel axles from Tulsa Power
Electric Brake Replacement
Hydraulic lift replacements
1.2.3.3.7 1 453 Main Drill Cable Reel/Main Hose Reel Load Sharing (PY4)
455 1.2 1.2.3.3.7.1 Load sharing: Coordination, Design, Documentation (PY4) Should have Started C 6 1 195d 12/20/21 09/16/22 12/20/21 8:00 AM 09/16/22 4:59 PM 0.15845233 0% Yellow $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer, PSL_Shop Recondition slip rings
2 new steel axles from Tulsa Power
Electric Brake Replacement
Hydraulic lift replacements
1.2.3.3.7.1 1 454 Load sharing: Coordination, Design, Documentation (PY4)
456 1.2 1.2.3.3.7.2 Load sharing: Modeling and Software Development, Bench Testing (PY4) Should have Started C 6 1 130d 12/20/21 06/17/22 12/20/21 8:00 AM 06/17/22 4:59 PM 454SS 0.23839224 0% Red $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer, PSL_Shop Recondition slip rings
2 new steel axles from Tulsa Power
Electric Brake Replacement
Hydraulic lift replacements
1.2.3.3.7.2 1 455 Load sharing: Modeling and Software Development, Bench Testing (PY4)
457 1.2 1.2.3.3.7.3 Load sharing: Full scale Test Setup (PY4) Not Started C 6 1 100d 04/04/22 08/19/22 04/04/22 8:00 AM 08/19/22 4:59 PM 455SS +75d 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer, PSL_Shop Recondition slip rings
2 new steel axles from Tulsa Power
Electric Brake Replacement
Hydraulic lift replacements
1.2.3.3.7.3 1 456 Load sharing: Full scale Test Setup (PY4)
458 1.2 1.2.3.3.7.4 Load sharing: Full-scale Testing - Diameter Correction and Prelim Load Share (PY4) Not Started C 6 1 140d 03/14/22 09/23/22 03/14/22 8:00 AM 09/23/22 4:59 PM 455SS +60d 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer, PSL_Shop Recondition slip rings
2 new steel axles from Tulsa Power
Electric Brake Replacement
Hydraulic lift replacements
1.2.3.3.7.4 1 457 Load sharing: Full-scale Testing - Diameter Correction and Prelim Load Share (PY4)
459 1.2 1.2.3.3.7.5 Load Sharing: Full-scale Testing - Load Share & Tuning (PY5) Not Started C 6 1 90d 02/13/23 06/16/23 02/13/23 8:00 AM 06/16/23 4:59 PM 457FS +100d 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer, PSL_Shop Recondition slip rings
2 new steel axles from Tulsa Power
Electric Brake Replacement
Hydraulic lift replacements
1.2.3.3.7.5 1 458 Load Sharing: Full-scale Testing - Load Share & Tuning (PY5)
460 1.2 1.2.3.3.8 Reels & Winches: Reel Load Sharing Testing Complete Not Started C 5 1 1 0 06/16/23 06/16/23 06/16/23 4:59 PM 06/16/23 4:59 PM 454, 455, 456, 457, 458 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer, PSL_Shop Recondition slip rings
2 new steel axles from Tulsa Power
Electric Brake Replacement
Hydraulic lift replacements
1.2.3.3.8 1 459 Reels & Winches: Reel Load Sharing Testing Complete
461 1.2 1.2.3.3.9 Reels & Winches: Drill Reels Sliprings - Final Testing & Prep Not Started C 5 1 10d 06/10/23 06/22/23 06/10/23 8:00 AM 06/22/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer, PSL_Shop Recondition slip rings
2 new steel axles from Tulsa Power
Electric Brake Replacement
Hydraulic lift replacements
1.2.3.3.9 1 460 Reels & Winches: Drill Reels Sliprings - Final Testing & Prep
462 1.2 1.2.3.3.10 Reels & Winches: TU20 Sliprings - Spec, Procure, Test Not Started C 5 1 8w 03/30/23 05/24/23 03/30/23 8:00 AM 05/24/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer, PSL_Shop Recondition slip rings
2 new steel axles from Tulsa Power
Electric Brake Replacement
Hydraulic lift replacements
1.2.3.3.10 1 461 Reels & Winches: TU20 Sliprings - Spec, Procure, Test
463 1.2 1.2.3.3.11 Reels & Winches: Reel Components & Spares (PY6). TU20 brakes Not Started C 5 1 8w 03/01/24 04/25/24 03/01/24 8:00 AM 04/25/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer, PSL_Shop Recondition slip rings
2 new steel axles from Tulsa Power
Electric Brake Replacement
Hydraulic lift replacements
1.2.3.3.11 1 462 Reels & Winches: Reel Components & Spares (PY6). TU20 brakes
464 1.2 1.2.3.4 Downhole Main Drill Hose Complete P 4 1 561d 10/01/18 11/23/20 10/01/18 8:00 AM 11/23/20 4:59 PM 98% 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.4 1 463 Downhole Main Drill Hose
465 1.2 1.2.3.4.1 Request Budgetary Cost Estimate Complete C 5 1 3d 10/01/18 10/03/18 10/01/18 8:00 AM 10/03/18 4:59 PM 89% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.3.4.1 1 464 Request Budgetary Cost Estimate
466 1.2 1.2.3.4.2 Confirm & Specify Drill Hose Complete C 5 1 40d 10/01/19 11/25/19 10/01/19 8:00 AM 11/25/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Analyze new downhole loads - 5 days
Adjust tension members in yellow hose formula - 10 days
1.2.3.4.2 1 465 Confirm & Specify Drill Hose
467 1.2 1.2.3.4.3 Procure drill hose (Manufacture by IVG) Complete C 5 1 240d 09/17/19 08/17/20 09/17/19 8:00 AM 08/17/20 4:59 PM 467, 465SS -10d 100% 100% Gray Production started end of Feb, COVID factory shut down 3/27, restart in April, still on schedule $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Work with IVG to strengthen tension member in yellow hose
(We might not need to do this and can just order yellow stripe hose as is - depends on new load requirements)
Quote and order drill hose
1.2.3.4.3 1 466 Procure drill hose (Manufacture by IVG)
468 1.2 1.2.3.4.4 Procurement - Down Payment (~20%) Complete C 5 1 1 1 1d 09/13/19 09/13/19 09/13/19 8:00 AM 09/13/19 4:59 PM 100% 100% Gray Pulled forward to take advantage of discount offered by IVG - Submit PO by 9/15 and receive 10% off $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.4.4 1 467 Procurement - Down Payment (~20%)
469 1.2 1.2.3.4.5 Procurement - Final Payment (Remainder), Ship to PSL Complete C 5 1 1 1 1d 08/18/20 08/18/20 08/18/20 8:00 AM 08/18/20 4:59 PM 466 100% 100% Gray Pulled forward to take advantage of discount offered by IVG - Submit PO by 9/15 and receive 10% off $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Added $20,000 for Shipment to PSL 1.2.3.4.5 1 468 Procurement - Final Payment (Remainder), Ship to PSL
470 1.2 1.2.3.4.6 Manufacture Strain Reliefs (at PSL) Complete C 5 1 80d 09/13/19 01/02/20 09/13/19 8:00 AM 01/02/20 4:59 PM 100% 100% Gray First article received, PO submitted, parts COVID delay, due mid May $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Drafter, PSL_Engineer, PSL_Shop Convert drawings to CAD models
Make key changes to strain relief design, draw
Fabricate at PSL
Ship strain reliefs to IVG

Labor = $56,672 ($62,340) (per Tom Harrington, PSL Shop Supervisor)
Material = $28,328 ($31,160)
Shipping to IVG = $3,000
-------------------------------
$96,500 (w/10% MOE)

46 Strain Reliefs (23 hose sections)
8 aluminum sections/relief (16 total)
1.2.3.4.6 1 469 Manufacture Strain Reliefs (at PSL)
471 1.2 1.2.3.4.7 Ship Strain Reliefs to Italy (Mnftr Install on Hose) Complete C 5 1 140d 01/03/20 07/16/20 01/03/20 8:00 AM 07/16/20 4:59 PM 469 100% 100% Gray Shipping early June $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$4,375 - Dedicated Truckload
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

2 - crates - shipped internationally
$600 materials, $1,200 shipping
1.2.3.4.7 1 470 Ship Strain Reliefs to Italy (Mnftr Install on Hose)
472 1.2 1.2.3.4.8 Prepare Hose at PSL, Crate for Shipment, Hold 1 Year Complete C 5 1 5d 11/17/20 11/23/20 11/17/20 8:00 AM 11/23/20 4:59 PM 470FS +87d, 468 95% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead 1.2.3.4.8 1 471 Prepare Hose at PSL, Crate for Shipment, Hold 1 Year
473 1.2 1.2.3.4.9 Ship Drill Hose from IVG (ComSur-CHC, Vessel-ZCM, Outdoor storage ZCM) Complete C 5 1 1 1 1d 10/30/20 10/30/20 10/30/20 8:00 AM 10/30/20 4:59 PM 470FS +75d 100% 100% Gray Drop Ship to CHC by 11/15/20
Vessel to ZCM 11/20 - 2/21
Store (outdoor) ZCM 2/21 - 1/22
Fly ZCM-NPX 1/22
Store (DNF) NPX 1/22 to 11/22
Spool on MSHR 11/22
Drilling begins 12/22
$0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.4.9 1 472 Ship Drill Hose from IVG (ComSur-CHC, Vessel-ZCM, Outdoor storage ZCM)
474 1.2 1.2.3.5 Downhole Main Cables Complete P 4 1 447d 10/01/19 06/16/21 10/01/19 8:00 AM 06/16/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.5 1 473 Downhole Main Cables
475 1.2 1.2.3.5.1 Main Drill Cable Spec Review & Revisions Complete C 5 1 119d 10/01/19 03/13/20 10/01/19 8:00 AM 03/13/20 4:59 PM 100% 100% Gray RFP still in progress $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.3.5.1 1 474 Main Drill Cable Spec Review & Revisions
476 1.2 1.2.3.5.2 Combo Cable - Spec Review & Revisions Complete C 5 1 119d 10/01/19 03/13/20 10/01/19 8:00 AM 03/13/20 4:59 PM 474SS 100% 100% Gray delayed, limited access $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.3.5.2 1 475 Combo Cable - Spec Review & Revisions
477 1.2 1.2.3.5.3 Test Combo Cable (2 at PSL) Complete C 5 1 40d 03/16/20 05/08/20 03/16/20 8:00 AM 05/08/20 4:59 PM 475 99% 100% Gray Testing plans delayed (COVID) $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician 1.2.3.5.3 1 476 Test Combo Cable (2 at PSL)
478 1.2 1.2.3.5.4 Test Main Drill Cable & Unjacketed Spare Complete C 5 1 60d 03/16/20 06/05/20 03/16/20 8:00 AM 06/05/20 4:59 PM 476SS 100% 100% Gray Preliminary electrical tests performed, visual inspection, otherwise delayed $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician 1.2.3.5.4 1 477 Test Main Drill Cable & Unjacketed Spare
479 1.2 1.2.3.5.5 Procure Main Drill Cable Complete C 5 1 180d 10/08/20 06/16/21 10/08/20 8:00 AM 06/16/21 4:59 PM 100% 100% Gray Shipment delayed until fall 2021 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Quote from South Bay - Nov 12, 2018
$42.75/meter @ 3200m

Cortland quote from 2008 was $80,300

- Need to confirm includes connectors, shipping, spool, etc.
- Also, need 2nd quote from ?? (Cortland)
1.2.3.5.5 1 478 Procure Main Drill Cable
480 1.2 1.2.3.5.6 Jacket Spare Cable (by vendor, currently at PSL) Complete C 5 1 60d 06/08/20 08/28/20 06/08/20 8:00 AM 08/28/20 4:59 PM 477 100% 100% Gray Vendors not able to do this, will probably need to change baseline to procuring another entirely new cable as spare $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician Quote from - Cortland Cable (Doug Bentley) from 2008 was $15,800
(PO # X441652-92041 08/07/2008)
I've doubled the amount quoted since it's 10 years old, inflation and material increase, as well as other vendors had no interest in doing this so an uncertainty factor.
1.2.3.5.6 1 479 Jacket Spare Cable (by vendor, currently at PSL)
481 1.2 1.2.3.5.7 Connectors - Procure & Install, Both Cables (at vendor) Complete C 5 1 60d 03/25/21 06/16/21 03/25/21 8:00 AM 06/16/21 4:59 PM 478FF 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 4 connectors - $1,200 each, plus installation (by vendor) 1.2.3.5.7 1 480 Connectors - Procure & Install, Both Cables (at vendor)
482 1.2 1.2.3.5.8 Spool Main Drill Cable onto Winch/Spool Complete C 5 1 15d 08/31/20 09/18/20 08/31/20 8:00 AM 09/18/20 4:59 PM 479 98% 100% Gray New activity. Requires cable spooler (now at PSL) $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician 1.2.3.5.8 1 481 Spool Main Drill Cable onto Winch/Spool
483 1.2 1.2.3.6 Design and Construct Main Hose Reel Heating System Not Started P 4 1 160d 02/27/22 10/06/22 02/27/22 8:00 AM 10/06/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $15,639.82 0% Ian McEwen 1.2.3.6 1 482 Design and Construct Main Hose Reel Heating System
484 1.2 1.2.3.6.1 Design, Fabricate and Test Hose Reel Heating System Not Started P 5 1 125d 04/15/22 10/06/22 04/15/22 8:00 AM 10/06/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.6.1 1 483 Design, Fabricate and Test Hose Reel Heating System
485 1.2 1.2.3.6.1.1 Connectorize Heated Blankets Not Started C 6 1 1w 10/01/22 10/06/22 10/01/22 8:00 AM 10/06/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.3.6.1.1 1 484 Connectorize Heated Blankets
486 1.2 1.2.3.6.1.2 Attach RTDs to Inner Insulation & Heated Blankets Not Started C 6 1 4w 04/15/22 05/12/22 04/15/22 8:00 AM 05/12/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.3.6.1.2 1 485 Attach RTDs to Inner Insulation & Heated Blankets
487 1.2 1.2.3.6.1.3 Design and Fab RTD Patch Panel Not Started C 6 1 21d 04/15/22 05/13/22 04/15/22 8:00 AM 05/13/22 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 1.2.3.6.1.3 1 Design and Fab RTD Patch Panel
488 1.2 1.2.3.6.2 Procure Components for Hose Reel Heating System (Insulated Blankets & Tarps) Not Started P 5 1 40d 04/02/22 05/26/22 04/02/22 8:00 AM 05/26/22 4:59 PM 0% Green $0.00 $5,919.97 $0.00 $5,919.97 0% $0.00 Ian McEwen 1.2.3.6.2 1 487 Procure Components for Hose Reel Heating System (Insulated Blankets & Tarps)
489 1.2 1.2.3.6.2.1 Size and Procure Insulated Tarps for Inner/Outer Layers Not Started C 6 1 20d 04/02/22 04/28/22 04/02/22 8:00 AM 04/28/22 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 1.2.3.6.2.1 1 Size and Procure Insulated Tarps for Inner/Outer Layers
490 1.2 1.2.3.6.2.2 Size and Procure Outer Canvas Tarp Not Started C 6 1 20d 04/29/22 05/26/22 04/29/22 8:00 AM 05/26/22 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 1.2.3.6.2.2 1 Size and Procure Outer Canvas Tarp
491 1.2 1.2.3.6.3 Hose Reel Heating System Testing Not Started P 5 1 20d 02/27/22 03/24/22 02/27/22 8:00 AM 03/24/22 4:59 PM 0% Green $0.00 $9,719.85 $0.00 $9,719.85 0% $0.00 Ian McEwen 1.2.3.6.3 1 490 Hose Reel Heating System Testing
492 1.2 1.2.3.6.3.1 Cold Test Hose Heating Controller System Not Started C 6 1 4w 02/27/22 03/24/22 02/27/22 8:00 AM 03/24/22 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.3.6.3.1 1 491 Cold Test Hose Heating Controller System
493 1.2 1.2.3.6.4 Develop RedLion FlexEdge Controller SW functionality Not Started P 5 1 135d 03/25/22 09/29/22 03/25/22 8:00 AM 09/29/22 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.6.4 1 492 Develop RedLion FlexEdge Controller SW functionality
494 1.2 1.2.3.6.4.1 Develop User Interface, Primarily for Blanket Setpoints, Alarm Setpoints Not Started C 6 1 3w 03/25/22 04/14/22 03/25/22 8:00 AM 04/14/22 4:59 PM 491 0 Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.6.4.1 1 493 Develop User Interface, Primarily for Blanket Setpoints, Alarm Setpoints
495 1.2 1.2.3.6.4.2 Develop/Test Blanket Temp Control Not Started C 6 1 4w 04/15/22 05/12/22 04/15/22 8:00 AM 05/12/22 4:59 PM 493 0 Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.6.4.2 1 494 Develop/Test Blanket Temp Control
496 1.2 1.2.3.6.4.3 Finalize Data Logging Not Started C 6 1 10d 05/13/22 05/26/22 05/13/22 8:00 AM 05/26/22 4:59 PM 494 0 Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.6.4.3 1 495 Finalize Data Logging
497 1.2 1.2.3.6.4.4 Develop/Test Alerting Notifications Not Started C 6 1 10d 09/16/22 09/29/22 09/16/22 8:00 AM 09/29/22 4:59 PM 495FS +80d 0 Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.6.4.4 1 496 Develop/Test Alerting Notifications
498 1.2 1.2.3.6.4.5 Document Subsystem Not Started C 6 1 10d 09/16/22 09/29/22 09/16/22 8:00 AM 09/29/22 4:59 PM 496SS 0 Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.6.4.5 1 497 Document Subsystem
499 1.2 1.2.3.6.5 System Tests Not Started C 5 1 6w 08/19/22 09/29/22 08/19/22 8:00 AM 09/29/22 4:59 PM 494FS +70d 0 Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.6.5 1 498 System Tests
500 1.2 1.2.3.6.6 Make Installation Drawing Not Started C 5 1 2w 08/16/22 08/29/22 08/16/22 8:00 AM 08/29/22 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.6.6 1 499 Make Installation Drawing
501 1.2 1.2.3.6.7 Prepare for Shipment Not Started C 5 1 3d 09/30/22 10/04/22 09/30/22 8:00 AM 10/04/22 4:59 PM 498 0 Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.3.6.7 1 500 Prepare for Shipment
502 1.2 1.2.4 Computing and Control System - Off-ice Started P 3 1 1898d 01/02/19 04/23/26 01/02/19 8:00 AM 04/23/26 4:59 PM 20.11% 26.00% Green $0.00 $0.00 $119,363.24 $593,433.41 20% Ian McEwen 1.2.4 1 501 Computing and Control System - Off-ice
503 1.2 1.2.4.1 Architecture Started P 4 1 1898d 01/02/19 04/23/26 01/02/19 8:00 AM 04/23/26 4:59 PM 0% 46.00% Green $0.00 $0.00 $0.00 $23,999.63 0% Ian McEwen 1.2.4.1 1 502 Architecture
504 1.2 1.2.4.1.1 Evaluate EHWD system Complete C 5 1 1 80d 01/02/19 04/23/19 01/02/19 8:00 AM 04/23/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.1.1 1 503 Evaluate EHWD system
505 1.2 1.2.4.1.2 ICUD Requirements & Architecture Plan Complete C 5 1 80d 04/24/19 08/13/19 04/24/19 8:00 AM 08/13/19 4:59 PM 503 100% 100% Gray underway, SCADA options under evaluation $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.1.2 1 504 ICUD Requirements & Architecture Plan
506 1.2 1.2.4.1.3 Control Systems - Preliminary Design Review Complete C 5 1 1 1 1d 08/14/19 08/14/19 08/14/19 8:00 AM 08/14/19 4:59 PM 504 100% 100% Gray November 2019 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.1.3 1 505 Control Systems - Preliminary Design Review
507 1.2 1.2.4.1.4 System Design Complete C 5 1 120d 08/15/19 01/29/20 08/15/19 8:00 AM 01/29/20 4:59 PM 505 100% 100% Gray underway $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.1.4 1 506 System Design
508 1.2 1.2.4.1.5 Control Systems - 60% Design Review Complete Not Started C 5 1 1 0 04/15/22 04/15/22 04/15/22 8:00 AM 04/15/22 8:00 AM 0% 0% Green $0.00 $4,799.93 $0.00 $4,799.93 0% $0.00 Ian McEwen 1.2.4.1.5 1 507 Control Systems - 60% Design Review Complete
509 1.2 1.2.4.1.6 Control Systems - Electrical Schematic Update 1 Not Started C 5 1 110d 02/15/22 07/18/22 02/15/22 8:00 AM 07/18/22 4:59 PM 0% 0% Green $0.00 $19,199.71 $0.00 $19,199.71 0% $0.00 Ian McEwen 1.2.4.1.6 1 508 Control Systems - Electrical Schematic Update 1
510 1.2 1.2.4.1.7 Coordination with USAP IT (PY4) Not Started C 5 1 2w 05/15/22 05/26/22 05/15/22 8:00 AM 05/26/22 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 1.2.4.1.7 1 509 Coordination with USAP IT (PY4)
511 1.2 1.2.4.1.8 Coordination with USAP IT (PY5) Not Started C 5 1 4w 06/01/23 06/28/23 06/01/23 8:00 AM 06/28/23 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 1.2.4.1.8 1 510 Coordination with USAP IT (PY5)
512 1.2 1.2.4.1.9 CS Drawings & Documentation (PY5) Not Started C 5 1 12w 07/03/23 09/22/23 07/03/23 8:00 AM 09/22/23 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 1.2.4.1.9 1 511 CS Drawings & Documentation (PY5)
513 1.2 1.2.4.1.10 CS Drawings & Documentation (PY6) Not Started C 5 1 12w 08/03/24 10/24/24 08/03/24 8:00 AM 10/24/24 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 1.2.4.1.10 1 512 CS Drawings & Documentation (PY6)
514 1.2 1.2.4.1.11 CS Drawings & Documentation (PY7) Not Started C 5 1 12w 08/03/25 10/23/25 08/03/25 8:00 AM 10/23/25 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.1.11 1 513 CS Drawings & Documentation (PY7)
515 1.2 1.2.4.1.12 CS Drawings & Documentation (PY8) Started C 5 1 8w 03/01/26 04/23/26 03/01/26 8:00 AM 04/23/26 4:59 PM 0% 28.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.1.12 1 514 CS Drawings & Documentation (PY8)
516 1.2 1.2.4.2 Control System Hardware Started P 4 1 904d 11/01/21 04/25/25 11/01/21 8:00 AM 04/25/25 4:59 PM 0.24090167 22.00% Green delayed, limited access for evaluation phase, but making progress $0.00 $0.00 $69,203.87 $287,270.18 24% Ian McEwen 1.2.4.2 1 515 Control System Hardware
517 1.2 1.2.4.2.1 PLC Motor Controllers and Readouts Not Started P 5 1 103d 05/10/22 09/29/22 05/10/22 8:00 AM 09/29/22 4:59 PM 19% 0% Yellow delayed, limited access for evaluation phase, but making progress $5,500.00 $5,500.00 $5,500.00 $29,259.70 19% $0.00 Ian McEwen 1.2.4.2.1 1 516 PLC Motor Controllers and Readouts
518 1.2 1.2.4.2.1.1 Design, Build and Test New PLC and Network Box for HPP Not Started P 6 1 52d 05/10/22 07/20/22 05/10/22 8:00 AM 07/20/22 4:59 PM 0% 0% Green delayed, limited access for evaluation phase, but making progress $0.00 $23,759.70 $0.00 $23,759.70 0% $0.00 Ian McEwen 1.2.4.2.1.1 1 517 Design, Build and Test New PLC and Network Box for HPP
519 1.2 1.2.4.2.1.1.1 PLC and Network Box for HPP Design & Build Not Started C 7 1 52d 05/10/22 07/20/22 05/10/22 8:00 AM 07/20/22 4:59 PM 0% 0% Green delayed, limited access for evaluation phase, but making progress $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.2.1.1.1 1 518 PLC and Network Box for HPP Design & Build
520 1.2 1.2.4.2.1.1.2 PLC and Network Cox for HPP Constructed, Tested & Complete Not Started C 7 1 1 0 07/20/22 07/20/22 07/20/22 4:59 PM 07/20/22 4:59 PM 518 0% 0% Green delayed, limited access for evaluation phase, but making progress $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.2.1.1.2 1 519 PLC and Network Cox for HPP Constructed, Tested & Complete
521 1.2 1.2.4.2.1.2 Design, Build & Test RWCR Control Box Not Started C 6 1 65d 07/01/22 09/29/22 07/01/22 8:00 AM 09/29/22 4:59 PM 0% 0% Green delayed, limited access for evaluation phase, but making progress $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.2.1.2 1 520 Design, Build & Test RWCR Control Box
522 1.2 1.2.4.2.2 Sensors Started P 5 1 102d 05/28/22 10/17/22 05/28/22 8:00 AM 10/17/22 4:59 PM 59% 17.00% Red delayed, waiting for 19/20 retro $20,899.83 $34,399.78 $35,299.61 $59,599.39 59% $5,847.96 Ian McEwen PSL_Software Engineer 1.2.4.2.2 1 521 Sensors
523 1.2 1.2.4.2.2.1 HPP Sensor Box Testing Started C 6 1 60d 06/22/22 09/13/22 06/22/22 8:00 AM 09/13/22 4:59 PM 52% 33.00% Yellow delayed, waiting for 19/20 retro $7,199.89 $13,799.79 $7,199.89 $13,799.79 52% $4,553.93 Ian McEwen PSL_Software Engineer 1.2.4.2.2.1 1 522 HPP Sensor Box Testing
524 1.2 1.2.4.2.2.2 Specify, Procure and Test Water Tank Depth & Temp Sensor Box Testing Started C 6 1 41d 06/26/22 08/19/22 06/26/22 8:00 AM 08/19/22 4:59 PM 63% 53.00% Yellow delayed, waiting for 19/20 retro $7,199.89 $11,399.83 $7,199.89 $11,399.83 63% $6,041.91 Ian McEwen PSL_Software Engineer 1.2.4.2.2.2 1 523 Specify, Procure and Test Water Tank Depth & Temp Sensor Box Testing
525 1.2 1.2.4.2.2.3 Specify System Sensors Not Started C 6 1 90d 05/28/22 09/29/22 05/28/22 8:00 AM 09/29/22 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 1.2.4.2.2.3 1 524 Specify System Sensors
526 1.2 1.2.4.2.2.4 Procure System Sensors (PY4) Not Started C 6 1 8w 06/13/22 08/05/22 06/13/22 8:00 AM 08/05/22 4:59 PM 524SS +2w 0 Green $0.00 $0.00 $0.00 $0.00 1.2.4.2.2.4 1 525 Procure System Sensors (PY4)
527 1.2 1.2.4.2.2.5 Procure System Sensors (PY5) Not Started C 6 1 2w 10/04/22 10/17/22 10/04/22 8:00 AM 10/17/22 4:59 PM 524FS +2d, 525 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.2.5 1 526 Procure System Sensors (PY5)
528 1.2 1.2.4.2.3 Network Controllers Started P 5 1 67d 04/15/22 07/18/22 04/15/22 8:00 AM 07/18/22 4:59 PM 0% 35.00% Green $0.00 $8,799.93 $0.00 $32,439.56 0% $3,079.97 Ian McEwen PSL_Engineer, PSL_Software Engineer Jeanne's Notes:

$5,000 for components.
$34,213 for DGHs.
1.2.4.2.3 1 527 Network Controllers
529 1.2 1.2.4.2.3.1 Plan MHP Network Box Upgrade Started C 6 1 65d 04/15/22 07/14/22 04/15/22 8:00 AM 07/14/22 4:59 PM 507 0% 70.0% Green $0.00 $8,879.86 $0.00 $8,879.86 0% $6,215.90 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.2.3.1 1 528 Plan MHP Network Box Upgrade
530 1.2 1.2.4.2.3.2 Redesign, Build and Test Network Box for PHS Not Started C 6 1 66d 04/18/22 07/18/22 04/18/22 8:00 AM 07/18/22 4:59 PM 528SS, 508FF 0% 0% Green $0.00 $14,759.77 $0.00 $14,759.77 0% $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.2.3.2 1 529 Redesign, Build and Test Network Box for PHS
531 1.2 1.2.4.2.4 Indoor Cables (sensor and network) Started C 5 1 110d 02/09/22 07/12/22 02/09/22 8:00 AM 07/12/22 4:59 PM 24% 24.00% Green $3,084.64 $12,853.87 $3,084.64 $12,853.87 24% $3,084.93 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.2.4 1 530 Indoor Cables (sensor and network)
532 1.2 1.2.4.2.5 Infrastructure Repair & Upgrade (w/sub-tasks) Started C 5 1 178d 01/26/22 09/30/22 01/26/22 8:00 AM 09/30/22 4:59 PM 530SS -10d 2% 60.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.2.5 1 531 Infrastructure Repair & Upgrade (w/sub-tasks)
533 1.2 1.2.4.2.6 Return Water Pump Noise Mitigation Subsys. Testing Not Started C 5 1 314d 04/01/22 06/14/23 04/01/22 8:00 AM 06/14/23 4:59 PM 0% 0% Green $0.00 $18,719.71 $0.00 $18,719.71 0% $0.00 Ian McEwen 1.2.4.2.6 1 532 Return Water Pump Noise Mitigation Subsys. Testing
534 1.2 1.2.4.2.7 TOS pendant I/O box Rebuild & Testing - (one finished, 7 remaining) Started C 5 1 314d 04/01/22 06/14/23 04/01/22 8:00 AM 06/14/23 4:59 PM 532FF 40% 60.0% Green $11,279.83 $28,199.57 $11,279.83 $28,199.57 40% $16,919.74 Ian McEwen 1.2.4.2.7 1 533 TOS pendant I/O box Rebuild & Testing - (one finished, 7 remaining)
535 1.2 1.2.4.2.8 TOS and DCC PLC Box Design, Build, Test (three new boxes) Started C 5 1 189d 01/11/22 09/30/22 01/11/22 8:00 AM 09/30/22 4:59 PM 11% 5.00% Yellow $9,239.86 $82,798.73 $9,239.86 $82,798.73 11% $4,139.94 Ian McEwen 1.2.4.2.8 1 534 TOS and DCC PLC Box Design, Build, Test (three new boxes)
536 1.2 1.2.4.2.9 Rodwell Control Interface Definition, - (New I/O box for this Unit) Started C 5 1 75d 11/01/21 02/11/22 11/01/21 8:00 AM 02/11/22 4:59 PM 21% 15.00% Yellow $4,799.93 $23,399.64 $4,799.93 $23,399.64 21% $3,509.95 Ian McEwen 1.2.4.2.9 1 535 Rodwell Control Interface Definition, - (New I/O box for this Unit)
537 1.2 1.2.4.2.10 Computing Equipment - TestBed Not Started P 5 1 120d 02/28/22 08/12/22 02/28/22 8:00 AM 08/12/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 1.2.4.2.10 1 536 Computing Equipment - TestBed
538 1.2 1.2.4.2.10.1 CS HW TestBed Ignition Server Testing Not Started C 6 1 24w 02/28/22 08/12/22 02/28/22 8:00 AM 08/12/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.10.1 1 537 CS HW TestBed Ignition Server Testing
539 1.2 1.2.4.2.10.2 CS HW TestBed Database Server Testing Not Started C 6 1 24w 02/28/22 08/12/22 02/28/22 8:00 AM 08/12/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.10.2 1 538 CS HW TestBed Database Server Testing
540 1.2 1.2.4.2.10.3 CS HW TestBed Peripherals Testing Not Started C 6 1 24w 02/28/22 08/12/22 02/28/22 8:00 AM 08/12/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.10.3 1 539 CS HW TestBed Peripherals Testing
541 1.2 1.2.4.2.11 Computing Equipment - Production Not Started P 5 1 103d 02/01/23 06/23/23 02/01/23 8:00 AM 06/23/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 1.2.4.2.11 1 540 Computing Equipment - Production
542 1.2 1.2.4.2.11.1 CS HW Production Ignition Servers (3x: DCC, TOS1, TOS2) Not Started C 6 1 65d 02/01/23 05/02/23 02/01/23 8:00 AM 05/02/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.11.1 1 541 CS HW Production Ignition Servers (3x: DCC, TOS1, TOS2)
543 1.2 1.2.4.2.11.2 CS HW Production Database Server (1x: DCC) Not Started C 6 1 65d 02/01/23 05/02/23 02/01/23 8:00 AM 05/02/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.11.2 1 542 CS HW Production Database Server (1x: DCC)
544 1.2 1.2.4.2.11.3 CS HW Production Peripherals (3x sets: DCC, TOS1, TOS2) Not Started C 6 1 8w 03/01/23 04/25/23 03/01/23 8:00 AM 04/25/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.11.3 1 543 CS HW Production Peripherals (3x sets: DCC, TOS1, TOS2)
545 1.2 1.2.4.2.11.4 CS HW DCC Core Switch & Security Appliance Not Started C 6 1 8w 03/15/23 05/09/23 03/15/23 8:00 AM 05/09/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.11.4 1 544 CS HW DCC Core Switch & Security Appliance
546 1.2 1.2.4.2.11.5 CS HW Production Main PLC - PLC (redundant), I/O, network, UPS, in a box (3x: DCC, TOS1, TOS2) Not Started C 6 1 60d 04/03/23 06/23/23 04/03/23 8:00 AM 06/23/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.11.5 1 545 CS HW Production Main PLC - PLC (redundant), I/O, network, UPS, in a box (3x: DCC, TOS1, TOS2)
547 1.2 1.2.4.2.12 CS HW Build Mobile DCC Not Started C 5 1 20d 04/01/22 04/28/22 04/01/22 8:00 AM 04/28/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.12 1 546 CS HW Build Mobile DCC
548 1.2 1.2.4.2.13 CS HW PY6 Resupply Not Started C 5 1 40d 03/03/24 04/25/24 03/03/24 8:00 AM 04/25/24 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.13 1 547 CS HW PY6 Resupply
549 1.2 1.2.4.2.14 CS HW PY7 Resupply Not Started C 5 1 40d 03/03/25 04/25/25 03/03/25 8:00 AM 04/25/25 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.2.4.2.14 1 548 CS HW PY7 Resupply
550 1.2 1.2.4.3 Control System Software Started P 4 1 1226d 11/04/20 07/24/25 11/04/20 8:00 AM 07/24/25 4:59 PM 34% 20.0% Yellow $0.00 $0.00 $35,159.61 $104,785.83 34% Ian McEwen 1.2.4.3 1 549 Control System Software
551 1.2 1.2.4.3.1 Motor Controllers and Readouts Should have Started C 5 1 498d 11/04/20 09/30/22 11/04/20 8:00 AM 09/30/22 4:59 PM 0% 0% Green 1st order placed $0.00 $4,799.93 $0.00 $4,799.93 0% $0.00 Ian McEwen PSL_Software Engineer 1.2.4.3.1 1 550 Motor Controllers and Readouts
552 1.2 1.2.4.3.2 Data Acquisition Started P 5 1 105d 10/01/21 02/24/22 10/01/21 8:00 AM 02/24/22 4:59 PM 58% 29.00% Red $2,399.96 $17,906.93 $35,159.61 $60,386.42 58% $5,193.01 Ian McEwen PSL_Software Engineer 1.2.4.3.2 1 551 Data Acquisition
553 1.2 1.2.4.3.2.1 DGH Programming, Testing and Cataloging Should have Started C 6 1 57d 12/08/21 02/24/22 12/08/21 8:00 AM 02/24/22 4:59 PM 553FS +5d 0% 0% Green $0.00 $9,719.85 $0.00 $9,719.85 0% $0.00 Ian McEwen PSL_Software Engineer 1.2.4.3.2.1 1 552 DGH Programming, Testing and Cataloging
554 1.2 1.2.4.3.2.2 Payout Encoder Specify, Procure, and Test Started C 6 1 43d 10/01/21 11/30/21 10/01/21 8:00 AM 11/30/21 4:59 PM 100% 40.0% Red $17,999.87 $17,999.87 $17,999.87 $17,999.87 100% $7,199.95 Ian McEwen PSL_Software Engineer 1.2.4.3.2.2 1 553 Payout Encoder Specify, Procure, and Test
555 1.2 1.2.4.3.2.3 HPP Sensor DGH Box Testing Started C 6 1 30d 10/13/21 11/23/21 10/13/21 8:00 AM 11/23/21 4:59 PM 553FF -5d 100% 70.0% Red $14,759.77 $14,759.77 $14,759.77 $14,759.77 100% $10,331.84 Ian McEwen PSL_Software Engineer 1.2.4.3.2.3 1 554 HPP Sensor DGH Box Testing
556 1.2 1.2.4.3.3 System Operator Functions - SW/HW Trial in Testbed Started P 5 1 90d 05/01/22 09/01/22 05/01/22 8:00 AM 09/01/22 4:59 PM 0% 50.0% Green $0.00 $34,799.56 $0.00 $34,799.56 0% $17,399.78 Ian McEwen PSL_Software Engineer 1.2.4.3.3 1 555 System Operator Functions - SW/HW Trial in Testbed
557 1.2 1.2.4.3.3.1 Control System Software: System Operator Functions - PY4 software/hardware trials completed Started C 6 1 90d 05/01/22 09/01/22 05/01/22 8:00 AM 09/01/22 4:59 PM 0% 50.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Software Engineer 1.2.4.3.3.1 1 556 Control System Software: System Operator Functions - PY4 software/hardware trials completed
558 1.2 1.2.4.3.4 PLC & Software Development (w/sub-tasks) Started C 5 897d 04/22/21 10/02/24 04/22/21 8:00 AM 10/02/24 4:59 PM 550FF +520d 23% 65.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.4 1 557 PLC & Software Development (w/sub-tasks)
559 1.2 1.2.4.3.5 SCADA Monitoring Software and Server Procurement Not Started C 5 151d 04/01/22 10/28/22 04/01/22 8:00 AM 10/28/22 4:59 PM 0% 0% Green $0.00 $4,799.93 $0.00 $4,799.93 0% $0.00 Ian McEwen 1.2.4.3.5 1 558 SCADA Monitoring Software and Server Procurement
560 1.2 1.2.4.3.6 SCADA Screen Development Not Started C 5 100d 10/31/22 03/17/23 10/31/22 8:00 AM 03/17/23 4:59 PM 558 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.6 1 559 SCADA Screen Development
561 1.2 1.2.4.3.7 CS SW Configure Mobile DCC Test System Not Started C 5 8w 04/29/22 06/23/22 04/29/22 8:00 AM 06/23/22 4:59 PM 546 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.7 1 560 CS SW Configure Mobile DCC Test System
562 1.2 1.2.4.3.8 CS SW TestBed Operator Screen Development (HMI/SCADA) - Develop DCC-MDS SW functionality Complete P 5 10d 10/31/22 11/11/22 10/31/22 8:00 AM 11/11/22 4:59 PM 558 0 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.8 1 561 CS SW TestBed Operator Screen Development (HMI/SCADA) - Develop DCC-MDS SW functionality
563 1.2 1.2.4.3.8.1 TestBed System Screens Complete C 6 2w 10/31/22 11/11/22 10/31/22 8:00 AM 11/11/22 4:59 PM 0 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.8.1 1 562 TestBed System Screens
564 1.2 1.2.4.3.8.2 High-Pressure Pump Control Screen Complete C 6 2w 10/31/22 11/11/22 10/31/22 8:00 AM 11/11/22 4:59 PM 0 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.8.2 1 563 High-Pressure Pump Control Screen
565 1.2 1.2.4.3.8.3 VT Pump Control Screens Complete C 6 2w 10/31/22 11/11/22 10/31/22 8:00 AM 11/11/22 4:59 PM 0 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.8.3 1 564 VT Pump Control Screens
566 1.2 1.2.4.3.8.4 Heater-based Sensor Readout Screen Complete C 6 2w 10/31/22 11/11/22 10/31/22 8:00 AM 11/11/22 4:59 PM 0 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.8.4 1 565 Heater-based Sensor Readout Screen
567 1.2 1.2.4.3.8.5 Bldg Sensor Screen Complete C 6 2w 10/31/22 11/11/22 10/31/22 8:00 AM 11/11/22 4:59 PM 0 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.8.5 1 566 Bldg Sensor Screen
568 1.2 1.2.4.3.8.6 Heater Control Screen Complete C 6 2w 10/31/22 11/11/22 10/31/22 8:00 AM 11/11/22 4:59 PM 0% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.8.6 1 567 Heater Control Screen
569 1.2 1.2.4.3.9 CS SW SES Operator Screen development Not Started P 5 387d 04/03/23 09/27/24 04/03/23 8:00 AM 09/27/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9 1 568 CS SW SES Operator Screen development
570 1.2 1.2.4.3.9.1 Develop MHP-MDS UI Screens [x4] Not Started P 6 277d 04/03/23 04/26/24 04/03/23 8:00 AM 04/26/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.1 1 569 Develop MHP-MDS UI Screens [x4]
571 1.2 1.2.4.3.9.1.1 Local-Panel MDS-specific HMI (PY5) Not Started C 7 2w 04/03/23 04/14/23 04/03/23 8:00 AM 04/14/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.1.1 1 570 Local-Panel MDS-specific HMI (PY5)
572 1.2 1.2.4.3.9.1.2 Local-Panel MDS-specific HMI (PY6) Not Started C 7 2w 04/01/24 04/12/24 04/01/24 8:00 AM 04/12/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.1.2 1 571 Local-Panel MDS-specific HMI (PY6)
573 1.2 1.2.4.3.9.1.3 DCC-based SCADA UI (PY5) Not Started C 7 2w 04/17/23 04/28/23 04/17/23 8:00 AM 04/28/23 4:59 PM 570 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.1.3 1 572 DCC-based SCADA UI (PY5)
574 1.2 1.2.4.3.9.1.4 DCC-based SCADA UI (PY6) Not Started C 7 2w 04/15/24 04/26/24 04/15/24 8:00 AM 04/26/24 4:59 PM 571 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.1.4 1 573 DCC-based SCADA UI (PY6)
575 1.2 1.2.4.3.9.2 Develop FuelSystem-MDS UI Screens Not Started P 6 279d 05/01/23 05/28/24 05/01/23 8:00 AM 05/28/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.2 1 574 Develop FuelSystem-MDS UI Screens
576 1.2 1.2.4.3.9.2.1 Local-Panel MDS-specific HMI (PY5) Not Started C 7 2w 05/01/23 05/12/23 05/01/23 8:00 AM 05/12/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.2.1 1 575 Local-Panel MDS-specific HMI (PY5)
577 1.2 1.2.4.3.9.2.2 Local-Panel MDS-specific HMI (PY6) Not Started C 7 2w 05/01/24 05/14/24 05/01/24 8:00 AM 05/14/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.2.2 1 576 Local-Panel MDS-specific HMI (PY6)
578 1.2 1.2.4.3.9.2.3 DCC-based SCADA (PY5) Not Started C 7 2w 05/15/23 05/26/23 05/15/23 8:00 AM 05/26/23 4:59 PM 575 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.2.3 1 577 DCC-based SCADA (PY5)
579 1.2 1.2.4.3.9.2.4 DCC-based SCADA (PY6) Not Started C 7 2w 05/15/24 05/28/24 05/15/24 8:00 AM 05/28/24 4:59 PM 576 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.2.4 1 578 DCC-based SCADA (PY6)
580 1.2 1.2.4.3.9.3 Develop GenSets-MDS UI Screens [x3] Not Started P 6 279d 06/01/23 06/28/24 06/01/23 8:00 AM 06/28/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.3 1 579 Develop GenSets-MDS UI Screens [x3]
581 1.2 1.2.4.3.9.3.1 Local-Panel MDS-specific HMI (PY5) Not Started C 7 2w 06/01/23 06/14/23 06/01/23 8:00 AM 06/14/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.3.1 1 580 Local-Panel MDS-specific HMI (PY5)
582 1.2 1.2.4.3.9.3.2 Local-Panel MDS-specific HMI (PY6) Not Started C 7 2w 06/03/24 06/14/24 06/03/24 8:00 AM 06/14/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.3.2 1 581 Local-Panel MDS-specific HMI (PY6)
583 1.2 1.2.4.3.9.3.3 DCC-based SCADA (PY5) Not Started C 7 2w 06/15/23 06/28/23 06/15/23 8:00 AM 06/28/23 4:59 PM 580 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.3.3 1 582 DCC-based SCADA (PY5)
584 1.2 1.2.4.3.9.3.4 DCC-based SCADA (PY6) Not Started C 7 2w 06/17/24 06/28/24 06/17/24 8:00 AM 06/28/24 4:59 PM 581 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.3.4 1 583 DCC-based SCADA (PY6)
585 1.2 1.2.4.3.9.4 Develop Rodwell System UI Screens Not Started P 6 277d 07/03/23 07/26/24 07/03/23 8:00 AM 07/26/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.4 1 584 Develop Rodwell System UI Screens
586 1.2 1.2.4.3.9.4.1 Local-Panel MDS-specific HMI (PY5) Not Started C 7 2w 07/03/23 07/14/23 07/03/23 8:00 AM 07/14/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.4.1 1 585 Local-Panel MDS-specific HMI (PY5)
587 1.2 1.2.4.3.9.4.2 Local-Panel MDS-specific HMI (PY6) Not Started C 7 2w 07/01/24 07/12/24 07/01/24 8:00 AM 07/12/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.4.2 1 586 Local-Panel MDS-specific HMI (PY6)
588 1.2 1.2.4.3.9.4.3 DCC-based SCADA (PY5) Not Started C 7 2w 07/17/23 07/28/23 07/17/23 8:00 AM 07/28/23 4:59 PM 585 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.4.3 1 587 DCC-based SCADA (PY5)
589 1.2 1.2.4.3.9.4.4 DCC-based SCADA (PY6) Not Started C 7 2w 07/15/24 07/26/24 07/15/24 8:00 AM 07/26/24 4:59 PM 586 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.4.4 1 588 DCC-based SCADA (PY6)
590 1.2 1.2.4.3.9.5 Develop HPP-MDS UI Screens Not Started P 6 279d 08/01/23 08/28/24 08/01/23 8:00 AM 08/28/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.5 1 589 Develop HPP-MDS UI Screens
591 1.2 1.2.4.3.9.5.1 Local-Panel MDS-specific HMI (PY5) Not Started C 7 2w 08/01/23 08/14/23 08/01/23 8:00 AM 08/14/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.5.1 1 590 Local-Panel MDS-specific HMI (PY5)
592 1.2 1.2.4.3.9.5.2 Local-Panel MDS-specific HMI (PY6) Not Started C 7 2w 08/01/24 08/14/24 08/01/24 8:00 AM 08/14/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.5.2 1 591 Local-Panel MDS-specific HMI (PY6)
593 1.2 1.2.4.3.9.5.3 DCC-based SCADA (PY5) Not Started C 7 2w 08/15/23 08/28/23 08/15/23 8:00 AM 08/28/23 4:59 PM 590 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.5.3 1 592 DCC-based SCADA (PY5)
594 1.2 1.2.4.3.9.5.4 DCC-based SCADA (PY6) Not Started C 7 2w 08/15/24 08/28/24 08/15/24 8:00 AM 08/28/24 4:59 PM 591 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.5.4 1 593 DCC-based SCADA (PY6)
595 1.2 1.2.4.3.9.6 Develop PHS-MDS UI Screens Not Started P 6 278d 09/01/23 09/27/24 09/01/23 8:00 AM 09/27/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.6 1 594 Develop PHS-MDS UI Screens
596 1.2 1.2.4.3.9.6.1 Local-Panel MDS-specific HMI (PY5) Not Started C 7 2w 09/01/23 09/14/23 09/01/23 8:00 AM 09/14/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.6.1 1 595 Local-Panel MDS-specific HMI (PY5)
597 1.2 1.2.4.3.9.6.2 Local-Panel MDS-specific HMI (PY6) Not Started C 7 2w 09/02/24 09/13/24 09/02/24 8:00 AM 09/13/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.6.2 1 596 Local-Panel MDS-specific HMI (PY6)
598 1.2 1.2.4.3.9.6.3 DCC-based SCADA (PY5) Not Started C 7 2w 09/15/23 09/28/23 09/15/23 8:00 AM 09/28/23 4:59 PM 595 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.6.3 1 597 DCC-based SCADA (PY5)
599 1.2 1.2.4.3.9.6.4 DCC-based SCADA (PY6) Not Started C 7 2w 09/16/24 09/27/24 09/16/24 8:00 AM 09/27/24 4:59 PM 596 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.9.6.4 1 598 DCC-based SCADA (PY6)
600 1.2 1.2.4.3.10 CS SW TOS Operator Screen Development Not Started P 5 379d 05/01/23 10/15/24 05/01/23 8:00 AM 10/15/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10 1 599 CS SW TOS Operator Screen Development
601 1.2 1.2.4.3.10.1 SCADA - DrillHead (PY5) Not Started C 6 3w 05/01/23 05/19/23 05/01/23 8:00 AM 05/19/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.1 1 600 SCADA - DrillHead (PY5)
602 1.2 1.2.4.3.10.2 SCADA - DrillHead (PY6) Not Started C 6 3w 05/01/24 05/21/24 05/01/24 8:00 AM 05/21/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.2 1 601 SCADA - DrillHead (PY6)
603 1.2 1.2.4.3.10.3 SCADA - Drill_Settings (PY5) Not Started C 6 3w 05/22/23 06/09/23 05/22/23 8:00 AM 06/09/23 4:59 PM 600 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.3 1 602 SCADA - Drill_Settings (PY5)
604 1.2 1.2.4.3.10.4 SCADA - Drill_Settings (PY6) Not Started C 6 3w 05/22/24 06/11/24 05/22/24 8:00 AM 06/11/24 4:59 PM 601 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.4 1 603 SCADA - Drill_Settings (PY6)
605 1.2 1.2.4.3.10.5 SCADA - Drilling_Drill Control (PY5) Not Started C 6 3w 06/12/23 06/30/23 06/12/23 8:00 AM 06/30/23 4:59 PM 602 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.5 1 604 SCADA - Drilling_Drill Control (PY5)
606 1.2 1.2.4.3.10.6 SCADA - Drilling_Drill Control (PY6) Not Started C 6 3w 06/12/24 07/02/24 06/12/24 8:00 AM 07/02/24 4:59 PM 603 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.6 1 605 SCADA - Drilling_Drill Control (PY6)
607 1.2 1.2.4.3.10.7 SCADA - Drilling_Cable Level Wind (PY5) Not Started C 6 3w 07/03/23 07/21/23 07/03/23 8:00 AM 07/21/23 4:59 PM 604 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.7 1 606 SCADA - Drilling_Cable Level Wind (PY5)
608 1.2 1.2.4.3.10.8 SCADA - Drilling_Cable Level Wind (PY6) Not Started C 6 3w 07/03/24 07/23/24 07/03/24 8:00 AM 07/23/24 4:59 PM 605 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.8 1 607 SCADA - Drilling_Cable Level Wind (PY6)
609 1.2 1.2.4.3.10.9 SCADA - Drilling_Hose Level Wind (PY5) Not Started C 6 3w 07/24/23 08/11/23 07/24/23 8:00 AM 08/11/23 4:59 PM 606 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.9 1 608 SCADA - Drilling_Hose Level Wind (PY5)
610 1.2 1.2.4.3.10.10 SCADA - Drilling_Hose Level Wind (PY6) Not Started C 6 3w 07/24/24 08/13/24 07/24/24 8:00 AM 08/13/24 4:59 PM 607 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.10 1 609 SCADA - Drilling_Hose Level Wind (PY6)
611 1.2 1.2.4.3.10.11 SCADA - Return Water Pump (PY5) Not Started C 6 3w 08/14/23 09/01/23 08/14/23 8:00 AM 09/01/23 4:59 PM 608 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.11 1 610 SCADA - Return Water Pump (PY5)
612 1.2 1.2.4.3.10.12 SCADA - Return Water Pump (PY6) Not Started C 6 3w 08/14/24 09/03/24 08/14/24 8:00 AM 09/03/24 4:59 PM 609 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.12 1 611 SCADA - Return Water Pump (PY6)
613 1.2 1.2.4.3.10.13 SCADA - Deployment - Cable (PY5) Not Started C 6 3w 09/04/23 09/22/23 09/04/23 8:00 AM 09/22/23 4:59 PM 610 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.13 1 612 SCADA - Deployment - Cable (PY5)
614 1.2 1.2.4.3.10.14 SCADA - Deployment - Cable (PY6) Not Started C 6 3w 09/04/24 09/24/24 09/04/24 8:00 AM 09/24/24 4:59 PM 611 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.14 1 613 SCADA - Deployment - Cable (PY6)
615 1.2 1.2.4.3.10.15 SCADA - Deployment Settings (PY5) Not Started C 6 3w 09/25/23 10/13/23 09/25/23 8:00 AM 10/13/23 4:59 PM 612 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.15 1 614 SCADA - Deployment Settings (PY5)
616 1.2 1.2.4.3.10.16 SCADA - Deployment Settings (PY6) Not Started C 6 3w 09/25/24 10/15/24 09/25/24 8:00 AM 10/15/24 4:59 PM 613 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.10.16 1 615 SCADA - Deployment Settings (PY6)
617 1.2 1.2.4.3.11 CS SW dB Design, my SQL Not Started P 5 319d 04/05/23 06/27/24 04/05/23 8:00 AM 06/27/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.11 1 616 CS SW dB Design, my SQL
618 1.2 1.2.4.3.11.1 Build DCC dB schema (PY5) Not Started C 6 4w 04/05/23 05/02/23 04/05/23 8:00 AM 05/02/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.11.1 1 617 Build DCC dB schema (PY5)
619 1.2 1.2.4.3.11.2 Build DCC dB schema (PY6) Not Started C 6 4w 04/05/24 05/02/24 04/05/24 8:00 AM 05/02/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.11.2 1 618 Build DCC dB schema (PY6)
620 1.2 1.2.4.3.11.3 Build Drill dB schema (PY5) Not Started C 6 4w 05/03/23 05/30/23 05/03/23 8:00 AM 05/30/23 4:59 PM 617 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.11.3 1 619 Build Drill dB schema (PY5)
621 1.2 1.2.4.3.11.4 Build Drill dB schema (PY6) Not Started C 6 4w 05/03/24 05/30/24 05/03/24 8:00 AM 05/30/24 4:59 PM 618 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.11.4 1 620 Build Drill dB schema (PY6)
622 1.2 1.2.4.3.11.5 Build Deploy dB schema (PY5) Not Started C 6 4w 05/31/23 06/27/23 05/31/23 8:00 AM 06/27/23 4:59 PM 619 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.11.5 1 621 Build Deploy dB schema (PY5)
623 1.2 1.2.4.3.11.6 Build Deploy dB schema (PY6) Not Started C 6 4w 05/31/24 06/27/24 05/31/24 8:00 AM 06/27/24 4:59 PM 620 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.11.6 1 622 Build Deploy dB schema (PY6)
624 1.2 1.2.4.3.12 CS SW Standup Production Computing Hardware, Configure, Verify before Shipment (3x systems) (PY6) Not Started C 5 20w 03/01/24 07/18/24 03/01/24 8:00 AM 07/18/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.12 1 623 CS SW Standup Production Computing Hardware, Configure, Verify before Shipment (3x systems) (PY6)
625 1.2 1.2.4.3.13 CS SW MDS-specific HMI Refinement (PY7) Not Started C 5 16w 04/05/25 07/24/25 04/05/25 8:00 AM 07/24/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.13 1 624 CS SW MDS-specific HMI Refinement (PY7)
626 1.2 1.2.4.3.14 CS SW DCC-based SCADA Refinement (PY7) Not Started C 5 16w 04/05/25 07/24/25 04/05/25 8:00 AM 07/24/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.14 1 625 CS SW DCC-based SCADA Refinement (PY7)
627 1.2 1.2.4.3.15 CS SW TOS-based SCADA Refinement (PY7) Not Started C 5 16w 04/05/25 07/24/25 04/05/25 8:00 AM 07/24/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.15 1 626 CS SW TOS-based SCADA Refinement (PY7)
628 1.2 1.2.4.3.16 CS SW dB Refinement (PY7) Not Started C 5 16w 04/05/25 07/24/25 04/05/25 8:00 AM 07/24/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.16 1 627 CS SW dB Refinement (PY7)
629 1.2 1.2.4.4 Motor Drives Started P 4 1 840d 03/09/22 06/04/25 03/09/22 8:00 AM 06/04/25 4:59 PM 1% 16.00% Green $0.00 $0.00 $599.99 $51,239.21 1% Ian McEwen 1.2.4.4 1 628 Motor Drives
630 1.2 1.2.4.4.1 Requirements, Functional Not Started C 5 1 110d 04/14/22 09/14/22 04/14/22 8:00 AM 09/14/22 4:59 PM 0% 0% Green This activity was started earlier than planned $0.00 $28,799.56 $0.00 $28,799.56 0% $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.4.1 1 629 Requirements, Functional
631 1.2 1.2.4.4.2 Requirements, Electrical Complete C 5 1 120d 05/26/22 11/09/22 05/26/22 8:00 AM 11/09/22 4:59 PM 629SS +30d 0% 100% Gray Need to define braking resistors and filters $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.4.2 1 630 Requirements, Electrical
632 1.2 1.2.4.4.3 Specify and Procure Not Started C 5 1 35d 08/05/22 09/22/22 08/05/22 8:00 AM 09/22/22 4:59 PM 0% 0% Green working on final requirements spring 2020 $0.00 $3,839.94 $0.00 $3,839.94 0% $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.4.3 1 631 Specify and Procure
633 1.2 1.2.4.4.4 Programming and Testing at PSL Started C 5 1 776d 06/07/22 06/04/25 06/07/22 8:00 AM 06/04/25 4:59 PM 631SS -43d 7% 7.00% Green $599.99 $8,999.86 $599.99 $8,999.86 7% $629.99 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.4.4 1 632 Programming and Testing at PSL
634 1.2 1.2.4.4.5 Plan Installations of New Motor Drives in Former Unico Locations Not Started C 5 1 45d 03/09/22 05/10/22 03/09/22 8:00 AM 05/10/22 4:59 PM 0% 0% Green $0.00 $9,599.85 $0.00 $9,599.85 0% $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.4.5 1 633 Plan Installations of New Motor Drives in Former Unico Locations
635 1.2 1.2.4.5 E-Stop System Started P 4 1 1143d 01/29/21 06/25/25 01/29/21 8:00 AM 06/25/25 4:59 PM 21% 45.00% Green $0.00 $0.00 $14,399.78 $67,558.96 21% Ian McEwen 1.2.4.5 1 634 E-Stop System
636 1.2 1.2.4.5.1 Evaluate EHWD system Complete C 5 1 60d 01/29/21 04/22/21 01/29/21 8:00 AM 04/22/21 4:59 PM 100% 100% Gray delayed, limited access to retro $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.5.1 1 635 Evaluate EHWD system
637 1.2 1.2.4.5.2 Define Requirements Started C 5 1 79d 10/01/21 01/19/22 10/01/21 8:00 AM 01/19/22 4:59 PM 50% 35.00% Yellow Requirements definition and redesign underway $4,799.93 $9,599.85 $4,799.93 $9,599.85 50% $3,359.95 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.5.2 1 636 Define Requirements
638 1.2 1.2.4.5.3 TOS E-stop Box Analysis, Documentation Updates Started C 5 1 71d 12/16/21 03/24/22 12/16/21 8:00 AM 03/24/22 4:59 PM 639SS +54d 0% 50.0% Green $0.00 $12,239.81 $0.00 $12,239.81 0% $6,119.91 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.5.3 1 637 TOS E-stop Box Analysis, Documentation Updates
639 1.2 1.2.4.5.4 System E-stop Controller Redesign, Build, Test Started C 5 1 90d 12/14/21 04/18/22 12/14/21 8:00 AM 04/18/22 4:59 PM 0% 50.0% Green $0.00 $21,119.68 $0.00 $21,119.68 0% Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.5.4 1 638 System E-stop Controller Redesign, Build, Test
640 1.2 1.2.4.5.5 TOS E-stop Controller Redesign, Build, Test Started C 5 1 102d 10/01/21 02/21/22 10/01/21 8:00 AM 02/21/22 4:59 PM 39% 50.0% Green $9,599.85 $24,599.62 $9,599.85 $24,599.62 39% Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.5.5 1 639 TOS E-stop Controller Redesign, Build, Test
641 1.2 1.2.4.5.6 E-Stop Resupply (PY6) Not Started C 5 8w 05/01/24 06/25/24 05/01/24 8:00 AM 06/25/24 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 1.2.4.5.6 1 640 E-Stop Resupply (PY6)
642 1.2 1.2.4.5.7 E-Stop Resupply (PY7) Not Started C 5 8w 05/01/25 06/25/25 05/01/25 8:00 AM 06/25/25 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 1.2.4.5.7 1 641 E-Stop Resupply (PY7)
643 1.2 1.2.4.6 Drill Control Center Started P 4 1 586d 04/29/21 07/27/23 04/29/21 8:00 AM 07/27/23 4:59 PM 0% 24.00% Green $0.00 $0.00 $0.00 $6,899.96 0% Ian McEwen 1.2.4.6 1 642 Drill Control Center
644 1.2 1.2.4.6.1 Computing System Started C 5 1 586d 04/29/21 07/27/23 04/29/21 8:00 AM 07/27/23 4:59 PM 34% 23.00% Yellow delayed $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer Computers, racks, monitors, hardware, with backup system 1.2.4.6.1 1 643 Computing System
645 1.2 1.2.4.6.2 Electrical Improvements - Heater Upgrade Design and Procure Started C 5 1 15d 08/15/22 09/02/22 08/15/22 8:00 AM 09/02/22 4:59 PM 0 40.0% Green $0.00 $6,899.96 $0.00 $6,899.96 0% Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.6.2 1 644 Electrical Improvements - Heater Upgrade Design and Procure
646 1.2 1.2.4.6.3 Update Workspace (desk, chairs), Procure Printer & Accessories Started C 5 1 30d 02/01/23 03/14/23 02/01/23 8:00 AM 03/14/23 4:59 PM 0% 40.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.4.6.3 1 645 Update Workspace (desk, chairs), Procure Printer & Accessories
647 1.2 1.2.4.7 Outdoor Cables Should have Started P 4 1 838d 01/15/22 04/09/25 01/15/22 8:00 AM 04/09/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $51,679.62 0% Ian McEwen 1.2.4.7 1 646 Outdoor Cables
648 1.2 1.2.4.7.1 Evaluate/Inventory SES & SES to TOS Cables - Signal Should have Started C 5 1 30d 01/15/22 02/24/22 01/15/22 8:00 AM 02/24/22 4:59 PM 0% 0% Green inventory consolidation from 19/20 season in progress, waiting on access to 19/20 retro $0.00 $4,799.93 $0.00 $4,799.93 0% $0.00 Ian McEwen 1.2.4.7.1 1 647 Evaluate/Inventory SES & SES to TOS Cables - Signal
649 1.2 1.2.4.7.2 Design and Procure Replacement Components - Signal Not Started C 5 1 23d 02/25/22 03/29/22 02/25/22 8:00 AM 03/29/22 4:59 PM 647 0% 0% Green $0.00 $37,159.85 $0.00 $37,159.85 0% $0.00 Ian McEwen 1.2.4.7.2 1 648 Design and Procure Replacement Components - Signal
650 1.2 1.2.4.7.3 Fabricate and Test SES & SES to TOS Cables - Signal Not Started C 5 1 305d 05/27/22 07/27/23 05/27/22 8:00 AM 07/27/23 4:59 PM 648FS +42d 0 0% Green inventory consolidation from 19/20 season in progress, waiting on access to 19/20 retro $0.00 $9,719.85 $0.00 $9,719.85 0% Ian McEwen 1.2.4.7.3 1 649 Fabricate and Test SES & SES to TOS Cables - Signal
651 1.2 1.2.4.7.4 CS Cabling Resupply (PY6) Not Started C 5 1 2w 03/27/24 04/09/24 03/27/24 8:00 AM 04/09/24 4:59 PM 0 0% Green inventory consolidation from 19/20 season in progress, waiting on access to 19/20 retro $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.7.4 1 650 CS Cabling Resupply (PY6)
652 1.2 1.2.4.7.5 CS Cabling Resupply (PY7) Not Started C 5 1 2w 03/27/25 04/09/25 03/27/25 8:00 AM 04/09/25 4:59 PM 0% 0% Green inventory consolidation from 19/20 season in progress, waiting on access to 19/20 retro $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.7.5 1 651 CS Cabling Resupply (PY7)
653 1.2 1.2.4.8 Controls Subsystems (PY5-PY8) Should have Started P 4 1 672d 01/03/22 08/02/24 01/03/22 8:00 AM 08/02/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8 1 652 Controls Subsystems (PY5-PY8)
654 1.2 1.2.4.8.1 CS MHPs Not Started P 5 1 250d 05/02/22 04/14/23 05/02/22 8:00 AM 04/14/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.1 1 653 CS MHPs
655 1.2 1.2.4.8.1.1 CS MHP HW1: Network and Network Box Refurb & Config Not Started P 6 1 60d 05/02/22 07/22/22 05/02/22 8:00 AM 07/22/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.1.1 1 654 CS MHP HW1: Network and Network Box Refurb & Config
656 1.2 1.2.4.8.1.1.1 Program and catalog replacement flow and control DGH modules for all MHP heaters Not Started C 7 1 4w 05/02/22 05/27/22 05/02/22 8:00 AM 05/27/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.2.3.1 - 80,0,0 1.2.4.8.1.1.1 1 655 Program and catalog replacement flow and control DGH modules for all MHP heaters
657 1.2 1.2.4.8.1.1.2 Procure and configure PLC-to-DGH gateways, develop instructions for field installation and test Not Started C 7 1 4w 05/30/22 06/24/22 05/30/22 8:00 AM 06/24/22 4:59 PM 655 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.2.3.1 - 40,0,3600 1.2.4.8.1.1.2 1 656 Procure and configure PLC-to-DGH gateways, develop instructions for field installation and test
658 1.2 1.2.4.8.1.1.3 Select and procure backup power supplies for MHP network boxes Not Started C 7 1 4w 06/27/22 07/22/22 06/27/22 8:00 AM 07/22/22 4:59 PM 656 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.2.3.1 - 8,0,800 1.2.4.8.1.1.3 1 657 Select and procure backup power supplies for MHP network boxes
659 1.2 1.2.4.8.1.2 CS MHP HW2-3: Heater Controller Temp Displays & Controllers Not Started P 6 1 140d 10/03/22 04/14/23 10/03/22 8:00 AM 04/14/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.1.2 1 658 CS MHP HW2-3: Heater Controller Temp Displays & Controllers
660 1.2 1.2.4.8.1.2.1 Procure sample temperature display and digital thermostat, install in test bed heater, test Not Started C 7 1 6w 10/03/22 11/11/22 10/03/22 8:00 AM 11/11/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.2.1.3 - 32,0,300 1.2.4.8.1.2.1 1 659 Procure sample temperature display and digital thermostat, install in test bed heater, test
661 1.2 1.2.4.8.1.2.2 Select and procure temperature display units for heater controls, conversion hardware Not Started C 7 1 6w 11/14/22 12/23/22 11/14/22 8:00 AM 12/23/22 4:59 PM 659 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.2.1.3 - 32,0,2400 1.2.4.8.1.2.2 1 660 Select and procure temperature display units for heater controls, conversion hardware
662 1.2 1.2.4.8.1.2.3 Replace temperature display units, remove RTD DGHs, transfer net connections, test Not Started C 7 1 8w 12/26/22 02/17/23 12/26/22 8:00 AM 02/17/23 4:59 PM 660 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.2.1.3 - 40,160,0 1.2.4.8.1.2.3 1 661 Replace temperature display units, remove RTD DGHs, transfer net connections, test
663 1.2 1.2.4.8.1.2.4 Select and procure digital thermostats for heater controls, conversion hardware Not Started C 7 1 6w 02/20/23 03/31/23 02/20/23 8:00 AM 03/31/23 4:59 PM 661 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.2.1.3 - 32,0,3200 1.2.4.8.1.2.4 1 662 Select and procure digital thermostats for heater controls, conversion hardware
664 1.2 1.2.4.8.1.2.5 Write thermostat field replacement procedure Not Started C 7 1 2w 04/03/23 04/14/23 04/03/23 8:00 AM 04/14/23 4:59 PM 662 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.2.1.3 - 24,0,0 1.2.4.8.1.2.5 1 663 Write thermostat field replacement procedure
665 1.2 1.2.4.8.1.3 CS MHP HW4-6: Maintain Documentation, Prepare Field Plans Not Started P 6 1 80d 11/01/22 02/20/23 11/01/22 8:00 AM 02/20/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.1.3 1 664 CS MHP HW4-6: Maintain Documentation, Prepare Field Plans
666 1.2 1.2.4.8.1.3.1 Write rewiring and test instructions for MHP E-stop boxes (fixes switch contact selections made in Gen 1) Not Started C 7 1 4w 11/01/22 11/28/22 11/01/22 8:00 AM 11/28/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking 1.2.4.8.1.3.1 1 665 Write rewiring and test instructions for MHP E-stop boxes (fixes switch contact selections made in Gen 1)
667 1.2 1.2.4.8.1.3.2 Write test procedures for dry heater tests Not Started C 7 1 4w 11/29/22 12/26/22 11/29/22 8:00 AM 12/26/22 4:59 PM 665 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking 1.2.4.8.1.3.2 1 666 Write test procedures for dry heater tests
668 1.2 1.2.4.8.1.3.3 Assemble equipment to test flow meters (excitation coil and portable pulse generator) Not Started C 7 1 4w 12/27/22 01/23/23 12/27/22 8:00 AM 01/23/23 4:59 PM 666 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking 1.2.4.8.1.3.3 1 667 Assemble equipment to test flow meters (excitation coil and portable pulse generator)
669 1.2 1.2.4.8.1.3.4 Write flow meter test procedure and assemble test kit Not Started C 7 1 4w 01/24/23 02/20/23 01/24/23 8:00 AM 02/20/23 4:59 PM 667 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking 1.2.4.8.1.3.4 1 668 Write flow meter test procedure and assemble test kit
670 1.2 1.2.4.8.1.4 CS MHP HW7: Select and procure MHP network switches (4), mount in protective enclosure Not Started C 6 1 6w 06/01/22 07/12/22 06/01/22 8:00 AM 07/12/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.2.3.1 - 24,40,3200 1.2.4.8.1.4 1 669 CS MHP HW7: Select and procure MHP network switches (4), mount in protective enclosure
671 1.2 1.2.4.8.1.5 CS MHP SW: Develop PLC-MHP MDS SW Functionality [Entire MHP system] Not Started P 6 1 198d 07/13/22 04/14/23 07/13/22 8:00 AM 04/14/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.1.5 1 670 CS MHP SW: Develop PLC-MHP MDS SW Functionality [Entire MHP system]
672 1.2 1.2.4.8.1.5.1 Develop heater-based sensor readout; (heater temp/flow manifold pressures Not Started C 7 1 3w 01/02/23 01/20/23 01/02/23 8:00 AM 01/20/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.4 relationship. Deliverable supports FS1 tasking. 1.2.4.8.1.5.1 1 671 Develop heater-based sensor readout; (heater temp/flow manifold pressures
673 1.2 1.2.4.8.1.5.2 Develop environmental sensor readout; (bldg temps, smoke, e-stop) Not Started C 7 1 3w 01/23/23 02/10/23 01/23/23 8:00 AM 02/10/23 4:59 PM 671 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.4 relationship. Deliverable supports FS1 tasking. 1.2.4.8.1.5.2 1 672 Develop environmental sensor readout; (bldg temps, smoke, e-stop)
674 1.2 1.2.4.8.1.5.3 Develop heater control; (ON/OFF, Thermostat setpoint) Not Started C 7 1 3w 02/13/23 03/03/23 02/13/23 8:00 AM 03/03/23 4:59 PM 672 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.4 relationship. Deliverable supports FS1 tasking. 1.2.4.8.1.5.3 1 673 Develop heater control; (ON/OFF, Thermostat setpoint)
675 1.2 1.2.4.8.1.5.4 Configure network switch Not Started C 7 1 2w 07/13/22 07/26/22 07/13/22 8:00 AM 07/26/22 4:59 PM 669 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.2.3.1 relationship 1.2.4.8.1.5.4 1 674 Configure network switch
676 1.2 1.2.4.8.1.5.5 Configure RTA gateway to M-DGH interface Not Started C 7 1 2w 07/27/22 08/09/22 07/27/22 8:00 AM 08/09/22 4:59 PM 656, 674 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.2.3.1 relationship 1.2.4.8.1.5.5 1 675 Configure RTA gateway to M-DGH interface
677 1.2 1.2.4.8.1.5.6 Configure M-DGHs Not Started C 7 1 2w 08/10/22 08/23/22 08/10/22 8:00 AM 08/23/22 4:59 PM 675 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.2.3.1 relationship 1.2.4.8.1.5.6 1 676 Configure M-DGHs
678 1.2 1.2.4.8.1.5.7 Implement interlocks Not Started C 7 1 4w 03/06/23 03/31/23 03/06/23 8:00 AM 03/31/23 4:59 PM 673, 676 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.4 relationship. Deliverable supports FS1 tasking. 1.2.4.8.1.5.7 1 677 Implement interlocks
679 1.2 1.2.4.8.1.5.8 Document Subsystem Not Started C 7 1 2w 04/03/23 04/14/23 04/03/23 8:00 AM 04/14/23 4:59 PM 677 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.1.4 relationship. Deliverable supports FS1 tasking. 1.2.4.8.1.5.8 1 678 Document Subsystem
680 1.2 1.2.4.8.1.6 CS MHP HW ready to pack for shipment Not Started C 6 1 1 0 04/14/23 04/14/23 04/14/23 4:59 PM 04/14/23 4:59 PM 654, 658, 669, 674, 675, 676 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Vessel 2022-DNF 1.2.4.8.1.6 1 679 CS MHP HW ready to pack for shipment
681 1.2 1.2.4.8.2 CS PHS & WT2 Not Started P 5 1 300d 05/01/22 06/22/23 05/01/22 8:00 AM 06/22/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2 1 680 CS PHS & WT2
682 1.2 1.2.4.8.2.1 CS PHS HW1: Motor Drive Config & Install Kits Not Started P 6 1 80d 07/01/22 10/20/22 07/01/22 8:00 AM 10/20/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.1 1 681 CS PHS HW1: Motor Drive Config & Install Kits
683 1.2 1.2.4.8.2.1.1 Procure motor drives (2 transfer pumps) Not Started C 7 1 8w 07/01/22 08/25/22 07/01/22 8:00 AM 08/25/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.4.3 - 8,0,3000 1.2.4.8.2.1.1 1 682 Procure motor drives (2 transfer pumps)
684 1.2 1.2.4.8.2.1.2 Configure VFDs with accessories, connection pigtails, document Not Started C 7 1 6w 08/26/22 10/06/22 08/26/22 8:00 AM 10/06/22 4:59 PM 682 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.4.5 - 40,8,0 1.2.4.8.2.1.2 1 683 Configure VFDs with accessories, connection pigtails, document
685 1.2 1.2.4.8.2.1.3 Develop VFD installation strategy & document, procure materials Not Started C 7 1 2w 10/07/22 10/20/22 10/07/22 8:00 AM 10/20/22 4:59 PM 683 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.1.3 1 684 Develop VFD installation strategy & document, procure materials
686 1.2 1.2.4.8.2.2 CS PHS HW2: Estop Box Re-outfitting Not Started P 6 1 40d 06/01/22 07/26/22 06/01/22 8:00 AM 07/26/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.2 1 685 CS PHS HW2: Estop Box Re-outfitting
687 1.2 1.2.4.8.2.2.1 Select and procure E-stop relays Not Started C 7 1 4w 06/01/22 06/28/22 06/01/22 8:00 AM 06/28/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.5.4 - 4,0,200 1.2.4.8.2.2.1 1 686 Select and procure E-stop relays
688 1.2 1.2.4.8.2.2.2 Develop and document E-stop box rewiring instructions Not Started C 7 1 4w 06/29/22 07/26/22 06/29/22 8:00 AM 07/26/22 4:59 PM 686 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.5.4 - 4,0,0 1.2.4.8.2.2.2 1 687 Develop and document E-stop box rewiring instructions
689 1.2 1.2.4.8.2.3 CS PHS HW3: Network Box Refurb & Config Not Started P 6 1 100d 09/01/22 01/18/23 09/01/22 8:00 AM 01/18/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.3 1 688 CS PHS HW3: Network Box Refurb & Config
690 1.2 1.2.4.8.2.3.1 Select and procure PHS network switch, mount in protective enclosure Not Started C 7 1 4w 09/01/22 09/28/22 09/01/22 8:00 AM 09/28/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.2.3.2 - 16,32,1200 1.2.4.8.2.3.1 1 689 Select and procure PHS network switch, mount in protective enclosure
691 1.2 1.2.4.8.2.3.2 Select and procure new power supplies for the network box, procure one RS-485 gateway Not Started C 7 1 4w 09/29/22 10/26/22 09/29/22 8:00 AM 10/26/22 4:59 PM 689 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.3.2 1 690 Select and procure new power supplies for the network box, procure one RS-485 gateway
692 1.2 1.2.4.8.2.3.3 Redesign and rebuild PHS network box with new I/O, document as-built configuration Not Started C 7 1 4w 10/27/22 11/23/22 10/27/22 8:00 AM 11/23/22 4:59 PM 690 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.3.3 1 691 Redesign and rebuild PHS network box with new I/O, document as-built configuration
693 1.2 1.2.4.8.2.3.4 Indicate where approximately 20 sensor and network cables terminate in PHS and document config. plans Not Started C 7 1 4w 11/24/22 12/21/22 11/24/22 8:00 AM 12/21/22 4:59 PM 691 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.3.4 1 692 Indicate where approximately 20 sensor and network cables terminate in PHS and document config. plans
694 1.2 1.2.4.8.2.3.5 Configure heater-mounted DGH modules, develop and document DGH installation and test plans Not Started C 7 1 4w 12/22/22 01/18/23 12/22/22 8:00 AM 01/18/23 4:59 PM 692 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.3.5 1 693 Configure heater-mounted DGH modules, develop and document DGH installation and test plans
695 1.2 1.2.4.8.2.4 CS PHS HW4: New E-stop Slap Switch & Box for Outdoor Location Not Started C 6 1 2w 01/19/23 02/01/23 01/19/23 8:00 AM 02/01/23 4:59 PM 693 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.4 1 694 CS PHS HW4: New E-stop Slap Switch & Box for Outdoor Location
696 1.2 1.2.4.8.2.5 CS PHS HW5: Develop heater test procedures, configure test tools, document test plans Not Started C 6 1 4w 02/02/23 03/01/23 02/02/23 8:00 AM 03/01/23 4:59 PM 694 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.5 1 695 CS PHS HW5: Develop heater test procedures, configure test tools, document test plans
697 1.2 1.2.4.8.2.6 CS PHS HW6: WT Level Sensors Not Started P 6 1 90d 05/01/22 09/01/22 05/01/22 8:00 AM 09/01/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.6 1 696 CS PHS HW6: WT Level Sensors
698 1.2 1.2.4.8.2.6.1 Select and procure new tank level and temperature sensors Not Started C 7 1 2w 05/01/22 05/12/22 05/01/22 8:00 AM 05/12/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.2.2.2 - 32,0,1200 1.2.4.8.2.6.1 1 697 Select and procure new tank level and temperature sensors
699 1.2 1.2.4.8.2.6.2 Install one level sensors in the test bed and operate over some period Not Started C 7 1 8w 05/13/22 07/07/22 05/13/22 8:00 AM 07/07/22 4:59 PM 697 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.2.2.2 - 24,0,600 1.2.4.8.2.6.2 1 698 Install one level sensors in the test bed and operate over some period
700 1.2 1.2.4.8.2.6.3 Test level sensor tolerance of environmental conditions and system noise Not Started C 7 1 2w 07/08/22 07/21/22 07/08/22 8:00 AM 07/21/22 4:59 PM 698 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.2.2.2 - 40,8,0 1.2.4.8.2.6.3 1 699 Test level sensor tolerance of environmental conditions and system noise
701 1.2 1.2.4.8.2.6.4 Design and build cables for tank sensors Not Started C 7 1 6w 07/22/22 09/01/22 07/22/22 8:00 AM 09/01/22 4:59 PM 699 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in 1.2.4.2.2.2 - 16,32,400 1.2.4.8.2.6.4 1 700 Design and build cables for tank sensors
702 1.2 1.2.4.8.2.7 CS PHS HW7-8: Maintain Documentation, Prepare Field Plans Not Started P 6 1 60d 04/01/23 06/22/23 04/01/23 8:00 AM 06/22/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.7 1 701 CS PHS HW7-8: Maintain Documentation, Prepare Field Plans
703 1.2 1.2.4.8.2.7.1 Develop and document test plans for all PHS system components Not Started C 7 1 8w 04/01/23 05/25/23 04/01/23 8:00 AM 05/25/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.2.7.1 1 702 Develop and document test plans for all PHS system components
704 1.2 1.2.4.8.2.7.2 Review Gen-1 docs, identify where sensor connections terminated, plan for reconnection and test Not Started C 7 1 4w 05/26/23 06/22/23 05/26/23 8:00 AM 06/22/23 4:59 PM 702 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.2.7.2 1 703 Review Gen-1 docs, identify where sensor connections terminated, plan for reconnection and test
705 1.2 1.2.4.8.2.8 Develop PLC-PHS MDS SW Functionality Not Started P 6 1 172d 09/29/22 05/26/23 09/29/22 8:00 AM 05/26/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.8 1 704 Develop PLC-PHS MDS SW Functionality
706 1.2 1.2.4.8.2.8.1 Develop heater-based sensor readout; (heater temp/flow manifold pressures) Not Started C 7 1 4w 01/02/23 01/27/23 01/02/23 8:00 AM 01/27/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.2.8.1 1 705 Develop heater-based sensor readout; (heater temp/flow manifold pressures)
707 1.2 1.2.4.8.2.8.2 Develop environmental sensor readout; (bldg temps, smoke, e-stop) Not Started C 7 1 2w 01/30/23 02/10/23 01/30/23 8:00 AM 02/10/23 4:59 PM 705 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.2.8.2 1 706 Develop environmental sensor readout; (bldg temps, smoke, e-stop)
708 1.2 1.2.4.8.2.8.3 Develop water tank sensors readout Not Started C 7 1 3w 02/13/23 03/03/23 02/13/23 8:00 AM 03/03/23 4:59 PM 706 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.2.8.3 1 707 Develop water tank sensors readout
709 1.2 1.2.4.8.2.8.4 Develop heater control; (ON/OFF, Thermostat setpoint) Not Started C 7 1 2w 03/06/23 03/17/23 03/06/23 8:00 AM 03/17/23 4:59 PM 707 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.2.8.4 1 708 Develop heater control; (ON/OFF, Thermostat setpoint)
710 1.2 1.2.4.8.2.8.5 Develop AB drive/pump control; (variable speed velocity drives) Not Started C 7 1 4w 03/20/23 04/14/23 03/20/23 8:00 AM 04/14/23 4:59 PM 708 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.2.8.5 1 709 Develop AB drive/pump control; (variable speed velocity drives)
711 1.2 1.2.4.8.2.8.6 Configure/document network switch Not Started C 7 1 2w 09/29/22 10/12/22 09/29/22 8:00 AM 10/12/22 4:59 PM 689 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.8.6 1 710 Configure/document network switch
712 1.2 1.2.4.8.2.8.7 Configure/document RTA gateway to M-DGH interface Not Started C 7 1 2w 10/13/22 10/26/22 10/13/22 8:00 AM 10/26/22 4:59 PM 710 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.8.7 1 711 Configure/document RTA gateway to M-DGH interface
713 1.2 1.2.4.8.2.8.8 Configure/document Point I/O Block Not Started C 7 1 2w 10/27/22 11/09/22 10/27/22 8:00 AM 11/09/22 4:59 PM 711 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.8.8 1 712 Configure/document Point I/O Block
714 1.2 1.2.4.8.2.8.9 Configure/document M-DGHs (Heater-mounted + all others) Not Started C 7 1 2w 11/10/22 11/23/22 11/10/22 8:00 AM 11/23/22 4:59 PM 712 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.8.9 1 713 Configure/document M-DGHs (Heater-mounted + all others)
715 1.2 1.2.4.8.2.8.10 Implement interlocks Not Started C 7 1 4w 04/17/23 05/12/23 04/17/23 8:00 AM 05/12/23 4:59 PM 713, 709 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.4 relationship. Deliverable supports FS2 tasking. 1.2.4.8.2.8.10 1 714 Implement interlocks
716 1.2 1.2.4.8.2.8.11 Document Subsystem Not Started C 7 1 2w 05/15/23 05/26/23 05/15/23 8:00 AM 05/26/23 4:59 PM 714 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS2 tasking. 1.2.4.8.2.8.11 1 715 Document Subsystem
717 1.2 1.2.4.8.2.9 CS PHS HW ready to pack for shipment Not Started C 6 1 1 0 01/18/23 01/18/23 01/18/23 4:59 PM 01/18/23 4:59 PM 681, 685, 688, 696, 710, 711, 712, 713 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.2.9 1 716 CS PHS HW ready to pack for shipment
718 1.2 1.2.4.8.3 CS TOS & Reels Should have Started P 5 1 450d 01/03/22 09/22/23 01/03/22 8:00 AM 09/22/23 4:59 PM 2% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3 1 717 CS TOS & Reels
719 1.2 1.2.4.8.3.1 CS TOS HW1: Motor Drive Config & Install Kits Not Started P 6 1 130d 08/01/22 01/27/23 08/01/22 8:00 AM 01/27/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.1 1 718 CS TOS HW1: Motor Drive Config & Install Kits
720 1.2 1.2.4.8.3.1.1 Procure TOS motor drives (16 VFDs) and accessories Not Started C 7 1 4w 08/01/22 08/26/22 08/01/22 8:00 AM 08/26/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in PY4 (1.2.4.4.3) - 0,0,15000 1.2.4.8.3.1.1 1 719 Procure TOS motor drives (16 VFDs) and accessories
721 1.2 1.2.4.8.3.1.2 (PY4) Configure VFDs with accessories, connection pigtails, document Not Started C 7 1 6w 08/29/22 10/07/22 08/29/22 8:00 AM 10/07/22 4:59 PM 719 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in PY4 (1.2.4.4.5) - 120,64,6000 1.2.4.8.3.1.2 1 720 (PY4) Configure VFDs with accessories, connection pigtails, document
722 1.2 1.2.4.8.3.1.3 Configure VFDs with accessories, connection pigtails, document Not Started C 7 1 8w 10/10/22 12/02/22 10/10/22 8:00 AM 12/02/22 4:59 PM 720 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.1.3 1 721 Configure VFDs with accessories, connection pigtails, document
723 1.2 1.2.4.8.3.1.4 Develop VFD mechanical and electrical installation strategies & document, procure materials Not Started C 7 1 4w 12/05/22 12/30/22 12/05/22 8:00 AM 12/30/22 4:59 PM 721 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.1.4 1 722 Develop VFD mechanical and electrical installation strategies & document, procure materials
724 1.2 1.2.4.8.3.1.5 SW configuration and autotuning, make plan - MDCR/LW, DSHR/LW, RWHR, RWCR, Tower Hoist Not Started C 7 1 4w 01/02/23 01/27/23 01/02/23 8:00 AM 01/27/23 4:59 PM 722 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.3.1.5 1 723 SW configuration and autotuning, make plan - MDCR/LW, DSHR/LW, RWHR, RWCR, Tower Hoist
725 1.2 1.2.4.8.3.2 CS TOS HW2: Estop Not Started P 6 1 210d 09/01/22 06/21/23 09/01/22 8:00 AM 06/21/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.2 1 724 CS TOS HW2: Estop
726 1.2 1.2.4.8.3.2.1 Review Gen 1 documentation against as-built units located at PSL; mark up and update drawings Not Started C 7 1 2w 09/01/22 09/14/22 09/01/22 8:00 AM 09/14/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.1.4) - 80,0,0 1.2.4.8.3.2.1 1 725 Review Gen 1 documentation against as-built units located at PSL; mark up and update drawings
727 1.2 1.2.4.8.3.2.2 Document changes to E-stop and Reel stop interfaces to motor drives, procure materials, implement Not Started C 7 1 4w 09/15/22 10/12/22 09/15/22 8:00 AM 10/12/22 4:59 PM 725 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.2.2 1 726 Document changes to E-stop and Reel stop interfaces to motor drives, procure materials, implement
728 1.2 1.2.4.8.3.2.3 Test refurbished E-stop panels with reel safety junction boxes, I/O boxes, network boxes, drives Not Started C 7 1 4w 10/13/22 11/09/22 10/13/22 8:00 AM 11/09/22 4:59 PM 726 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.2.3 1 727 Test refurbished E-stop panels with reel safety junction boxes, I/O boxes, network boxes, drives
729 1.2 1.2.4.8.3.2.4 Develop and document E-stop switch re-wiring plans for TOS, procure spare slap switches Not Started C 7 1 8w 11/10/22 01/04/23 11/10/22 8:00 AM 01/04/23 4:59 PM 727 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.5.3) - 16,0,400 1.2.4.8.3.2.4 1 728 Develop and document E-stop switch re-wiring plans for TOS, procure spare slap switches
730 1.2 1.2.4.8.3.2.5 (PY4) Design new E-stop controllers for TOS, build and test boxes Not Started C 7 1 12w 01/05/23 03/29/23 01/05/23 8:00 AM 03/29/23 4:59 PM 728 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.4.5) - 40,16,1000 1.2.4.8.3.2.5 1 729 (PY4) Design new E-stop controllers for TOS, build and test boxes
731 1.2 1.2.4.8.3.2.6 Design new E-stop controllers for TOS, build and test boxes Not Started C 7 1 12w 03/30/23 06/21/23 03/30/23 8:00 AM 06/21/23 4:59 PM 729 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.2.6 1 730 Design new E-stop controllers for TOS, build and test boxes
732 1.2 1.2.4.8.3.3 CS TOS HW3: Network & PLC Not Started P 6 1 160d 12/01/22 07/12/23 12/01/22 8:00 AM 07/12/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.3 1 731 CS TOS HW3: Network & PLC
733 1.2 1.2.4.8.3.3.1 Spec and procure new power supplies for TOS network boxes, procure DGH gateway, document changes Not Started C 7 1 6w 12/01/22 01/11/23 12/01/22 8:00 AM 01/11/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.3.1 1 732 Spec and procure new power supplies for TOS network boxes, procure DGH gateway, document changes
734 1.2 1.2.4.8.3.3.2 Document plans for TOS network box upgrades, specify and procure tools and materials Not Started C 7 1 4w 01/12/23 02/08/23 01/12/23 8:00 AM 02/08/23 4:59 PM 732 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.3.2 1 733 Document plans for TOS network box upgrades, specify and procure tools and materials
735 1.2 1.2.4.8.3.3.3 Spec TOS network switch location, spec cables to drives, I/O boxes, network box, DCC modem, PC, PLC, e-stop controller Not Started C 7 1 6w 02/09/23 03/22/23 02/09/23 8:00 AM 03/22/23 4:59 PM 733 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.3.3 1 734 Spec TOS network switch location, spec cables to drives, I/O boxes, network box, DCC modem, PC, PLC, e-stop controller
736 1.2 1.2.4.8.3.3.4 Design enclosures for TOS PLCs and attached I/O used for payout encoders, load cells; procure parts Not Started C 7 1 8w 03/23/23 05/17/23 03/23/23 8:00 AM 05/17/23 4:59 PM 734 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.3.4 1 735 Design enclosures for TOS PLCs and attached I/O used for payout encoders, load cells; procure parts
737 1.2 1.2.4.8.3.3.5 Construct enclosures for TOS PLCs and attached I/O , test Not Started C 7 1 8w 05/18/23 07/12/23 05/18/23 8:00 AM 07/12/23 4:59 PM 735 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.3.5 1 736 Construct enclosures for TOS PLCs and attached I/O , test
738 1.2 1.2.4.8.3.4 CS TOS HW4: I/O Boxes Not Started P 6 1 190d 05/02/22 01/20/23 05/02/22 8:00 AM 01/20/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.4 1 737 CS TOS HW4: I/O Boxes
739 1.2 1.2.4.8.3.4.1 Design I/O box upgrades using A-B Point I/O modules, install Not Started C 7 1 16w 05/02/22 08/19/22 05/02/22 8:00 AM 08/19/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.2.7) - 160,24,4000 1.2.4.8.3.4.1 1 738 Design I/O box upgrades using A-B Point I/O modules, install
740 1.2 1.2.4.8.3.4.2 Test I/O boxes with pendants and motor drives Not Started C 7 1 8w 08/22/22 10/14/22 08/22/22 8:00 AM 10/14/22 4:59 PM 738 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in(1.2.4.2.7) - 32,0,0 1.2.4.8.3.4.2 1 739 Test I/O boxes with pendants and motor drives
741 1.2 1.2.4.8.3.4.3 Design and build cables for I/O box connections to motor drives and E-stop box Not Started C 7 1 8w 10/17/22 12/09/22 10/17/22 8:00 AM 12/09/22 4:59 PM 739 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.2.7) - 80,40,3000 1.2.4.8.3.4.3 1 740 Design and build cables for I/O box connections to motor drives and E-stop box
742 1.2 1.2.4.8.3.4.4 Rebuild two portable I/O boxes, test (used to operate return water cable reel motor drives with pendant) Not Started C 7 1 6w 12/12/22 01/20/23 12/12/22 8:00 AM 01/20/23 4:59 PM 740 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.2.7) - 60,0,3000 1.2.4.8.3.4.4 1 741 Rebuild two portable I/O boxes, test (used to operate return water cable reel motor drives with pendant)
743 1.2 1.2.4.8.3.5 CS TOS HW5-6: Maintain Documentation, Develop Field Plans Not Started P 6 1 40d 01/02/23 02/24/23 01/02/23 8:00 AM 02/24/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.5 1 742 CS TOS HW5-6: Maintain Documentation, Develop Field Plans
744 1.2 1.2.4.8.3.5.1 Develop and document on-ice test plans for E-stop, Reel-Stop, and Fault Detection hardware Not Started C 7 1 4w 01/02/23 01/27/23 01/02/23 8:00 AM 01/27/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.5.1 1 743 Develop and document on-ice test plans for E-stop, Reel-Stop, and Fault Detection hardware
745 1.2 1.2.4.8.3.5.2 Develop and document on-ice test plans for integrated hardware Not Started C 7 1 4w 01/30/23 02/24/23 01/30/23 8:00 AM 02/24/23 4:59 PM 743 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.5.2 1 744 Develop and document on-ice test plans for integrated hardware
746 1.2 1.2.4.8.3.6 CS TOS HW7: Tower Payout Encoders & Load Cells Should have Started P 6 1 260d 01/03/22 12/30/22 01/03/22 8:00 AM 12/30/22 4:59 PM 27% 0% Red $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.6 1 745 CS TOS HW7: Tower Payout Encoders & Load Cells
747 1.2 1.2.4.8.3.6.1 Review documentation, specify hose and cable payout encoders, specify load cells, procure Should have Started C 7 1 8w 01/03/22 02/25/22 01/03/22 8:00 AM 02/25/22 4:59 PM 53% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.6.1 1 746 Review documentation, specify hose and cable payout encoders, specify load cells, procure
748 1.2 1.2.4.8.3.6.2 Test load cells and payout encoders with PLC, verify functionality required for payout control, load sharing Not Started C 7 1 8w 11/07/22 12/30/22 11/07/22 8:00 AM 12/30/22 4:59 PM 746FS +36w 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.6.2 1 747 Test load cells and payout encoders with PLC, verify functionality required for payout control, load sharing
749 1.2 1.2.4.8.3.7 CS TOS HW8: Line Filters for All Drives in TOS2, Identify and Procure Not Started C 6 1 8w 01/02/23 02/24/23 01/02/23 8:00 AM 02/24/23 4:59 PM 747 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.5.4.3) - 32,0,3200 1.2.4.8.3.7 1 748 CS TOS HW8: Line Filters for All Drives in TOS2, Identify and Procure
750 1.2 1.2.4.8.3.8 CS TOS HW9: Tower Hoist Reconnect Materials TOS2, Identify and Procure Not Started C 6 1 4w 02/27/23 03/24/23 02/27/23 8:00 AM 03/24/23 4:59 PM 748 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.8 1 749 CS TOS HW9: Tower Hoist Reconnect Materials TOS2, Identify and Procure
751 1.2 1.2.4.8.3.9 CS TOS HW10: Review deployment plans and HW, integrate with drill Not Started C 6 1 10w 03/27/23 06/02/23 03/27/23 8:00 AM 06/02/23 4:59 PM 749 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.9 1 750 CS TOS HW10: Review deployment plans and HW, integrate with drill
752 1.2 1.2.4.8.3.10 CS TOS Develop PLC Space SW Functionality Not Started P 6 1 190d 01/02/23 09/22/23 01/02/23 8:00 AM 09/22/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.10 1 751 CS TOS Develop PLC Space SW Functionality
753 1.2 1.2.4.8.3.10.1 Develop general control/monitoring software Not Started C 7 1 10w 01/02/23 03/10/23 01/02/23 8:00 AM 03/10/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.3.10.1 1 752 Develop general control/monitoring software
754 1.2 1.2.4.8.3.10.2 Develop reel control software(MCR/LW, DSHR/LW, RWHR, RWCR, Tower Winch) Not Started C 7 1 6w 03/13/23 04/21/23 03/13/23 8:00 AM 04/21/23 4:59 PM 752 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.3.10.2 1 753 Develop reel control software(MCR/LW, DSHR/LW, RWHR, RWCR, Tower Winch)
755 1.2 1.2.4.8.3.10.3 Develop tension-sharing algorithm software (MCR/LW, DSHR/LW) Not Started C 7 1 12w 04/24/23 07/14/23 04/24/23 8:00 AM 07/14/23 4:59 PM 753 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.3.10.3 1 754 Develop tension-sharing algorithm software (MCR/LW, DSHR/LW)
756 1.2 1.2.4.8.3.10.4 Develop drillhead data monitoring interface) Not Started C 7 1 4w 07/17/23 08/11/23 07/17/23 8:00 AM 08/11/23 4:59 PM 754 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.3.10.4 1 755 Develop drillhead data monitoring interface)
757 1.2 1.2.4.8.3.10.5 Configure/document network switch Not Started C 7 1 2w 02/09/23 02/22/23 02/09/23 8:00 AM 02/22/23 4:59 PM 733 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.10.5 1 756 Configure/document network switch
758 1.2 1.2.4.8.3.10.6 Configure RTA gateway to M-DGH interface Not Started C 7 1 2w 02/23/23 03/08/23 02/23/23 8:00 AM 03/08/23 4:59 PM 756 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.10.6 1 757 Configure RTA gateway to M-DGH interface
759 1.2 1.2.4.8.3.10.7 Configure M-DGHs Not Started C 7 1 2w 03/09/23 03/22/23 03/09/23 8:00 AM 03/22/23 4:59 PM 757 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.3.10.7 1 758 Configure M-DGHs
760 1.2 1.2.4.8.3.10.8 Implement interlocks Not Started C 7 1 4w 08/14/23 09/08/23 08/14/23 8:00 AM 09/08/23 4:59 PM 758, 755 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.4 Relationship. Deliverable supports FS2 tasking. 1.2.4.8.3.10.8 1 759 Implement interlocks
761 1.2 1.2.4.8.3.10.9 Document Subsystem Not Started C 7 1 2w 09/11/23 09/22/23 09/11/23 8:00 AM 09/22/23 4:59 PM 759 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS2 tasking. 1.2.4.8.3.10.9 1 760 Document Subsystem
762 1.2 1.2.4.8.3.11 CS TOS HW ready to pack for shipment Not Started C 6 1 1 0 07/12/23 07/12/23 07/12/23 4:59 PM 07/12/23 4:59 PM 719, 720, 721, 722, 724, 731, 737, 742, 745, 756, 757, 758 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Comsur2023-DNF 1.2.4.8.3.11 1 761 CS TOS HW ready to pack for shipment
763 1.2 1.2.4.8.4 CS Drillheads (CS HW, not actual drillheads) Not Started P 5 1 110d 05/01/23 09/29/23 05/01/23 8:00 AM 09/29/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.4 1 762 CS Drillheads (CS HW, not actual drillheads)
764 1.2 1.2.4.8.4.1 CS HW Drillhead sofware/hardware production version Not Started C 6 1 8w 05/01/23 06/23/23 05/01/23 8:00 AM 06/23/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen RaspPi drillhead configuration and testing
Procure components
Integrate into drillhead power supply chassis
Finalize and test drillhead power supply chassis
1.2.4.8.4.1 1 763 CS HW Drillhead sofware/hardware production version
765 1.2 1.2.4.8.4.2 Develop Linux SW Functionality Not Started P 6 1 70d 06/26/23 09/29/23 06/26/23 8:00 AM 09/29/23 4:59 PM 763 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.4.2 1 764 Develop Linux SW Functionality
766 1.2 1.2.4.8.4.2.1 Port C-Lang ingest process to rPI platform & test Not Started C 7 1 6w 06/26/23 08/04/23 06/26/23 8:00 AM 08/04/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.4.2.1 1 765 Port C-Lang ingest process to rPI platform & test
767 1.2 1.2.4.8.4.2.2 Integrate rPI platform into PLC infrastructure Not Started C 7 1 6w 08/07/23 09/15/23 08/07/23 8:00 AM 09/15/23 4:59 PM 765 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.4.2.2 1 766 Integrate rPI platform into PLC infrastructure
768 1.2 1.2.4.8.4.2.3 Document Subsystem Not Started C 7 1 2w 09/18/23 09/29/23 09/18/23 8:00 AM 09/29/23 4:59 PM 766 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.4.2.3 1 767 Document Subsystem
769 1.2 1.2.4.8.4.3 CS Drillheads HW ready to pack for shipment Not Started C 6 1 1 0 09/29/23 09/29/23 09/29/23 4:59 PM 09/29/23 4:59 PM 763, 764 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Vessel 2023-DNF 1.2.4.8.4.3 1 768 CS Drillheads HW ready to pack for shipment
770 1.2 1.2.4.8.5 CS DCC, WT1, and Fuel Daytank Not Started P 5 1 195d 01/02/23 09/29/23 01/02/23 8:00 AM 09/29/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5 1 769 CS DCC, WT1, and Fuel Daytank
771 1.2 1.2.4.8.5.1 Design, construct and test master E-stop controller, produce documentation and user instructions Not Started C 6 1 16w 01/02/23 04/21/23 01/02/23 8:00 AM 04/21/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5.1 1 770 Design, construct and test master E-stop controller, produce documentation and user instructions
772 1.2 1.2.4.8.5.2 Design and construct general-purpose I/O box for fuel sled, gather required component stock to install Not Started C 6 1 6w 04/24/23 06/02/23 04/24/23 8:00 AM 06/02/23 4:59 PM 770 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5.2 1 771 Design and construct general-purpose I/O box for fuel sled, gather required component stock to install
773 1.2 1.2.4.8.5.3 Procure 20 kW three-phase heater for DCC and 208V breakers Not Started C 6 1 3w 06/05/23 06/23/23 06/05/23 8:00 AM 06/23/23 4:59 PM 771 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5.3 1 772 Procure 20 kW three-phase heater for DCC and 208V breakers
774 1.2 1.2.4.8.5.4 WT1 VT pump drives: procure, configure, rewire plan Not Started C 6 1 8w 06/26/23 08/18/23 06/26/23 8:00 AM 08/18/23 4:59 PM 772 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5.4 1 773 WT1 VT pump drives: procure, configure, rewire plan
775 1.2 1.2.4.8.5.5 WT1 VT pump drives: final configure Not Started C 6 1 2w 08/21/23 09/01/23 08/21/23 8:00 AM 09/01/23 4:59 PM 773 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5.5 1 774 WT1 VT pump drives: final configure
776 1.2 1.2.4.8.5.6 WT1 VT pump drives: install plan and kit Not Started C 6 1 4w 09/04/23 09/29/23 09/04/23 8:00 AM 09/29/23 4:59 PM 774 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5.6 1 775 WT1 VT pump drives: install plan and kit
777 1.2 1.2.4.8.5.7 Develop PLC-Fuel DayTank SW Functionality Not Started P 6 1 80d 06/01/23 09/20/23 06/01/23 8:00 AM 09/20/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5.7 1 776 Develop PLC-Fuel DayTank SW Functionality
778 1.2 1.2.4.8.5.7.1 Develop fuel system sensor readout ; (multi-level tank status, control relay status ) Not Started C 7 1 6w 06/01/23 07/12/23 06/01/23 8:00 AM 07/12/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5.7.1 1 777 Develop fuel system sensor readout ; (multi-level tank status, control relay status )
779 1.2 1.2.4.8.5.7.2 Configure/document Point I/O Block Not Started C 7 1 4w 07/13/23 08/09/23 07/13/23 8:00 AM 08/09/23 4:59 PM 777 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5.7.2 1 778 Configure/document Point I/O Block
780 1.2 1.2.4.8.5.7.3 Document Subsystem Not Started C 7 1 2w 08/10/23 08/23/23 08/10/23 8:00 AM 08/23/23 4:59 PM 778 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5.7.3 1 779 Document Subsystem
781 1.2 1.2.4.8.5.7.4 Implement interlocks Not Started C 7 1 4w 08/24/23 09/20/23 08/24/23 8:00 AM 09/20/23 4:59 PM 779 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.5.7.4 1 780 Implement interlocks
782 1.2 1.2.4.8.5.8 CS DCC HW ready to pack for shipment Not Started C 6 1 1 0 09/29/23 09/29/23 09/29/23 4:59 PM 09/29/23 4:59 PM 770, 771, 772, 773, 774, 775, 776 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Vessel 2023-DNF 1.2.4.8.5.8 1 781 CS DCC HW ready to pack for shipment
783 1.2 1.2.4.8.6 CS Gensets Not Started P 5 1 100d 03/18/24 08/02/24 03/18/24 8:00 AM 08/02/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.6 1 782 CS Gensets
784 1.2 1.2.4.8.6.1 CS Gensets HW - identify, procure, assemble Not Started C 6 1 10w 03/18/24 05/24/24 03/18/24 8:00 AM 05/24/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.6.1 1 783 CS Gensets HW - identify, procure, assemble
785 1.2 1.2.4.8.6.2 Develop PLC-Gens MDSs SW Functionality Not Started P 6 1 80d 04/15/24 08/02/24 04/15/24 8:00 AM 08/02/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.6.2 1 784 Develop PLC-Gens MDSs SW Functionality
786 1.2 1.2.4.8.6.2.1 Develop sensor readout; (bldg temps, fuel temps, supply/return water temps) Not Started C 7 1 4w 04/15/24 05/10/24 04/15/24 8:00 AM 05/10/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.6.2.1 1 785 Develop sensor readout; (bldg temps, fuel temps, supply/return water temps)
787 1.2 1.2.4.8.6.2.2 Develop sensor readout; (engine jacket temps, exhaust temps, drip pan status) Not Started C 7 1 4w 05/13/24 06/07/24 05/13/24 8:00 AM 06/07/24 4:59 PM 785 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.6.2.2 1 786 Develop sensor readout; (engine jacket temps, exhaust temps, drip pan status)
788 1.2 1.2.4.8.6.2.3 Configure/document network switch Not Started C 7 1 2w 06/10/24 06/21/24 06/10/24 8:00 AM 06/21/24 4:59 PM 786 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.6.2.3 1 787 Configure/document network switch
789 1.2 1.2.4.8.6.2.4 Configure/document RTA gateway to M-DGH interface Not Started C 7 1 2w 06/24/24 07/05/24 06/24/24 8:00 AM 07/05/24 4:59 PM 787 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.6.2.4 1 788 Configure/document RTA gateway to M-DGH interface
790 1.2 1.2.4.8.6.2.5 Configure/document M-DGHs Not Started C 7 1 2w 07/08/24 07/19/24 07/08/24 8:00 AM 07/19/24 4:59 PM 788 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.6.2.5 1 789 Configure/document M-DGHs
791 1.2 1.2.4.8.6.2.6 Document Subsystem Not Started C 7 1 2w 07/22/24 08/02/24 07/22/24 8:00 AM 08/02/24 4:59 PM 789 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.6.2.6 1 790 Document Subsystem
792 1.2 1.2.4.8.6.3 CS Gensets HW ready to pack for shipment Not Started C 6 1 1 0 08/02/24 08/02/24 08/02/24 4:59 PM 08/02/24 4:59 PM 783, 784 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Vessel 2023-DNF 1.2.4.8.6.3 1 791 CS Gensets HW ready to pack for shipment
793 1.2 1.2.4.8.7 CS HPP Not Started P 5 1 213d 10/03/22 07/26/23 10/03/22 8:00 AM 07/26/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7 1 792 CS HPP
794 1.2 1.2.4.8.7.1 CS HPP HW1: Motor Drive Config & Install Kits Not Started P 6 1 100d 10/03/22 02/17/23 10/03/22 8:00 AM 02/17/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.1 1 793 CS HPP HW1: Motor Drive Config & Install Kits
795 1.2 1.2.4.8.7.1.1 Procure HPP motor drives (four PF-755 50 hp vfds) (8 hours, task is finished) Not Started C 7 1 8w 10/03/22 11/25/22 10/03/22 8:00 AM 11/25/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.4.3) - 0,0,5000 1.2.4.8.7.1.1 1 794 Procure HPP motor drives (four PF-755 50 hp vfds) (8 hours, task is finished)
796 1.2 1.2.4.8.7.1.2 Configure four HPP VFDs with accessories, connection pigtails, document Not Started C 7 1 4w 11/28/22 12/23/22 11/28/22 8:00 AM 12/23/22 4:59 PM 794 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.4.5) - 80,16,0 1.2.4.8.7.1.2 1 795 Configure four HPP VFDs with accessories, connection pigtails, document
797 1.2 1.2.4.8.7.1.3 Develop VFD mechanical and electrical installation strategies & document, procure materials Not Started C 7 1 4w 12/26/22 01/20/23 12/26/22 8:00 AM 01/20/23 4:59 PM 795 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.1.3 1 796 Develop VFD mechanical and electrical installation strategies & document, procure materials
798 1.2 1.2.4.8.7.1.4 SW configuration and autotuning Not Started C 7 1 4w 01/23/23 02/17/23 01/23/23 8:00 AM 02/17/23 4:59 PM 796 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.1.4 1 797 SW configuration and autotuning
799 1.2 1.2.4.8.7.2 CS HPP HW2: Signal and Readout Definition, Procedures Not Started P 6 1 50d 10/03/22 12/09/22 10/03/22 8:00 AM 12/09/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.2 1 798 CS HPP HW2: Signal and Readout Definition, Procedures
800 1.2 1.2.4.8.7.2.1 Define requirements and procedures for reading signals applied to HPP motor drives Not Started C 7 1 4w 10/03/22 10/28/22 10/03/22 8:00 AM 10/28/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.2.1 1 799 Define requirements and procedures for reading signals applied to HPP motor drives
801 1.2 1.2.4.8.7.2.2 Define method of verifying sensor readout accuracy (reading vs stimulus) Not Started C 7 1 4w 10/31/22 11/25/22 10/31/22 8:00 AM 11/25/22 4:59 PM 799 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.2.2 1 800 Define method of verifying sensor readout accuracy (reading vs stimulus)
802 1.2 1.2.4.8.7.2.3 Develop and document test procedures for on-ice personnel Not Started C 7 1 2w 11/28/22 12/09/22 11/28/22 8:00 AM 12/09/22 4:59 PM 800 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.2.3 1 801 Develop and document test procedures for on-ice personnel
803 1.2 1.2.4.8.7.3 CS HPP HW3: PLC Hardware, Box Build, Testing Not Started P 6 1 130d 11/01/22 05/01/23 11/01/22 8:00 AM 05/01/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.3 1 802 CS HPP HW3: PLC Hardware, Box Build, Testing
804 1.2 1.2.4.8.7.3.1 Define core HPP PLC functions and requirements, define needed I/O connections Not Started C 7 1 6w 11/01/22 12/12/22 11/01/22 8:00 AM 12/12/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.3.1 1 803 Define core HPP PLC functions and requirements, define needed I/O connections
805 1.2 1.2.4.8.7.3.2 Select PLC, Enclosure, Power supplies, I/O expansion cards, power distribution, connectors and cables Not Started C 7 1 4w 12/13/22 01/09/23 12/13/22 8:00 AM 01/09/23 4:59 PM 803 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.3.2 1 804 Select PLC, Enclosure, Power supplies, I/O expansion cards, power distribution, connectors and cables
806 1.2 1.2.4.8.7.3.3 Design and Construct PLC enclosure Not Started C 7 1 8w 01/10/23 03/06/23 01/10/23 8:00 AM 03/06/23 4:59 PM 804 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.3.3 1 805 Design and Construct PLC enclosure
807 1.2 1.2.4.8.7.3.4 Test HPP PLC enclosure with HPP Network box Not Started C 7 1 8w 03/07/23 05/01/23 03/07/23 8:00 AM 05/01/23 4:59 PM 805 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.3.4 1 806 Test HPP PLC enclosure with HPP Network box
808 1.2 1.2.4.8.7.4 CS HPP HW4: Charge Pump Motor Controllers Not Started P 6 1 110d 12/01/22 05/03/23 12/01/22 8:00 AM 05/03/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.4 1 807 CS HPP HW4: Charge Pump Motor Controllers
809 1.2 1.2.4.8.7.4.1 Install PF-70 motor drive in test bed, configure with local control system, test Not Started C 7 1 8w 12/01/22 01/25/23 12/01/22 8:00 AM 01/25/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.4.4) - 40,0,0 1.2.4.8.7.4.1 1 808 Install PF-70 motor drive in test bed, configure with local control system, test
810 1.2 1.2.4.8.7.4.2 Procure additional drives for charge pumps (4), AC and network pigtail materials Not Started C 7 1 10w 01/26/23 04/05/23 01/26/23 8:00 AM 04/05/23 4:59 PM 808 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.4.2 1 809 Procure additional drives for charge pumps (4), AC and network pigtail materials
811 1.2 1.2.4.8.7.4.3 Connectorize four drives with power and network pigtails, test each in test bed Not Started C 7 1 4w 04/06/23 05/03/23 04/06/23 8:00 AM 05/03/23 4:59 PM 809 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.4.3 1 810 Connectorize four drives with power and network pigtails, test each in test bed
812 1.2 1.2.4.8.7.5 CS HPP HW5: Sensor Box Reconfig & Test Not Started P 6 1 80d 01/02/23 04/21/23 01/02/23 8:00 AM 04/21/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.5 1 811 CS HPP HW5: Sensor Box Reconfig & Test
813 1.2 1.2.4.8.7.5.1 Build and test a portable network box for sensor box testing (Gateway, power supply, connectors) Not Started C 7 1 8w 01/02/23 02/24/23 01/02/23 8:00 AM 02/24/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.2.2.1) - 24,16,1200 1.2.4.8.7.5.1 1 812 Build and test a portable network box for sensor box testing (Gateway, power supply, connectors)
814 1.2 1.2.4.8.7.5.2 Procure and configure test equipment needed to calibrate individual sensors, provide user instructions Not Started C 7 1 4w 02/27/23 03/24/23 02/27/23 8:00 AM 03/24/23 4:59 PM 812 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.2.2.1) - 24,8,800 1.2.4.8.7.5.2 1 813 Procure and configure test equipment needed to calibrate individual sensors, provide user instructions
815 1.2 1.2.4.8.7.5.3 Connect HPP sensor readout box with sensor box, connect to network box, test all sensors and document Not Started C 7 1 4w 03/27/23 04/21/23 03/27/23 8:00 AM 04/21/23 4:59 PM 813 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.2.2.1) - 40,24,0 1.2.4.8.7.5.3 1 814 Connect HPP sensor readout box with sensor box, connect to network box, test all sensors and document
816 1.2 1.2.4.8.7.6 CS HPP HW6: Sensor Box DGH Reconfig & Test Not Started C 6 1 8w 02/01/23 03/28/23 02/01/23 8:00 AM 03/28/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.2.2.1, 1.2.4.3.2.3) - 80,0,0 1.2.4.8.7.6 1 815 CS HPP HW6: Sensor Box DGH Reconfig & Test
817 1.2 1.2.4.8.7.7 CS HPP HW7: Estop box Re-outfitting Not Started P 6 1 50d 04/03/23 06/09/23 04/03/23 8:00 AM 06/09/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.7 1 816 CS HPP HW7: Estop box Re-outfitting
818 1.2 1.2.4.8.7.7.1 Select and procure E-stop relays for pump VFD Enable signals Not Started C 7 1 4w 04/03/23 04/28/23 04/03/23 8:00 AM 04/28/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.7.1 1 817 Select and procure E-stop relays for pump VFD Enable signals
819 1.2 1.2.4.8.7.7.2 Develop and document rewiring instructions for HPP E-stop box Not Started C 7 1 6w 05/01/23 06/09/23 05/01/23 8:00 AM 06/09/23 4:59 PM 817 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.7.2 1 818 Develop and document rewiring instructions for HPP E-stop box
820 1.2 1.2.4.8.7.8 CS HPP HW8: Network Box Refurb & Config Not Started P 6 1 130d 12/01/22 05/31/23 12/01/22 8:00 AM 05/31/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.8 1 819 CS HPP HW8: Network Box Refurb & Config
821 1.2 1.2.4.8.7.8.1 Select and procure a wall-mount managed Ethernet switch for the HPP electrical closet Not Started C 7 1 4w 12/01/22 12/28/22 12/01/22 8:00 AM 12/28/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.2.1.1) - 8,0,1400 1.2.4.8.7.8.1 1 820 Select and procure a wall-mount managed Ethernet switch for the HPP electrical closet
822 1.2 1.2.4.8.7.8.2 Select and procure new power supplies for the network box, procure one RS-485 gateway Not Started C 7 1 4w 12/29/22 01/25/23 12/29/22 8:00 AM 01/25/23 4:59 PM 820 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.2.1.1) - 8,0,400 1.2.4.8.7.8.2 1 821 Select and procure new power supplies for the network box, procure one RS-485 gateway
823 1.2 1.2.4.8.7.8.3 Refurbish the HPP network box, document as-built configureation Not Started C 7 1 12w 01/26/23 04/19/23 01/26/23 8:00 AM 04/19/23 4:59 PM 821 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.2.1.1) - 40,8,0 1.2.4.8.7.8.3 1 822 Refurbish the HPP network box, document as-built configureation
824 1.2 1.2.4.8.7.8.4 Select and procure HPP network switch enclosure, integrate with switch Not Started C 7 1 6w 04/20/23 05/31/23 04/20/23 8:00 AM 05/31/23 4:59 PM 822 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PY4 carried in (1.2.4.2.1.1) - 16,24,1200 1.2.4.8.7.8.4 1 823 Select and procure HPP network switch enclosure, integrate with switch
825 1.2 1.2.4.8.7.9 CS HPP HW9-10: Maintain Documentation, Prepare Field Plans Not Started P 6 1 40d 06/01/23 07/26/23 06/01/23 8:00 AM 07/26/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.9 1 824 CS HPP HW9-10: Maintain Documentation, Prepare Field Plans
826 1.2 1.2.4.8.7.9.1 Develop and document test plans for all HPP system components Not Started C 7 1 4w 06/01/23 06/28/23 06/01/23 8:00 AM 06/28/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.9.1 1 825 Develop and document test plans for all HPP system components
827 1.2 1.2.4.8.7.9.2 Review Gen-1 docs, identify where sensor connections terminated, plan for field integration and test Not Started C 7 1 4w 06/29/23 07/26/23 06/29/23 8:00 AM 07/26/23 4:59 PM 825 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.9.2 1 826 Review Gen-1 docs, identify where sensor connections terminated, plan for field integration and test
828 1.2 1.2.4.8.7.10 Develop Local HPP PLC SW Functionality Not Started P 6 1 130d 01/02/23 06/30/23 01/02/23 8:00 AM 06/30/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.10 1 827 Develop Local HPP PLC SW Functionality
829 1.2 1.2.4.8.7.10.1 Develop water path sensor readout; (pressure, temp, flow) Not Started C 7 1 4w 01/02/23 01/27/23 01/02/23 8:00 AM 01/27/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.7.10.1 1 828 Develop water path sensor readout; (pressure, temp, flow)
830 1.2 1.2.4.8.7.10.2 Develop environmental sensor readout; (bldg temps, smoke, e-stop) Not Started C 7 1 2w 01/30/23 02/10/23 01/30/23 8:00 AM 02/10/23 4:59 PM 828 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS1 tasking. 1.2.4.8.7.10.2 1 829 Develop environmental sensor readout; (bldg temps, smoke, e-stop)
831 1.2 1.2.4.8.7.10.3 Build shared data-tagging w/ DCC core controller Not Started C 7 1 4w 02/13/23 03/10/23 02/13/23 8:00 AM 03/10/23 4:59 PM 829 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.10.3 1 830 Build shared data-tagging w/ DCC core controller
832 1.2 1.2.4.8.7.10.4 Develop AB drive/pump control; (variable speed velocity drives) Not Started C 7 1 4w 03/13/23 04/07/23 03/13/23 8:00 AM 04/07/23 4:59 PM 830 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.10.4 1 831 Develop AB drive/pump control; (variable speed velocity drives)
833 1.2 1.2.4.8.7.10.5 Develop charge pump control; (variable speed velocity drives OR Soft Starter) Not Started C 7 1 2w 04/10/23 04/21/23 04/10/23 8:00 AM 04/21/23 4:59 PM 831 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.10.5 1 832 Develop charge pump control; (variable speed velocity drives OR Soft Starter)
834 1.2 1.2.4.8.7.10.6 Configure/document network switch Not Started C 7 1 2w 04/24/23 05/05/23 04/24/23 8:00 AM 05/05/23 4:59 PM 832 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.10.6 1 833 Configure/document network switch
835 1.2 1.2.4.8.7.10.7 Configure/document RTA gateway to M-DGH interface Not Started C 7 1 2w 05/08/23 05/19/23 05/08/23 8:00 AM 05/19/23 4:59 PM 833 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.10.7 1 834 Configure/document RTA gateway to M-DGH interface
836 1.2 1.2.4.8.7.10.8 Configure/document M-DGHs Not Started C 7 1 2w 05/22/23 06/02/23 05/22/23 8:00 AM 06/02/23 4:59 PM 834 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.10.8 1 835 Configure/document M-DGHs
837 1.2 1.2.4.8.7.10.9 Implement interlocks Not Started C 7 1 2w 06/05/23 06/16/23 06/05/23 8:00 AM 06/16/23 4:59 PM 835 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS2 tasking. 1.2.4.8.7.10.9 1 836 Implement interlocks
838 1.2 1.2.4.8.7.10.10 Document Subsystem Not Started C 7 1 2w 06/19/23 06/30/23 06/19/23 8:00 AM 06/30/23 4:59 PM 836 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.4 relationship. Deliverable supports FS2 tasking. 1.2.4.8.7.10.10 1 837 Document Subsystem
839 1.2 1.2.4.8.7.11 CS HPP HW Ready to Pack for Shipment Not Started C 6 1 1 0 07/26/23 07/26/23 07/26/23 4:59 PM 07/26/23 4:59 PM 793, 798, 802, 807, 811, 816, 819, 824, 830, 831, 832, 833, 834, 835 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.7.11 1 838 CS HPP HW Ready to Pack for Shipment
840 1.2 1.2.4.8.8 CS ARA Rodwell System Not Started P 5 1 251d 05/02/22 04/17/23 05/02/22 8:00 AM 04/17/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.8 1 839 CS ARA Rodwell System
841 1.2 1.2.4.8.8.1 CS ARA Rodwell System HW Not Started P 6 1 140d 05/02/22 11/11/22 05/02/22 8:00 AM 11/11/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.8.1 1 840 CS ARA Rodwell System HW
842 1.2 1.2.4.8.8.1.1 CS ARA HW: new system controls and tie-in design Not Started C 7 1 8w 05/02/22 06/24/22 05/02/22 8:00 AM 06/24/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.8.1.1 1 841 CS ARA HW: new system controls and tie-in design
843 1.2 1.2.4.8.8.1.2 Review ARA drill system documentation and develop a new configuration for Rodewell Not Started C 7 1 4w 06/27/22 07/22/22 06/27/22 8:00 AM 07/22/22 4:59 PM 841 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.6.6.1 relationship. 1.2.4.8.8.1.2 1 842 Review ARA drill system documentation and develop a new configuration for Rodewell
844 1.2 1.2.4.8.8.1.3 Select and procure new motor drives for Rodwell pump and combo-cable winch Not Started C 7 1 6w 07/25/22 09/02/22 07/25/22 8:00 AM 09/02/22 4:59 PM 842 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.6.6.2 relationship. 1.2.4.8.8.1.3 1 843 Select and procure new motor drives for Rodwell pump and combo-cable winch
845 1.2 1.2.4.8.8.1.4 Procure gateway for monitoring control pane instruments, plan for installation in the control box Not Started C 7 1 2w 09/05/22 09/16/22 09/05/22 8:00 AM 09/16/22 4:59 PM 843 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.6.6.2 relationship. 1.2.4.8.8.1.4 1 844 Procure gateway for monitoring control pane instruments, plan for installation in the control box
846 1.2 1.2.4.8.8.1.5 Select and procure new hardware to capture flow sensor pulse rates (A-B I/O hardware) Not Started C 7 1 4w 09/19/22 10/14/22 09/19/22 8:00 AM 10/14/22 4:59 PM 844 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.6.6.2 relationship. 1.2.4.8.8.1.5 1 845 Select and procure new hardware to capture flow sensor pulse rates (A-B I/O hardware)
847 1.2 1.2.4.8.8.1.6 Design and Build network cable, E-stop cable, for connecting rodwell system to drill system Not Started C 7 1 4w 10/17/22 11/11/22 10/17/22 8:00 AM 11/11/22 4:59 PM 845 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.6.6.2 relationship. 1.2.4.8.8.1.6 1 846 Design and Build network cable, E-stop cable, for connecting rodwell system to drill system
848 1.2 1.2.4.8.8.2 Develop PLC-Rodwell SW Functionality Not Started P 6 1 120d 11/01/22 04/17/23 11/01/22 8:00 AM 04/17/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.8.2 1 847 Develop PLC-Rodwell SW Functionality
849 1.2 1.2.4.8.8.2.1 Develop ARA-drill sensor readout; (heater flows, head press, tank level) Not Started C 7 1 4w 11/01/22 11/28/22 11/01/22 8:00 AM 11/28/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.8.2.1 1 848 Develop ARA-drill sensor readout; (heater flows, head press, tank level)
850 1.2 1.2.4.8.8.2.2 Develop AB drive/pump control; (variable speed velocity drives) Not Started C 7 1 6w 11/29/22 01/09/23 11/29/22 8:00 AM 01/09/23 4:59 PM 848 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.8.2.2 1 849 Develop AB drive/pump control; (variable speed velocity drives)
851 1.2 1.2.4.8.8.2.3 Configure/document Point I/O Block Not Started C 7 1 4w 01/10/23 02/06/23 01/10/23 8:00 AM 02/06/23 4:59 PM 849 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.8.2.3 1 850 Configure/document Point I/O Block
852 1.2 1.2.4.8.8.2.4 Configure/document network switch Not Started C 7 1 2w 02/07/23 02/20/23 02/07/23 8:00 AM 02/20/23 4:59 PM 850 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.8.2.4 1 851 Configure/document network switch
853 1.2 1.2.4.8.8.2.5 Configure/document RTA gateway to M-DGH interface Not Started C 7 1 2w 02/21/23 03/06/23 02/21/23 8:00 AM 03/06/23 4:59 PM 851 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.8.2.5 1 852 Configure/document RTA gateway to M-DGH interface
854 1.2 1.2.4.8.8.2.6 Configure/document M-DGHs Not Started C 7 1 2w 03/07/23 03/20/23 03/07/23 8:00 AM 03/20/23 4:59 PM 852 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.8.8.2.6 1 853 Configure/document M-DGHs
855 1.2 1.2.4.8.8.2.7 Implement interlocks Not Started C 7 1 2w 03/21/23 04/03/23 03/21/23 8:00 AM 04/03/23 4:59 PM 853 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.4.3.4 relationship. Deliverable supports FS2 tasking. 1.2.4.8.8.2.7 1 854 Implement interlocks
856 1.2 1.2.4.8.8.2.8 Document Subsystem Not Started C 7 1 2w 04/04/23 04/17/23 04/04/23 8:00 AM 04/17/23 4:59 PM 854 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Deliverable supports FS2 tasking. 1.2.4.8.8.2.8 1 855 Document Subsystem
857 1.2 1.2.4.8.8.3 CS ARA HW Ready to Pack for Shipment Not Started C 6 1 1 0 03/20/23 03/20/23 03/20/23 4:59 PM 03/20/23 4:59 PM 840, 848, 849, 850, 851, 852, 853 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Comsur 2023-DNF 1.2.4.8.8.3 1 856 CS ARA HW Ready to Pack for Shipment
858 1.2 1.2.5 Power Generation & Distribution Started P 3 1 1864d 01/24/19 03/30/26 01/24/19 8:00 AM 03/30/26 4:59 PM 0% 74.00% Green $0.00 $0.00 $0.00 $4,799.93 0% Ian McEwen 1.2.5 1 857 Power Generation & Distribution
859 1.2 1.2.5.1 Generator 1 Complete P 4 1 186d 01/24/19 10/10/19 01/24/19 8:00 AM 10/10/19 4:59 PM 98% 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.1 1 858 Generator 1
860 1.2 1.2.5.1.1 GEN-1: Arrange Retro from McMurdo to PTH (Vessel) Complete C 5 1 60d 01/24/19 04/17/19 01/24/19 8:00 AM 04/17/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.5.1.1 1 859 GEN-1: Arrange Retro from McMurdo to PTH (Vessel)
861 1.2 1.2.5.1.2 GEN-1: Transport from PTH to CAT Vendor Complete C 5 1 10d 04/18/19 05/01/19 04/18/19 8:00 AM 05/01/19 4:59 PM 859 97% 100% Gray Delayed NSF custodian approval $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Dedicated truck - Port Hueneme to CAT shop
$7,000 typ PTH-PSL. Reduced to $4,000 for plan to find CAT shop in CA
1.2.5.1.2 1 860 GEN-1: Transport from PTH to CAT Vendor
862 1.2 1.2.5.1.3 GEN-1: Specify SOW and Integration Complete C 5 1 10d 05/02/19 05/15/19 05/02/19 8:00 AM 05/15/19 4:59 PM 860 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Travel - Engineer travel to CAT shop to review/define SOW with PP engineers 1.2.5.1.3 1 861 GEN-1: Specify SOW and Integration
863 1.2 1.2.5.1.4 GEN-1: Generator Overhaul by Vendor Complete C 5 1 100d 05/02/19 09/18/19 05/02/19 8:00 AM 09/18/19 4:59 PM 861SS 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Capital Cost - Unknown at time of schedule/budget development.
ASC recalls other GEN overhauls at <$100k 8 years ago. This figure allows a safety margin of the unknown additional SOW or inflationary costs
1.2.5.1.4 1 862 GEN-1: Generator Overhaul by Vendor
864 1.2 1.2.5.1.5 GEN-1: Acceptance Testing (at vendor) Complete C 5 1 5d 09/19/19 09/25/19 09/19/19 8:00 AM 09/25/19 4:59 PM 862 95% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Travel - 2 Engineers for testing and approval 1.2.5.1.5 1 863 GEN-1: Acceptance Testing (at vendor)
865 1.2 1.2.5.1.6 GEN-1: Transport from Vendor to PTH Complete C 5 1 10d 09/26/19 10/09/19 09/26/19 8:00 AM 10/09/19 4:59 PM 863 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Dedicated truck - CAT shop to Port Hueneme, CA
$7,000 typ PSL-PTH. Reduced to $4,000 for plan to find CAT shop in CA
1.2.5.1.6 1 864 GEN-1: Transport from Vendor to PTH
866 1.2 1.2.5.1.7 GEN-1: Ship from PTH (VSL-ZCM, Traverse-NPX) Complete C 5 1 1 1 1d 10/10/19 10/10/19 10/10/19 8:00 AM 10/10/19 4:59 PM 864 100% 100% Gray GEN-1 is in McMurdo awaiting transport to Pole in 20/21 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.1.7 1 865 GEN-1: Ship from PTH (VSL-ZCM, Traverse-NPX)
867 1.2 1.2.5.2 Generators 2, 3, and PDM Started P 4 1 1228d 03/18/19 11/30/23 03/18/19 8:00 AM 11/30/23 4:59 PM 0% 75.00% Green $0.00 $0.00 $0.00 $4,799.93 0% Ian McEwen Arctic Energy's quote for this structure was $500k 1.2.5.2 1 866 Generators 2, 3, and PDM
868 1.2 1.2.5.2.1 GEN-2, 3, PDM - Arrange Testing/Repairs at McMurdo Complete C 5 1 160d 03/18/19 10/25/19 03/18/19 8:00 AM 10/25/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Develop testing plans, locate engineering drawings, gather historical information, etc.
Design Review, Field Input, Planning
1.2.5.2.1 1 867 GEN-2, 3, PDM - Arrange Testing/Repairs at McMurdo
869 1.2 1.2.5.2.2 GEN-2 - Develop SOW for Gen 2 Repairs Subcontract in New Zealand & Communicate with Vendor Not Started C 5 1 40d 03/01/22 04/25/22 03/01/22 8:00 AM 04/25/22 4:59 PM 0% 0% Green Write SOW, evaluate responses, and communicate with chosen vendor $0.00 $4,799.93 $0.00 $4,799.93 0% $0.00 Ian McEwen PSL_Engineer Sub-Contract to include:
- Review of engineering drawings
- Tune-up SOW development
- CAT Engineer deployment to McMurdo for ~1 month
- Perform testing on Gen2 & 3
- Perform tune-up and on-site repairs activities
- Develop SOW for any future/recommended repairs
1.2.5.2.2 1 868 GEN-2 - Develop SOW for Gen 2 Repairs Subcontract in New Zealand & Communicate with Vendor
870 1.2 1.2.5.2.3 GEN-2, 3, PDM - Procure Testing Equipment/Repair Parts Complete C 5 1 227d 10/01/20 08/13/21 10/01/20 8:00 AM 08/13/21 4:59 PM 100% 100% Gray Spare parts list developed, still researching requirements $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Syncronize components
Replacement switchgear
Container repair parts
1.2.5.2.3 1 869 GEN-2, 3, PDM - Procure Testing Equipment/Repair Parts
871 1.2 1.2.5.2.4 GEN 1, 2, 3, PDM - Procure/Fabricate Aluminum Skis Complete C 5 1 45d 10/01/20 12/02/20 10/01/20 8:00 AM 12/02/20 4:59 PM 869SS 99% 100% Gray skis required, drawings complete, out for bid $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Shop $20,000 - Aluminum I-Beams, Plates, Bolts, Hitch Point, Tow Bars, Etc 1.2.5.2.4 1 870 GEN 1, 2, 3, PDM - Procure/Fabricate Aluminum Skis
872 1.2 1.2.5.2.5 GEN-2, 3, PDM - Procure Repair Parts Complete C 5 1 113d 03/03/21 08/06/21 03/03/21 8:00 AM 08/06/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.2.5 1 871 GEN-2, 3, PDM - Procure Repair Parts
873 1.2 1.2.5.2.6 GEN-1, 2, 3 - Procure Batteries Not Started C 5 1 5d 10/01/22 10/06/22 10/01/22 8:00 AM 10/06/22 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.2.6 1 872 GEN-1, 2, 3 - Procure Batteries
874 1.2 1.2.5.2.7 Generator 2 Subcontract Repairs in New Zealand Not Started C 5 1 44d 11/15/22 01/13/23 11/15/22 8:00 AM 01/13/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.2.7 1 873 Generator 2 Subcontract Repairs in New Zealand
875 1.2 1.2.5.2.8 PDM - Procure Batteries Not Started C 5 1 5d 07/01/23 07/06/23 07/01/23 8:00 AM 07/06/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.2.8 1 874 PDM - Procure Batteries
876 1.2 1.2.5.2.9 Develop SOW for South Pole Power Generation Technical Support Subcontract & Communicate with Vendor (PY6) Not Started C 5 1 44d 10/01/23 11/30/23 10/01/23 8:00 AM 11/30/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.2.9 1 875 Develop SOW for South Pole Power Generation Technical Support Subcontract & Communicate with Vendor (PY6)
877 1.2 1.2.5.2.10 Predeployment Coordination with Power Generation Technical Support Subcontract Vendor (PY6) Not Started C 5 1 44d 08/01/23 09/29/23 08/01/23 8:00 AM 09/29/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.2.10 1 876 Predeployment Coordination with Power Generation Technical Support Subcontract Vendor (PY6)
878 1.2 1.2.5.3 ISO-3 Sled (Task removed - left here as place holder w/ Notes Intact) Complete P 4 1d 03/01/19 03/01/19 03/01/19 8:00 AM 03/01/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.3 1 877 ISO-3 Sled (Task removed - left here as place holder w/ Notes Intact)
879 1.2 1.2.5.3.1 ISO-3 Sled: Design Review & Custom Specification Complete C 5 1d 03/01/19 03/01/19 03/01/19 8:00 AM 03/01/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.5.3.1 1 878 ISO-3 Sled: Design Review & Custom Specification
880 1.2 1.2.5.3.2 ISO-3 Sled: Final Design Review Complete C 5 1 1d 03/01/19 03/01/19 03/01/19 8:00 AM 03/01/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.3.2 1 879 ISO-3 Sled: Final Design Review
881 1.2 1.2.5.3.3 ISO-3 Sled: Procurement & Fabrication Complete C 5 1 1d 03/01/19 03/01/19 03/01/19 8:00 AM 03/01/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer $100,000 price tag provided by ASC (Street & Kippenham 11/14/18)

ASC has not had these fabricated to date, this estimate (from ASC) is based on ISO-2 sleds actual cost of $65,000/each

We added on 20% for some contingency, shipping to PTH costs, as well as any custom fabrications/add-ons for decking, or to accommodate structure attachments.

Travel cost is for 2 engineers to visit the fabricator for confirmation and any customizations

Consider using our own local fabricator, based on ASC specs, so we can review, monitor, but most importantly design/fabricate our custom decks/rails.
1.2.5.3.3 1 880 ISO-3 Sled: Procurement & Fabrication
882 1.2 1.2.5.3.4 ISO-3 Sled: Ship from vendor (Air-ZCM) Complete C 5 1 1d 03/01/19 03/01/19 03/01/19 8:00 AM 03/01/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

1 truckload - ISO Sled, 4-5 Sets of Skis
1.2.5.3.4 1 881 ISO-3 Sled: Ship from vendor (Air-ZCM)
883 1.2 1.2.5.4 System Electrical Distribution Started P 4 1 1381d 12/01/20 03/30/26 12/01/20 8:00 AM 03/30/26 4:59 PM 18% 70.0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.4 1 882 System Electrical Distribution
884 1.2 1.2.5.4.1 System Elec Dist: Evaluate EHWD system Complete C 5 1 40d 12/01/20 01/25/21 12/01/20 8:00 AM 01/25/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.5.4.1 1 883 System Elec Dist: Evaluate EHWD system
885 1.2 1.2.5.4.2 System Elec Dist: Define Requirements Complete C 5 1 60d 01/26/21 04/19/21 01/26/21 8:00 AM 04/19/21 4:59 PM 883 100% 100% Gray compiling additional info post 19/20 season, need to incorporate additional systems $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.5.4.2 1 884 System Elec Dist: Define Requirements
886 1.2 1.2.5.4.3 System Elec Dist: Design & Procure Started C 5 1 8d 10/20/22 10/31/22 10/20/22 8:00 AM 10/31/22 4:59 PM 0% 50.0% Green delayed $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Replacement cables, connectors, for electrical distribution throughout EHWD & TOS 1.2.5.4.3 1 885 System Elec Dist: Design & Procure
887 1.2 1.2.5.4.4 System Elec Dist: Design Review Complete C 5 1 1 1 1d 07/26/22 07/26/22 07/26/22 8:00 AM 07/26/22 4:59 PM 885FS -70d 0% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.4.4 1 886 System Elec Dist: Design Review
888 1.2 1.2.5.4.5 System Elec Dist: Build and Test Subcomponents Started C 5 1 96d 12/01/22 04/13/23 12/01/22 8:00 AM 04/13/23 4:59 PM 886, 885SS +30d 0% 85.00% Green delayed $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.5.4.5 1 887 System Elec Dist: Build and Test Subcomponents
889 1.2 1.2.5.4.6 System Electrical Drawings & Documentation (PY5) Not Started C 5 12d 03/01/23 03/16/23 03/01/23 8:00 AM 03/16/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.4.6 1 888 System Electrical Drawings & Documentation (PY5)
890 1.2 1.2.5.4.7 System Electrical Drawings & Documentation (PY6) Not Started C 5 12d 03/15/24 04/01/24 03/15/24 8:00 AM 04/01/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.4.7 1 889 System Electrical Drawings & Documentation (PY6)
891 1.2 1.2.5.4.8 System Electrical Resupply (PY6) Not Started C 5 7d 04/15/24 04/23/24 04/15/24 8:00 AM 04/23/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.4.8 1 890 System Electrical Resupply (PY6)
892 1.2 1.2.5.4.9 System Electrical Drawings & Documentation (PY7) Not Started C 5 12d 03/15/25 03/31/25 03/15/25 8:00 AM 03/31/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.4.9 1 891 System Electrical Drawings & Documentation (PY7)
893 1.2 1.2.5.4.10 System Electrical Resupply (PY7) Not Started C 5 7d 04/15/25 04/23/25 04/15/25 8:00 AM 04/23/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.4.10 1 892 System Electrical Resupply (PY7)
894 1.2 1.2.5.4.11 System Electrical Drawings & Documentation (PY8) Not Started C 5 12d 03/15/26 03/30/26 03/15/26 8:00 AM 03/30/26 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.5.4.11 1 893 System Electrical Drawings & Documentation (PY8)
895 1.2 1.2.6 Water Handling Systems - Off-ice Started P 3 1 1253d 09/13/19 07/05/24 09/13/19 8:00 AM 07/05/24 4:59 PM 32.72% 67.00% Green $0.00 $0.00 $43,617.45 $133,287.77 33% Ian McEwen 1.2.6 1 894 Water Handling Systems - Off-ice
896 1.2 1.2.6.1 Water Tanks Started P 4 1 857d 01/04/21 04/19/24 01/04/21 8:00 AM 04/19/24 4:59 PM 33% 88.00% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.6.1 1 895 Water Tanks
897 1.2 1.2.6.1.1 Identify Upgrades-Replacements and Spares Complete C 5 1 60d 01/04/21 03/26/21 01/04/21 8:00 AM 03/26/21 4:59 PM 100% 100% Gray in progress $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead Welding liner
Doghouse repairs
1.2.6.1.1 1 896 Identify Upgrades-Replacements and Spares
898 1.2 1.2.6.1.2 Procure Repair Parts, Replacements (PY4) Started C 5 1 8d 05/20/22 05/31/22 05/20/22 8:00 AM 05/31/22 4:59 PM 0% 50.0% Green in progress, no procurements yet $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire 1.2.6.1.2 1 897 Procure Repair Parts, Replacements (PY4)
899 1.2 1.2.6.1.3 Procure Repair Parts, Replacements (PY6) Not Started C 5 1 5d 04/15/24 04/19/24 04/15/24 8:00 AM 04/19/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.6.1.3 1 898 Procure Repair Parts, Replacements (PY6)
900 1.2 1.2.6.2 Pumps Started P 4 1 877d 12/04/20 04/18/24 12/04/20 8:00 AM 04/18/24 4:59 PM 100% 60.0% Red $0.00 $0.00 $20,326.83 $20,326.83 100% Ian McEwen 1.2.6.2 1 899 Pumps
901 1.2 1.2.6.2.1 Identify Upgrades-Replacements and Spares Complete C 5 1 80d 12/04/20 03/25/21 12/04/20 8:00 AM 03/25/21 4:59 PM 100% 100% Gray delayed but still in progress $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.2.1 1 900 Identify Upgrades-Replacements and Spares
902 1.2 1.2.6.2.2 Procure Repair/Replacement Components (2020-21) Complete C 5 1 100d 10/01/21 02/17/22 10/01/21 8:00 AM 02/17/22 4:59 PM 100% 100% Gray delayed $18,406.86 $18,406.86 $18,406.86 $18,406.86 100% $18,406.86 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Costs: from Gen1, PY07 Budget
CE:
$ 28,600 - Submerssible pumps (2-RWS,2-Return)
$ 16,962 - High Pressure Pump, Motor & Stand
$ 8,800 - VT Pumps (2)
$ 6,600 - Charge Pumps (2)
----------------------------------
$60,962

All costs split between 2019 & 2020
1.2.6.2.2 1 901 Procure Repair/Replacement Components (2020-21)
903 1.2 1.2.6.2.3 Configure Pumps/Plumbing Started C 5 1 14d 03/18/22 04/06/22 03/18/22 8:00 AM 04/06/22 4:59 PM 901FS +20d 100% 25.00% Red $1,919.97 $1,919.97 $1,919.97 $1,919.97 100% $479.99 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Costs: from Gen1, PY07 Budget
CE:
$ 28,600 - Submerssible pumps (2-RWS,2-Return)
$ 16,962 - High Pressure Pump, Motor & Stand
$ 8,800 - VT Pumps (2)
$ 6,600 - Charge Pumps (2)
----------------------------------
$60,962

Procurements divided betwen 2019 & 2020
1.2.6.2.3 1 902 Configure Pumps/Plumbing
904 1.2 1.2.6.2.4 Charge Pump Soft-starter Box Rebuild (four units) Not Started C 5 1 86d 04/07/22 08/04/22 04/07/22 8:00 AM 08/04/22 4:59 PM 902 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Costs: from Gen1, PY07 Budget
CE:
$ 28,600 - Submerssible pumps (2-RWS,2-Return)
$ 16,962 - High Pressure Pump, Motor & Stand
$ 8,800 - VT Pumps (2)
$ 6,600 - Charge Pumps (2)
----------------------------------
$60,962

Procurements divided betwen 2019 & 2020
1.2.6.2.4 1 903 Charge Pump Soft-starter Box Rebuild (four units)
905 1.2 1.2.6.2.5 Procure Repair/Replacement Components (PY5) Not Started C 5 1 14d 04/01/23 04/19/23 04/01/23 8:00 AM 04/19/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Costs: from Gen1, PY07 Budget
CE:
$ 28,600 - Submerssible pumps (2-RWS,2-Return)
$ 16,962 - High Pressure Pump, Motor & Stand
$ 8,800 - VT Pumps (2)
$ 6,600 - Charge Pumps (2)
----------------------------------
$60,962

Procurements divided betwen 2019 & 2020
1.2.6.2.5 1 904 Procure Repair/Replacement Components (PY5)
906 1.2 1.2.6.2.6 Procure Repair/Replacement Components (PY6) Not Started C 5 1 14d 04/01/24 04/18/24 04/01/24 8:00 AM 04/18/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Costs: from Gen1, PY07 Budget
CE:
$ 28,600 - Submerssible pumps (2-RWS,2-Return)
$ 16,962 - High Pressure Pump, Motor & Stand
$ 8,800 - VT Pumps (2)
$ 6,600 - Charge Pumps (2)
----------------------------------
$60,962

Procurements divided betwen 2019 & 2020
1.2.6.2.6 1 905 Procure Repair/Replacement Components (PY6)
907 1.2 1.2.6.3 Filtration and Condensate Management Started P 4 1 557d 11/01/20 12/19/22 11/01/20 8:00 AM 12/19/22 4:59 PM 31% 71.00% Green Note: some of the target % do not look correct $0.00 $0.00 $7,410.67 $23,881.48 31% Ian McEwen 1.2.6.3 1 906 Filtration and Condensate Management
908 1.2 1.2.6.3.1 Define Requirements & Research Methodologies Complete C 5 1 45d 11/01/20 12/31/20 11/01/20 8:00 AM 12/31/20 4:59 PM 99% 100% Gray need better requirements definition from physics $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.6.3.1 1 907 Define Requirements & Research Methodologies
909 1.2 1.2.6.3.2 Confirm w/ASC & NSF - Disposal of Condensate Not Started C 5 1 20d 03/01/22 03/28/22 03/01/22 8:00 AM 03/28/22 4:59 PM 50% 0% Red in progress $719.99 $1,439.98 $719.99 $1,439.98 50% $0.00 Ian McEwen PSL_Engineer 2000 gals/hole x 7 holes = 14,000 gals
Ice melt water - trace elements from heaters, hose, tanks
1.2.6.3.2 1 908 Confirm w/ASC & NSF - Disposal of Condensate
910 1.2 1.2.6.3.3 Develop Drilling Algorithms Complete C 5 1 75d 03/01/22 06/13/22 03/01/22 8:00 AM 06/13/22 4:59 PM 908SS 0% 100% Gray Have a baseline set of drill strategies $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer This is to include: idleing at bottom of hole for 2 hours; drilling a 40 (?) hour hole? 70cm 1.2.6.3.3 1 909 Develop Drilling Algorithms
911 1.2 1.2.6.3.4 Review & Identify Filtration Sub-System Upgrades Complete C 5 1 75d 06/14/22 09/26/22 06/14/22 8:00 AM 09/26/22 4:59 PM 909 0% 100% Gray need better requirements definition from physics $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.6.3.4 1 910 Review & Identify Filtration Sub-System Upgrades
912 1.2 1.2.6.3.5 Procure Filtration Upgrade-Replacement Components Started C 5 1 60d 09/27/22 12/19/22 09/27/22 8:00 AM 12/19/22 4:59 PM 910 0% 95.00% Green summer of 2020 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 6 Bag Filters
Plumbing & Instrumentation
Booster Pump System
Centrifugal Filters
1.2.6.3.5 1 911 Procure Filtration Upgrade-Replacement Components
913 1.2 1.2.6.3.6 Build & Test Filtration System Started C 5 1 22d 04/28/22 05/27/22 04/28/22 8:00 AM 05/27/22 4:59 PM 100% 95.00% Green $4,791.58 $4,791.58 $4,791.58 $4,791.58 100% $4,552.00 Ian McEwen Driller_PSL_Lead 1.2.6.3.6 1 912 Build & Test Filtration System
914 1.2 1.2.6.3.7 Design Condensate Collection, Treatment, and Disposal System Started C 5 1 60d 02/19/22 05/12/22 02/19/22 8:00 AM 05/12/22 4:59 PM 100% 25.00% Red $1,899.10 $1,899.10 $1,899.10 $1,899.10 100% $474.78 Ian McEwen Driller_PSL_Lead 1.2.6.3.7 1 913 Design Condensate Collection, Treatment, and Disposal System
915 1.2 1.2.6.3.8 Procure Condensate Disposal System Components Not Started C 5 1 23d 06/15/22 07/15/22 06/15/22 8:00 AM 07/15/22 4:59 PM 0% 0% Green $0.00 $15,750.83 $0.00 $15,750.83 0% $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.3.8 1 914 Procure Condensate Disposal System Components
916 1.2 1.2.6.3.9 Construct/Test Condensate Disposal System Not Started C 5 1 25d 07/18/22 08/19/22 07/18/22 8:00 AM 08/19/22 4:59 PM 914 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.3.9 1 915 Construct/Test Condensate Disposal System
917 1.2 1.2.6.4 Interconnects - External Started P 4 1 1253d 09/13/19 07/05/24 09/13/19 8:00 AM 07/05/24 4:59 PM 0% 60.0% Green $0.00 $0.00 $0.00 $30,679.70 0% Ian McEwen 1.2.6.4 1 916 Interconnects - External
918 1.2 1.2.6.4.1 Procure Replacements and Spares/Unheated (IVG Hose) Complete C 5 1 240d 09/13/19 08/13/20 09/13/19 8:00 AM 08/13/20 4:59 PM 100% 100% Gray This activity was started earlier than planned to take advantage of discount offer from IVG. SSJ has been submitted for gov waiver. Optimistic IVG deadline $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer Blue IVG Hose MDS hose.
Budgetary estimate from IVG
Paolo Valende 07/09/18
IVG_budgetaryestimateworksheet_20180709b.xlsx
1.2.6.4.1 1 917 Procure Replacements and Spares/Unheated (IVG Hose)
919 1.2 1.2.6.4.2 Identify/Spec Replacements and Spare Heated Hose Not Started C 5 1 20d 05/01/22 05/26/22 05/01/22 8:00 AM 05/26/22 4:59 PM 0% 0% Green in progress $0.00 $4,799.93 $0.00 $4,799.93 0% $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer 1.2.6.4.2 1 918 Identify/Spec Replacements and Spare Heated Hose
920 1.2 1.2.6.4.3 Procure Replacements and Spares Not Started C 5 1 20d 05/01/22 05/26/22 05/01/22 8:00 AM 05/26/22 4:59 PM 0% 0% Green $0.00 $9,799.93 $0.00 $9,799.93 0% $0.00 Ian McEwen PSL_Drill_Manager, PSL_Engineer Engineering Judgement $50,000
(Gen1 - 1st order - $100,000)
1.2.6.4.3 1 919 Procure Replacements and Spares
921 1.2 1.2.6.4.4 Procure Remaining Materials & Fabricate Heated Hose Not Started C 5 1 45d 05/10/22 07/11/22 05/10/22 8:00 AM 07/11/22 4:59 PM 0% 0% Green $0.00 $14,599.85 $0.00 $14,599.85 0% $0.00 Ian McEwen PSL_Drill_Manager, PSL_Engineer Engineering Judgement $50,000
(Gen1 - 1st order - $100,000)
1.2.6.4.4 1 920 Procure Remaining Materials & Fabricate Heated Hose
922 1.2 1.2.6.4.5 Assemble Hose End Ball Valves Complete C 5 1 30d 05/27/22 07/07/22 05/27/22 8:00 AM 07/07/22 4:59 PM 918FF, 919 0% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Drill_Manager, PSL_Engineer Engineering Judgement $50,000
(Gen1 - 1st order - $100,000)
1.2.6.4.5 1 921 Assemble Hose End Ball Valves
923 1.2 1.2.6.4.6 Finalize Design Gen Water Loop Not Started C 5 1 30d 07/08/22 08/18/22 07/08/22 8:00 AM 08/18/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Drill_Manager, PSL_Engineer Engineering Judgement $50,000
(Gen1 - 1st order - $100,000)
1.2.6.4.6 1 922 Finalize Design Gen Water Loop
924 1.2 1.2.6.4.7 Procure Gen Water Loop Materials & Assemble Not Started C 5 1 32d 05/23/24 07/05/24 05/23/24 8:00 AM 07/05/24 4:59 PM 922, 925 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Drill_Manager, PSL_Engineer Engineering Judgement $50,000
(Gen1 - 1st order - $100,000)
1.2.6.4.7 1 923 Procure Gen Water Loop Materials & Assemble
925 1.2 1.2.6.4.8 Procure Camp and Surface Hose Insulation (PY4) Not Started C 5 1 15d 07/02/22 07/21/22 07/02/22 8:00 AM 07/21/22 4:59 PM 0% 0% Green $0.00 $1,479.99 $0.00 $1,479.99 0% $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.6.4.8 1 924 Procure Camp and Surface Hose Insulation (PY4)
926 1.2 1.2.6.4.9 Procure External Interconnect Materials (PY6) Not Started C 5 1 15d 05/02/24 05/22/24 05/02/24 8:00 AM 05/22/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Software Engineer 1.2.6.4.9 1 925 Procure External Interconnect Materials (PY6)
927 1.2 1.2.6.5 MDS Internal Hoses Started P 4 1 40d 04/01/24 05/24/24 04/01/24 8:00 AM 05/24/24 4:59 PM 0% 24.00% Green $0.00 $0.00 $0.00 $5,179.97 0% Ian McEwen 1.2.6.5 1 926 MDS Internal Hoses
928 1.2 1.2.6.5.1 Identify Replacement Water Hoses (1-1/2", 3/4", and 1/2" Hose) Started C 5 1 20d 04/01/24 04/26/24 04/01/24 8:00 AM 04/26/24 4:59 PM 0% 36.00% Green Recon Season 19/20 Activity, delayed, limited retro access $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer 1.2.6.5.1 1 927 Identify Replacement Water Hoses (1-1/2", 3/4", and 1/2" Hose)
929 1.2 1.2.6.5.2 Identify Replacement Fuel Hoses Started C 5 1 20d 04/01/24 04/26/24 04/01/24 8:00 AM 04/26/24 4:59 PM 927SS 0% 36.00% Green Recon Season 19/20 Activity, delayed, limited retro access $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer 1.2.6.5.2 1 928 Identify Replacement Fuel Hoses
930 1.2 1.2.6.5.3 Procure Replacements and Spares Not Started C 5 1 20d 04/29/24 05/24/24 04/29/24 8:00 AM 05/24/24 4:59 PM 927, 928 0% 0% Green delayed $0.00 $5,179.97 $0.00 $5,179.97 0% $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer see "Aeroquip Internal Water Hose Cost Estimate" and referenced quote 1.2.6.5.3 1 929 Procure Replacements and Spares
931 1.2 1.2.6.6 ARA Hot Water Drill Subsystem Started P 4 1 160d 02/03/22 09/15/22 02/03/22 8:00 AM 09/15/22 8:00 AM 30% 35.00% Green $0.00 $0.00 $15,879.96 $53,219.79 30% Ian McEwen 1.2.6.6 1 930 ARA Hot Water Drill Subsystem
932 1.2 1.2.6.6.1 Design & Specify ARA Drill System Upgrades Started P 5 1 125d 02/03/22 07/27/22 02/03/22 8:00 AM 07/27/22 4:59 PM 0 35.00% Green delayed, limited site access $0.00 $3,759.99 $0.00 $3,759.99 0% Ian McEwen Driller_PSL_Lead 1.2.6.6.1 1 931 Design & Specify ARA Drill System Upgrades
933 1.2 1.2.6.6.1.1 Overall System Redesign and Integration Plan Started C 6 1 60d 02/03/22 04/27/22 02/03/22 8:00 AM 04/27/22 4:59 PM 0% 65.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.1.1 1 932 Overall System Redesign and Integration Plan
934 1.2 1.2.6.6.1.2 Design and Spec Pump and Downhole Assembly Started C 6 1 15d 04/28/22 05/18/22 04/28/22 8:00 AM 05/18/22 4:59 PM 932 0% 10.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire New pump $5507
New pressure transducers $3120
Other maintaintenance and replace $9000
See 1.2.6.6 BOE
1.2.6.6.1.2 1 933 Design and Spec Pump and Downhole Assembly
935 1.2 1.2.6.6.1.3 Design and Spec Pump Motor Controller Box Started C 6 1 15d 04/28/22 05/18/22 04/28/22 8:00 AM 05/18/22 4:59 PM 932 0% 30.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead 1.2.6.6.1.3 1 934 Design and Spec Pump Motor Controller Box
936 1.2 1.2.6.6.1.4 Specify Sensors Started C 6 1 15d 04/28/22 05/18/22 04/28/22 8:00 AM 05/18/22 4:59 PM 932 0% 65.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.1.4 1 935 Specify Sensors
937 1.2 1.2.6.6.1.5 Design Network/e-stop Interface Box Started C 6 1 65d 04/28/22 07/27/22 04/28/22 8:00 AM 07/27/22 4:59 PM 932 0% 10.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire New pump $5507
New pressure transducers $3120
Other maintaintenance and replace $9000
See 1.2.6.6 BOE
1.2.6.6.1.5 1 936 Design Network/e-stop Interface Box
938 1.2 1.2.6.6.1.6 Design HotBox Plumbing Manifold II Started C 6 1 25d 04/28/22 06/01/22 04/28/22 8:00 AM 06/01/22 4:59 PM 932 0% 30.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead 1.2.6.6.1.6 1 937 Design HotBox Plumbing Manifold II
939 1.2 1.2.6.6.2 Procure Repair Parts, Replacements, Spares Started P 5 1 15d 03/15/22 04/04/22 03/15/22 8:00 AM 04/04/22 4:59 PM 0.34091903 34.00% Green delayed, limited site access $15,879.96 $46,579.85 $15,879.96 $46,579.85 34% Ian McEwen Driller_PSL_Lead 1.2.6.6.2 1 938 Procure Repair Parts, Replacements, Spares
940 1.2 1.2.6.6.2.1 Pumps & Motors Started C 6 1 15d 03/15/22 04/04/22 03/15/22 8:00 AM 04/04/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.2.1 1 939 Pumps & Motors
941 1.2 1.2.6.6.2.2 Downhole Assembly Hardware (Mat'l, Fab, & Nozzles) Started C 6 1 15d 03/15/22 04/04/22 03/15/22 8:00 AM 04/04/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.2.2 1 940 Downhole Assembly Hardware (Mat'l, Fab, & Nozzles)
942 1.2 1.2.6.6.2.3 Pump Motor Control Box Started C 6 1 15d 03/15/22 04/04/22 03/15/22 8:00 AM 04/04/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.2.3 1 941 Pump Motor Control Box
943 1.2 1.2.6.6.2.4 Sensors Started C 6 1 15d 03/15/22 04/04/22 03/15/22 8:00 AM 04/04/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.2.4 1 942 Sensors
944 1.2 1.2.6.6.2.5 Network/e-stop Interface Box Components Started C 6 1 15d 03/15/22 04/04/22 03/15/22 8:00 AM 04/04/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.2.5 1 943 Network/e-stop Interface Box Components
945 1.2 1.2.6.6.2.6 HotBox II Plumbing Started C 6 1 15d 03/15/22 04/04/22 03/15/22 8:00 AM 04/04/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.2.6 1 944 HotBox II Plumbing
946 1.2 1.2.6.6.2.7 Control Center Instrument tie-in Started C 6 1 15d 03/15/22 04/04/22 03/15/22 8:00 AM 04/04/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.2.7 1 945 Control Center Instrument tie-in
947 1.2 1.2.6.6.2.8 Additional Hose, Cabling, Plumbing, & Hardware Started C 6 1 15d 03/15/22 04/04/22 03/15/22 8:00 AM 04/04/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.2.8 1 946 Additional Hose, Cabling, Plumbing, & Hardware
948 1.2 1.2.6.6.3 Subsystem Assembly, Integration, & Testing at PSL Started P 5 1 15d 07/03/22 07/21/22 07/03/22 8:00 AM 07/21/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $2,879.96 $0.00 $2,879.96 0% Ian McEwen Driller_PSL_Lead 1.2.6.6.3 1 947 Subsystem Assembly, Integration, & Testing at PSL
949 1.2 1.2.6.6.3.1 Legacy Pump Module Assessment Started C 6 1 15d 07/03/22 07/21/22 07/03/22 8:00 AM 07/21/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.3.1 1 948 Legacy Pump Module Assessment
950 1.2 1.2.6.6.3.2 Fab Downhole Assembly Parts and Assemblies Started C 6 1 15d 07/03/22 07/21/22 07/03/22 8:00 AM 07/21/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.3.2 1 949 Fab Downhole Assembly Parts and Assemblies
951 1.2 1.2.6.6.3.3 Assemble Downhole Assemblies Started C 6 1 15d 07/03/22 07/21/22 07/03/22 8:00 AM 07/21/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.3.3 1 950 Assemble Downhole Assemblies
952 1.2 1.2.6.6.3.4 Configure Pump Motor Controller Started C 6 1 15d 07/03/22 07/21/22 07/03/22 8:00 AM 07/21/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.3.4 1 951 Configure Pump Motor Controller
953 1.2 1.2.6.6.3.5 Test New Downhole Assemblies with Controller Started C 6 1 15d 07/03/22 07/21/22 07/03/22 8:00 AM 07/21/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.3.5 1 952 Test New Downhole Assemblies with Controller
954 1.2 1.2.6.6.3.6 Build and Test Network/e-stop Interface Box Started C 6 1 15d 07/03/22 07/21/22 07/03/22 8:00 AM 07/21/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.3.6 1 953 Build and Test Network/e-stop Interface Box
955 1.2 1.2.6.6.3.7 Test SplashCam Camera System Started C 6 1 15d 07/03/22 07/21/22 07/03/22 8:00 AM 07/21/22 4:59 PM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.3.7 1 954 Test SplashCam Camera System
956 1.2 1.2.6.6.4 ARA System Ready to Pack for Shipment Started C 5 1 1 0 09/15/22 09/15/22 09/15/22 8:00 AM 09/15/22 8:00 AM 0 34.00% Green delayed, limited site access $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead 1.2.6.6.4 1 955 ARA System Ready to Pack for Shipment
957 1.2 1.2.7 Support Equipment - Off-ice Started P 3 1 1948d 10/01/18 03/31/26 10/01/18 8:00 AM 03/31/26 4:59 PM 20.41% 40.0% Green $0.00 $0.00 $13,664.92 $66,956.56 20% Ian McEwen 1.2.7 1 956 Support Equipment - Off-ice
958 1.2 1.2.7.1 Independent Firn Drill Started P 4 1 935d 04/01/19 10/28/22 04/01/19 8:00 AM 10/28/22 4:59 PM 100% 96.00% Green $0.00 $0.00 $1,359.99 $1,359.99 100% Ian McEwen 1.2.7.1 1 957 Independent Firn Drill
959 1.2 1.2.7.1.1 System Evalation & Testing at PSL Complete C 5 1 40d 04/01/19 05/24/19 04/01/19 8:00 AM 05/24/19 4:59 PM 99% 100% Gray Hiring delays $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician 1.2.7.1.1 1 958 System Evalation & Testing at PSL
960 1.2 1.2.7.1.2 Identify & Procure Upgrade-Replacements, Spares Complete C 5 1 40d 05/27/19 07/19/19 05/27/19 8:00 AM 07/19/19 4:59 PM 958 99% 100% Gray Hiring delays $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Technician Combination of vendor quotes and engineering estimates
Replace heaters, pumps, shelter, inst. hyd pot union
1.2.7.1.2 1 959 Identify & Procure Upgrade-Replacements, Spares
961 1.2 1.2.7.1.3 Final Install & Testing at PSL Complete C 5 1 60d 07/22/19 10/11/19 07/22/19 8:00 AM 10/11/19 4:59 PM 959 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Technician 1.2.7.1.3 1 960 Final Install & Testing at PSL
962 1.2 1.2.7.1.4 Prepare to Ship Complete C 5 1 5d 10/14/19 10/18/19 10/14/19 8:00 AM 10/18/19 4:59 PM 960 93% 100% Gray Will ship 11/15 and still make vessel (as planned) $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead 1.2.7.1.4 1 961 Prepare to Ship
963 1.2 1.2.7.1.5 Ship IFD to McMurdo (VSL-ZCM, Traverse-NPX) Complete C 5 1 1 1 0 10/18/19 10/18/19 10/18/19 4:59 PM 10/18/19 4:59 PM 961 100% 100% Gray IFD is in McM $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

1 - Dedicated truck
1.2.7.1.5 1 962 Ship IFD to McMurdo (VSL-ZCM, Traverse-NPX)
964 1.2 1.2.7.1.6 Procure Brake Solenoid Complete C 5 1 5d 10/21/21 10/27/21 10/21/21 8:00 AM 10/27/21 4:59 PM 100% 100% Gray IFD is in McM $1,359.99 $1,359.99 $1,359.99 $1,359.99 100% $1,359.99 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

1 - Dedicated truck
1.2.7.1.6 1 963 Procure Brake Solenoid
965 1.2 1.2.7.1.7 IFD Follow-up Tasks (PY5) Started C 5 1 15d 10/10/22 10/28/22 10/10/22 8:00 AM 10/28/22 4:59 PM 0% 55% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead 1.2.7.1.7 1 964 IFD Follow-up Tasks (PY5)
966 1.2 1.2.7.2 Maintenance/Repair Inventory Started P 4 1 893d 01/01/22 06/11/25 01/01/22 8:00 AM 06/11/25 4:59 PM 21% 37.00% Green $0.00 $0.00 $7,879.96 $37,959.80 21% Ian McEwen 1.2.7.2 1 965 Maintenance/Repair Inventory
967 1.2 1.2.7.2.1 Identify Spares and Replacements Started C 5 1 300d 01/01/22 02/23/23 01/01/22 8:00 AM 02/23/23 4:59 PM 67% 55% Yellow $1,919.97 $2,879.96 $1,919.97 $2,879.96 67% $1,583.98 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead 1.2.7.2.1 1 966 Identify Spares and Replacements
968 1.2 1.2.7.2.2 Procure Spares and Replacements Started C 5 1 851d 03/01/22 06/11/25 03/01/22 8:00 AM 06/11/25 4:59 PM 966SS +41d 46% 32% Yellow $5,959.99 $12,879.96 $5,959.99 $12,879.96 46% $4,121.59 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Spare parts & inventory procurement across all 5 years.
Engineering estimate
1.2.7.2.2 1 967 Procure Spares and Replacements
969 1.2 1.2.7.2.3 Procure Hose Stock and Fittings (PY4) Started C 5 1 30d 02/01/22 03/14/22 02/01/22 8:00 AM 03/14/22 4:59 PM 0% 40% Green $0.00 $17,399.96 $0.00 $17,399.96 0% $6,959.99 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Spare parts & inventory procurement across all 5 years.
Engineering estimate
1.2.7.2.3 1 968 Procure Hose Stock and Fittings (PY4)
970 1.2 1.2.7.2.4 Procure Hose Stock and Fittings (FY5) Started C 5 1 30d 05/01/23 06/09/23 05/01/23 8:00 AM 06/09/23 4:59 PM 0% 40% Green $0.00 $4,799.93 $0.00 $4,799.93 0% $1,919.97 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Spare parts & inventory procurement across all 5 years.
Engineering estimate
1.2.7.2.4 1 969 Procure Hose Stock and Fittings (FY5)
971 1.2 1.2.7.2.5 Spare Parts Inventory and Catalog - Electrical/Controls Started C 5 1 170d 05/01/23 12/26/23 05/01/23 8:00 AM 12/26/23 4:59 PM 969SS 0% 32% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Spare parts & inventory procurement across all 5 years.
Engineering estimate
1.2.7.2.5 1 970 Spare Parts Inventory and Catalog - Electrical/Controls
972 1.2 1.2.7.3 Shops (MECC, SEW, TOW, OML) Not Started P 4 1 313d 06/01/22 08/11/23 06/01/22 8:00 AM 08/11/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.7.3 1 971 Shops (MECC, SEW, TOW, OML)
973 1.2 1.2.7.3.1 Identify Upgrade-Replacements, Spares Not Started C 5 1 281d 06/01/22 06/28/23 06/01/22 8:00 AM 06/28/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead 1.2.7.3.1 1 972 Identify Upgrade-Replacements, Spares
974 1.2 1.2.7.3.2 Procure Upgrade-Replacements, Spares Not Started C 5 1 204d 11/01/22 08/11/23 11/01/22 8:00 AM 08/11/23 4:59 PM 972SS +109d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Gen1 Budget for Repairs & Parts - Capitalized for Upgrade
Work benches, Power connectors
1.2.7.3.2 1 973 Procure Upgrade-Replacements, Spares
975 1.2 1.2.7.4 TestBed Started P 4 1 1948d 10/01/18 03/31/26 10/01/18 8:00 AM 03/31/26 4:59 PM 25% 42.00% Green $0.00 $0.00 $2,822.23 $11,354.14 25% Ian McEwen 1.2.7.4 1 974 TestBed
976 1.2 1.2.7.4.1 Commissioning for Motor Drive Testing (2018) Complete C 5 1 120d 10/01/18 03/15/19 10/01/18 8:00 AM 03/15/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer 1.2.7.4.1 1 975 Commissioning for Motor Drive Testing (2018)
977 1.2 1.2.7.4.2 Identify & Procure Upgrade & Replacement Parts Complete C 5 1 160d 03/18/19 10/25/19 03/18/19 8:00 AM 10/25/19 4:59 PM 975 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician Tools, tower parts, hose, filters, TU15 repairs/upgrades, fuel system
Engineering estimate
1.2.7.4.2 1 976 Identify & Procure Upgrade & Replacement Parts
978 1.2 1.2.7.4.3 Commission/Maintainence/Decommission (2019) Complete C 5 1 160d 04/15/19 11/22/19 04/15/19 8:00 AM 11/22/19 4:59 PM 100% 100% Gray Shut down activities planned for late Nov, then will be at 100% $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician 1.2.7.4.3 1 977 Commission/Maintainence/Decommission (2019)
979 1.2 1.2.7.4.4 Commission/Maintainence/Decommission (2020) Complete C 5 1 160d 04/13/20 11/20/20 04/13/20 8:00 AM 11/20/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician 1.2.7.4.4 1 978 Commission/Maintainence/Decommission (2020)
980 1.2 1.2.7.4.5 Commission/Maintenance/Decommission (PY3) Complete C 5 1 160d 02/12/21 09/23/21 02/12/21 8:00 AM 09/23/21 4:59 PM 100% 100% Gray $2,822.23 $2,822.23 $2,822.23 $2,822.23 100% $2,822.23 Ian McEwen PSL_Engineer, PSL_Technician 1.2.7.4.5 1 979 Commission/Maintenance/Decommission (PY3)
981 1.2 1.2.7.4.6 Commission/Maintenance/Decommission (PY4) Not Started C 5 1 159d 02/11/22 09/21/22 02/11/22 8:00 AM 09/21/22 4:59 PM 0 0% Green $0.00 $8,531.91 $0.00 $8,531.91 0% Ian McEwen PSL_Engineer, PSL_Technician 1.2.7.4.6 1 980 Commission/Maintenance/Decommission (PY4)
982 1.2 1.2.7.4.7 Commission/Maintenance/Decommission (PY5) Not Started C 5 1 260d 10/03/22 09/29/23 10/03/22 8:00 AM 09/29/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician 1.2.7.4.7 1 981 Commission/Maintenance/Decommission (PY5)
983 1.2 1.2.7.4.8 Commission/Maintenance/Decommission (PY6) Not Started C 5 1 258d 10/02/23 09/30/24 10/02/23 8:00 AM 09/30/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician 1.2.7.4.8 1 982 Commission/Maintenance/Decommission (PY6)
984 1.2 1.2.7.4.9 Commission/Maintenance/Decommission (PY7) Not Started C 5 1 258d 10/01/24 09/30/25 10/01/24 8:00 AM 09/30/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician 1.2.7.4.9 1 983 Commission/Maintenance/Decommission (PY7)
985 1.2 1.2.7.4.10 Commission/Maintenance/Decommission (PY8) Not Started C 5 1 127d 10/01/25 03/31/26 10/01/25 8:00 AM 03/31/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer, PSL_Technician 1.2.7.4.10 1 984 Commission/Maintenance/Decommission (PY8)
986 1.2 1.2.7.5 Tools and Equipment Started P 4 1 1669d 03/01/19 07/31/25 03/01/19 8:00 AM 07/31/25 4:59 PM 10% 15.00% Green $0.00 $0.00 $1,602.76 $16,282.64 10% Ian McEwen 1.2.7.5 1 985 Tools and Equipment
987 1.2 1.2.7.5.1 Procure 287B Skidsteer (or similar) Complete C 5 1 29d 08/21/19 09/30/19 08/21/19 8:00 AM 09/30/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire 12/17/18 - Quote from Fabick Cat. My aount includes 5.5% sales tax

12/12/18 - Estimate provided by Fabickcat sales rep, requested detailed quote

11/1/18 - ASC (Street) recommends IceCube purchase dedicated skidsteer, as NPX fleet is aging as well as can not confirm usage due to competition and condition
1.2.7.5.1 1 986 Procure 287B Skidsteer (or similar)
988 1.2 1.2.7.5.2 Procure 2 Snowmobiles Complete C 5 1 29d 08/21/19 09/30/19 08/21/19 8:00 AM 09/30/19 4:59 PM 986FF 99% 100% Gray 2 snowmos procured and shipped 2019 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire 4 - Snomobiles - IceCube PO $7,969 in 2009 x 20% inflation
4 - Cargo Sleds - IceCube PO $2,250 in 2009 x 20% inflation

Shipped to PSL for retrofit with block heaters, then shipped with Oct 2020 cargo for vessel to ZCM. Traverse to NPX in Nov 2021

Logistics:
4 Crates @ 300 for crating (must rebuild for shipment to NPX)
1.2.7.5.2 1 987 Procure 2 Snowmobiles
989 1.2 1.2.7.5.3 Ship 2 Snowmobiles Complete C 5 1 1 1d 09/30/19 09/30/19 09/30/19 8:00 AM 09/30/19 4:59 PM 987FF 100% 100% Gray 2 snowmos arrived at NPX 12/19, 287 in McMurdo, 2 more snowmos to ship 20/21 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

1 - Dedicated truck
1.2.7.5.3 1 988 Ship 2 Snowmobiles
990 1.2 1.2.7.5.4 Identify Tools & Equipment, & Consumables Should have Started C 5 1 936d 03/01/19 09/30/22 03/01/19 8:00 AM 09/30/22 4:59 PM 0% 0% Green $0.00 $6,719.90 $0.00 $6,719.90 0% $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead 1.2.7.5.4 1 989 Identify Tools & Equipment, & Consumables
991 1.2 1.2.7.5.5 Procure Tools & Equipment, & Consumables Started C 5 1 1669d 03/01/19 07/31/25 03/01/19 8:00 AM 07/31/25 4:59 PM 989SS 0% 20% Green $0.00 $7,959.99 $0.00 $7,959.99 0% $1,592.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Gen1 - This was an average annual budget for consumable tools, batteries, etc. 1.2.7.5.5 1 990 Procure Tools & Equipment, & Consumables
992 1.2 1.2.7.5.6 Complete Hose Crimper Calibration Complete C 5 1 7d 10/10/21 10/18/21 10/10/21 8:00 AM 10/18/21 4:59 PM 100% 100% Gray $1,602.76 $1,602.76 $1,602.76 $1,602.76 100% $1,602.76 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead Gen1 - This was an average annual budget for consumable tools, batteries, etc. 1.2.7.5.6 1 991 Complete Hose Crimper Calibration
993 1.2 1.2.8 Drill Field Seasons - Antarctica Started P 3 1 1904d 11/02/18 03/03/26 11/02/18 8:00 AM 03/03/26 4:59 PM 0.00% 7.00% Green $0.00 $0.00 $0.00 $84,798.90 0% Ian McEwen 1.2.8 1 992 Drill Field Seasons - Antarctica
994 1.2 1.2.8.1 Seasonal Staffing & Training, Off-Ice Coordination Started P 4 1 1777d 11/02/18 09/02/25 11/02/18 8:00 AM 09/02/25 4:59 PM 0.00% 4.00% Green $0.00 $0.00 $0.00 $43,297.90 0% Ian McEwen 1.2.8.1 1 993 Seasonal Staffing & Training, Off-Ice Coordination
995 1.2 1.2.8.1.1 2019 Off-Ice EHWD & Safety Training - 12 Drillers Complete C 5 1 5d 07/29/19 08/02/19 07/29/19 8:00 AM 08/02/19 4:59 PM 93% 100% Gray Draft training plan developed $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_Contributed, Driller_PSL_DirectHire, Driller_PSL_Lead DRILL TEAM 8 for Training
Travel Costs - 3 local, 4 domestic, 1 international

Domestic Flights - 4 (@$500) = $2,000
International Flights - 1 (@ $1,000) = $1,000
*Hotel Rooms (@$122) x 5 x 5 nights = $2,562
*Per Diem (@$54) x 5 x 5 = $1,134

TOTAL = $6,696

*WI - Federal Rates, 2018
1.2.8.1.1 1 994 2019 Off-Ice EHWD & Safety Training - 12 Drillers
996 1.2 1.2.8.1.2 FS1 Off-Ice Safety Training & PPE Procurement - 10 FTE Drillers (10-primary 2-alternates) & 1 Safety Officer Not Started C 5 1 60d 05/31/23 08/22/23 05/31/23 8:00 AM 08/22/23 4:59 PM 0% 0% Green ADJUST FOR RESOURCE LOADING $0.00 $43,297.90 $0.00 $43,297.90 0% $0.00 Ian McEwen Driller_Contributed, Driller_PSL_DirectHire, Driller_PSL_Lead DRILL TEAM 30 for Training (15 direct, 15 contributed)
1-Dar
10-Drillers (direct hires)
15-Drillers (contributed)
4-PSL Engineers/Others

Travel Costs - 4 local, 18 domestic, 8 int'l
Domestic Flights - 18 (@$500) = $9,000
International Flights - 8 (@ $1,000) = $8,000
*Hotel Rooms (@$122) x 26 x 13 nights = $41,236
*Per Diem (@$54) x 26 x 13 days = $18,252

TOTAL = $76,488

*WI - Federal Rates, 2018
1.2.8.1.2 1 995 FS1 Off-Ice Safety Training & PPE Procurement - 10 FTE Drillers (10-primary 2-alternates) & 1 Safety Officer
997 1.2 1.2.8.1.3 FS2 Off-Ice Safety Training & PPE Procurement - 16 Drillers (14 - Primary 2 - alternates) & 1 Safety Officer Not Started C 5 1 60d 05/31/24 08/22/24 05/31/24 8:00 AM 08/22/24 4:59 PM 0% 0% Green ADJUST FOR RESOURCE LOADING $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_Contributed, Driller_PSL_DirectHire, Driller_PSL_Lead DRILL TEAM 30 for Training (15 direct, 15 contributed)
1-Dennis
10-Drillers (direct hires)
15-Drillers (contributed)
4-PSL Engineers/Others

Travel Costs - 4 local, 18 domestic, 8 int'l
Domestic Flights - 18 (@$500) = $9,000
International Flights - 8 (@ $1,000) = $8,000
*Hotel Rooms (@$122) x 26 x 13 nights = $41,236
*Per Diem (@$54) x 26 x 13 days = $18,252

TOTAL = $76,488

*WI - Federal Rates, 2018
1.2.8.1.3 1 996 FS2 Off-Ice Safety Training & PPE Procurement - 16 Drillers (14 - Primary 2 - alternates) & 1 Safety Officer
998 1.2 1.2.8.1.4 FS3 Off-Ice Safety Training & PPE Procurement - 32 Drillers (28 - primary 4 - alternates) & 1 Safety Officer Not Started C 5 1 60d 05/28/25 08/19/25 05/28/25 8:00 AM 08/19/25 4:59 PM 0% 0% Green ADJUST FOR RESOURCE LOADING $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_Contributed, Driller_PSL_DirectHire, Driller_PSL_Lead DRILL TEAM 30 for Training (15 direct, 15 contributed)
1-Dennis
10-Drillers (direct hires)
15-Drillers (contributed)
4-PSL Engineers/Others

Travel Costs - 4 local, 18 domestic, 8 int'l
Domestic Flights - 18 (@$500) = $9,000
International Flights - 8 (@ $1,000) = $8,000
*Hotel Rooms (@$122) x 26 x 13 nights = $41,236
*Per Diem (@$54) x 26 x 13 days = $18,252

TOTAL = $76,488

*WI - Federal Rates, 2018
1.2.8.1.4 1 997 FS3 Off-Ice Safety Training & PPE Procurement - 32 Drillers (28 - primary 4 - alternates) & 1 Safety Officer
999 1.2 1.2.8.1.5 FS3 Off-Ice Logging Winch Training with IDP (3 Drillers 1 day) Not Started C 5 1 1d 08/19/25 08/19/25 08/19/25 8:00 AM 08/19/25 4:59 PM 997FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.1.5 1 998 FS3 Off-Ice Logging Winch Training with IDP (3 Drillers 1 day)
1000 1.2 1.2.8.1.6 2018-19 Season Readiness Review Complete C 5 1 1 1d 11/02/18 11/02/18 11/02/18 8:00 AM 11/02/18 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.1.6 1 999 2018-19 Season Readiness Review
1001 1.2 1.2.8.1.7 2019-20 Season Readiness Review Complete C 5 1 1 1d 09/02/19 09/02/19 09/02/19 8:00 AM 09/02/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.1.7 1 1000 2019-20 Season Readiness Review
1002 1.2 1.2.8.1.8 FS1 Field Season Readiness Review Not Started C 5 1 1 1 1d 09/02/23 09/02/23 09/02/23 8:00 AM 09/02/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.1.8 1 1001 FS1 Field Season Readiness Review
1003 1.2 1.2.8.1.9 FS2 Field Season Readiness Review Not Started C 5 1 1 1 1d 09/02/24 09/02/24 09/02/24 8:00 AM 09/02/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.1.9 1 1002 FS2 Field Season Readiness Review
1004 1.2 1.2.8.1.10 FS3 Field Season Readiness Review Not Started C 5 1 1 1 1d 09/02/25 09/02/25 09/02/25 8:00 AM 09/02/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.1.10 1 1003 FS3 Field Season Readiness Review
1005 1.2 1.2.8.2 2019/20 On-Ice Activities Complete P 4 1 156d 10/26/19 05/29/20 10/26/19 8:00 AM 05/29/20 4:59 PM 95.71% 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen - Deployment/Redeployment
- Ground Penetrating Radar
- Tower Structural Analysis
- Follow-up retro of other at-risk components
- Chase things through McM (IFD, PDM, Fuel Tower, SALSA equip)
- Begin Component Testing
- Begin Repair/Replacements
- Fire up heaters (1-2 MDS at a time)

* Season cost higher due to no contributed drillers (per Kael 1/11/19) - adds $50k
1.2.8.2 1 1004 2019/20 On-Ice Activities
1006 1.2 1.2.8.3.1 General Complete P 5 1 151d 11/01/19 05/29/20 11/01/19 8:00 AM 05/29/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.1 1 1005 General
1007 1.2 1.2.8.3.1.1 Cargo Retro (19/20) Complete C 6 1 151d 11/01/19 05/29/20 11/01/19 8:00 AM 05/29/20 4:59 PM 100% 100% Gray Retro held in Port H. due to COVID $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Cargo estimates from John Arnolde (Logistics Mgr, PSL):
$7,000 - Dedicated truckload ($4,375 alternative, but not reliable, so using the $7k)
$ 800 - Typical 4'x4'x8' Crate (weight ~1,500#)
$ 300 - Crate Materials (4'x4'x8')

1 truck
1.2.8.3.1.1 1 1006 Cargo Retro (19/20)
1008 1.2 1.2.8.3.1.2 Deployment Travel & PQ Costs (19/20) Complete C 6 1 80d 11/01/19 02/20/20 11/01/19 8:00 AM 02/20/20 4:59 PM 1006SS 100% 100% Gray Costs will not hit until expense reports turned in Jan/Feb $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_Contributed, Driller_PSL_DirectHire, Driller_PSL_Lead, PSL_Engineer Team of 8
1-Dennis
5-Direct-Hire Drillers
0-Contributed Drillers (no MOU committments until 2020)
2-PSL Engineers

Travel Labor: 48 hrs/ea (Labor)
- 3 days paid time during deployment
- 3 days paid time during redeployment

Travel Cost: $1,200/ea (Travel)

PQ Cost: $950/ea (M&S)
1.2.8.3.1.2 1 1007 Deployment Travel & PQ Costs (19/20)
1009 1.2 1.2.8.3.2 START NPX 2019/20 Season - Team (8) Arrives [ReC/Fire/Life Safety] Complete C 5 1 1 1d 11/15/19 11/15/19 11/15/19 8:00 AM 11/15/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.2 1 1008 START NPX 2019/20 Season - Team (8) Arrives [ReC/Fire/Life Safety]
1010 1.2 1.2.8.3.3 ASC/CRREL Ground Penetrating Radar Complete P 5 1 3d 12/16/19 12/18/19 12/16/19 8:00 AM 12/18/19 4:59 PM 89% 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.3 1 1009 ASC/CRREL Ground Penetrating Radar
1011 1.2 1.2.8.3.3.1 Perform GPR - Map Area to be drilled/instrumented Complete C 6 1 3d 12/16/19 12/18/19 12/16/19 8:00 AM 12/18/19 4:59 PM 89% 100% Gray Data requires CRREL interpretation, which will not occur until Aug 2020 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Antarctic Support Contractor, Driller_PSL_Lead, PSL_Engineer 1.2.8.3.3.1 1 1010 Perform GPR - Map Area to be drilled/instrumented
1012 1.2 1.2.8.3.4 EHWD: Upgrade & Replacement Work Complete P 5 1 56d 11/15/19 01/31/20 11/15/19 8:00 AM 01/31/20 4:59 PM 95% 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.4 1 1011 EHWD: Upgrade & Replacement Work
1013 1.2 1.2.8.3.4.1 EHWD Air Shipment Arrives, Upgrade Parts Complete C 6 1 1 1 1d 11/19/19 11/19/19 11/19/19 8:00 AM 11/19/19 4:59 PM 1013 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.4.1 1 1012 EHWD Air Shipment Arrives, Upgrade Parts
1014 1.2 1.2.8.3.4.2 Excavate EHWD & Equip Berms, Compact Temp-SES (ASC) Complete C 6 1 2d 11/15/19 11/18/19 11/15/19 8:00 AM 11/18/19 4:59 PM 1016SS 91% 100% Gray Interfacing Milestone/Activity (w/ASC) $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Antarctic Support Contractor, Driller_PSL_DirectHire, Driller_PSL_Lead, PSL_Engineer 1.2.8.3.4.2 1 1013 Excavate EHWD & Equip Berms, Compact Temp-SES (ASC)
1015 1.2 1.2.8.3.4.3 Deliver MECC, Power, Heat, Outhouse to EHWD Berm Complete C 6 1 2d 11/19/19 11/20/19 11/19/19 8:00 AM 11/20/19 4:59 PM 1013 84% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Antarctic Support Contractor, Driller_PSL_DirectHire, Driller_PSL_Lead, PSL_Engineer 1.2.8.3.4.3 1 1014 Deliver MECC, Power, Heat, Outhouse to EHWD Berm
1016 1.2 1.2.8.3.4.4 Deliver & Layout Test SES for Cable/Hose Review Complete C 6 1 4d 11/19/19 11/22/19 11/19/19 8:00 AM 11/22/19 4:59 PM 1014SS 91% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire 1.2.8.3.4.4 1 1015 Deliver & Layout Test SES for Cable/Hose Review
1017 1.2 1.2.8.3.4.5 Connect Temporary Station Power throughout SES Complete C 6 1 4d 11/15/19 11/20/19 11/15/19 8:00 AM 11/20/19 4:59 PM 94% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, PSL_Engineer 1.2.8.3.4.5 1 1016 Connect Temporary Station Power throughout SES
1018 1.2 1.2.8.3.4.6 EHWD: REPAIRS & UPGRADES THROUGHOUT Complete C 6 1 45d 11/21/19 01/22/20 11/21/19 8:00 AM 01/22/20 4:59 PM 1016 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead, PSL_Engineer Team of 8 (1-Drill Mgr, 7-Drillers)

- Testing of all DGH's (1 person month)
- Electrical review, panels, transformers, module infrastructure
- Safety systems review & testing: Fire suppression, etc
- MHP: Thorough inspection, cleaning as needed, detailed report & inventory
- TU20 Rebuilds: Hydraulics, pkg & ship axles (1 person month)
- Drill Tower Structural Analysis
- Retro of suspect/test-failed equipment
- Pull all hoses and cables for inventory and begin testing
- Photograph/Measure Motor Drive Locations to design retrofit kit for new drives
1.2.8.3.4.6 1 1017 EHWD: REPAIRS & UPGRADES THROUGHOUT
1019 1.2 1.2.8.3.4.7 Perform Structural Analysis of Drill Towers Complete C 6 1 5d 11/19/19 11/25/19 11/19/19 8:00 AM 11/25/19 4:59 PM 95% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen PSL_Engineer Perform structural analysis and inspection. Methods and criteria need development. 1.2.8.3.4.7 1 1018 Perform Structural Analysis of Drill Towers
1020 1.2 1.2.8.3.4.8 ICL: Inspect and develop plan for cable access into east tower (ASC) Complete C 6 16d 01/10/20 01/31/20 01/10/20 8:00 AM 01/31/20 4:59 PM 98% 100% Gray ASC Activity - $0 cost to UW $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.4.8 1 1019 ICL: Inspect and develop plan for cable access into east tower (ASC)
1021 1.2 1.2.8.3.4.9 Pre-compact new ICL road relocation (ASC) Complete C 6 16d 01/10/20 01/31/20 01/10/20 8:00 AM 01/31/20 4:59 PM 1019SS 98% 100% Gray Interfacing Milestone/Activity (w/ASC) $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.4.9 1 1020 Pre-compact new ICL road relocation (ASC)
1022 1.2 1.2.8.3.4.10 Survey & Pre-Compact SES Complete C 6 16d 01/10/20 01/31/20 01/10/20 8:00 AM 01/31/20 4:59 PM 1020SS 98% 100% Gray Interfacing Milestone/Activity (w/ASC) $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.4.10 1 1021 Survey & Pre-Compact SES
1023 1.2 1.2.8.3.5 End of NPX Season Close-Out Work Complete P 5 1 5d 01/23/20 01/29/20 01/23/20 8:00 AM 01/29/20 4:59 PM 88% 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.5 1 1022 End of NPX Season Close-Out Work
1024 1.2 1.2.8.3.5.1 Document, Photograph Equip & Upgrade Work, Further Req's Complete C 6 1 5d 01/23/20 01/29/20 01/23/20 8:00 AM 01/29/20 4:59 PM 1017 95% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead, PSL_Engineer 1.2.8.3.5.1 1 1023 Document, Photograph Equip & Upgrade Work, Further Req's
1025 1.2 1.2.8.3.5.2 Winterize/Close/Store all EHWD Equipment Complete C 6 1 2d 01/23/20 01/24/20 01/23/20 8:00 AM 01/24/20 4:59 PM 1023SS 84% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead, PSL_Engineer 1.2.8.3.5.2 1 1024 Winterize/Close/Store all EHWD Equipment
1026 1.2 1.2.8.3.5.3 Retro all components, crate, pack and deliver to cargo Complete C 6 1 2d 01/23/20 01/24/20 01/23/20 8:00 AM 01/24/20 4:59 PM 1024SS 84% 100% Gray Interfacing Milestone/Activity (w/ASC) $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_DirectHire, Driller_PSL_Lead, PSL_Engineer 1.2.8.3.5.3 1 1025 Retro all components, crate, pack and deliver to cargo
1027 1.2 1.2.8.3.6 END NPX 2019/20 Season Complete C 5 1 1d 02/03/20 02/03/20 02/03/20 8:00 AM 02/03/20 4:59 PM 1021 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.6 1 1026 END NPX 2019/20 Season
1028 1.2 1.2.8.3.7 Other Field Activities (19/20) Complete P 5 1 71d 10/26/19 02/01/20 10/26/19 8:00 AM 02/01/20 4:59 PM 98% 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.7 1 1027 Other Field Activities (19/20)
1029 1.2 1.2.8.3.7.7 Prepare work pad (SPoTSA), provide power, fuel & support - McMurdo Complete C 6 5d 10/26/19 10/31/19 10/26/19 8:00 AM 10/31/19 4:59 PM 94% 100% Gray Interfacing Milestone/Activity (w/ASC) $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.7.7 1 1028 Prepare work pad (SPoTSA), provide power, fuel & support - McMurdo
1030 1.2 1.2.8.3.7.1 GEN 2, 3, PDM: Inspect/Test/Tune in McMurdo (incl subcontract) Complete C 6 1 23d 11/18/19 12/18/19 11/18/19 8:00 AM 12/18/19 4:59 PM 99% 100% Gray Expenses will not hit until Jan/Feb after sub-contractors invoice $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer Work w/ASC to set up testing infrastructure (tank, fuel, hoses, cables, load bank, etc). ASC to move GENs & PDM into/out of position. Sub-contractor and Engineers to determine problems, attempt to repair, develop list of components to procure (off-ice in 2020) for installation/repair work in 2020-21 season. Decide whether to hold PDM at McMurdo for rework in 2020/21 of traverse to NPX and complete tasking there.
TOTAL BUDGETED for this is $200,000
2019/20 - $50,000 for sub-contract, equipment, and tune-up parts
2020 - $100,000 for procurements of replacement parts
2020/21 - $50,000 for subcontractor to return to ZCM or NPX to perform repairs
1.2.8.3.7.1 1 1029 GEN 2, 3, PDM: Inspect/Test/Tune in McMurdo (incl subcontract)
1031 1.2 1.2.8.3.7.2 Generator-1: Arrives in ZCM (Winter Storage) Complete C 6 1 1d 02/01/20 02/01/20 02/01/20 8:00 AM 02/01/20 4:59 PM 100% 100% Gray Should arrive vessel Feb 2020 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.7.2 1 1030 Generator-1: Arrives in ZCM (Winter Storage)
1032 1.2 1.2.8.3.7.3 Fuel Tower: Inspect & Test in McMurdo Complete C 6 1 22d 11/01/19 12/02/19 11/01/19 8:00 AM 12/02/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Antarctic Support Contractor, Driller_PSL_Lead, PSL_Engineer 1.2.8.3.7.3 1 1031 Fuel Tower: Inspect & Test in McMurdo
1033 1.2 1.2.8.3.7.4 Cable Tensioner: Inspect & Test Complete C 6 1 22d 11/01/19 12/02/19 11/01/19 8:00 AM 12/02/19 4:59 PM 1031SS 99% 100% Gray This is actually at PSL, will be tested/inspected in summer 2020 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Driller_PSL_Lead, PSL_Engineer 1.2.8.3.7.4 1 1032 Cable Tensioner: Inspect & Test
1034 1.2 1.2.8.3.7.5 Reel Container: Inspect & Inventory Complete C 6 1 22d 11/01/19 12/02/19 11/01/19 8:00 AM 12/02/19 4:59 PM 1032SS 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Antarctic Support Contractor, Driller_PSL_Lead, PSL_Engineer Consists of:
Reel container
Misc other equipment
1.2.8.3.7.5 1 1033 Reel Container: Inspect & Inventory
1035 1.2 1.2.8.3.7.6 IFD: Arrival (from PSL) & Storage in McMurdo (defunct) Complete C 6 1 1 1d 02/01/20 02/01/20 02/01/20 8:00 AM 02/01/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.7.6 1 1034 IFD: Arrival (from PSL) & Storage in McMurdo (defunct)
1036 1.2 1.2.8.3 2020/21 & 2021/22 On-Ice Activities Complete P 4 1 1d 03/01/21 03/01/21 03/01/21 8:00 AM 03/01/21 4:59 PM 100.00% 100% Gray $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3 1 1035 2020/21 & 2021/22 On-Ice Activities
1037 1.2 1.2.8.3.1 Drill Pad/Road Grooming & T&L Support (ASC) Complete C 5 1d 03/01/21 03/01/21 03/01/21 8:00 AM 03/01/21 4:59 PM 100.00% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.3.1 1 1036 Drill Pad/Road Grooming & T&L Support (ASC)
1038 1.2 1.2.8.4 USAP Field Season 0 (FY23) Not Started P 4 1 189d 09/01/22 05/23/23 09/01/22 8:00 AM 05/23/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.4 1 1037 USAP Field Season 0 (FY23)
1039 1.2 1.2.8.4.1 Milestones Not Started P 5 1 108d 10/01/22 03/01/23 10/01/22 8:00 AM 03/01/23 8:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 1.2.8.4.1 1 1038 Milestones
1040 1.2 1.2.8.4.1.1 McM Mainbody Season Begins (USAP) Not Started C 6 1 1 0 10/01/22 10/01/22 10/01/22 8:00 AM 10/01/22 8:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.4.1.1 1 1039 McM Mainbody Season Begins (USAP)
1041 1.2 1.2.8.4.1.2 South Pole Season Begins (USAP) Not Started C 6 1 1 0 11/01/22 11/01/22 11/01/22 8:00 AM 11/01/22 8:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.4.1.2 1 1040 South Pole Season Begins (USAP)
1042 1.2 1.2.8.4.1.3 Pole Season Ends (USAP) Not Started C 6 1 1 0 02/15/23 02/15/23 02/15/23 8:00 AM 02/15/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.4.1.3 1 1041 Pole Season Ends (USAP)
1043 1.2 1.2.8.4.1.4 MCM Season Ends (USAP) Not Started C 6 1 1 0 03/01/23 03/01/23 03/01/23 8:00 AM 03/01/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.4.1.4 1 1042 MCM Season Ends (USAP)
1044 1.2 1.2.8.4.2 Cargo Movements (USAP) Not Started P 5 1 97d 10/01/22 02/13/23 10/01/22 8:00 AM 02/13/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.4.2 1 1043 Cargo Movements (USAP)
1045 1.2 1.2.8.4.2.1 Pole (USAP) Not Started P 6 1 75d 11/01/22 02/13/23 11/01/22 8:00 AM 02/13/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.4.2.1 1 1044 Pole (USAP)
1046 1.2 1.2.8.4.2.1.1 LC130 - Pole (USAP) Not Started P 7 1 75d 11/01/22 02/13/23 11/01/22 8:00 AM 02/13/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.1 1 1045 LC130 - Pole (USAP)
1047 1.2 1.2.8.4.2.1.1.1 Fuel - 2 Missions, 6000 gallons (USAP) Not Started C 8 1 75d 11/01/22 02/13/23 11/01/22 8:00 AM 02/13/23 4:59 PM 1040 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.1.1 1 1046 Fuel - 2 Missions, 6000 gallons (USAP)
1048 1.2 1.2.8.4.2.1.2 SPOT1 (USAP) Not Started P 7 1 1 0 12/01/22 12/01/22 12/01/22 8:00 AM 12/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.4.2.1.2 1 1047 SPOT1 (USAP)
1049 1.2 1.2.8.4.2.1.2.1 Fuel Tower Arrives (Bermed at SPOTSA) (USAP) Not Started C 8 1 1 0 12/01/22 12/01/22 12/01/22 8:00 AM 12/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.2.1 1 1048 Fuel Tower Arrives (Bermed at SPOTSA) (USAP)
1050 1.2 1.2.8.4.2.1.2.2 8' Refit Container Arrives (USAP) Not Started C 8 1 1 0 12/01/22 12/01/22 12/01/22 8:00 AM 12/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.2.2 1 1049 8' Refit Container Arrives (USAP)
1051 1.2 1.2.8.4.2.1.2.3 Generator Hoods (SPOTSA Bermed) Arrives (USAP) Not Started C 8 1 1 0 12/01/22 12/01/22 12/01/22 8:00 AM 12/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.2.3 1 1050 Generator Hoods (SPOTSA Bermed) Arrives (USAP)
1052 1.2 1.2.8.4.2.1.2.4 Weight Stack (SPOTSA Bermed) Arrives (USAP) Not Started C 8 1 1 0 12/01/22 12/01/22 12/01/22 8:00 AM 12/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.2.4 1 1051 Weight Stack (SPOTSA Bermed) Arrives (USAP)
1053 1.2 1.2.8.4.2.1.2.5 Generator Hoods (Intake) Arrives (USAP) Not Started C 8 1 1 0 12/01/22 12/01/22 12/01/22 8:00 AM 12/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.2.5 1 1052 Generator Hoods (Intake) Arrives (USAP)
1054 1.2 1.2.8.4.2.1.2.6 Generator Hoods (Exhaust) Arrives (USAP) Not Started C 8 1 1 0 12/01/22 12/01/22 12/01/22 8:00 AM 12/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.2.6 1 1053 Generator Hoods (Exhaust) Arrives (USAP)
1055 1.2 1.2.8.4.2.1.2.7 Container Skis Arrives (USAP) Not Started C 8 1 1 0 12/01/22 12/01/22 12/01/22 8:00 AM 12/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.2.7 1 1054 Container Skis Arrives (USAP)
1056 1.2 1.2.8.4.2.1.2.8 ARA Trailer Arrives (USAP) Not Started C 8 1 1 0 12/01/22 12/01/22 12/01/22 8:00 AM 12/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.2.8 1 1055 ARA Trailer Arrives (USAP)
1057 1.2 1.2.8.4.2.1.2.9 Traverse Accelerometer Logger Arrives (USAP) Not Started C 8 1 1 0 12/01/22 12/01/22 12/01/22 8:00 AM 12/01/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.8.4.2.1.2.9 1 1056 Traverse Accelerometer Logger Arrives (USAP)
1058 1.2 1.2.8.4.2.1.3 SPOT2 (USAP) Not Started P 7 1 1 1d 01/01/23 01/01/23 01/01/23 8:00 AM 01/01/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.4.2.1.3 1 1057 SPOT2 (USAP)
1059 1.2 1.2.8.4.2.1.3.1 Generator Module 1 Arrives (USAP) Not Started C 8 1 1 0 01/01/23 01/01/23 01/01/23 8:00 AM 01/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.3.1 1 1058 Generator Module 1 Arrives (USAP)
1060 1.2 1.2.8.4.2.1.3.2 Generator Module 3 Arrives (USAP) Not Started C 8 1 1 0 01/01/23 01/01/23 01/01/23 8:00 AM 01/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.3.2 1 1059 Generator Module 3 Arrives (USAP)
1061 1.2 1.2.8.4.2.1.3.3 Firn Drill Arrives (USAP) Not Started C 8 1 1 0 01/01/23 01/01/23 01/01/23 8:00 AM 01/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.3.3 1 1060 Firn Drill Arrives (USAP)
1062 1.2 1.2.8.4.2.1.3.4 Refit Container A (20' ISO) Arrives (USAP) Not Started C 8 1 1 0 01/01/23 01/01/23 01/01/23 8:00 AM 01/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.3.4 1 1061 Refit Container A (20' ISO) Arrives (USAP)
1063 1.2 1.2.8.4.2.1.3.5 Refit Container B (20' ISO) Arrives (USAP) Not Started C 8 1 1 0 01/01/23 01/01/23 01/01/23 8:00 AM 01/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.3.5 1 1062 Refit Container B (20' ISO) Arrives (USAP)
1064 1.2 1.2.8.4.2.1.3.6 Main Cable Reel (MCR) Arrives (USAP) Not Started C 8 1 1 0 01/01/23 01/01/23 01/01/23 8:00 AM 01/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.3.6 1 1063 Main Cable Reel (MCR) Arrives (USAP)
1065 1.2 1.2.8.4.2.1.3.7 Return Water Cable Reel (RWCR) Arrives (USAP) Not Started C 8 1 1 0 01/01/23 01/01/23 01/01/23 8:00 AM 01/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.3.7 1 1064 Return Water Cable Reel (RWCR) Arrives (USAP)
1066 1.2 1.2.8.4.2.1.3.8 Traverse Accelerometer Logger Arrives (USAP) Not Started C 8 1 1d 01/01/23 01/01/23 01/01/23 8:00 AM 01/01/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.8.4.2.1.3.8 1 1065 Traverse Accelerometer Logger Arrives (USAP)
1067 1.2 1.2.8.4.2.1.4 SPOT3 (USAP) Not Started P 7 1 1 0 02/01/23 02/01/23 02/01/23 8:00 AM 02/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.4.2.1.4 1 1066 SPOT3 (USAP)
1068 1.2 1.2.8.4.2.1.4.1 HPU2 Arrives (USAP) Not Started C 8 1 1 0 02/01/23 02/01/23 02/01/23 8:00 AM 02/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.2.1.4.1 1 1067 HPU2 Arrives (USAP)
1069 1.2.8.4.2.2 McMurdo (USAP) Not Started P 6 1 92d 10/01/22 02/06/23 10/01/22 8:00 AM 02/06/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 1.2.8.4.2.2 1 1068 McMurdo (USAP)
1070 1.2 1.2.8.4.2.2.1 SAAM (USAP) Not Started P 7 1 17d 10/01/22 10/25/22 10/01/22 8:00 AM 10/25/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.8.4.2.2.1 1 1069 SAAM (USAP)
1071 1.2 1.2.8.4.1.2.1.1 Southbound: Accelerometers (For SPoT data gathering) Not Started C 8 1 1 0 10/01/22 10/01/22 10/01/22 8:00 AM 10/01/22 8:00 AM 1039 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.1.2.1.1 1 1070 Southbound: Accelerometers (For SPoT data gathering)
1072 1.2 1.2.8.4.1.2.1.2 Northbound: Generator 2 (Destined for Terra Cat) Not Started C 8 1 1 0 10/25/22 10/25/22 10/25/22 8:00 AM 10/25/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.1.2.1.2 1 1071 Northbound: Generator 2 (Destined for Terra Cat)
1073 1.2 1.2.8.4.2.2.1.1 Traverse Accelerometer Logger Shipment (USAP) Not Started C 8 1 1d 10/18/22 10/18/22 10/18/22 8:00 AM 10/18/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.8.4.2.2.1.1 1 1072 Traverse Accelerometer Logger Shipment (USAP)
1074 1.2 1.2.8.4.2.2.2 Vessel (USAP) Not Started P 7 1 2d 02/05/23 02/06/23 02/05/23 8:00 AM 02/06/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.8.4.2.2.2 1 1073 Vessel (USAP)
1075 1.2 1.2.8.4.1.2.2.1 Generator 2 (Return from Terra Cat) Not Started C 8 1 1d 02/05/23 02/05/23 02/05/23 8:00 AM 02/05/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.1.2.2.1 1 1074 Generator 2 (Return from Terra Cat)
1076 1.2 1.2.8.4.2.2.2.1 Generator 2 - Loaded in Lyttleton (USAP) Not Started C 8 1 1d 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.8.4.2.2.2.1 1 1075 Generator 2 - Loaded in Lyttleton (USAP)
1077 1.2 1.2.8.4.2.2.2.2 Refit Container C (20' ISO) Arrives (USAP) Not Started C 8 1 1d 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.8.4.2.2.2.2 1 1076 Refit Container C (20' ISO) Arrives (USAP)
1078 1.2 1.2.8.4.2.2.2.3 ARA Drill Components Crate 1 - DNF (USAP) Not Started C 8 1 1d 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.8.4.2.2.2.3 1 1077 ARA Drill Components Crate 1 - DNF (USAP)
1079 1.2 1.2.8.4.2.2.2.4 Drill Heads X, Y, & R - DNF (USAP) Not Started C 8 1 1d 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.8.4.2.2.2.4 1 1078 Drill Heads X, Y, & R - DNF (USAP)
1080 1.2 1.2.8.4.2.2.2.5 Controls Component Crates Shipment 1 DNF (USAP) Not Started C 8 1 1d 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.8.4.2.2.2.5 1 1079 Controls Component Crates Shipment 1 DNF (USAP)
1081 1.2 1.2.8.4.3 USAP Deliverables Not Started P 5 1 189d 09/01/22 05/23/23 09/01/22 8:00 AM 05/23/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 1.2.8.4.3 1 1080 USAP Deliverables
1082 1.2 1.2.8.4.3.1 Relocation of Gen 2 to Phoenix from SPOTSA for Shipping to CHC (USAP) Not Started C 6 1 1d 09/01/22 09/01/22 09/01/22 8:00 AM 09/01/22 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.1 1 1081 Relocation of Gen 2 to Phoenix from SPOTSA for Shipping to CHC (USAP)
1083 1.2 1.2.8.4.3.2 SPOT Cargo Support (USAP) Not Started C 6 1 159d 10/03/22 05/11/23 10/03/22 8:00 AM 05/11/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.4.3.2 1 1082 SPOT Cargo Support (USAP)
1084 1.2 1.2.8.4.3.3 Transportation/Logistics & Fuels Support McM/Pole (USAP) Not Started C 6 1 90d 10/05/22 02/07/23 10/05/22 8:00 AM 02/07/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.3 1 1083 Transportation/Logistics & Fuels Support McM/Pole (USAP)
1085 1.2 1.2.8.4.3.4 Cargo Storage Support Pole & MCM (USAP) Not Started C 6 1 75d 11/01/22 02/13/23 11/01/22 8:00 AM 02/13/23 4:59 PM 1039, 1040 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.4 1 1084 Cargo Storage Support Pole & MCM (USAP)
1086 1.2 1.2.8.4.3.5 Crane Support MCM & Pole for Onload and Offload of Cargo & Set Gens on Skis (USAP) Not Started C 6 1 40d 11/10/22 01/04/23 11/10/22 8:00 AM 01/04/23 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.5 1 1085 Crane Support MCM & Pole for Onload and Offload of Cargo & Set Gens on Skis (USAP)
1087 1.2 1.2.8.4.3.6 SES & Drill Pad Hardening/Grooming (USAP) Not Started C 6 1 21d 12/01/22 12/29/22 12/01/22 8:00 AM 12/29/22 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.6 1 1086 SES & Drill Pad Hardening/Grooming (USAP)
1088 1.2 1.2.8.4.3.7 Drill Storage Site Drift Removal (USAP) Not Started C 6 1 21d 12/01/22 12/29/22 12/01/22 8:00 AM 12/29/22 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.7 1 1087 Drill Storage Site Drift Removal (USAP)
1089 1.2 1.2.8.4.3.8 Overwinter Storage Electrical Infrastructure Installation (USAP) Not Started C 6 1 1d 12/06/22 12/06/22 12/06/22 8:00 AM 12/06/22 4:59 PM 1039, 1040FS +25d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.8 1 1088 Overwinter Storage Electrical Infrastructure Installation (USAP)
1090 1.2 1.2.8.4.3.15 287 Loader Repairs & Pole Prep (USAP) - winter Not Started C 6 1 2w 05/10/23 05/23/23 05/10/23 8:00 AM 05/23/23 4:59 PM 1041FS +60d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.15 1 1089 287 Loader Repairs & Pole Prep (USAP) - winter
1091 1.2 1.2.8.4.3.9 Complete CRREL Gen Maintenance & Repairs and Install Louver Covers (USAP) Not Started C 6 1 7d 01/03/23 01/11/23 01/03/23 8:00 AM 01/11/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.9 1 1090 Complete CRREL Gen Maintenance & Repairs and Install Louver Covers (USAP)
1092 1.2 1.2.8.4.3.10 Confirm/Inspect CRREL Gen cables 2-100amp w/ Hubbell/Appleton Connectors (USAP) Not Started C 6 1 1 0 01/11/23 01/11/23 01/11/23 4:59 PM 01/11/23 4:59 PM 1090 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.10 1 1091 Confirm/Inspect CRREL Gen cables 2-100amp w/ Hubbell/Appleton Connectors (USAP)
1093 1.2 1.2.8.4.3.11 Excavate SPoTSA Storage Site (USAP) Not Started C 6 1d 11/08/22 11/08/22 11/08/22 8:00 AM 11/08/22 4:59 PM 1039, 1040FS +5d 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.11 1 1092 Excavate SPoTSA Storage Site (USAP)
1094 1.2 1.2.8.4.3.12 SPOTSA Berm Maintenance (USAP) Not Started C 6 1 3d 01/25/23 01/27/23 01/25/23 8:00 AM 01/27/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.12 1 1093 SPOTSA Berm Maintenance (USAP)
1095 1.2 1.2.8.4.3.13 Relocation of Gen 2 from Pier to Overwinter Storage Site (USAP) Not Started C 6 1 1d 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.13 1 1094 Relocation of Gen 2 from Pier to Overwinter Storage Site (USAP)
1096 1.2 1.2.8.4.3.14 CRREL/Survey GPR Support for Trench Lane & Hole Site Proofing (USAP) Not Started C 6 1 1d 12/15/22 12/15/22 12/15/22 8:00 AM 12/15/22 4:59 PM 1087SS +10d 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.4.3.14 1 1095 CRREL/Survey GPR Support for Trench Lane & Hole Site Proofing (USAP)
1097 1.2 1.2.8.5 USAP Field Season 1 (FY24) Not Started P 4 1 279d 02/01/23 02/29/24 02/01/23 8:00 AM 02/29/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $41,501.00 0% Ian McEwen 1.2.8.5 1 1096 USAP Field Season 1 (FY24)
1098 1.2 1.2.8.5.1 FS1 Milestones Not Started P 5 1 193d 02/15/23 11/12/23 02/15/23 8:00 AM 11/12/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 1.2.8.5.1 1 1097 FS1 Milestones
1099 1.2 1.2.8.5.1.1 McM Mainbody Season Begins (USAP) Not Started C 6 1 1 0 10/01/23 10/01/23 10/01/23 8:00 AM 10/01/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.1.1 1 1098 McM Mainbody Season Begins (USAP)
1100 1.2 1.2.8.5.1.2 South Pole Season Begins (USAP) Not Started C 6 1 1 0 11/01/23 11/01/23 11/01/23 8:00 AM 11/01/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.1.2 1 1099 South Pole Season Begins (USAP)
1101 1.2 1.2.8.5.1.3 ICU Team Arrives [Headcount 11] Not Started C 6 1 1 0 11/12/23 11/12/23 11/12/23 8:00 AM 11/12/23 8:00 AM 0.00% 0% Green tentatively set to 16 $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.1.3 1 1100 ICU Team Arrives [Headcount 11]
1102 1.2 1.2.8.5.1.4 Pole Season Ends (USAP) Not Started C 6 1 1 0 02/15/23 02/15/23 02/15/23 8:00 AM 02/15/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.1.4 1 1101 Pole Season Ends (USAP)
1103 1.2 1.2.8.5.1.5 MCM Season Ends (USAP) Not Started C 6 1 1 0 03/01/23 03/01/23 03/01/23 8:00 AM 03/01/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.1.5 1 1102 MCM Season Ends (USAP)
1104 1.2 1.2.8.5.2 PQ, ECW & Deployment Travel Costs (FS1) Not Started C 5 1 192d 06/02/23 02/29/24 06/02/23 8:00 AM 02/29/24 4:59 PM 0.00% 0% Green $0.00 $41,501.00 $0.00 $41,501.00 0% $0.00 Ian McEwen Driller_Contributed, Driller_PSL_DirectHire, Driller_PSL_Lead, PSL_Engineer Team of 8
1-Dar
3-Direct-Hire Drillers
2-Contributed Drillers
2-PSL Engineers

Travel Labor: 48 hrs/ea (Labor)
- 3 days paid time during deployment
- 3 days paid time during redeployment

Travel Cost: $1,800/ea (Travel)

PQ Cost: $950/ea (M&S)
1.2.8.5.2 1 1103 PQ, ECW & Deployment Travel Costs (FS1)
1105 1.2 1.2.8.5.3 USAP Cargo Movements (FY24) Not Started P 5 1 70d 11/01/23 02/12/24 11/01/23 8:00 AM 02/12/24 8:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.3 1 1104 USAP Cargo Movements (FY24)
1106 1.2 1.2.8.5.3.1 Pole (USAP) Not Started P 6 1 60d 11/15/23 02/12/24 11/15/23 8:00 AM 02/12/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.3.1 1 1105 Pole (USAP)
1107 1.2 1.2.8.5.3.1.1 LC130 - Pole (USAP) Not Started P 7 1 1 60d 11/15/23 02/12/24 11/15/23 8:00 AM 02/12/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.3.1.1 1 1106 LC130 - Pole (USAP)
1108 1.2 1.2.8.5.3.1.1.1 Controls Component Crates Shipment 1 DNF (USAP) Not Started C 8 1 1 0 11/15/23 11/15/23 11/15/23 8:00 AM 11/15/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.1.1.1 1 1107 Controls Component Crates Shipment 1 DNF (USAP)
1109 1.2 1.2.8.5.3.1.1.2 Controls Component Crates Shipment 2 DNF (USAP) Not Started C 8 1 1 0 11/15/23 11/15/23 11/15/23 8:00 AM 11/15/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.1.1.2 1 1108 Controls Component Crates Shipment 2 DNF (USAP)
1110 1.2 1.2.8.5.3.1.1.3 ARA Drill System Components - Crate 1 (DNF) (USAP) Not Started C 8 1 1 0 11/15/23 11/15/23 11/15/23 8:00 AM 11/15/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.1.1.3 1 1109 ARA Drill System Components - Crate 1 (DNF) (USAP)
1111 1.2 1.2.8.5.3.1.1.4 Drill Heads X, Y, & R - DNF (USAP) Not Started C 8 1 1d 02/06/24 02/06/24 02/06/24 8:00 AM 02/06/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.8.5.3.1.1.4 1 1110 Drill Heads X, Y, & R - DNF (USAP)
1112 1.2 1.2.8.5.3.1.1.5 Fuel - 19 Missions, 55,200 gallons (USAP) Not Started C 8 1 1 0 02/12/24 02/12/24 02/12/24 8:00 AM 02/12/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.1.1.5 1 1111 Fuel - 19 Missions, 55,200 gallons (USAP)
1113 1.2 1.2.8.5.3.1.2 SPOT1 - Pole (USAP) Not Started P 7 1 1 0 12/01/23 12/01/23 12/01/23 8:00 AM 12/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.3.1.2 1 1112 SPOT1 - Pole (USAP)
1114 1.2 1.2.8.5.3.1.2.1 Gen 2 (USAP) Not Started C 8 1 1 0 12/01/23 12/01/23 12/01/23 8:00 AM 12/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.1.2.1 1 1113 Gen 2 (USAP)
1115 1.2 1.2.8.5.3.1.2.2 Refit Container C (20' ISO) Arrives (USAP) Not Started C 8 1 1 0 12/01/23 12/01/23 12/01/23 8:00 AM 12/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.1.2.2 1 1114 Refit Container C (20' ISO) Arrives (USAP)
1116 1.2 1.2.8.5.3.1.3 SPOT2 - Pole (USAP) Not Started P 7 1 1 0 01/01/24 01/01/24 01/01/24 8:00 AM 01/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.3.1.3 1 1115 SPOT2 - Pole (USAP)
1117 1.2 1.2.8.5.3.1.3.1 Placeholder Not Started C 8 1 1 0 01/01/24 01/01/24 01/01/24 8:00 AM 01/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.1.3.1 1 1116 Placeholder
1118 1.2 1.2.8.5.3.1.4 SPOT3 - Pole (USAP) Not Started P 7 1 1 0 02/01/24 02/01/24 02/01/24 8:00 AM 02/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.3.1.4 1 1117 SPOT3 - Pole (USAP)
1119 1.2 1.2.8.5.3.1.4.1 Placeholder Not Started C 8 1 1 0 02/01/24 02/01/24 02/01/24 8:00 AM 02/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.1.4.1 1 1118 Placeholder
1120 1.2 1.2.8.5.3.2 MCM (USAP) Not Started P 6 1 65d 11/01/23 02/05/24 11/01/23 8:00 AM 02/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.3.2 1 1119 MCM (USAP)
1121 1.2 1.2.8.5.3.2.1 SAAM (ComSur) (USAP) Not Started P 7 1 1 0 11/01/23 11/01/23 11/01/23 8:00 AM 11/01/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.2.1 1 1120 SAAM (ComSur) (USAP)
1122 1.2 1.2.8.5.3.2.1.1 Controls Component Crates Shipment 2 DNF (USAP) Not Started C 8 1 1 0 11/01/23 11/01/23 11/01/23 8:00 AM 11/01/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.2.1.1 1 1121 Controls Component Crates Shipment 2 DNF (USAP)
1123 1.2 1.2.8.5.3.2.2 Vessel - MCM (USAP) Not Started P 7 1 1 0 02/05/24 02/05/24 02/05/24 8:00 AM 02/05/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.2.2 1 1122 Vessel - MCM (USAP)
1124 1.2 1.2.8.5.3.2.2.1 Load Member Cable Reel (?) (USAP) Not Started C 8 1 1 0 02/05/24 02/05/24 02/05/24 8:00 AM 02/05/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.2.2.1 1 1123 Load Member Cable Reel (?) (USAP)
1125 1.2 1.2.8.5.3.3 Retrograde (USAP) Not Started C 6 1 1 0 02/05/24 02/05/24 02/05/24 8:00 AM 02/05/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.3 1 1124 Retrograde (USAP)
1126 1.2 1.2.8.5.3.4 Cargo Storage Support Pole and McMurdo (USAP) Not Started C 6 1 1 0 11/01/23 11/01/23 11/01/23 8:00 AM 11/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.3.4 1 1125 Cargo Storage Support Pole and McMurdo (USAP)
1127 1.2 1.2.8.5.4 Early Season Kick-off Tasking Not Started P 5 1 68d 11/07/23 02/13/24 11/07/23 8:00 AM 02/13/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.4 1 1126 Early Season Kick-off Tasking
1128 1.2 1.2.8.5.4.1 Excavate EHWD & Equipment Berms for Access (USAP) Not Started C 6 1 5d 11/07/23 11/13/23 11/07/23 8:00 AM 11/13/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.4.1 1 1127 Excavate EHWD & Equipment Berms for Access (USAP)
1129 1.2 1.2.8.5.4.2 Deliver MECC & Fuel Tank, Shop, SEW to Cryo (USAP) Not Started C 6 1 3d 11/09/23 11/13/23 11/09/23 8:00 AM 11/13/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.4.2 1 1128 Deliver MECC & Fuel Tank, Shop, SEW to Cryo (USAP)
1130 1.2 1.2.8.5.4.3 Set-up Cryo Worksite Power Feed & Fuel (USAP) Not Started C 6 1 5d 11/07/23 11/13/23 11/07/23 8:00 AM 11/13/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.4.3 1 1129 Set-up Cryo Worksite Power Feed & Fuel (USAP)
1131 1.2 1.2.8.5.4.4 Set-up MECC & Shop for Season Activities (Driller) Not Started C 6 1 3d 11/14/23 11/16/23 11/14/23 8:00 AM 11/16/23 4:59 PM 1128 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.4.4 1 1130 Set-up MECC & Shop for Season Activities (Driller)
1132 1.2 1.2.8.5.4.5 Re-establish SES Pad, Groom & Compact Roads (USAP) Not Started C 6 1 8d 11/21/23 12/01/23 11/21/23 8:00 AM 12/01/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.4.5 1 1131 Re-establish SES Pad, Groom & Compact Roads (USAP)
1133 1.2 1.2.8.5.4.6 Provide Heaters (PolarTherm) (USAP) Not Started C 6 1 62d 11/15/23 02/13/24 11/15/23 8:00 AM 02/13/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.4.6 1 1132 Provide Heaters (PolarTherm) (USAP)
1134 1.2 1.2.8.5.4.7 Provide 287B Skidsteer & Snomo's (USAP) Not Started C 6 1 1d 11/15/23 11/15/23 11/15/23 8:00 AM 11/15/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.4.7 1 1133 Provide 287B Skidsteer & Snomo's (USAP)
1135 1.2 1.2.8.5.4.8 Provide Fire Extinguishers (USAP) Not Started C 6 1 1d 11/15/23 11/15/23 11/15/23 8:00 AM 11/15/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.4.8 1 1134 Provide Fire Extinguishers (USAP)
1136 1.2 1.2.8.5.4.9 SEW Season Prep Activities Not Started P 6 1 3d 11/13/23 11/15/23 11/13/23 8:00 AM 11/15/23 4:59 PM 1100SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.4.9 1 1135 SEW Season Prep Activities
1137 1.2 1.2.8.5.4.9.1 Stock Shelves/Cabinets w/ Needed Hardware and Tools Not Started C 7 1 3d 11/13/23 11/15/23 11/13/23 8:00 AM 11/15/23 4:59 PM 1100SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.4.9.1 1 1136 Stock Shelves/Cabinets w/ Needed Hardware and Tools
1138 1.2 1.2.8.5.4.9.2 Install new DGH Gateway/Ethernet box, Connect to Gen-1 Network Box, M-DGHs & Test Not Started C 7 1 2d 11/13/23 11/14/23 11/13/23 8:00 AM 11/14/23 4:59 PM 1100SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.4.9.2 1 1137 Install new DGH Gateway/Ethernet box, Connect to Gen-1 Network Box, M-DGHs & Test
1139 1.2 1.2.8.5.5 Generators & PDM Not Started P 5 1 21d 11/22/23 12/22/23 11/22/23 4:59 PM 12/22/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.5 1 1138 Generators & PDM
1140 1.2 1.2.8.5.5.1 Receive & Set Gen 2 on Skis with Crane & Deliver to Cryo (USAP) Not Started C 6 1 1d 12/01/23 12/01/23 12/01/23 8:00 AM 12/01/23 4:59 PM 1113 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.5.5.1 1 1139 Receive & Set Gen 2 on Skis with Crane & Deliver to Cryo (USAP)
1141 1.2 1.2.8.5.5.2 Generators 1, 3 & PDM Delivered to Cryo (USAP) Not Started C 6 1 1 0 11/24/23 11/24/23 11/24/23 8:00 AM 11/24/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.5.2 1 1140 Generators 1, 3 & PDM Delivered to Cryo (USAP)
1142 1.2 1.2.8.5.5.3 CRELL Gen Delivered to Cryo (USAP) Not Started C 6 1 1 0 11/22/23 11/22/23 11/22/23 4:59 PM 11/22/23 4:59 PM 1127FS +7d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.5.3 1 1141 CRELL Gen Delivered to Cryo (USAP)
1143 1.2 1.2.8.5.5.4 Prepare CRREL Gen for Firn Drill Testing (USAP) Not Started C 6 1 5d 12/05/23 12/11/23 12/05/23 8:00 AM 12/11/23 4:59 PM 1141FS +7d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.5.4 1 1142 Prepare CRREL Gen for Firn Drill Testing (USAP)
1144 1.2 1.2.8.5.5.5 Generators & PDM - Repairs & Pre-operational Checks Not Started C 6 1 7d 11/24/23 12/04/23 11/24/23 8:00 AM 12/04/23 4:59 PM 1140 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.5.5.5 1 1143 Generators & PDM - Repairs & Pre-operational Checks
1145 1.2 1.2.8.5.5.8 Install 3rd Disconnect on PDM (USAP) Not Started C 6 1 2d 11/24/23 11/27/23 11/24/23 8:00 AM 11/27/23 4:59 PM 1140 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/ Generator Contractor 1.2.8.5.5.8 1 1144 Install 3rd Disconnect on PDM (USAP)
1146 1.2 1.2.8.5.5.9 Gen3 Preventative Maintenance (PM) (USAP) Not Started C 6 1 2d 12/01/23 12/04/23 12/01/23 8:00 AM 12/04/23 4:59 PM 1143FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.5.9 1 1145 Gen3 Preventative Maintenance (PM) (USAP)
1147 1.2 1.2.8.5.5.10 Deliver Fuel Tank & Fuel (USAP) Not Started C 6 1 2d 12/05/23 12/06/23 12/05/23 8:00 AM 12/06/23 4:59 PM 1143, 1144, 1145 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.5.5.10 1 1146 Deliver Fuel Tank & Fuel (USAP)
1148 1.2 1.2.8.5.5.11 Ready, Start-up & Exercise Gen1, Gen 2, & Gen3 (Driller & USAP) Not Started C 6 1 2d 12/05/23 12/06/23 12/05/23 8:00 AM 12/06/23 4:59 PM 1143, 1144, 1145 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.5.5.11 1 1147 Ready, Start-up & Exercise Gen1, Gen 2, & Gen3 (Driller & USAP)
1149 1.2 1.2.8.5.5.12 Install Intake & Exhaust Hoods Not Started C 6 1 4d 12/07/23 12/12/23 12/07/23 8:00 AM 12/12/23 4:59 PM 1147 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.5.5.12 1 1148 Install Intake & Exhaust Hoods
1150 1.2 1.2.8.5.5.13 Intake & Exhaust Hoods Installation Support (953 w/ stinger) (USAP) Not Started C 6 1 4d 12/05/23 12/08/23 12/05/23 8:00 AM 12/08/23 4:59 PM 1147SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.5.5.13 1 1149 Intake & Exhaust Hoods Installation Support (953 w/ stinger) (USAP)
1151 1.2 1.2.8.5.5.14 Relocate Gen 1, Gen 2, & Gen 3, & PDM from Cryo to SES (USAP) Not Started C 6 1 3d 12/11/23 12/13/23 12/11/23 8:00 AM 12/13/23 4:59 PM 1149 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.5.14 1 1150 Relocate Gen 1, Gen 2, & Gen 3, & PDM from Cryo to SES (USAP)
1152 1.2 1.2.8.5.5.15 Winterize Gen Modules and PDM (Driller & USAP) Not Started C 6 1 2d 12/21/23 12/22/23 12/21/23 8:00 AM 12/22/23 4:59 PM 1150FS +5d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.5.15 1 1151 Winterize Gen Modules and PDM (Driller & USAP)
1153 1.2 1.2.8.5.6 EHWD: Upgrade & Replacement Work Not Started P 5 1 54d 11/13/23 01/31/24 11/13/23 4:59 PM 01/31/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6 1 1152 EHWD: Upgrade & Replacement Work
1154 1.2 1.2.8.5.6.1 Global Computing & Controls Not Started P 6 1 6d 01/05/24 01/12/24 01/05/24 8:00 AM 01/12/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.1 1 1153 Global Computing & Controls
1155 1.2 1.2.8.5.6.1.1 Assess SES/TOS Interconnect Inventory Not Started C 7 1 3d 01/10/24 01/12/24 01/10/24 8:00 AM 01/12/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.1.1 1 1154 Assess SES/TOS Interconnect Inventory
1156 1.2 1.2.8.5.6.1.2 Install and Test Modbus DGH Modules Not Started C 7 1 2d 01/05/24 01/08/24 01/05/24 8:00 AM 01/08/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.1.2 1 1155 Install and Test Modbus DGH Modules
1157 1.2 1.2.8.5.6.2 Drill Control Center (DCC) Not Started P 6 1 2d 11/13/23 11/15/23 11/13/23 4:59 PM 11/15/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.2 1 1156 Drill Control Center (DCC)
1158 1.2 1.2.8.5.6.2.1 DCC Relocated to Cryo (USAP) Not Started C 7 1 1 0 11/13/23 11/13/23 11/13/23 4:59 PM 11/13/23 4:59 PM 1127 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.2.1 1 1157 DCC Relocated to Cryo (USAP)
1159 1.2 1.2.8.5.6.2.2 Replace Electric Heater in Electrical Closet Not Started C 7 1 2d 11/14/23 11/15/23 11/14/23 8:00 AM 11/15/23 4:59 PM 1157 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.2.2 1 1158 Replace Electric Heater in Electrical Closet
1160 1.2 1.2.8.5.6.2.3 Clean-up Workspace & Configure Not Started C 7 1 2d 11/14/23 11/15/23 11/14/23 8:00 AM 11/15/23 4:59 PM 1157 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.2.3 1 1159 Clean-up Workspace & Configure
1161 1.2 1.2.8.5.6.3 Main Heating Plants (MHP) Not Started P 6 1 18d 11/14/23 12/08/23 11/14/23 8:00 AM 12/08/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3 1 1160 Main Heating Plants (MHP)
1162 1.2 1.2.8.5.6.3.1 MHP Relocation Support (USAP) Not Started C 7 1 1d 11/14/23 11/14/23 11/14/23 8:00 AM 11/14/23 4:59 PM 1127 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.3.1 1 1161 MHP Relocation Support (USAP)
1163 1.2 1.2.8.5.6.3.2 Install MHP Fall Restraint Towers (USAP) Not Started C 7 1 1d 11/15/23 11/15/23 11/15/23 8:00 AM 11/15/23 4:59 PM 1161 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.3.2 1 1162 Install MHP Fall Restraint Towers (USAP)
1164 1.2 1.2.8.5.6.3.3 MHP1 Not Started P 7 1 14d 11/14/23 12/05/23 11/14/23 5:00 PM 12/05/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.3 1 1163 MHP1
1165 1.2 1.2.8.5.6.3.3.1 Mechanical Refit & Repairs (MHP1) Not Started P 8 1 12d 11/14/23 12/01/23 11/14/23 5:00 PM 12/01/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.3.1 1 1164 Mechanical Refit & Repairs (MHP1)
1166 1.2 1.2.8.5.6.3.3.1.1 Heater Flush and Pressure Test Not Started C 9 1 e4d 11/14/23 11/18/23 11/14/23 5:00 PM 11/18/23 4:59 PM 1161 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.3.1.1 1 1165 Heater Flush and Pressure Test
1167 1.2 1.2.8.5.6.3.3.1.2 Plumbing Upgrades & Repairs Not Started C 9 1 e3d 11/27/23 11/30/23 11/27/23 5:00 PM 11/30/23 4:59 PM 1183 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.3.1.2 1 1166 Plumbing Upgrades & Repairs
1168 1.2 1.2.8.5.6.3.3.1.3 Fuel System Upgrades and Repairs Not Started C 9 1 e1d 11/14/23 11/15/23 11/14/23 5:00 PM 11/15/23 4:59 PM 1161 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.3.1.3 1 1167 Fuel System Upgrades and Repairs
1169 1.2 1.2.8.5.6.3.3.1.4 Exhaust System Upgrades and Repairs Not Started C 9 1 e1d 11/15/23 11/16/23 11/15/23 5:00 PM 11/16/23 4:59 PM 1161, 1162 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Contract_Driller 1.2.8.5.6.3.3.1.4 1 1168 Exhaust System Upgrades and Repairs
1170 1.2 1.2.8.5.6.3.3.1.5 MHP Subsystem Evaluation Not Started C 9 1 e1d 11/30/23 12/01/23 11/30/23 5:00 PM 12/01/23 4:59 PM 1166, 1168, 1165, 1167FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer 1.2.8.5.6.3.3.1.5 1 1169 MHP Subsystem Evaluation
1171 1.2 1.2.8.5.6.3.3.1.6 MHP1 Mechanical Complete Not Started C 9 1 1 0 12/01/23 12/01/23 12/01/23 4:59 PM 12/01/23 4:59 PM 1169 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.3.1.6 1 1170 MHP1 Mechanical Complete
1172 1.2 1.2.8.5.6.3.3.2 Electrical/Controls Refit & Repairs (MHP1) Not Started P 8 1 14d 11/14/23 12/05/23 11/14/23 5:00 PM 12/05/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.3.2 1 1171 Electrical/Controls Refit & Repairs (MHP1)
1173 1.2 1.2.8.5.6.3.3.2.1 Install PLC-to-DGH Gateway in Network Box, Install M-DGHs, & Test Not Started C 9 1 e1d 11/17/23 11/18/23 11/17/23 5:00 PM 11/18/23 4:59 PM 1189 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.3.2.1 1 1172 Install PLC-to-DGH Gateway in Network Box, Install M-DGHs, & Test
1174 1.2 1.2.8.5.6.3.3.2.2 Install Refurbished Heater Control Assemblies on All Heaters (M-DGHs pre-installed) Not Started C 9 1 e3d 11/14/23 11/17/23 11/14/23 5:00 PM 11/17/23 4:59 PM 1161 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.3.3.2.2 1 1173 Install Refurbished Heater Control Assemblies on All Heaters (M-DGHs pre-installed)
1175 1.2 1.2.8.5.6.3.3.2.3 Replace Thermostats in Heaters & Test Not Started C 9 1 e2d 12/02/23 12/04/23 12/02/23 5:00 PM 12/04/23 4:59 PM 1191 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.3.3.2.3 1 1174 Replace Thermostats in Heaters & Test
1176 1.2 1.2.8.5.6.3.3.2.4 Reconfigure MHP E-stop Panel to Function with N.C. Slap Switch Contacts Not Started C 9 1 e1d 11/18/23 11/19/23 11/18/23 5:00 PM 11/19/23 4:59 PM 1172 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.3.2.4 1 1175 Reconfigure MHP E-stop Panel to Function with N.C. Slap Switch Contacts
1177 1.2 1.2.8.5.6.3.3.2.5 Test E-stop and Heater Controls with No Water Not Started C 9 1 e2d 11/19/23 11/21/23 11/19/23 5:00 PM 11/21/23 4:59 PM 1175 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.3.2.5 1 1176 Test E-stop and Heater Controls with No Water
1178 1.2 1.2.8.5.6.3.3.2.6 Test Flow Sensor Operation with No Water Not Started C 9 1 e1d 12/04/23 12/05/23 12/04/23 5:00 PM 12/05/23 4:59 PM 1174 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.3.2.6 1 1177 Test Flow Sensor Operation with No Water
1179 1.2 1.2.8.5.6.3.3.2.7 Install Ethernet Switch, Connect to Network Box, Route Cable to DCC & Test Not Started C 9 1 e1d 11/30/23 12/01/23 11/30/23 5:00 PM 12/01/23 4:59 PM 1194 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.3.2.7 1 1178 Install Ethernet Switch, Connect to Network Box, Route Cable to DCC & Test
1180 1.2 1.2.8.5.6.3.3.2.8 MHP1 Controls Complete Not Started C 9 1 1 0 12/05/23 12/05/23 12/05/23 4:59 PM 12/05/23 4:59 PM 1172, 1173, 1174, 1175, 1176, 1177, 1178FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.3.2.8 1 1179 MHP1 Controls Complete
1181 1.2 1.2.8.5.6.3.4 MHP2 Not Started P 7 1 14d 11/15/23 12/06/23 11/15/23 5:00 PM 12/06/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.4 1 1180 MHP2
1182 1.2 1.2.8.5.6.3.4.1 Mechanical Refit & Repairs (MHP2) Not Started P 8 1 8d 11/15/23 11/28/23 11/15/23 5:00 PM 11/28/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.4.1 1 1181 Mechanical Refit & Repairs (MHP2)
1183 1.2 1.2.8.5.6.3.4.1.1 Heater Flush and Pressure Test Not Started C 9 1 e3d 11/18/23 11/21/23 11/18/23 5:00 PM 11/21/23 4:59 PM 1165 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.4.1.1 1 1182 Heater Flush and Pressure Test
1184 1.2 1.2.8.5.6.3.4.1.2 Plumbing Upgrades & Repairs Not Started C 9 1 e3d 11/24/23 11/27/23 11/24/23 5:00 PM 11/27/23 4:59 PM 1199 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.4.1.2 1 1183 Plumbing Upgrades & Repairs
1185 1.2 1.2.8.5.6.3.4.1.3 Fuel System Upgrades and Repairs Not Started C 9 1 e1d 11/15/23 11/16/23 11/15/23 5:00 PM 11/16/23 4:59 PM 1167 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.4.1.3 1 1184 Fuel System Upgrades and Repairs
1186 1.2 1.2.8.5.6.3.4.1.4 Exhaust System Upgrades and Repairs Not Started C 9 1 e1d 11/16/23 11/17/23 11/16/23 5:00 PM 11/17/23 4:59 PM 1168 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Contract_Driller 1.2.8.5.6.3.4.1.4 1 1185 Exhaust System Upgrades and Repairs
1187 1.2 1.2.8.5.6.3.4.1.5 MHP2 Subsystem Evaluation Not Started C 9 1 e1d 11/27/23 11/28/23 11/27/23 5:00 PM 11/28/23 4:59 PM 1182, 1183, 1185, 1186, 1184FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer 1.2.8.5.6.3.4.1.5 1 1186 MHP2 Subsystem Evaluation
1188 1.2 1.2.8.5.6.3.4.1.6 MHP2 Mechanical Complete Not Started C 9 1 1 0 11/28/23 11/28/23 11/28/23 4:59 PM 11/28/23 4:59 PM 1186 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.4.1.6 1 1187 MHP2 Mechanical Complete
1189 1.2 1.2.8.5.6.3.4.2 Electrical/Controls Refit & Repairs (MHP2) Not Started P 8 1 13d 11/16/23 12/06/23 11/16/23 5:00 PM 12/06/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.4.2 1 1188 Electrical/Controls Refit & Repairs (MHP2)
1190 1.2 1.2.8.5.6.3.4.2.1 Install PLC-to-DGH Gateway in Network Box, Install M-DGHs, & Test Not Started C 9 1 e1d 11/16/23 11/17/23 11/16/23 5:00 PM 11/17/23 4:59 PM 1205 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.4.2.1 1 1189 Install PLC-to-DGH Gateway in Network Box, Install M-DGHs, & Test
1191 1.2 1.2.8.5.6.3.4.2.2 Install Refurbished Heater Control Assemblies on All Heaters (M-DGHs pre-installed) Not Started C 9 1 e3d 11/17/23 11/20/23 11/17/23 5:00 PM 11/20/23 4:59 PM 1173 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.3.4.2.2 1 1190 Install Refurbished Heater Control Assemblies on All Heaters (M-DGHs pre-installed)
1192 1.2 1.2.8.5.6.3.4.2.3 Replace Thermostats in Heaters & Test Not Started C 9 1 e2d 11/30/23 12/02/23 11/30/23 5:00 PM 12/02/23 4:59 PM 1207 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.3.4.2.3 1 1191 Replace Thermostats in Heaters & Test
1193 1.2 1.2.8.5.6.3.4.2.4 Test E-stop and Heater Controls with No Water Not Started C 9 1 e2d 11/21/23 11/23/23 11/21/23 5:00 PM 11/23/23 4:59 PM 1176 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.4.2.4 1 1192 Test E-stop and Heater Controls with No Water
1194 1.2 1.2.8.5.6.3.4.2.5 Test Flow Sensor Operation with No Water Not Started C 9 1 e1d 12/05/23 12/06/23 12/05/23 5:00 PM 12/06/23 4:59 PM 1177 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.4.2.5 1 1193 Test Flow Sensor Operation with No Water
1195 1.2 1.2.8.5.6.3.4.2.6 Install Ethernet Switch, Connect to Network Box, Route Cable to DCC & Test Not Started C 9 1 e1d 11/29/23 11/30/23 11/29/23 5:00 PM 11/30/23 4:59 PM 1210 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.4.2.6 1 1194 Install Ethernet Switch, Connect to Network Box, Route Cable to DCC & Test
1196 1.2 1.2.8.5.6.3.4.2.7 MHP2 Controls Complete Not Started C 9 1 1 0 12/06/23 12/06/23 12/06/23 4:59 PM 12/06/23 4:59 PM 1189, 1190, 1191, 1192, 1193, 1194 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.4.2.7 1 1195 MHP2 Controls Complete
1197 1.2 1.2.8.5.6.3.5 MHP3 Not Started P 7 1 15d 11/15/23 12/07/23 11/15/23 5:00 PM 12/07/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.5 1 1196 MHP3
1198 1.2 1.2.8.5.6.3.5.1 Mechanical Refit & Repairs (MHP3) Not Started P 8 1 5d 11/16/23 11/25/23 11/16/23 5:00 PM 11/25/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.5.1 1 1197 Mechanical Refit & Repairs (MHP3)
1199 1.2 1.2.8.5.6.3.5.1.1 Heater Flush and Pressure Test Not Started C 9 1 e3d 11/21/23 11/24/23 11/21/23 5:00 PM 11/24/23 4:59 PM 1182 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.5.1.1 1 1198 Heater Flush and Pressure Test
1200 1.2 1.2.8.5.6.3.5.1.2 Plumbing Upgrades & Repairs Not Started C 9 1 e3d 11/21/23 11/24/23 11/21/23 5:00 PM 11/24/23 4:59 PM 1215 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.5.1.2 1 1199 Plumbing Upgrades & Repairs
1201 1.2 1.2.8.5.6.3.5.1.3 Fuel System Upgrades and Repairs Not Started C 9 1 e1d 11/16/23 11/17/23 11/16/23 5:00 PM 11/17/23 4:59 PM 1184 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.5.1.3 1 1200 Fuel System Upgrades and Repairs
1202 1.2 1.2.8.5.6.3.5.1.4 Exhaust System Upgrades and Repairs Not Started C 9 1 e1d 11/17/23 11/18/23 11/17/23 5:00 PM 11/18/23 4:59 PM 1185 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Contract_Driller 1.2.8.5.6.3.5.1.4 1 1201 Exhaust System Upgrades and Repairs
1203 1.2 1.2.8.5.6.3.5.1.5 MHP3 Subsystem Evaluation Not Started C 9 1 e1d 11/24/23 11/25/23 11/24/23 5:00 PM 11/25/23 4:59 PM 1198, 1199, 1201, 1202, 1200 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer 1.2.8.5.6.3.5.1.5 1 1202 MHP3 Subsystem Evaluation
1204 1.2 1.2.8.5.6.3.5.1.6 MHP3 Mechanical Complete Not Started C 9 1 1 0 11/25/23 11/25/23 11/25/23 4:59 PM 11/25/23 4:59 PM 1202 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.5.1.6 1 1203 MHP3 Mechanical Complete
1205 1.2 1.2.8.5.6.3.5.2 Electrical/Controls Refit & Repairs (MHP3) Not Started P 8 1 15d 11/15/23 12/07/23 11/15/23 5:00 PM 12/07/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.5.2 1 1204 Electrical/Controls Refit & Repairs (MHP3)
1206 1.2 1.2.8.5.6.3.5.2.1 Install PLC-to-DGH Gateway in Network Box, Install M-DGHs, & Test Not Started C 9 1 e1d 11/15/23 11/16/23 11/15/23 5:00 PM 11/16/23 4:59 PM 1221 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.5.2.1 1 1205 Install PLC-to-DGH Gateway in Network Box, Install M-DGHs, & Test
1207 1.2 1.2.8.5.6.3.5.2.2 Install Refurbished Heater Control Assemblies on All Heaters (M-DGHs pre-installed) Not Started C 9 1 e3d 11/20/23 11/23/23 11/20/23 5:00 PM 11/23/23 4:59 PM 1190 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.3.5.2.2 1 1206 Install Refurbished Heater Control Assemblies on All Heaters (M-DGHs pre-installed)
1208 1.2 1.2.8.5.6.3.5.2.3 Replace Thermostats in Heaters & Test Not Started C 9 1 e2d 11/28/23 11/30/23 11/28/23 5:00 PM 11/30/23 4:59 PM 1223 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.3.5.2.3 1 1207 Replace Thermostats in Heaters & Test
1209 1.2 1.2.8.5.6.3.5.2.4 Test E-stop and Heater Controls with No Water Not Started C 9 1 e2d 11/23/23 11/25/23 11/23/23 5:00 PM 11/25/23 4:59 PM 1192 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.5.2.4 1 1208 Test E-stop and Heater Controls with No Water
1210 1.2 1.2.8.5.6.3.5.2.5 Test Flow Sensor Operation with No Water Not Started C 9 1 e1d 12/06/23 12/07/23 12/06/23 5:00 PM 12/07/23 4:59 PM 1193 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.5.2.5 1 1209 Test Flow Sensor Operation with No Water
1211 1.2 1.2.8.5.6.3.5.2.6 Install Ethernet Switch, Connect to Network Box, Route Cable to DCC & Test Not Started C 9 1 e1d 11/28/23 11/29/23 11/28/23 5:00 PM 11/29/23 4:59 PM 1226 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.5.2.6 1 1210 Install Ethernet Switch, Connect to Network Box, Route Cable to DCC & Test
1212 1.2 1.2.8.5.6.3.5.2.7 MHP3 Controls Complete Not Started C 9 1 1 0 12/07/23 12/07/23 12/07/23 4:59 PM 12/07/23 4:59 PM 1205, 1206, 1207, 1208, 1209, 1210 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.5.2.7 1 1211 MHP3 Controls Complete
1213 1.2 1.2.8.5.6.3.6 MHP4 Not Started P 7 1 17d 11/14/23 12/08/23 11/14/23 5:00 PM 12/08/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.6 1 1212 MHP4
1214 1.2 1.2.8.5.6.3.6.1 Mechanical Refit & Repairs (MHP4) Not Started P 8 1 5d 11/17/23 11/27/23 11/17/23 5:00 PM 11/27/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.6.1 1 1213 Mechanical Refit & Repairs (MHP4)
1215 1.2 1.2.8.5.6.3.6.1.1 Heater Flush and Pressure Test Not Started C 9 1 e2d 11/24/23 11/26/23 11/24/23 5:00 PM 11/26/23 4:59 PM 1198 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.6.1.1 1 1214 Heater Flush and Pressure Test
1216 1.2 1.2.8.5.6.3.6.1.2 Plumbing Upgrades & Repairs Not Started C 9 1 e3d 11/18/23 11/21/23 11/18/23 5:00 PM 11/21/23 4:59 PM 1216 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.6.1.2 1 1215 Plumbing Upgrades & Repairs
1217 1.2 1.2.8.5.6.3.6.1.3 Fuel System Upgrades and Repairs Not Started C 9 1 e1d 11/17/23 11/18/23 11/17/23 5:00 PM 11/18/23 4:59 PM 1200 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.3.6.1.3 1 1216 Fuel System Upgrades and Repairs
1218 1.2 1.2.8.5.6.3.6.1.4 Exhaust System Upgrades and Repairs Not Started C 9 1 e1d 11/18/23 11/19/23 11/18/23 5:00 PM 11/19/23 4:59 PM 1201 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Contract_Driller 1.2.8.5.6.3.6.1.4 1 1217 Exhaust System Upgrades and Repairs
1219 1.2 1.2.8.5.6.3.6.1.5 MHP4 Subsystem Evaluation Not Started C 9 1 e1d 11/26/23 11/27/23 11/26/23 5:00 PM 11/27/23 4:59 PM 1214, 1215, 1216, 1217 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer 1.2.8.5.6.3.6.1.5 1 1218 MHP4 Subsystem Evaluation
1220 1.2 1.2.8.5.6.3.6.1.6 MHP4 Mechanical Complete Not Started C 9 1 1 0 11/27/23 11/27/23 11/27/23 4:59 PM 11/27/23 4:59 PM 1218 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.6.1.6 1 1219 MHP4 Mechanical Complete
1221 1.2 1.2.8.5.6.3.6.2 Electrical/Controls Refit & Repairs (MHP4) Not Started P 8 1 17d 11/14/23 12/08/23 11/14/23 5:00 PM 12/08/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.6.2 1 1220 Electrical/Controls Refit & Repairs (MHP4)
1222 1.2 1.2.8.5.6.3.6.2.1 Install PLC-to-DGH Gateway in Network Box, Install M-DGHs, & Test Not Started C 9 1 e1d 11/14/23 11/15/23 11/14/23 5:00 PM 11/15/23 4:59 PM 1161 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.6.2.1 1 1221 Install PLC-to-DGH Gateway in Network Box, Install M-DGHs, & Test
1223 1.2 1.2.8.5.6.3.6.2.2 Install Refurbished Heater Control Assemblies on All Heaters (M-DGHs pre-installed) Not Started C 9 1 e3d 11/23/23 11/26/23 11/23/23 5:00 PM 11/26/23 4:59 PM 1206 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.3.6.2.2 1 1222 Install Refurbished Heater Control Assemblies on All Heaters (M-DGHs pre-installed)
1224 1.2 1.2.8.5.6.3.6.2.3 Replace Thermostats in Heaters & Test Not Started C 9 1 e2d 11/26/23 11/28/23 11/26/23 5:00 PM 11/28/23 4:59 PM 1222 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.3.6.2.3 1 1223 Replace Thermostats in Heaters & Test
1225 1.2 1.2.8.5.6.3.6.2.4 Test E-stop and Heater Controls with No Water Not Started C 9 1 e2d 11/25/23 11/27/23 11/25/23 5:00 PM 11/27/23 4:59 PM 1208 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.6.2.4 1 1224 Test E-stop and Heater Controls with No Water
1226 1.2 1.2.8.5.6.3.6.2.5 Test Flow Sensor Operation with No Water Not Started C 9 1 e1d 12/07/23 12/08/23 12/07/23 5:00 PM 12/08/23 4:59 PM 1209 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.6.2.5 1 1225 Test Flow Sensor Operation with No Water
1227 1.2 1.2.8.5.6.3.6.2.6 Install Ethernet Switch, Connect to Network Box, Route Cable to DCC & Test Not Started C 9 1 e1d 11/27/23 11/28/23 11/27/23 5:00 PM 11/28/23 4:59 PM 1224 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.3.6.2.6 1 1226 Install Ethernet Switch, Connect to Network Box, Route Cable to DCC & Test
1228 1.2 1.2.8.5.6.3.6.2.7 MHP4 Controls Complete Not Started C 9 1 1 0 12/08/23 12/08/23 12/08/23 4:59 PM 12/08/23 4:59 PM 1221, 1222, 1223, 1224, 1225, 1226 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.3.6.2.7 1 1227 MHP4 Controls Complete
1229 1.2 1.2.8.5.6.4 Pre-Heat System (PHS) Not Started P 6 1 12d 11/27/23 12/12/23 11/27/23 8:00 AM 12/12/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.4 1 1228 Pre-Heat System (PHS)
1230 1.2 1.2.8.5.6.4.1 PHS Relocation Support (USAP) Not Started C 7 1 1d 11/27/23 11/27/23 11/27/23 8:00 AM 11/27/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.4.1 1 1229 PHS Relocation Support (USAP)
1231 1.2 1.2.8.5.6.4.2 Install PHS Fall Restraint Towers (USAP) Not Started C 7 1 1d 11/28/23 11/28/23 11/28/23 8:00 AM 11/28/23 4:59 PM 1229 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.4.2 1 1230 Install PHS Fall Restraint Towers (USAP)
1232 1.2 1.2.8.5.6.4.3 Mechanical Refit & Repairs (PHS) Not Started P 7 1 11d 11/28/23 12/12/23 11/28/23 8:00 AM 12/12/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.4.3 1 1231 Mechanical Refit & Repairs (PHS)
1233 1.2 1.2.8.5.6.4.3.1 Heater Flush and Pressure Test Not Started C 8 1 2d 11/28/23 11/29/23 11/28/23 8:00 AM 11/29/23 4:59 PM 1229 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.4.3.1 1 1232 Heater Flush and Pressure Test
1234 1.2 1.2.8.5.6.4.3.2 Plumbing Upgrades & Repairs Not Started C 8 1 1d 11/30/23 11/30/23 11/30/23 8:00 AM 11/30/23 4:59 PM 1232 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.4.3.2 1 1233 Plumbing Upgrades & Repairs
1235 1.2 1.2.8.5.6.4.3.3 Fuel System Upgrades & Repairs Not Started C 8 1 1d 12/01/23 12/01/23 12/01/23 8:00 AM 12/01/23 4:59 PM 1233 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.4.3.3 1 1234 Fuel System Upgrades & Repairs
1236 1.2 1.2.8.5.6.4.3.4 Exhaust System Upgrades & Repairs Not Started C 8 1 1d 11/29/23 11/29/23 11/29/23 8:00 AM 11/29/23 4:59 PM 1230 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Contract_Driller 1.2.8.5.6.4.3.4 1 1235 Exhaust System Upgrades & Repairs
1237 1.2 1.2.8.5.6.4.3.5 Install Condensate System Not Started C 8 1 6d 12/01/23 12/08/23 12/01/23 8:00 AM 12/08/23 4:59 PM 1233 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.4.3.5 1 1236 Install Condensate System
1238 1.2 1.2.8.5.6.4.3.6 Install Filtration System Not Started C 8 1 6d 12/01/23 12/08/23 12/01/23 8:00 AM 12/08/23 4:59 PM 1233 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.4.3.6 1 1237 Install Filtration System
1239 1.2 1.2.8.5.6.4.3.7 PHS Subsystem Evaluation Not Started C 8 1 1 1d 12/12/23 12/12/23 12/12/23 8:00 AM 12/12/23 4:59 PM 1248, 1237 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.4.3.7 1 1238 PHS Subsystem Evaluation
1240 1.2 1.2.8.5.6.4.3.8 PHS Mechanical Complete Not Started C 8 1 1 0 12/12/23 12/12/23 12/12/23 4:59 PM 12/12/23 4:59 PM 1232, 1233, 1235, 1236, 1237, 1238 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.4.3.8 1 1239 PHS Mechanical Complete
1241 1.2 1.2.8.5.6.4.4 Electrical/Controls Refit & Repairs (PHS) Not Started P 7 1 11d 11/28/23 12/12/23 11/28/23 8:00 AM 12/12/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.4.4 1 1240 Electrical/Controls Refit & Repairs (PHS)
1242 1.2 1.2.8.5.6.4.4.1 Mount 4 Motor Drives, Connect AC Input and Output Leads Not Started C 8 1 4d 11/28/23 12/01/23 11/28/23 8:00 AM 12/01/23 4:59 PM 1229 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.4.4.1 1 1241 Mount 4 Motor Drives, Connect AC Input and Output Leads
1243 1.2 1.2.8.5.6.4.4.2 Install New Motor-enable Relays in E-stop Box, Test with Motor Drives Not Started C 8 1 2d 12/04/23 12/05/23 12/04/23 8:00 AM 12/05/23 4:59 PM 1241 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.4.4.2 1 1242 Install New Motor-enable Relays in E-stop Box, Test with Motor Drives
1244 1.2 1.2.8.5.6.4.4.3 Install Refurbished Network Box and Heater M-DGHs, Connect Sensor Cables, & Test Not Started C 8 1 3d 12/04/23 12/06/23 12/04/23 8:00 AM 12/06/23 4:59 PM 1241 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.4.4.3 1 1243 Install Refurbished Network Box and Heater M-DGHs, Connect Sensor Cables, & Test
1245 1.2 1.2.8.5.6.4.4.4 Replace Outdoor E-stop Slap Switch Not Started C 8 1 0.5d 12/07/23 12/07/23 12/07/23 8:00 AM 12/07/23 11:59 AM 1243 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.4.4.4 1 1244 Replace Outdoor E-stop Slap Switch
1246 1.2 1.2.8.5.6.4.4.5 Test Heater Controls Not Started C 8 1 2d 12/06/23 12/07/23 12/06/23 8:00 AM 12/07/23 4:59 PM 1242 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.4.4.5 1 1245 Test Heater Controls
1247 1.2 1.2.8.5.6.4.4.6 Connect and Test Tank Temperature and Level Sensors Not Started C 8 1 2d 12/07/23 12/11/23 12/07/23 1:00 PM 12/11/23 11:59 AM 1244 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.4.4.6 1 1246 Connect and Test Tank Temperature and Level Sensors
1248 1.2 1.2.8.5.6.4.4.7 Test Integrated Subsystem with Mobile HMI: Controls, Feedback, Operational Logic Not Started C 8 1 3d 12/08/23 12/12/23 12/08/23 8:00 AM 12/12/23 4:59 PM 1245 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.4.4.7 1 1247 Test Integrated Subsystem with Mobile HMI: Controls, Feedback, Operational Logic
1249 1.2 1.2.8.5.6.4.4.8 Connect and Test Environmental Sensors (temperature, fire/smoke, flooding) Not Started C 8 1 2d 12/08/23 12/11/23 12/08/23 8:00 AM 12/11/23 4:59 PM 1245 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.4.4.8 1 1248 Connect and Test Environmental Sensors (temperature, fire/smoke, flooding)
1250 1.2 1.2.8.5.6.4.4.9 PHS Subsystem Evaluation Not Started C 8 1 1 1d 12/12/23 12/12/23 12/12/23 8:00 AM 12/12/23 4:59 PM 1248, 1237 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.4.4.9 1 1249 PHS Subsystem Evaluation
1251 1.2 1.2.8.5.6.4.4.10 PHS Controls Complete Not Started C 8 1 1 0 12/12/23 12/12/23 12/12/23 4:59 PM 12/12/23 4:59 PM 1241, 1242, 1243, 1244, 1245, 1246, 1247, 1248, 1249 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.4.4.10 1 1250 PHS Controls Complete
1252 1.2 1.2.8.5.6.5 HPP Not Started P 6 1 21d 12/08/23 01/09/24 12/08/23 8:00 AM 01/09/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.5 1 1251 HPP
1253 1.2 1.2.8.5.6.5.1 HPP Relocation Support (USAP) Not Started C 7 1 1d 12/08/23 12/08/23 12/08/23 8:00 AM 12/08/23 4:59 PM 1425 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.5.1 1 1252 HPP Relocation Support (USAP)
1254 1.2 1.2.8.5.6.5.2 Install HPP Fall Restraint Towers (USAP) Not Started C 7 1 1d 12/11/23 12/11/23 12/11/23 8:00 AM 12/11/23 4:59 PM 1252 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.5.2 1 1253 Install HPP Fall Restraint Towers (USAP)
1255 1.2 1.2.8.5.6.5.3 Mechanical Refit & Repairs (HPP) Not Started P 7 1 6d 12/11/23 12/18/23 12/11/23 8:00 AM 12/18/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.5.3 1 1254 Mechanical Refit & Repairs (HPP)
1256 1.2 1.2.8.5.6.5.3.1 Plumbing Upgrades & Repairs Not Started C 8 1 2d 12/11/23 12/12/23 12/11/23 8:00 AM 12/12/23 4:59 PM 1425FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.5.3.1 1 1255 Plumbing Upgrades & Repairs
1257 1.2 1.2.8.5.6.5.3.2 Fuel System Upgrades and Repairs Not Started C 8 1 1d 12/11/23 12/11/23 12/11/23 8:00 AM 12/11/23 4:59 PM 1252 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.5.3.2 1 1256 Fuel System Upgrades and Repairs
1258 1.2 1.2.8.5.6.5.3.3 Exhaust System Upgrades and Repairs Not Started C 8 1 1d 12/12/23 12/12/23 12/12/23 8:00 AM 12/12/23 4:59 PM 1253 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Contract_Driller 1.2.8.5.6.5.3.3 1 1257 Exhaust System Upgrades and Repairs
1259 1.2 1.2.8.5.6.5.3.4 High Pressure Pump Upgrade & Repairs Not Started C 8 1 3d 12/13/23 12/15/23 12/13/23 8:00 AM 12/15/23 4:59 PM 1255 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer 1.2.8.5.6.5.3.4 1 1258 High Pressure Pump Upgrade & Repairs
1260 1.2 1.2.8.5.6.5.3.5 HPP Subsystem Evaluation Not Started C 8 1 1d 12/18/23 12/18/23 12/18/23 8:00 AM 12/18/23 4:59 PM 1258 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer 1.2.8.5.6.5.3.5 1 1259 HPP Subsystem Evaluation
1261 1.2 1.2.8.5.6.5.3.6 HPP Mechanical Complete Not Started C 8 1 1 0 12/15/23 12/15/23 12/15/23 4:59 PM 12/15/23 4:59 PM 1258 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.5.3.6 1 1260 HPP Mechanical Complete
1262 1.2 1.2.8.5.6.5.4 Electrical/Controls Refit & Repairs (HPP) Not Started P 7 1 18d 12/13/23 01/09/24 12/13/23 8:00 AM 01/09/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.5.4 1 1261 Electrical/Controls Refit & Repairs (HPP)
1263 1.2 1.2.8.5.6.5.4.1 Mount 4 Motor Drives, Connect AC Input & Output Leads Not Started C 8 1 4d 12/13/23 12/18/23 12/13/23 8:00 AM 12/18/23 4:59 PM 1255 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.5.4.1 1 1262 Mount 4 Motor Drives, Connect AC Input & Output Leads
1264 1.2 1.2.8.5.6.5.4.2 Test Motor Drive Connections to E-stop, Sensors, Air Dampers, Inlet Pressure Switches Not Started C 8 1 2d 12/19/23 12/20/23 12/19/23 8:00 AM 12/20/23 4:59 PM 1262 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.5.4.2 1 1263 Test Motor Drive Connections to E-stop, Sensors, Air Dampers, Inlet Pressure Switches
1265 1.2 1.2.8.5.6.5.4.3 Install New PLC box in HPP, Connect to Network Box, Test with Mobile HMI Not Started C 8 1 4d 12/13/23 12/18/23 12/13/23 8:00 AM 12/18/23 4:59 PM 1255 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.5.4.3 1 1264 Install New PLC box in HPP, Connect to Network Box, Test with Mobile HMI
1266 1.2 1.2.8.5.6.5.4.4 Install 4 Refurbished Soft-Start Boxes in HPP, Connect to AC & New PLC Box Not Started C 8 1 2d 12/19/23 12/20/23 12/19/23 8:00 AM 12/20/23 4:59 PM 1264 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.5.4.4 1 1265 Install 4 Refurbished Soft-Start Boxes in HPP, Connect to AC & New PLC Box
1267 1.2 1.2.8.5.6.5.4.5 Install Re-built Pressure and Flow Sensor Box in HPP & Test Not Started C 8 1 2d 12/21/23 12/22/23 12/21/23 8:00 AM 12/22/23 4:59 PM 1263 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.5.4.5 1 1266 Install Re-built Pressure and Flow Sensor Box in HPP & Test
1268 1.2 1.2.8.5.6.5.4.6 Install Rebuilt DGH box for Reading Pressure and Flow Sensors & Test Not Started C 8 1 2d 12/21/23 12/22/23 12/21/23 8:00 AM 12/22/23 4:59 PM 1265 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.5.4.6 1 1267 Install Rebuilt DGH box for Reading Pressure and Flow Sensors & Test
1269 1.2 1.2.8.5.6.5.4.7 Install New Motor-enable Relays in E-stop box, Test with Motor Drives Not Started C 8 1 2d 12/26/23 12/27/23 12/26/23 8:00 AM 12/27/23 4:59 PM 1266 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.5.4.7 1 1268 Install New Motor-enable Relays in E-stop box, Test with Motor Drives
1270 1.2 1.2.8.5.6.5.4.8 Install Refurbished Network box with M-DGHs, Connect Sensor Cables, & Test Not Started C 8 1 3d 12/26/23 12/28/23 12/26/23 8:00 AM 12/28/23 4:59 PM 1267 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.5.4.8 1 1269 Install Refurbished Network box with M-DGHs, Connect Sensor Cables, & Test
1271 1.2 1.2.8.5.6.5.4.9 Test Integrated Subsystem with Mobile HMI: Controls, Feedback, & Operational Logic Not Started C 8 1 5d 12/28/23 01/04/24 12/28/23 8:00 AM 01/04/24 4:59 PM 1269FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.5.4.9 1 1270 Test Integrated Subsystem with Mobile HMI: Controls, Feedback, & Operational Logic
1272 1.2 1.2.8.5.6.5.4.10 Connect and Test Environmental Sensors (temperature, fire/smoke, flooding) Not Started C 8 1 2d 01/05/24 01/08/24 01/05/24 8:00 AM 01/08/24 4:59 PM 1270 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.5.4.10 1 1271 Connect and Test Environmental Sensors (temperature, fire/smoke, flooding)
1273 1.2 1.2.8.5.6.5.4.11 Test Air-handling System in HPP Not Started C 8 1 2d 12/26/23 12/27/23 12/26/23 8:00 AM 12/27/23 4:59 PM 1252FS +10d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.5.4.11 1 1272 Test Air-handling System in HPP
1274 1.2 1.2.8.5.6.5.4.12 HPP Subsystem Evaluation Not Started C 8 1 1d 01/09/24 01/09/24 01/09/24 8:00 AM 01/09/24 4:59 PM 1262, 1263, 1264, 1265, 1266, 1267, 1268, 1269, 1270, 1271, 1272 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.5.4.12 1 1273 HPP Subsystem Evaluation
1275 1.2 1.2.8.5.6.5.4.13 HPP Controls Complete Not Started C 8 1 1 0 01/09/24 01/09/24 01/09/24 4:59 PM 01/09/24 4:59 PM 1273 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.5.4.13 1 1274 HPP Controls Complete
1276 1.2 1.2.8.5.6.6 Water Tanks & Handling Systems (VT & Submersible) Not Started P 6 1 8d 12/12/23 12/21/23 12/12/23 8:00 AM 12/21/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.6 1 1275 Water Tanks & Handling Systems (VT & Submersible)
1277 1.2 1.2.8.5.6.6.1 Water Tank Relocation Support (USAP) Not Started C 7 1 1d 12/13/23 12/13/23 12/13/23 8:00 AM 12/13/23 4:59 PM 1426, 1427 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.6.1 1 1276 Water Tank Relocation Support (USAP)
1278 1.2 1.2.8.5.6.6.2 Water Tanks Mechanical Refit & Repairs (VT & Submersible) Not Started P 7 1 8d 12/12/23 12/21/23 12/12/23 8:00 AM 12/21/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.6.2 1 1277 Water Tanks Mechanical Refit & Repairs (VT & Submersible)
1279 1.2 1.2.8.5.6.6.2.1 Water Tank Modifications (Railings & Ladders) Not Started C 8 1 4d 12/14/23 12/19/23 12/14/23 8:00 AM 12/19/23 4:59 PM 1276 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Contract_Driller 1.2.8.5.6.6.2.1 1 1278 Water Tank Modifications (Railings & Ladders)
1280 1.2 1.2.8.5.6.6.2.2 Water Tanks Plumbing (Vert pumps, Sub. Pumps, Manifolds) Not Started C 8 1 4d 12/18/23 12/21/23 12/18/23 8:00 AM 12/21/23 4:59 PM 1278FS -2d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.6.2.2 1 1279 Water Tanks Plumbing (Vert pumps, Sub. Pumps, Manifolds)
1281 1.2 1.2.8.5.6.6.2.3 Crane Support for Vertical Turbine Pump Installation (USAP) Not Started C 8 1 1d 12/20/23 12/20/23 12/20/23 8:00 AM 12/20/23 4:59 PM 1279SS +2d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.6.2.3 1 1280 Crane Support for Vertical Turbine Pump Installation (USAP)
1282 1.2 1.2.8.5.6.6.2.4 Construct and Install Water Tank Doghouses (USAP) Not Started C 8 1 7d 12/12/23 12/20/23 12/12/23 8:00 AM 12/20/23 4:59 PM 1279FF -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.6.2.4 1 1281 Construct and Install Water Tank Doghouses (USAP)
1283 1.2 1.2.8.5.6.6.2.5 Water Tank Subsystem Evaluation Not Started C 8 1 1d 12/21/23 12/21/23 12/21/23 8:00 AM 12/21/23 4:59 PM 1279FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer 1.2.8.5.6.6.2.5 1 1282 Water Tank Subsystem Evaluation
1284 1.2 1.2.8.5.6.6.2.6 Water Tank Mechanicals Complete Not Started C 8 1 1 0 12/21/23 12/21/23 12/21/23 4:59 PM 12/21/23 4:59 PM 1278, 1279, 1280, 1281, 1282 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.6.2.6 1 1283 Water Tank Mechanicals Complete
1285 1.2 1.2.8.5.6.6.3 Water Tanks Electrical/Controls Refit & Repairs (VT & Submersible) Not Started P 7 1 1d 12/21/23 12/21/23 12/21/23 8:00 AM 12/21/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.6.3 1 1284 Water Tanks Electrical/Controls Refit & Repairs (VT & Submersible)
1286 1.2 1.2.8.5.6.6.3.1 Sensor Updates and Wiring Evaluation Not Started C 8 1 1d 12/21/23 12/21/23 12/21/23 8:00 AM 12/21/23 4:59 PM 1279FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.6.3.1 1 1285 Sensor Updates and Wiring Evaluation
1287 1.2 1.2.8.5.6.6.3.2 Water Tank Electrical/Controls Complete Not Started C 8 1 1 0 12/21/23 12/21/23 12/21/23 4:59 PM 12/21/23 4:59 PM 1278, 1279, 1280, 1281, 1282 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.6.3.2 1 1286 Water Tank Electrical/Controls Complete
1288 1.2 1.2.8.5.6.7 TOS & Towers Not Started P 6 1 34d 12/01/23 01/20/24 12/01/23 8:00 AM 01/20/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.7 1 1287 TOS & Towers
1289 1.2 1.2.8.5.6.7.1 TOS/Tower Relocation Support (USAP) Not Started C 7 1 1d 12/01/23 12/01/23 12/01/23 8:00 AM 12/01/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.7.1 1 1288 TOS/Tower Relocation Support (USAP)
1290 1.2 1.2.8.5.6.7.2 TOS Team 1 Not Started P 7 1 5d 12/01/23 12/10/23 12/01/23 5:00 PM 12/10/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.7.2 1 1289 TOS Team 1
1291 1.2 1.2.8.5.6.7.2.1 Mate TOS1/Tower1 Not Started C 8 1 e1d 12/01/23 12/02/23 12/01/23 5:00 PM 12/02/23 4:59 PM 1288 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.7.2.1 1 1290 Mate TOS1/Tower1
1292 1.2 1.2.8.5.6.7.2.2 Mate TOS2/Tower2 Not Started C 8 1 e1d 12/01/23 12/02/23 12/01/23 5:00 PM 12/02/23 4:59 PM 1288 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.7.2.2 1 1291 Mate TOS2/Tower2
1293 1.2 1.2.8.5.6.7.2.3 Evaluate Structures & Inventory TOS2/Tower2 Not Started C 8 1 e2d 12/02/23 12/04/23 12/02/23 5:00 PM 12/04/23 4:59 PM 1291 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.7.2.3 1 1292 Evaluate Structures & Inventory TOS2/Tower2
1294 1.2 1.2.8.5.6.7.2.4 Evaluate Structures & Inventory TOS1/Tower1 Not Started C 8 1 e2d 12/04/23 12/06/23 12/04/23 5:00 PM 12/06/23 4:59 PM 1292 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.7.2.4 1 1293 Evaluate Structures & Inventory TOS1/Tower1
1295 1.2 1.2.8.5.6.7.2.5 Fuel and Exhaust System Upgrades and Repairs TOS1/Tower1 Not Started C 8 1 e1d 12/06/23 12/07/23 12/06/23 5:00 PM 12/07/23 4:59 PM 1293 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.7.2.5 1 1294 Fuel and Exhaust System Upgrades and Repairs TOS1/Tower1
1296 1.2 1.2.8.5.6.7.2.6 Fuel and Exhaust System Upgrades and Repairs TOS2/Tower2 Not Started C 8 1 e1d 12/07/23 12/08/23 12/07/23 5:00 PM 12/08/23 4:59 PM 1294 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.7.2.6 1 1295 Fuel and Exhaust System Upgrades and Repairs TOS2/Tower2
1297 1.2 1.2.8.5.6.7.2.7 Evaluate TOS/Tower Interconnects TOS2/Tower2 Not Started C 8 1 e1d 12/08/23 12/09/23 12/08/23 5:00 PM 12/09/23 4:59 PM 1295 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.2.7 1 1296 Evaluate TOS/Tower Interconnects TOS2/Tower2
1298 1.2 1.2.8.5.6.7.2.8 Evaluate TOS/Tower Interconnects TOS1/Tower1 Not Started C 8 1 e1d 12/09/23 12/10/23 12/09/23 5:00 PM 12/10/23 4:59 PM 1296 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.2.8 1 1297 Evaluate TOS/Tower Interconnects TOS1/Tower1
1299 1.2 1.2.8.5.6.7.2.9 TOS/Tower Team 1 Tasking Complete Not Started C 8 1 1 0 12/10/23 12/10/23 12/10/23 4:59 PM 12/10/23 4:59 PM 1290, 1291, 1292, 1293, 1294, 1295, 1296, 1297 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.7.2.9 1 1298 TOS/Tower Team 1 Tasking Complete
1300 1.2 1.2.8.5.6.7.3 TOS Team 2 Not Started P 7 1 33d 12/02/23 01/20/24 12/02/23 5:00 PM 01/20/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.7.3 1 1299 TOS Team 2
1301 1.2 1.2.8.5.6.7.3.1 TOS1 - Install 8 Motor Drives, Connect AC Input & Output Leads, Connect to Network & I/O Boxes Not Started C 8 1 e8d 12/02/23 12/10/23 12/02/23 5:00 PM 12/10/23 4:59 PM 1291 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.3.1 1 1300 TOS1 - Install 8 Motor Drives, Connect AC Input & Output Leads, Connect to Network & I/O Boxes
1302 1.2 1.2.8.5.6.7.3.2 TOS2 - Install 8 Motor Drives, Connect AC Input & Output Leads, Connect to Network & I/O Boxes Not Started C 8 1 e8d 12/10/23 12/18/23 12/10/23 5:00 PM 12/18/23 4:59 PM 1300 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.3.2 1 1301 TOS2 - Install 8 Motor Drives, Connect AC Input & Output Leads, Connect to Network & I/O Boxes
1303 1.2 1.2.8.5.6.7.3.3 TOS2 - Install and Test New Payout Encoders, Load Cells, and Connections to new PLC Box Not Started C 8 1 e4d 12/18/23 12/22/23 12/18/23 5:00 PM 12/22/23 4:59 PM 1301 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.3.3 1 1302 TOS2 - Install and Test New Payout Encoders, Load Cells, and Connections to new PLC Box
1304 1.2 1.2.8.5.6.7.3.4 TOS1 - Install and Test New Payout Encoders, Load Cells, and Connections to new PLC Box Not Started C 8 1 e4d 12/22/23 12/26/23 12/22/23 5:00 PM 12/26/23 4:59 PM 1302 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.3.4 1 1303 TOS1 - Install and Test New Payout Encoders, Load Cells, and Connections to new PLC Box
1305 1.2 1.2.8.5.6.7.3.5 TOS2 - Install Missing TOS2 Line Filters for all Motor Drives (removed in 2010 by G.T.) Not Started C 8 1 3d 12/27/23 12/29/23 12/27/23 8:00 AM 12/29/23 4:59 PM 1303 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.3.5 1 1304 TOS2 - Install Missing TOS2 Line Filters for all Motor Drives (removed in 2010 by G.T.)
1306 1.2 1.2.8.5.6.7.3.6 TOS2 - Test MCR Drives w/ SHR motors, Limit Switches, E/R-stops, Pendant and Sensors Not Started C 8 1 e4d 12/29/23 01/02/24 12/29/23 5:00 PM 01/02/24 4:59 PM 1304 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.3.6 1 1305 TOS2 - Test MCR Drives w/ SHR motors, Limit Switches, E/R-stops, Pendant and Sensors
1307 1.2 1.2.8.5.6.7.3.7 TOS1 - Test MCR Drives w/ SHR motors, Limit Switches, E/R-stops, Pendant and Sensors Not Started C 8 1 e4d 01/02/24 01/06/24 01/02/24 5:00 PM 01/06/24 4:59 PM 1305 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.3.7 1 1306 TOS1 - Test MCR Drives w/ SHR motors, Limit Switches, E/R-stops, Pendant and Sensors
1308 1.2 1.2.8.5.6.7.3.8 TOS1 - Test MSHR Drives with SHR Motors, Limit Switches, E/R-stops, Pendant and Sensors Not Started C 8 1 e4d 01/06/24 01/10/24 01/06/24 5:00 PM 01/10/24 4:59 PM 1306 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.3.8 1 1307 TOS1 - Test MSHR Drives with SHR Motors, Limit Switches, E/R-stops, Pendant and Sensors
1309 1.2 1.2.8.5.6.7.3.9 TOS2 - Test MSHR Drives with SHR Motors, Limit Switches, E/R-stops, Pendant and Sensors Not Started C 8 1 e4d 01/10/24 01/14/24 01/10/24 5:00 PM 01/14/24 4:59 PM 1307 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.3.9 1 1308 TOS2 - Test MSHR Drives with SHR Motors, Limit Switches, E/R-stops, Pendant and Sensors
1310 1.2 1.2.8.5.6.7.3.10 TOS2 - Test Return Water Pump Motor Drive Not Started C 8 1 e3d 01/14/24 01/17/24 01/14/24 5:00 PM 01/17/24 4:59 PM 1308 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.3.10 1 1309 TOS2 - Test Return Water Pump Motor Drive
1311 1.2 1.2.8.5.6.7.3.11 TOS1 - Test Return Water Pump Motor Drive Not Started C 8 1 e3d 01/17/24 01/20/24 01/17/24 5:00 PM 01/20/24 4:59 PM 1309 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.3.11 1 1310 TOS1 - Test Return Water Pump Motor Drive
1312 1.2 1.2.8.5.6.7.3.12 TOS/Tower Team 2 Tasking Complete Not Started C 8 1 1 0 01/20/24 01/20/24 01/20/24 4:59 PM 01/20/24 4:59 PM 1300, 1301, 1302, 1303, 1304, 1305, 1306, 1307, 1308, 1309, 1310 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.7.3.12 1 1311 TOS/Tower Team 2 Tasking Complete
1313 1.2 1.2.8.5.6.7.4 TOS/Tower Team 3 Not Started P 7 1 33d 12/02/23 01/19/24 12/02/23 5:00 PM 01/19/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.7.4 1 1312 TOS/Tower Team 3
1314 1.2 1.2.8.5.6.7.4.1 TOS2 - Install and Test Refurbished E-stop Box Not Started C 8 1 e3d 12/02/23 12/05/23 12/02/23 5:00 PM 12/05/23 4:59 PM 1300SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.4.1 1 1313 TOS2 - Install and Test Refurbished E-stop Box
1315 1.2 1.2.8.5.6.7.4.2 TOS1 - Install and Test Refurbished E-stop Box Not Started C 8 1 e3d 12/05/23 12/08/23 12/05/23 5:00 PM 12/08/23 4:59 PM 1313 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.4.2 1 1314 TOS1 - Install and Test Refurbished E-stop Box
1316 1.2 1.2.8.5.6.7.4.3 TOS1 - Install 4 Rebuilt I/O Boxes for Cable Reel, Hose Reel, & RW Hose Reel Not Started C 8 1 e4d 12/08/23 12/12/23 12/08/23 5:00 PM 12/12/23 4:59 PM 1314 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.4.3 1 1315 TOS1 - Install 4 Rebuilt I/O Boxes for Cable Reel, Hose Reel, & RW Hose Reel
1317 1.2 1.2.8.5.6.7.4.4 TOS2 - Install 4 Rebuilt I/O Boxes for Cable Reel, Hose Reel, RW Hose Reel, & Tower Hoist Wiring Not Started C 8 1 e4d 12/12/23 12/16/23 12/12/23 5:00 PM 12/16/23 4:59 PM 1315 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.4.4 1 1316 TOS2 - Install 4 Rebuilt I/O Boxes for Cable Reel, Hose Reel, RW Hose Reel, & Tower Hoist Wiring
1318 1.2 1.2.8.5.6.7.4.5 Aerial Lift Support for Tower 2 Hoist Rewire (USAP) Not Started C 8 1 e4d 12/14/23 12/18/23 12/14/23 8:00 AM 12/18/23 7:59 AM 1316SS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.4.5 1 1317 Aerial Lift Support for Tower 2 Hoist Rewire (USAP)
1319 1.2 1.2.8.5.6.7.4.6 TOS1 - Install all Local Ethernet, E-stop, Fault Connections & Test Not Started C 8 1 e4d 12/16/23 12/20/23 12/16/23 5:00 PM 12/20/23 4:59 PM 1316 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.4.6 1 1318 TOS1 - Install all Local Ethernet, E-stop, Fault Connections & Test
1320 1.2 1.2.8.5.6.7.4.7 TOS2 - Install all Local Ethernet, E-stop, Fault Connections & Test Not Started C 8 1 e4d 12/20/23 12/24/23 12/20/23 5:00 PM 12/24/23 4:59 PM 1318 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.4.7 1 1319 TOS2 - Install all Local Ethernet, E-stop, Fault Connections & Test
1321 1.2 1.2.8.5.6.7.4.8 TOS1 - Install New DGH Gateway/Ethernet Switch/PLC box, Connect to Gen-1 Network Box Not Started C 8 1 e2d 12/24/23 12/26/23 12/24/23 5:00 PM 12/26/23 4:59 PM 1319 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.4.8 1 1320 TOS1 - Install New DGH Gateway/Ethernet Switch/PLC box, Connect to Gen-1 Network Box
1322 1.2 1.2.8.5.6.7.4.9 TOS2 - Install New DGH Gateway/Ethernet Switch/PLC box, Connect to Gen-1 Network Box Not Started C 8 1 e2d 12/26/23 12/28/23 12/26/23 5:00 PM 12/28/23 4:59 PM 1320 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.4.9 1 1321 TOS2 - Install New DGH Gateway/Ethernet Switch/PLC box, Connect to Gen-1 Network Box
1323 1.2 1.2.8.5.6.7.4.10 TOS2 - Test RWCR Motor, E & Reel Stops, Pendant and Sensors Not Started C 8 1 e2d 12/28/23 12/30/23 12/28/23 5:00 PM 12/30/23 4:59 PM 1321 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.4.10 1 1322 TOS2 - Test RWCR Motor, E & Reel Stops, Pendant and Sensors
1324 1.2 1.2.8.5.6.7.4.11 TOS1 - Test RWCR Motor, E & Reel Stops, Pendant and Sensors Not Started C 8 1 e2d 12/30/23 01/01/24 12/30/23 5:00 PM 01/01/24 4:59 PM 1322 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.4.11 1 1323 TOS1 - Test RWCR Motor, E & Reel Stops, Pendant and Sensors
1325 1.2 1.2.8.5.6.7.4.12 TOS1 - Test RWHR Motor, E & Reel Stops, Pendant and Sensors Not Started C 8 1 e2d 01/01/24 01/03/24 01/01/24 5:00 PM 01/03/24 4:59 PM 1323 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.4.12 1 1324 TOS1 - Test RWHR Motor, E & Reel Stops, Pendant and Sensors
1326 1.2 1.2.8.5.6.7.4.13 TOS2 - Test RWHR Motor, E & Reel Stops, Pendant and Sensors Not Started C 8 1 e2d 01/03/24 01/05/24 01/03/24 5:00 PM 01/05/24 4:59 PM 1324 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.4.13 1 1325 TOS2 - Test RWHR Motor, E & Reel Stops, Pendant and Sensors
1327 1.2 1.2.8.5.6.7.4.14 TOS2 - Install and Test Tower Hoist AC and Encoder Wiring (cut when hoist was removed for WISSARD) Not Started C 8 1 e2d 01/05/24 01/07/24 01/05/24 5:00 PM 01/07/24 4:59 PM 1325 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.4.14 1 1326 TOS2 - Install and Test Tower Hoist AC and Encoder Wiring (cut when hoist was removed for WISSARD)
1328 1.2 1.2.8.5.6.7.4.15 TOS2 - Test Tower Winch, E-stop, Reel Stop, Pendant, & Limit Switches Not Started C 8 1 e2d 01/07/24 01/09/24 01/07/24 5:00 PM 01/09/24 4:59 PM 1326 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.4.15 1 1327 TOS2 - Test Tower Winch, E-stop, Reel Stop, Pendant, & Limit Switches
1329 1.2 1.2.8.5.6.7.4.16 TOS1 - Test Tower Winch, E-stop, Reel Stop, Pendant, & Limit Switches Not Started C 8 1 e2d 01/09/24 01/11/24 01/09/24 5:00 PM 01/11/24 4:59 PM 1327 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.7.4.16 1 1328 TOS1 - Test Tower Winch, E-stop, Reel Stop, Pendant, & Limit Switches
1330 1.2 1.2.8.5.6.7.4.17 TOS2 - Test Integrated Subsystem with Mobile HMI: Controls, Feedback, Operational Logic Not Started C 8 1 e4d 01/11/24 01/15/24 01/11/24 5:00 PM 01/15/24 4:59 PM 1328 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.4.17 1 1329 TOS2 - Test Integrated Subsystem with Mobile HMI: Controls, Feedback, Operational Logic
1331 1.2 1.2.8.5.6.7.4.18 TOS1 - Test Integrated Subsystem with Mobile HMI: Controls, Feedback, Operational Logic Not Started C 8 1 e4d 01/15/24 01/19/24 01/15/24 5:00 PM 01/19/24 4:59 PM 1329 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.7.4.18 1 1330 TOS1 - Test Integrated Subsystem with Mobile HMI: Controls, Feedback, Operational Logic
1332 1.2 1.2.8.5.6.7.4.19 TOS/Tower Team 3 Tasking Complete Not Started C 8 1 1 0 01/19/24 01/19/24 01/19/24 4:59 PM 01/19/24 4:59 PM 1313, 1314, 1315, 1316, 1318, 1319, 1320, 1321, 1322, 1323, 1324, 1325, 1326, 1327, 1328, 1329, 1330 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.7.4.19 1 1331 TOS/Tower Team 3 Tasking Complete
1333 1.2 1.2.8.5.6.7.5 Subsystem Evaluation Not Started C 6 1 1 0 01/20/24 01/20/24 01/20/24 4:59 PM 01/20/24 4:59 PM 1298, 1311, 1331 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.7.5 1 1332 Subsystem Evaluation
1334 1.2 1.2.8.5.6.7.6 TOS/Tower Refit Complete Not Started C 6 1 1 0 01/20/24 01/20/24 01/20/24 4:59 PM 01/20/24 4:59 PM 1332 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.7.6 1 1333 TOS/Tower Refit Complete
1335 1.2 1.2.8.5.6.8 Reels Not Started P 6 1 21d 12/22/23 01/23/24 12/22/23 8:00 AM 01/23/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.8 1 1334 Reels
1336 1.2 1.2.8.5.6.8.1 Main Supply Hose Reel (MSHR) Not Started P 7 1 20d 12/22/23 01/22/24 12/22/23 8:00 AM 01/22/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.8.1 1 1335 Main Supply Hose Reel (MSHR)
1337 1.2 1.2.8.5.6.8.1.1 MSHR Relocation Support (USAP) Not Started C 8 1 1d 12/22/23 12/22/23 12/22/23 8:00 AM 12/22/23 4:59 PM 1431FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.8.1.1 1 1336 MSHR Relocation Support (USAP)
1338 1.2 1.2.8.5.6.8.1.2 Install Manifold, Heat Trace & Insulation Not Started C 8 1 4d 01/11/24 01/16/24 01/11/24 8:00 AM 01/16/24 4:59 PM 1307, 1336 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.8.1.2 1 1337 Install Manifold, Heat Trace & Insulation
1339 1.2 1.2.8.5.6.8.1.3 Inspect Drive and Control Components, Energize & Test Not Started C 8 1 2d 01/17/24 01/18/24 01/17/24 8:00 AM 01/18/24 4:59 PM 1337 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.8.1.3 1 1338 Inspect Drive and Control Components, Energize & Test
1340 1.2 1.2.8.5.6.8.1.4 MSHR Repairs & Refit Complete Not Started C 8 1 1 2d 01/19/24 01/22/24 01/19/24 8:00 AM 01/22/24 4:59 PM 1336, 1337, 1338 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.8.1.4 1 1339 MSHR Repairs & Refit Complete
1341 1.2 1.2.8.5.6.8.2 Return Water Hose Reel (RWHR) Not Started P 7 1 8d 01/01/24 01/10/24 01/01/24 8:00 AM 01/10/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.8.2 1 1340 Return Water Hose Reel (RWHR)
1342 1.2 1.2.8.5.6.8.2.1 RWHR Relocation Support (USAP) Not Started C 8 1 1d 01/01/24 01/01/24 01/01/24 8:00 AM 01/01/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.8.2.1 1 1341 RWHR Relocation Support (USAP)
1343 1.2 1.2.8.5.6.8.2.2 Install Microbrake & Service Drum Brake and Gear Box Not Started C 8 1 2d 01/02/24 01/03/24 01/02/24 8:00 AM 01/03/24 4:59 PM 1341 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.8.2.2 1 1342 Install Microbrake & Service Drum Brake and Gear Box
1344 1.2 1.2.8.5.6.8.2.3 Install Heat Trace & Insulation on Water Plumbing Not Started C 8 1 1d 01/04/24 01/04/24 01/04/24 8:00 AM 01/04/24 4:59 PM 1342 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.8.2.3 1 1343 Install Heat Trace & Insulation on Water Plumbing
1345 1.2 1.2.8.5.6.8.2.4 Install Motor Not Started C 8 1 2d 01/05/24 01/08/24 01/05/24 8:00 AM 01/08/24 4:59 PM 1343 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.8.2.4 1 1344 Install Motor
1346 1.2 1.2.8.5.6.8.2.5 Inspect Drive and Control Components, Energize & Test Not Started C 8 1 2d 01/09/24 01/10/24 01/09/24 8:00 AM 01/10/24 4:59 PM 1344 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.8.2.5 1 1345 Inspect Drive and Control Components, Energize & Test
1347 1.2 1.2.8.5.6.8.2.6 RWHR Refit & Repairs Complete Not Started C 8 1 1 0 01/10/24 01/10/24 01/10/24 4:59 PM 01/10/24 4:59 PM 1341, 1342, 1343, 1344, 1345 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.8.2.6 1 1346 RWHR Refit & Repairs Complete
1348 1.2 1.2.8.5.6.8.4 Return Water Cable Reel (RWCR) Not Started P 7 1 6d 01/01/24 01/08/24 01/01/24 8:00 AM 01/08/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.8.4 1 1347 Return Water Cable Reel (RWCR)
1349 1.2 1.2.8.5.6.8.4.1 RWCR Relocation Support (USAP) Not Started C 8 1 1d 01/01/24 01/01/24 01/01/24 8:00 AM 01/01/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.8.4.1 1 1348 RWCR Relocation Support (USAP)
1350 1.2 1.2.8.5.6.8.4.2 Install Slip Rings Not Started C 8 1 3d 01/02/24 01/04/24 01/02/24 8:00 AM 01/04/24 4:59 PM 1348 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.8.4.2 1 1349 Install Slip Rings
1351 1.2 1.2.8.5.6.8.4.3 Inspect Drive and Control Components, Energize & Test Not Started C 8 1 2d 01/05/24 01/08/24 01/05/24 8:00 AM 01/08/24 4:59 PM 1349 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.8.4.3 1 1350 Inspect Drive and Control Components, Energize & Test
1352 1.2 1.2.8.5.6.8.4.4 RWCR Repairs & Refit Complete Not Started C 8 1 1 0 01/08/24 01/08/24 01/08/24 4:59 PM 01/08/24 4:59 PM 1349, 1350 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.8.4.4 1 1351 RWCR Repairs & Refit Complete
1353 1.2 1.2.8.5.6.8.5 Main Cable Reel (MCR) Not Started P 7 1 12d 12/22/23 01/10/24 12/22/23 8:00 AM 01/10/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.8.5 1 1352 Main Cable Reel (MCR)
1354 1.2 1.2.8.5.6.8.5.1 MCR Relocation Support (USAP) Not Started C 8 1 1d 12/22/23 12/22/23 12/22/23 8:00 AM 12/22/23 4:59 PM 1431FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.8.5.1 1 1353 MCR Relocation Support (USAP)
1355 1.2 1.2.8.5.6.8.5.2 Install Slip Ring Not Started C 8 1 1d 12/26/23 12/26/23 12/26/23 8:00 AM 12/26/23 4:59 PM 1353 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.8.5.2 1 1354 Install Slip Ring
1356 1.2 1.2.8.5.6.8.5.3 Inspect Drive and Control Components, Energize & Test Not Started C 8 1 3d 01/08/24 01/10/24 01/08/24 8:00 AM 01/10/24 4:59 PM 1306, 1353 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.8.5.3 1 1355 Inspect Drive and Control Components, Energize & Test
1357 1.2 1.2.8.5.6.8.5.4 MCR Repair & Refit Complete Not Started C 8 1 1 0 01/10/24 01/10/24 01/10/24 4:59 PM 01/10/24 4:59 PM 1353, 1354, 1355 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.8.5.4 1 1356 MCR Repair & Refit Complete
1358 1.2 1.2.8.5.6.8.6 Berm all Reels for Winter (USAP) Not Started C 7 1 1d 01/23/24 01/23/24 01/23/24 8:00 AM 01/23/24 4:59 PM 1339, 1346, 1351, 1356 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.8.6 1 1357 Berm all Reels for Winter (USAP)
1359 1.2 1.2.8.5.6.9 Winches (TU-15, TU-20s) Not Started P 6 1 7d 01/09/24 01/17/24 01/09/24 8:00 AM 01/17/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.9 1 1358 Winches (TU-15, TU-20s)
1360 1.2 1.2.8.5.6.9.2 TU20 x 2 - Replace Hydraulic Pump & Upgrade Hydraulic Plumbing Not Started C 7 1 4d 01/09/24 01/12/24 01/09/24 8:00 AM 01/12/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.9.2 1 1359 TU20 x 2 - Replace Hydraulic Pump & Upgrade Hydraulic Plumbing
1361 1.2 1.2.8.5.6.9.3 TU15 - Replace Hydraulic Pump & Upgrade Hydraulic Plumbing Not Started C 7 1 2d 01/15/24 01/16/24 01/15/24 8:00 AM 01/16/24 4:59 PM 1359 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.9.3 1 1360 TU15 - Replace Hydraulic Pump & Upgrade Hydraulic Plumbing
1362 1.2 1.2.8.5.6.9.4 TU20 Test Brake/Control Interface Boxes w/ Brakes (FW rectifier and fuse) Not Started C 7 1 2d 01/12/24 01/15/24 01/12/24 8:00 AM 01/15/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.9.4 1 1361 TU20 Test Brake/Control Interface Boxes w/ Brakes (FW rectifier and fuse)
1363 1.2 1.2.8.5.6.9.5 TU20 - Install Slip Rings & Test Not Started C 7 1 3d 01/12/24 01/16/24 01/12/24 8:00 AM 01/16/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.9.5 1 1362 TU20 - Install Slip Rings & Test
1364 1.2 1.2.8.5.6.9.6 Inspect Drive and Control Components, Energize & Test Not Started C 7 1 2d 01/12/24 01/15/24 01/12/24 8:00 AM 01/15/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.6.9.6 1 1363 Inspect Drive and Control Components, Energize & Test
1365 1.2 1.2.8.5.6.9.7 Winches Complete Not Started C 7 1 1 0 01/16/24 01/16/24 01/16/24 4:59 PM 01/16/24 4:59 PM 1359, 1360, 1361, 1362, 1363 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.9.7 1 1364 Winches Complete
1366 1.2 1.2.8.5.6.9.8 Berm Winches for Winter (USAP) Not Started C 7 1 1d 01/17/24 01/17/24 01/17/24 8:00 AM 01/17/24 4:59 PM 1364 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.9.8 1 1365 Berm Winches for Winter (USAP)
1367 1.2 1.2.8.5.6.10 Independent Firn Drill (IFD) Not Started P 6 1 13d 01/06/24 01/23/24 01/06/24 8:00 AM 01/23/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.10 1 1366 Independent Firn Drill (IFD)
1368 1.2 1.2.8.5.6.10.1 Refit, Repairs, & Testing (IFD) Not Started P 7 1 9d 01/06/24 01/17/24 01/06/24 8:00 AM 01/17/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.10.1 1 1367 Refit, Repairs, & Testing (IFD)
1369 1.2 1.2.8.5.6.10.1.1 Deliver Firn Drill to Cryo Worksite (USAP) Not Started C 8 1 1d 01/06/24 01/06/24 01/06/24 8:00 AM 01/06/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.10.1.1 1 1368 Deliver Firn Drill to Cryo Worksite (USAP)
1370 1.2 1.2.8.5.6.10.1.2 Integrate & Support CRREL Gen for Firn Drill Testing (USAP) Not Started C 8 1 3d 01/08/24 01/10/24 01/08/24 8:00 AM 01/10/24 4:59 PM 1141, 1368 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.10.1.2 1 1369 Integrate & Support CRREL Gen for Firn Drill Testing (USAP)
1371 1.2 1.2.8.5.6.10.1.10 Replace Appleton Disconnect (USAP) Not Started C 8 1 2d 01/08/24 01/09/24 01/08/24 8:00 AM 01/09/24 4:59 PM 1368 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.10.1.10 1 1370 Replace Appleton Disconnect (USAP)
1372 1.2 1.2.8.5.6.10.1.3 Install Sheave - Crane or Station Hoist Not Started C 8 1 2d 01/10/24 01/11/24 01/10/24 8:00 AM 01/11/24 4:59 PM 1370 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.10.1.3 1 1371 Install Sheave - Crane or Station Hoist
1373 1.2 1.2.8.5.6.10.1.4 Crane or Station Hoist Support for Sheave Installation (USAP) Not Started C 8 1 2d 01/10/24 01/11/24 01/10/24 8:00 AM 01/11/24 4:59 PM 1370 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.10.1.4 1 1372 Crane or Station Hoist Support for Sheave Installation (USAP)
1374 1.2 1.2.8.5.6.10.1.5 Install Brake Pump & Solenoid Not Started C 8 1 1d 01/08/24 01/08/24 01/08/24 8:00 AM 01/08/24 4:59 PM 1368 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.10.1.5 1 1373 Install Brake Pump & Solenoid
1375 1.2 1.2.8.5.6.10.1.6 Install DNF - Black box, Thermostats, Power Meter, & Inst. Readout Not Started C 8 1 2d 01/08/24 01/09/24 01/08/24 8:00 AM 01/09/24 4:59 PM 1368 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.10.1.6 1 1374 Install DNF - Black box, Thermostats, Power Meter, & Inst. Readout
1376 1.2 1.2.8.5.6.10.1.7 Load Cell Calibration/Verification Not Started C 8 1 1d 01/12/24 01/12/24 01/12/24 8:00 AM 01/12/24 4:59 PM 1371 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.10.1.7 1 1375 Load Cell Calibration/Verification
1377 1.2 1.2.8.5.6.10.1.8 Supply Glycol PG (USAP) Not Started C 8 1 1 0 01/08/24 01/08/24 01/08/24 8:00 AM 01/08/24 8:00 AM 1369SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.10.1.8 1 1376 Supply Glycol PG (USAP)
1378 1.2 1.2.8.5.6.10.1.9 Fill System w/ Glycol Not Started C 8 1 1d 01/08/24 01/08/24 01/08/24 8:00 AM 01/08/24 4:59 PM 1376 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.10.1.9 1 1377 Fill System w/ Glycol
1379 1.2 1.2.8.5.6.10.1.11 Test Firn Drill Not Started C 8 1 3d 01/15/24 01/17/24 01/15/24 8:00 AM 01/17/24 4:59 PM 1369, 1371, 1372, 1373, 1374, 1375, 1376, 1377, 1370 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer 1.2.8.5.6.10.1.11 1 1378 Test Firn Drill
1380 1.2 1.2.8.5.6.10.2 Winterize (IFD) 2ME 2 TE Not Started C 7 1 2d 01/18/24 01/19/24 01/18/24 8:00 AM 01/19/24 4:59 PM 1378 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.10.2 1 1379 Winterize (IFD) 2ME 2 TE
1381 1.2 1.2.8.5.6.10.2 Stored IFD for Winter (USAP) Not Started C 7 1 2d 01/22/24 01/23/24 01/22/24 8:00 AM 01/23/24 4:59 PM 1379 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.10.2 1 1380 Stored IFD for Winter (USAP)
1382 1.2 1.2.8.5.6.11 Integrate ARA Drill (RodWell system) Not Started P 6 1 17d 01/01/24 01/23/24 01/01/24 8:00 AM 01/23/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11 1 1381 Integrate ARA Drill (RodWell system)
1383 1.2 1.2.8.5.6.11.1 Deliver ARA Drill To Cryo Worksite - Precommission Not Started C 7 1 1d 01/01/24 01/01/24 01/01/24 8:00 AM 01/01/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.1 1 1382 Deliver ARA Drill To Cryo Worksite - Precommission
1384 1.2 1.2.8.5.6.11.2 White Generator - Commission Not Started P 7 1 3d 01/02/24 01/04/24 01/02/24 8:00 AM 01/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.2 1 1383 White Generator - Commission
1385 1.2 1.2.8.5.6.11.2.1 Warm-up, Inspect Gen, Fill fluids, Install Fire Extinguisher, & Test-run John Deere with External Load Not Started C 8 1 1d 01/02/24 01/02/24 01/02/24 8:00 AM 01/02/24 4:59 PM 1382 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.2.1 1 1384 Warm-up, Inspect Gen, Fill fluids, Install Fire Extinguisher, & Test-run John Deere with External Load
1386 1.2 1.2.8.5.6.11.2.2 White Gen Electrical Rework Not Started C 8 1 2d 01/02/24 01/03/24 01/02/24 8:00 AM 01/03/24 4:59 PM 1382 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.2.2 1 1385 White Gen Electrical Rework
1387 1.2 1.2.8.5.6.11.2.3 Electrician Support for White Gen Rework (USAP) Not Started C 8 1 2d 01/02/24 01/03/24 01/02/24 8:00 AM 01/03/24 4:59 PM 1385SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.2.3 1 1386 Electrician Support for White Gen Rework (USAP)
1388 1.2 1.2.8.5.6.11.2.4 Install Control Interface Panel, Downhole Pump Controller, Ext. E-stop Slap, & Power up from Cryo Not Started C 8 1 1d 01/04/24 01/04/24 01/04/24 8:00 AM 01/04/24 4:59 PM 1386 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.2.4 1 1387 Install Control Interface Panel, Downhole Pump Controller, Ext. E-stop Slap, & Power up from Cryo
1389 1.2 1.2.8.5.6.11.3 Sled 2 Water Tank Sled - Precommission Not Started P 7 1 3d 01/03/24 01/05/24 01/03/24 8:00 AM 01/05/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.3 1 1388 Sled 2 Water Tank Sled - Precommission
1390 1.2 1.2.8.5.6.11.3.1 Warm-up & Inspect, Check HMW Sheets, & Tie-offs, Glycol Tank, Glycol Heater, Hoses & Connections Not Started C 8 1 1d 01/03/24 01/03/24 01/03/24 8:00 AM 01/03/24 4:59 PM 1384 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.3.1 1 1389 Warm-up & Inspect, Check HMW Sheets, & Tie-offs, Glycol Tank, Glycol Heater, Hoses & Connections
1391 1.2 1.2.8.5.6.11.3.2 Install ePump, Accessories, & ePump Controller (DNF-requires power) Not Started C 8 1 1d 01/04/24 01/04/24 01/04/24 8:00 AM 01/04/24 4:59 PM 1389 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.3.2 1 1390 Install ePump, Accessories, & ePump Controller (DNF-requires power)
1392 1.2 1.2.8.5.6.11.3.3 Checkout & Testing Sled 2 Not Started C 8 1 1d 01/05/24 01/05/24 01/05/24 8:00 AM 01/05/24 4:59 PM 1390 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.3.3 1 1391 Checkout & Testing Sled 2
1393 1.2 1.2.8.5.6.11.4 Sled 3 Drilling Sled - Precommission Not Started P 7 1 10d 01/05/24 01/18/24 01/05/24 8:00 AM 01/18/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.4 1 1392 Sled 3 Drilling Sled - Precommission
1394 1.2 1.2.8.5.6.11.4.1 Warm-up & Inspect Components, Install Stacks, Install Hoist, Top-off Fuel Tank, Reel Brake, Heat Trace Not Started C 8 1 2d 01/08/24 01/09/24 01/08/24 8:00 AM 01/09/24 4:59 PM 1391 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.4.1 1 1393 Warm-up & Inspect Components, Install Stacks, Install Hoist, Top-off Fuel Tank, Reel Brake, Heat Trace
1395 1.2 1.2.8.5.6.11.4.2 Plumbing Upgrades & Repairs Not Started C 8 1 2d 01/10/24 01/11/24 01/10/24 8:00 AM 01/11/24 4:59 PM 1393 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.4.2 1 1394 Plumbing Upgrades & Repairs
1396 1.2 1.2.8.5.6.11.4.3 ARA DCC Upgrades & Install Not Started C 8 1 2d 01/05/24 01/08/24 01/05/24 8:00 AM 01/08/24 4:59 PM 1387 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.4.3 1 1395 ARA DCC Upgrades & Install
1397 1.2 1.2.8.5.6.11.4.4 Hose Cable Bundle Replace Not Started C 8 1 5d 01/12/24 01/18/24 01/12/24 8:00 AM 01/18/24 4:59 PM 1394 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.4.4 1 1396 Hose Cable Bundle Replace
1398 1.2 1.2.8.5.6.11.5 Rodwell Drill Head Commissioning Not Started P 7 1 2d 01/19/24 01/22/24 01/19/24 8:00 AM 01/22/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.5 1 1397 Rodwell Drill Head Commissioning
1399 1.2 1.2.8.5.6.11.5.1 Locate Components, Set-up Drillheads on Bench, Inspect, Sensor tests Not Started C 8 1 1d 01/19/24 01/19/24 01/19/24 8:00 AM 01/19/24 4:59 PM 1396 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.5.1 1 1398 Locate Components, Set-up Drillheads on Bench, Inspect, Sensor tests
1400 1.2 1.2.8.5.6.11.5.2 Drillhead Chain Testing & Verification Not Started C 8 1 1d 01/22/24 01/22/24 01/22/24 8:00 AM 01/22/24 4:59 PM 1398 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.5.2 1 1399 Drillhead Chain Testing & Verification
1401 1.2 1.2.8.5.6.11.6 System Commissioning Not Started P 7 1 11d 01/09/24 01/23/24 01/09/24 8:00 AM 01/23/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.6 1 1400 System Commissioning
1402 1.2 1.2.8.5.6.11.6.1 System Commissioning Set-up Tasks & Global Tests Not Started C 8 1 1d 01/23/24 01/23/24 01/23/24 8:00 AM 01/23/24 4:59 PM 1399 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.6.1 1 1401 System Commissioning Set-up Tasks & Global Tests
1403 1.2 1.2.8.5.6.11.6.2 Hose Reel Commissioning Not Started C 8 1 2d 01/09/24 01/10/24 01/09/24 8:00 AM 01/10/24 4:59 PM 1395 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.6.2 1 1402 Hose Reel Commissioning
1404 1.2 1.2.8.5.6.11.6.3 Circulation Testing, w/ Glycol - Staged Approach Not Started C 8 1 1d 01/11/24 01/11/24 01/11/24 8:00 AM 01/11/24 4:59 PM 1402 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.6.3 1 1403 Circulation Testing, w/ Glycol - Staged Approach
1405 1.2 1.2.8.5.6.11.6.4 Heater Commissioning Not Started C 8 1 1d 01/12/24 01/12/24 01/12/24 8:00 AM 01/12/24 4:59 PM 1403 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.6.4 1 1404 Heater Commissioning
1406 1.2 1.2.8.5.6.11.6.5 Global Controls & E-stop Testing Not Started C 8 1 1d 01/11/24 01/11/24 01/11/24 8:00 AM 01/11/24 4:59 PM 1402 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.6.5 1 1405 Global Controls & E-stop Testing
1407 1.2 1.2.8.5.6.11.6.6 System Testing in Test Well Not Started C 8 1 1d 01/15/24 01/15/24 01/15/24 8:00 AM 01/15/24 4:59 PM 1404 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.6.6 1 1406 System Testing in Test Well
1408 1.2 1.2.8.5.6.11.7 System Winterize and Store Not Started P 7 1 3d 01/16/24 01/18/24 01/16/24 8:00 AM 01/18/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.7 1 1407 System Winterize and Store
1409 1.2 1.2.8.5.6.11.7.1 Drain & Blow-out System Not Started C 8 1 1d 01/16/24 01/16/24 01/16/24 8:00 AM 01/16/24 4:59 PM 1406 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.11.7.1 1 1408 Drain & Blow-out System
1410 1.2 1.2.8.5.6.11.7.2 Remove and Store DNF Hardware Not Started C 8 1 1d 01/17/24 01/17/24 01/17/24 8:00 AM 01/17/24 4:59 PM 1408 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.7.2 1 1409 Remove and Store DNF Hardware
1411 1.2 1.2.8.5.6.11.7.3 Tarp, Cover, & Plug Not Started C 8 1 1d 01/18/24 01/18/24 01/18/24 8:00 AM 01/18/24 4:59 PM 1409 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.11.7.3 1 1410 Tarp, Cover, & Plug
1412 1.2 1.2.8.5.6.12 Fuel Tower Not Started P 6 1 10d 11/27/23 12/08/23 11/27/23 8:00 AM 12/08/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.12 1 1411 Fuel Tower
1413 1.2 1.2.8.5.6.12.1 Fuel Tower Relocation Support (USAP) Not Started C 7 1 1d 11/27/23 11/27/23 11/27/23 8:00 AM 11/27/23 4:59 PM 1229FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.12.1 1 1412 Fuel Tower Relocation Support (USAP)
1414 1.2 1.2.8.5.6.12.2 Mechanical Repairs & Upgrades Not Started C 7 1 2d 12/01/23 12/04/23 12/01/23 8:00 AM 12/04/23 4:59 PM 1412FS +3d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.6.12.2 1 1413 Mechanical Repairs & Upgrades
1415 1.2 1.2.8.5.6.12.3 Test Existing Local Hardware, Control Functionality, Document Not Started C 7 1 2d 12/07/23 12/08/23 12/07/23 8:00 AM 12/08/23 4:59 PM 1413FS +2d 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.12.3 1 1414 Test Existing Local Hardware, Control Functionality, Document
1416 1.2 1.2.8.5.6.12.4 Fill Fuel Tower with Fuel Not Started C 7 1 1d 12/07/23 12/07/23 12/07/23 8:00 AM 12/07/23 4:59 PM 1413FS +2d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.6.12.4 1 1415 Fill Fuel Tower with Fuel
1417 1.2 1.2.8.5.6.12.5 Fuel Tower Ready to Supply Fuel Not Started C 7 1 1 0 12/07/23 12/07/23 12/07/23 4:59 PM 12/07/23 4:59 PM 1413FS +2d, 1415 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.12.5 1 1416 Fuel Tower Ready to Supply Fuel
1418 1.2 1.2.8.5.6.13 Heat Pump Unit 2 (HPU2) Not Started P 6 1 37d 12/08/23 01/31/24 12/08/23 8:00 AM 01/31/24 4:59 PM Tie to Gen complete 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.13 1 1417 Heat Pump Unit 2 (HPU2)
1419 1.2 1.2.8.5.6.13.1 HPU Relocation Support (USAP) Not Started C 7 1 4d 12/08/23 12/13/23 12/08/23 8:00 AM 12/13/23 4:59 PM 1425 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.6.13.1 1 1418 HPU Relocation Support (USAP)
1420 1.2 1.2.8.5.6.13.2 Initial Evaluation & Refit (HPU2) Not Started C 7 1 10d 01/18/24 01/31/24 01/18/24 8:00 AM 01/31/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.6.13.2 1 1419 Initial Evaluation & Refit (HPU2)
1421 1.2 1.2.8.5.7 Seasonal Equipment Site (SES) Setup Not Started P 5 1 28d 12/07/23 01/17/24 12/07/23 8:00 AM 01/17/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.7 1 1420 Seasonal Equipment Site (SES) Setup
1422 1.2 1.2.8.5.7.1 MHP Relocation to SES Not Started P 6 24d 12/07/23 01/11/24 12/07/23 8:00 AM 01/11/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.7.1 1 1421 MHP Relocation to SES
1423 1.2 1.2.8.5.7.1.1 Deliver Warm-up Shack Kuma Heated (USAP) Not Started C 7 1 1d 12/12/23 12/12/23 12/12/23 8:00 AM 12/12/23 4:59 PM 1427 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.1 1 1422 Deliver Warm-up Shack Kuma Heated (USAP)
1424 1.2 1.2.8.5.7.1.2 Driller Support for MHP Relocation (Driller) Not Started C 7 4d 12/19/23 12/22/23 12/19/23 8:00 AM 12/22/23 4:59 PM 1424SS, 1431FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Contract_Driller 1.2.8.5.7.1.2 1 1423 Driller Support for MHP Relocation (Driller)
1425 1.2 1.2.8.5.7.1.3 MHP1 Relocation to SES (USAP) Not Started C 7 1 1d 12/08/23 12/08/23 12/08/23 8:00 AM 12/08/23 4:59 PM 1170, 1179, 1425, 1131FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.3 1 1424 MHP1 Relocation to SES (USAP)
1426 1.2 1.2.8.5.7.1.4 MHP2 Relocation to SES (USAP) Not Started C 7 1 1d 12/07/23 12/07/23 12/07/23 8:00 AM 12/07/23 4:59 PM 1187, 1195, 1131FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.4 1 1425 MHP2 Relocation to SES (USAP)
1427 1.2 1.2.8.5.7.1.5 MHP3 Relocation to SES (USAP) Not Started C 7 1 1d 12/12/23 12/12/23 12/12/23 8:00 AM 12/12/23 4:59 PM 1203, 1211, 1131, 1427 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.5 1 1426 MHP3 Relocation to SES (USAP)
1428 1.2 1.2.8.5.7.1.6 MHP4 Relocation to SES (USAP) Not Started C 7 1 1d 12/11/23 12/11/23 12/11/23 8:00 AM 12/11/23 4:59 PM 1219, 1227, 1131 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.6 1 1427 MHP4 Relocation to SES (USAP)
1429 1.2 1.2.8.5.7.1.7 PHS Relocation to SES (USAP) Not Started C 7 1 1d 01/11/24 01/11/24 01/11/24 8:00 AM 01/11/24 4:59 PM 1239, 1250, 1131, 1430 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.7 1 1428 PHS Relocation to SES (USAP)
1430 1.2 1.2.8.5.7.1.8 Fuel Tower Relocation to SES (USAP) Not Started C 7 1 1d 01/11/24 01/11/24 01/11/24 8:00 AM 01/11/24 4:59 PM 1416, 1428FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.8 1 1429 Fuel Tower Relocation to SES (USAP)
1431 1.2 1.2.8.5.7.1.9 HPP Relocation to SES (USAP) Not Started C 7 1 1d 01/10/24 01/10/24 01/10/24 8:00 AM 01/10/24 4:59 PM 1260, 1274, 1131 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.9 1 1430 HPP Relocation to SES (USAP)
1432 1.2 1.2.8.5.7.1.10 Water Tanks Relocation to SES (USAP) Not Started C 7 1 1d 12/22/23 12/22/23 12/22/23 8:00 AM 12/22/23 4:59 PM 1283, 1131 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.10 1 1431 Water Tanks Relocation to SES (USAP)
1433 1.2 1.2.8.5.7.1.11 Gen1 Relocation to SES (USAP) Not Started C 7 1 1d 12/18/23 12/18/23 12/18/23 8:00 AM 12/18/23 4:59 PM #REF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.11 1 1432 Gen1 Relocation to SES (USAP)
1434 1.2 1.2.8.5.7.1.12 Gen2 Relocation to SES (USAP) Not Started C 7 1 1d 12/18/23 12/18/23 12/18/23 8:00 AM 12/18/23 4:59 PM #REF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.12 1 1433 Gen2 Relocation to SES (USAP)
1435 1.2 1.2.8.5.7.1.13 Gen3 Relocation to SES (USAP) Not Started C 7 1 1d 12/18/23 12/18/23 12/18/23 8:00 AM 12/18/23 4:59 PM #REF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.13 1 1434 Gen3 Relocation to SES (USAP)
1436 1.2 1.2.8.5.7.1.14 PDM Relocation to SES (USAP) Not Started C 7 1 1d 12/18/23 12/18/23 12/18/23 8:00 AM 12/18/23 4:59 PM #REF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.1.14 1 1435 PDM Relocation to SES (USAP)
1437 1.2 1.2.8.5.7.2 Provide Temp Small Temp Generator for SES and Establish (USAP) Not Started C 6 1 1d 12/12/23 12/12/23 12/12/23 8:00 AM 12/12/23 4:59 PM 1427 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.7.2 1 1436 Provide Temp Small Temp Generator for SES and Establish (USAP)
1438 1.2 1.2.8.5.7.3 Interconnect Evaluation - Hoses, Cables & Cable Trays for SES Not Started P 6 4d 01/12/24 01/17/24 01/12/24 8:00 AM 01/17/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.7.3 1 1437 Interconnect Evaluation - Hoses, Cables & Cable Trays for SES
1439 1.2 1.2.8.5.7.3.1 Cable Trays - Mount/Install Not Started C 7 1 4d 01/12/24 01/17/24 01/12/24 8:00 AM 01/17/24 4:59 PM 1424, 1425, 1426, 1427, 1428, 1430, 1431 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Contract_Driller 1.2.8.5.7.3.1 1 1438 Cable Trays - Mount/Install
1440 1.2 1.2.8.5.7.3.2 Hoses - Layout, Inventory, Repair & Test Not Started C 7 1 4d 01/12/24 01/17/24 01/12/24 8:00 AM 01/17/24 4:59 PM 1438SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.7.3.2 1 1439 Hoses - Layout, Inventory, Repair & Test
1441 1.2 1.2.8.5.7.3.3 Cables - Layout, Inventory, Repair & Test Not Started C 7 1 4d 01/12/24 01/17/24 01/12/24 8:00 AM 01/17/24 4:59 PM 1438SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.7.3.3 1 1440 Cables - Layout, Inventory, Repair & Test
1442 1.2 1.2.8.5.7.4 Establish Fuel Tower at SES Not Started C 6 1 2d 01/12/24 01/15/24 01/12/24 8:00 AM 01/15/24 4:59 PM 1429 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.5.7.4 1 1441 Establish Fuel Tower at SES
1443 1.2 1.2.8.5.7.5 SES Initial Setup Complete Not Started C 6 1 1 0 01/10/24 01/10/24 01/10/24 8:00 AM 01/10/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.7.5 1 1442 SES Initial Setup Complete
1444 1.2 1.2.8.5.8 End of NPX Season Close-Out Work Not Started P 5 1 11d 01/17/24 01/31/24 01/17/24 8:00 AM 01/31/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.8 1 1443 End of NPX Season Close-Out Work
1445 1.2 1.2.8.5.8.1 Document, Photograph Equip & Upgrade Work, Further Req's Not Started C 6 1 4d 01/23/24 01/26/24 01/23/24 8:00 AM 01/26/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/M_Engineer 1.2.8.5.8.1 1 1444 Document, Photograph Equip & Upgrade Work, Further Req's
1446 1.2 1.2.8.5.8.2 Remove DNF (Computer Equip, Drives, & Capacitors) & Store Not Started C 6 1 4d 01/22/24 01/25/24 01/22/24 8:00 AM 01/25/24 4:59 PM 1333, 1408 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Contract_Driller 1.2.8.5.8.2 1 1445 Remove DNF (Computer Equip, Drives, & Capacitors) & Store
1447 1.2 1.2.8.5.8.3 Winterize/Close/Store all EHWD Equipment Not Started C 6 1 e4d 01/24/24 01/28/24 01/24/24 8:00 AM 01/28/24 7:59 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.8.3 1 1446 Winterize/Close/Store all EHWD Equipment
1448 1.2 1.2.8.5.8.4 Setup & Connect Hose Heating Controller, test over FS1-FS2 winter Not Started C 6 1 2d 01/24/24 01/25/24 01/24/24 8:00 AM 01/25/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Contract_Driller 1.2.8.5.8.4 1 1447 Setup & Connect Hose Heating Controller, test over FS1-FS2 winter
1449 1.2 1.2.8.5.8.5 Crate, Pack and Deliver Retro to Cargo Not Started C 6 1 7d 01/17/24 01/25/24 01/17/24 8:00 AM 01/25/24 4:59 PM 1445FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Contract_Driller 1.2.8.5.8.5 1 1448 Crate, Pack and Deliver Retro to Cargo
1450 1.2 1.2.8.5.8.6 Winter Storage Support: TOS 1 & 2 (USAP) Not Started C 6 1 9d 01/20/24 01/31/24 01/20/24 8:00 AM 01/31/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.8.6 1 1449 Winter Storage Support: TOS 1 & 2 (USAP)
1451 1.2 1.2.8.5.8.7 Setup and Connect Hose Heating Controller, Test over FS1-FS2 Winter Not Started C 6 2d 01/22/24 01/23/24 01/22/24 8:00 AM 01/23/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.8.7 1 1450 Setup and Connect Hose Heating Controller, Test over FS1-FS2 Winter
1452 1.2 1.2.8.5.9 Other Field Activities (FS1) Not Started P 5 1 246d 02/01/23 01/15/24 02/01/23 8:00 AM 01/15/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.9 1 1451 Other Field Activities (FS1)
1453 1.2 1.2.8.5.9.1 MCM Logistics Rep (Driller) Not Started C 6 1 18d 10/25/23 11/17/23 10/25/23 8:00 AM 11/17/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.9.1 1 1452 MCM Logistics Rep (Driller)
1454 1.2 1.2.8.5.9.2 GPR Re-survey: Cable Routes & Hole Locations (USAP) Not Started C 6 1 12d 12/01/23 12/18/23 12/01/23 8:00 AM 12/18/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.9.2 1 1453 GPR Re-survey: Cable Routes & Hole Locations (USAP)
1455 1.2 1.2.8.5.9.3 Electrician Support - ICL Overwinter Storage & Rack Feeders (USAP) Not Started C 6 1 22d 12/05/23 01/05/24 12/05/23 8:00 AM 01/05/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.9.3 1 1454 Electrician Support - ICL Overwinter Storage & Rack Feeders (USAP)
1456 1.2 1.2.8.5.9.4 Logistics Support - MCM & Pole (USAP) Not Started C 6 1 44d 10/15/23 12/14/23 10/15/23 8:00 AM 12/14/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.9.4 1 1455 Logistics Support - MCM & Pole (USAP)
1457 1.2 1.2.8.5.9.5 Surface Cable, Hose, & Reels Over-Winter Storage - MCM (USAP) Not Started C 6 1 1d 01/15/24 01/15/24 01/15/24 8:00 AM 01/15/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.9.5 1 1456 Surface Cable, Hose, & Reels Over-Winter Storage - MCM (USAP)
1458 1.2 1.2.8.5.9.6 Drill Hose & Main/RWCR Over-Winter Storage - McM (USAP) Not Started C 6 1 5d 02/01/23 02/07/23 02/01/23 8:00 AM 02/07/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.5.9.6 1 1457 Drill Hose & Main/RWCR Over-Winter Storage - McM (USAP)
1459 1.2 1.2.8.5.10 ICU Field Team Redeployed Not Started C 5 1 1 0 01/29/24 01/29/24 01/29/24 4:59 PM 01/29/24 4:59 PM 1445, 1446, 1447FS +2d 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.10 1 1458 ICU Field Team Redeployed
1460 1.2 1.2.8.5.11 On-Ice Labor (FS1) Not Started C 5 1 192d 06/02/23 02/29/24 06/02/23 8:00 AM 02/29/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Team of 8
1-Dar
3-Direct-Hire Drillers
4-PSL Engineers

Travel Labor: 48 hrs/ea (Labor)
- 3 days paid time during deployment
- 3 days paid time during redeployment

Travel Cost: $1,800/ea (Travel)

PQ Cost: $950/ea (M&S)
1.2.8.5.11 1 1459 On-Ice Labor (FS1)
1461 1.2 1.2.8.5.12 END NPX FS1 Season Not Started C 5 1 1 0 01/31/24 01/31/24 01/31/24 4:59 PM 01/31/24 4:59 PM 1443FF 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.5.12 1 1460 END NPX FS1 Season
1462 1.2 1.2.8.6 USAP Field Season 2 (FY25) Not Started P 4 1 511d 02/12/24 02/03/26 02/12/24 8:00 AM 02/03/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6 1 1461 USAP Field Season 2 (FY25)
1463 1.2 1.2.8.6.1 FS2 Milestones Not Started P 5 1 193d 02/15/24 11/12/24 02/15/24 8:00 AM 11/12/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 1.2.8.6.1 1 1462 FS2 Milestones
1464 1.2 1.2.8.6.1.1 McM Mainbody Season Begins (USAP) Not Started C 6 1 1 0 10/01/24 10/01/24 10/01/24 8:00 AM 10/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.1.1 1 1463 McM Mainbody Season Begins (USAP)
1465 1.2 1.2.8.6.1.2 South Pole Season Begins (USAP) Not Started C 6 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.1.2 1 1464 South Pole Season Begins (USAP)
1466 1.2 1.2.8.6.1.3 ICU Team Arrives [Headcount 14] Not Started C 6 1 1 0 11/12/24 11/12/24 11/12/24 8:00 AM 11/12/24 8:00 AM 0 0% Green tentatively set to 16 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.1.3 1 1465 ICU Team Arrives [Headcount 14]
1467 1.2 1.2.8.6.1.4 Pole Season Ends (USAP) Not Started C 6 1 1 0 02/15/24 02/15/24 02/15/24 8:00 AM 02/15/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.1.4 1 1466 Pole Season Ends (USAP)
1468 1.2 1.2.8.6.1.5 MCM Season Ends (USAP) Not Started C 6 1 1 0 03/01/24 03/01/24 03/01/24 8:00 AM 03/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.1.5 1 1467 MCM Season Ends (USAP)
1469 1.2 1.2.8.6.2 PQ, ECW & Deployment Travel Costs (FS2) Team Not Started C 5 1 157d 07/01/24 02/07/25 07/01/24 8:00 AM 02/07/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Team of 14
1-Dar
6-Direct-Hire Drillers
6-Contributed Drillers
2-PSL Engineers

Travel Labor: 48 hrs/ea (Labor)
- 3 days paid time during deployment
- 3 days paid time during redeployment

Travel Cost: $1,800/ea (Travel)

PQ Cost: $950/ea (M&S)
1.2.8.6.2 1 1468 PQ, ECW & Deployment Travel Costs (FS2) Team
1470 1.2 1.2.8.6.3 USAP Cargo Movements (FY25) Not Started P 5 1 252d 02/12/24 02/01/25 02/12/24 8:00 AM 02/01/25 8:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3 1 1469 USAP Cargo Movements (FY25)
1471 1.2 1.2.8.6.3.1 Pole (USAP) Not Started P 6 1 252d 02/12/24 02/01/25 02/12/24 8:00 AM 02/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1 1 1470 Pole (USAP)
1472 1.2 1.2.8.6.3.1.1 LC130 - Pole (USAP) Not Started P 7 1 199d 02/12/24 11/15/24 02/12/24 8:00 AM 11/15/24 8:00 AM 0% 0 Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1.1 1 1471 LC130 - Pole (USAP)
1473 1.2 1.2.8.6.3.1.1.1 Controls Component Crates Shipment 3, DNF (USAP) Not Started C 8 1 1 0 11/15/24 11/15/24 11/15/24 8:00 AM 11/15/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1.1.1 1 1472 Controls Component Crates Shipment 3, DNF (USAP)
1474 1.2 1.2.8.6.3.1.1.2 Driller Resupply/Refit Container (8' ISO) (USAP) Not Started C 8 1 1 0 11/15/24 11/15/24 11/15/24 8:00 AM 11/15/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1.1.2 1 1473 Driller Resupply/Refit Container (8' ISO) (USAP)
1475 1.2 1.2.8.6.3.1.1.3 Drill Refit Components Crate, DNF (USAP) Not Started C 8 1 1 0 11/15/24 11/15/24 11/15/24 8:00 AM 11/15/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1.1.3 1 1474 Drill Refit Components Crate, DNF (USAP)
1476 1.2 1.2.8.6.3.1.1.4 Fuel - 10 Missions, 24,000 gallons (USAP) Not Started C 8 1 1 0 02/12/24 02/12/24 02/12/24 8:00 AM 02/12/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.3.1.1.4 1 1475 Fuel - 10 Missions, 24,000 gallons (USAP)
1477 1.2 1.2.8.6.3.1.2 SPOT1 - Pole (USAP) Not Started P 7 1 1 0 12/01/24 12/01/24 12/01/24 8:00 AM 12/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1.2 1 1476 SPOT1 - Pole (USAP)
1478 1.2 1.2.8.6.3.1.2.1 Drill Hose x 9 (USAP) Not Started C 8 1 1 0 12/01/24 12/01/24 12/01/24 8:00 AM 12/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1.2.1 1 1477 Drill Hose x 9 (USAP)
1479 1.2 1.2.8.6.3.1.3 SPOT2 - Pole (USAP) Not Started P 7 1 1 0 01/01/25 01/01/25 01/01/25 8:00 AM 01/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1.3 1 1478 SPOT2 - Pole (USAP)
1480 1.2 1.2.8.6.3.1.3.1 Drill Hose x3 (USAP) Not Started C 8 1 1 0 01/01/25 01/01/25 01/01/25 8:00 AM 01/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1.3.1 1 1479 Drill Hose x3 (USAP)
1481 1.2 1.2.8.6.3.1.3.2 Load Member Cable Reel ? (USAP) Not Started C 8 1 1 0 01/01/25 01/01/25 01/01/25 8:00 AM 01/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1.3.2 1 1480 Load Member Cable Reel ? (USAP)
1482 1.2 1.2.8.6.3.1.4 SPOT3 - Pole (USAP) Not Started P 7 1 1 0 02/01/25 02/01/25 02/01/25 8:00 AM 02/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1.4 1 1481 SPOT3 - Pole (USAP)
1483 1.2 1.2.8.6.3.1.4.1 TBD Not Started C 8 1 1 0 02/01/25 02/01/25 02/01/25 8:00 AM 02/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.1.4.1 1 1482 TBD
1484 1.2 1.2.8.6.3.2 MCM (USAP) Not Started P 6 1 50d 11/01/24 01/15/25 11/01/24 8:00 AM 01/15/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.2 1 1483 MCM (USAP)
1485 1.2 1.2.8.6.3.2.1 SAAM - ComSur (USAP) Not Started P 7 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.2.1 1 1484 SAAM - ComSur (USAP)
1486 1.2 1.2.8.6.3.2.1.1 Controls Component Crates Shipment 3 - DNF (USAP) Not Started C 8 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.2.1.1 1 1485 Controls Component Crates Shipment 3 - DNF (USAP)
1487 1.2 1.2.8.6.3.2.1.2 Driller Resupply/Refit Container (8' ISO) (USAP) Not Started C 8 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.2.1.2 1 1486 Driller Resupply/Refit Container (8' ISO) (USAP)
1488 1.2 1.2.8.6.3.2.1.3 Driller Resupply/Refit Crate - DNF (USAP) Not Started C 8 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.2.1.3 1 1487 Driller Resupply/Refit Crate - DNF (USAP)
1489 1.2 1.2.8.6.3.2.2 Vessel (USAP) Not Started P 7 1 1 0 01/15/25 01/15/25 01/15/25 8:00 AM 01/15/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.2.2 1 1488 Vessel (USAP)
1490 1.2 1.2.8.6.3.2.2.1 Placeholder Not Started C 8 1 1 0 01/15/25 01/15/25 01/15/25 8:00 AM 01/15/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.2.2.1 1 1489 Placeholder
1491 1.2 1.2.8.6.3.3 Retrograde - (USAP) Not Started C 5 1 1 0 01/15/25 01/15/25 01/15/25 8:00 AM 01/15/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.3 1 1490 Retrograde - (USAP)
1492 1.2 1.2.8.6.3.4 Cargo Storage Support Pole and McMurdo (USAP) Not Started C 5 1 51d 11/01/24 01/15/25 11/01/24 8:00 AM 01/15/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.4 1 1491 Cargo Storage Support Pole and McMurdo (USAP)
1493 1.2 1.2.8.6.4 Opening Activities & Seasonal Equipment Site (SES) Set-up Not Started P 5 1 55d 11/08/24 01/28/25 11/08/24 8:00 AM 01/28/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.4 1 1492 Opening Activities & Seasonal Equipment Site (SES) Set-up
1494 1.2 1.2.8.6.4.1 Re-establish SES Drill Pad, Excavate SES and ICL Road, Groom & Compact Roads (USAP) Not Started C 6 1 7d 11/08/24 11/18/24 11/08/24 8:00 AM 11/18/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.1 1 1493 Re-establish SES Drill Pad, Excavate SES and ICL Road, Groom & Compact Roads (USAP)
1495 1.2 1.2.8.6.4.2 Provide Support Generators - CRREL/Onan Genset (USAP) Not Started C 6 1 12d 11/15/24 12/03/24 11/15/24 8:00 AM 12/03/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.2 1 1494 Provide Support Generators - CRREL/Onan Genset (USAP)
1496 1.2 1.2.8.6.4.3 Deliver Early Season SES Warm-up Shack (USAP) Not Started C 6 1 1 0 11/15/24 11/15/24 11/15/24 8:00 AM 11/15/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.3 1 1495 Deliver Early Season SES Warm-up Shack (USAP)
1497 1.2 1.2.8.6.4.4 Provide Heaters, 953 Loader, 287B Skidsteer, Pax Van, & Snomo's (USAP) Not Started C 6 1 50d 11/15/24 01/28/25 11/15/24 8:00 AM 01/28/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.4 1 1496 Provide Heaters, 953 Loader, 287B Skidsteer, Pax Van, & Snomo's (USAP)
1498 1.2 1.2.8.6.4.5 Excavate Winter Storage Berms & Deliver Towers/Equipment (USAP) Not Started C 6 1 5d 11/08/24 11/14/24 11/08/24 8:00 AM 11/14/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.5 1 1497 Excavate Winter Storage Berms & Deliver Towers/Equipment (USAP)
1499 1.2 1.2.8.6.4.6 Excavate ICL Storage Site & Deliver TOS1/2, DCC, & MSHR to SES (USAP) Not Started C 6 1 5d 11/14/24 11/20/24 11/14/24 8:00 AM 11/20/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.6 1 1498 Excavate ICL Storage Site & Deliver TOS1/2, DCC, & MSHR to SES (USAP)
1500 1.2 1.2.8.6.4.7 Driller Support for SES Digout Not Started C 6 1 5d 11/15/24 11/21/24 11/15/24 8:00 AM 11/21/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.4.7 1 1499 Driller Support for SES Digout
1501 1.2 1.2.8.6.4.8 Built Ramp to Water Tank 1 (USAP) Not Started C 6 1 3d 11/16/24 11/19/24 11/16/24 8:00 AM 11/19/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.8 1 1500 Built Ramp to Water Tank 1 (USAP)
1502 1.2 1.2.8.6.4.9 SES Drill Camp Excavated & Established (USAP) Not Started C 6 1 1 0 11/17/24 11/17/24 11/17/24 8:00 AM 11/17/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.9 1 1501 SES Drill Camp Excavated & Established (USAP)
1503 1.2 1.2.8.6.4.10 SES IT Support Activities (USAP) Not Started C 6 1 1d 11/20/24 11/20/24 11/20/24 8:00 AM 11/20/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.10 1 1502 SES IT Support Activities (USAP)
1504 1.2 1.2.8.6.4.11 Fuel Tower: Connect, Test and Make Ready Not Started C 6 1 2d 11/21/24 11/22/24 11/21/24 8:00 AM 11/22/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.4.11 1 1503 Fuel Tower: Connect, Test and Make Ready
1505 1.2 1.2.8.6.4.12 Make Ready all SES Modules (DCC, PHS, MHPs, MECC, WTs, All) Not Started C 6 1 9d 11/14/24 11/26/24 11/14/24 8:00 AM 11/26/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.4.12 1 1504 Make Ready all SES Modules (DCC, PHS, MHPs, MECC, WTs, All)
1506 1.2 1.2.8.6.4.13 Complete Interconnects (DCC, PHS, MHPs, MECC, WTs, Gens, & PDMs) Not Started C 6 1 5d 11/14/24 11/20/24 11/14/24 8:00 AM 11/20/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.4.13 1 1505 Complete Interconnects (DCC, PHS, MHPs, MECC, WTs, Gens, & PDMs)
1507 1.2 1.2.8.6.4.14 Furnace Checkout & Fire Up (All Modules) Not Started C 6 1 3d 11/14/24 11/18/24 11/14/24 8:00 AM 11/18/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.4.14 1 1506 Furnace Checkout & Fire Up (All Modules)
1508 1.2 1.2.8.6.4.15 Perform Emergency Incident Drill & Safety Training Not Started C 6 1 2d 12/08/24 12/09/24 12/08/24 8:00 AM 12/09/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.4.15 1 1507 Perform Emergency Incident Drill & Safety Training
1509 1.2 1.2.8.6.4.16 Provide Fire Extinguishers (USAP) Not Started C 6 1 1 0 11/15/24 11/15/24 11/15/24 8:00 AM 11/15/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.16 1 1508 Provide Fire Extinguishers (USAP)
1510 1.2 1.2.8.6.4.17 Begin Delivery - 3k or 5k Fuel Tanks (USAP) Not Started C 6 1 1 0 11/15/24 11/15/24 11/15/24 8:00 AM 11/15/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.17 1 1509 Begin Delivery - 3k or 5k Fuel Tanks (USAP)
1511 1.2 1.2.8.6.4.18 Supply local fuel tanks for both TOSes (2x) and keep filled throughout (USAP) --> Change duration Not Started C 6 1 9d 11/15/24 11/27/24 11/15/24 8:00 AM 11/27/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.18 1 1510 Supply local fuel tanks for both TOSes (2x) and keep filled throughout (USAP) --> Change duration
1512 1.2 1.2.8.6.4.19 Fuel Tanks Connection Support (USAP) Not Started C 6 1 9d 11/15/24 11/27/24 11/15/24 8:00 AM 11/27/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.19 1 1511 Fuel Tanks Connection Support (USAP)
1513 1.2 1.2.8.6.4.20 SES Operational Not Started C 6 1 1 0 11/15/24 11/15/24 11/15/24 8:00 AM 11/15/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.4.20 1 1512 SES Operational
1514 1.2 1.2.8.6.5 Seasonal Equipment Site (SES) Maintenance & Support Not Started P 5 1 53d 11/15/24 01/31/25 11/15/24 8:00 AM 01/31/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.5 1 1513 Seasonal Equipment Site (SES) Maintenance & Support
1515 1.2 1.2.8.6.5.1 SES Maintenance Activities - Season-long Driller Support Not Started C 6 1 53d 11/15/24 01/31/25 11/15/24 8:00 AM 01/31/25 4:59 PM 1506FS -2d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.5.1 1 1514 SES Maintenance Activities - Season-long Driller Support
1516 1.2 1.2.8.6.5.2 Sustaining Fuel Deliveries - 3k or 5k Fuel Tanks (USAP) Not Started C 6 1 9d 11/15/24 11/27/24 11/15/24 8:00 AM 11/27/24 4:59 PM 1494SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.5.2 1 1515 Sustaining Fuel Deliveries - 3k or 5k Fuel Tanks (USAP)
1517 1.2 1.2.8.6.5.3 General Equipment Support - Moves, Season Snow Removal, Road Maint. (USAP) Not Started C 6 1 52d 11/15/24 01/30/25 11/15/24 8:00 AM 01/30/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.5.3 1 1516 General Equipment Support - Moves, Season Snow Removal, Road Maint. (USAP)
1518 1.2 1.2.8.6.5.4 Deliver 3000 gals Seed Water from Station (USAP) Not Started C 6 1 2d 12/12/24 12/13/24 12/12/24 8:00 AM 12/13/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.5.4 1 1517 Deliver 3000 gals Seed Water from Station (USAP)
1519 1.2 1.2.8.6.5.5 Create Storage Berms, End-of-the-World & SES (USAP) Not Started C 6 1 17d 12/15/24 01/08/25 12/15/24 8:00 AM 01/08/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.5.5 1 1518 Create Storage Berms, End-of-the-World & SES (USAP)
1520 1.2 1.2.8.6.5.6 Build Firn Hole Covers (USAP) Not Started C 6 1 5d 12/01/24 12/05/24 12/01/24 8:00 AM 12/05/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.5.6 1 1519 Build Firn Hole Covers (USAP)
1521 1.2 1.2.8.6.5.7 Deliver Compressor to SES (USAP) Not Started C 6 1 1d 12/01/24 12/01/24 12/01/24 8:00 AM 12/01/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.5.7 1 1520 Deliver Compressor to SES (USAP)
1522 1.2 1.2.8.6.5.8 Deliver & Warm Up Glycol Tank (USAP) Not Started C 6 1 1d 12/01/24 12/01/24 12/01/24 8:00 AM 12/01/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.5.8 1 1521 Deliver & Warm Up Glycol Tank (USAP)
1523 1.2 1.2.8.6.5.9 Create SES Snow Supply Stockpile (USAP) Not Started C 6 1 1d 12/01/24 12/01/24 12/01/24 8:00 AM 12/01/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.5.9 1 1522 Create SES Snow Supply Stockpile (USAP)
1524 1.2 1.2.8.6.6 Generators & PDM Not Started P 5 1 50d 11/14/24 01/28/25 11/14/24 5:00 PM 01/28/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.6 1 1523 Generators & PDM
1525 1.2 1.2.8.6.6.1 Deliver CRREL Gen for Early Season for SES Power (USAP) Not Started C 6 1 e1d 11/14/24 11/15/24 11/14/24 5:00 PM 11/15/24 4:59 PM 1497 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.6.6.1 1 1524 Deliver CRREL Gen for Early Season for SES Power (USAP)
1526 1.2 1.2.8.6.6.2 Supply Heat for CRREL Gen (USAP) Not Started C 6 1 e2d 11/15/24 11/17/24 11/15/24 5:00 PM 11/17/24 4:59 PM 1524 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.6.6.2 1 1525 Supply Heat for CRREL Gen (USAP)
1527 1.2 1.2.8.6.6.3 Connect CRREL Gen to SES through Transformer Skid & Start (Driller & USAP) Not Started C 6 1 e2d 11/15/24 11/17/24 11/15/24 5:00 PM 11/17/24 4:59 PM 1525FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.6.6.3 1 1526 Connect CRREL Gen to SES through Transformer Skid & Start (Driller & USAP)
1528 1.2 1.2.8.6.6.4 Temp SES Power Established Not Started C 6 1 1 0 11/21/24 11/21/24 11/21/24 4:59 PM 11/21/24 4:59 PM 1509SS +1d, 1499 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.6.6.4 1 1527 Temp SES Power Established
1529 1.2 1.2.8.6.6.5 Connect Fuel Hoses & Prime Gens 1-3 (Driller & USAP) Not Started C 6 1 e2d 11/21/24 11/23/24 11/21/24 5:00 PM 11/23/24 4:59 PM 1509SS +1d, 1499 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.6.6.5 1 1528 Connect Fuel Hoses & Prime Gens 1-3 (Driller & USAP)
1530 1.2 1.2.8.6.6.6 Generators & PDM - Pre-operational Checks Not Started C 6 1 e2d 11/21/24 11/23/24 11/21/24 5:00 PM 11/23/24 4:59 PM 1528SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.6.6.6 1 1529 Generators & PDM - Pre-operational Checks
1531 1.2 1.2.8.6.6.7 Contract Gen Tech Arrives Not Started C 6 1 1 0 11/23/24 11/23/24 11/23/24 8:00 AM 11/23/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.6.7 1 1530 Contract Gen Tech Arrives
1532 1.2 1.2.8.6.6.8 Ready & Start-up Gen1, Gen 2, & Gen3 (Driller & USAP) Not Started C 6 1 e2d 11/23/24 11/25/24 11/23/24 5:00 PM 11/25/24 4:59 PM 1528, 1529 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen E_Engineer/Generator_Contractor 1.2.8.6.6.8 1 1531 Ready & Start-up Gen1, Gen 2, & Gen3 (Driller & USAP)
1533 1.2 1.2.8.6.6.9 Parallel Gens through PDM Bays (Driller & Contract Gen Tech) Not Started C 6 1 e3d 11/25/24 11/28/24 11/25/24 5:00 PM 11/28/24 4:59 PM 1530, 1531 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.6.9 1 1532 Parallel Gens through PDM Bays (Driller & Contract Gen Tech)
1534 1.2 1.2.8.6.6.10 Load Test using Resistance Heaters (Driller & Contract Gen Tech) Not Started C 6 1 e2d 11/29/24 12/01/24 11/29/24 8:00 AM 12/01/24 7:59 AM 1531FS +2d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.6.6.10 1 1533 Load Test using Resistance Heaters (Driller & Contract Gen Tech)
1535 1.2 1.2.8.6.6.11 Test Safety Shut-downs (Driller & Contract Gen Tech) Not Started C 6 1 e2d 12/01/24 12/03/24 12/01/24 8:00 AM 12/03/24 7:59 AM 1533 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.6.6.11 1 1534 Test Safety Shut-downs (Driller & Contract Gen Tech)
1536 1.2 1.2.8.6.6.12 SES Power Plant Online Not Started C 6 1 1 0 12/03/24 12/03/24 12/03/24 7:59 AM 12/03/24 7:59 AM 1534 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.6.6.12 1 1535 SES Power Plant Online
1537 1.2 1.2.8.6.6.13 Integrate and test new generator and PDM controls/point I/O Not Started C 6 1 4d 12/03/24 12/06/24 12/03/24 8:00 AM 12/06/24 4:59 PM 1535 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.6.6.13 1 1536 Integrate and test new generator and PDM controls/point I/O
1538 1.2 1.2.8.6.6.14 Scheduled Preventive Maintenance (Driller & USAP) Not Started C 6 1 e20d 12/12/24 01/01/25 12/12/24 8:00 AM 01/01/25 7:59 AM 1535FS +7d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.6.6.14 1 1537 Scheduled Preventive Maintenance (Driller & USAP)
1539 1.2 1.2.8.6.6.15 Winterize Gen Modules and PDM (Driller & USAP) Not Started C 6 1 e2d 01/26/25 01/28/25 01/26/25 5:00 PM 01/28/25 4:59 PM 1660FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen M_Engineer/Contract_Driller 1.2.8.6.6.15 1 1538 Winterize Gen Modules and PDM (Driller & USAP)
1540 1.2 1.2.8.6.7 EHWD: Final Upgrade & Replacement Work Not Started P 5 1 51d 11/12/24 01/24/25 11/12/24 8:00 AM 01/24/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7 1 1539 EHWD: Final Upgrade & Replacement Work
1541 1.2 1.2.8.6.7.1 Drill Control Center (DCC) & Global Control System Not Started P 6 1 36d 11/12/24 01/03/25 11/12/24 8:00 AM 01/03/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1 1 1540 Drill Control Center (DCC) & Global Control System
1542 1.2 1.2.8.6.7.1.1 Relocate DCC to Cryo & Power-up (USAP) Not Started C 7 1 1d 11/12/24 11/12/24 11/12/24 8:00 AM 11/12/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.1 1 1541 Relocate DCC to Cryo & Power-up (USAP)
1543 1.2 1.2.8.6.7.1.2 Electrical Closet Rework (USAP) Not Started C 7 1 2d 11/13/24 11/14/24 11/13/24 8:00 AM 11/14/24 4:59 PM 1541 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.2 1 1542 Electrical Closet Rework (USAP)
1544 1.2 1.2.8.6.7.1.3 Install New Fuel Day Tank System Controls Not Started C 7 1 1d 11/15/24 11/15/24 11/15/24 8:00 AM 11/15/24 4:59 PM 1542 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.3 1 1543 Install New Fuel Day Tank System Controls
1545 1.2 1.2.8.6.7.1.4 Install and Wire 2x Motor Drives for WT1 VT Pumps Not Started C 7 1 1d 11/18/24 11/18/24 11/18/24 8:00 AM 11/18/24 4:59 PM 1543 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.4 1 1544 Install and Wire 2x Motor Drives for WT1 VT Pumps
1546 1.2 1.2.8.6.7.1.5 Install New E-Stop Controller Equipment Not Started C 7 1 2d 11/19/24 11/20/24 11/19/24 8:00 AM 11/20/24 4:59 PM 1544 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.5 1 1545 Install New E-Stop Controller Equipment
1547 1.2 1.2.8.6.7.1.6 Install Racks & Computing Equipment Not Started C 7 1 2d 11/21/24 11/22/24 11/21/24 8:00 AM 11/22/24 4:59 PM 1545 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.6 1 1546 Install Racks & Computing Equipment
1548 1.2 1.2.8.6.7.1.7 Install Core PLC System in DCC Not Started C 7 1 2d 11/25/24 11/26/24 11/25/24 8:00 AM 11/26/24 4:59 PM 1546 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.7 1 1547 Install Core PLC System in DCC
1549 1.2 1.2.8.6.7.1.8 Connect and Configure Hub and Spoke Elements, including Motor Drives Not Started C 7 1 2d 11/27/24 11/29/24 11/27/24 8:00 AM 11/29/24 4:59 PM 1547 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.8 1 1548 Connect and Configure Hub and Spoke Elements, including Motor Drives
1550 1.2 1.2.8.6.7.1.9 Relocate DCC to SES & Position (USAP) Not Started C 7 1 3d 12/02/24 12/04/24 12/02/24 8:00 AM 12/04/24 4:59 PM 1548 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.9 1 1549 Relocate DCC to SES & Position (USAP)
1551 1.2 1.2.8.6.7.1.10 Install and Commission Latest Software, SCADA, and Database Not Started C 7 1 3d 12/02/24 12/04/24 12/02/24 8:00 AM 12/04/24 4:59 PM 1548 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.10 1 1550 Install and Commission Latest Software, SCADA, and Database
1552 1.2 1.2.8.6.7.1.11 QA on Controls By SES Subsystem - Wet System Not Started C 7 1 10d 12/19/24 01/03/25 12/19/24 8:00 AM 01/03/25 4:59 PM 1550, 1517, 1631 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.11 1 1551 QA on Controls By SES Subsystem - Wet System
1553 1.2 1.2.8.6.7.1.12 Global Control System Online Not Started C 7 1 1 0 01/03/25 01/03/25 01/03/25 4:59 PM 01/03/25 4:59 PM 1551 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.1.12 1 1552 Global Control System Online
1554 1.2 1.2.8.6.7.2 Main Heating Plants Not Started P 6 1 9d 11/21/24 12/04/24 11/21/24 8:00 AM 12/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.2 1 1553 Main Heating Plants
1555 1.2 1.2.8.6.7.2.1 Mechanical Refit & Repairs (MHP) Not Started P 7 1 9d 11/21/24 12/04/24 11/21/24 8:00 AM 12/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.2.1 1 1554 Mechanical Refit & Repairs (MHP)
1556 1.2 1.2.8.6.7.2.1.1 Final Upgrade & Replacement Activities Not Started C 8 1 5d 11/21/24 11/27/24 11/21/24 8:00 AM 11/27/24 4:59 PM 1505 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.2.1.1 1 1555 Final Upgrade & Replacement Activities
1557 1.2 1.2.8.6.7.2.1.2 System Evaluation Not Started C 8 1 5d 11/27/24 12/04/24 11/27/24 8:00 AM 12/04/24 4:59 PM 1555FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.2.1.2 1 1556 System Evaluation
1558 1.2 1.2.8.6.7.2.2 Electrical/Controls Refit & Repairs (MHP) Not Started P 7 1 9d 11/21/24 12/04/24 11/21/24 8:00 AM 12/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.2.2 1 1557 Electrical/Controls Refit & Repairs (MHP)
1559 1.2 1.2.8.6.7.2.2.1 Final Upgrade & Replacement Activities Not Started C 8 1 5d 11/21/24 11/27/24 11/21/24 8:00 AM 11/27/24 4:59 PM 1505 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.2.2.1 1 1558 Final Upgrade & Replacement Activities
1560 1.2 1.2.8.6.7.2.2.2 System Evaluation and Final Testing Not Started C 8 1 5d 11/27/24 12/04/24 11/27/24 8:00 AM 12/04/24 4:59 PM 1558FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.2.2.2 1 1559 System Evaluation and Final Testing
1561 1.2 1.2.8.6.7.3 Pre-Heat System Not Started P 6 1 9d 11/21/24 12/04/24 11/21/24 8:00 AM 12/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.3 1 1560 Pre-Heat System
1562 1.2 1.2.8.6.7.3.1 Mechanical Refit & Repairs (PHS) Not Started P 7 1 9d 11/21/24 12/04/24 11/21/24 8:00 AM 12/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.3.1 1 1561 Mechanical Refit & Repairs (PHS)
1563 1.2 1.2.8.6.7.3.1.1 Install Filters in H2O System Not Started C 8 1 1d 11/21/24 11/21/24 11/21/24 8:00 AM 11/21/24 4:59 PM 1563SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.3.1.1 1 1562 Install Filters in H2O System
1564 1.2 1.2.8.6.7.3.1.2 Final Upgrade & Replacement Activities Not Started C 8 1 5d 11/21/24 11/27/24 11/21/24 8:00 AM 11/27/24 4:59 PM 1505 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.3.1.2 1 1563 Final Upgrade & Replacement Activities
1565 1.2 1.2.8.6.7.3.1.3 System Evaluation Not Started C 8 1 5d 11/27/24 12/04/24 11/27/24 8:00 AM 12/04/24 4:59 PM 1563FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.3.1.3 1 1564 System Evaluation
1566 1.2 1.2.8.6.7.3.2 Electrical/Controls Refit & Repairs (PHS) Not Started P 7 1 9d 11/21/24 12/04/24 11/21/24 8:00 AM 12/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.3.2 1 1565 Electrical/Controls Refit & Repairs (PHS)
1567 1.2 1.2.8.6.7.3.2.1 Final Upgrade & Replacement Activities Not Started C 8 1 5d 11/21/24 11/27/24 11/21/24 8:00 AM 11/27/24 4:59 PM 1505 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.3.2.1 1 1566 Final Upgrade & Replacement Activities
1568 1.2 1.2.8.6.7.3.2.2 System Evaluation and Final Testing Not Started C 8 1 5d 11/27/24 12/04/24 11/27/24 8:00 AM 12/04/24 4:59 PM 1566FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.3.2.2 1 1567 System Evaluation and Final Testing
1569 1.2 1.2.8.6.7.4 Water Tanks & Handling Systems (VT & Submersible) Not Started P 6 1 9d 11/21/24 12/04/24 11/21/24 8:00 AM 12/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.4 1 1568 Water Tanks & Handling Systems (VT & Submersible)
1570 1.2 1.2.8.6.7.4.1 Final Upgrade & Replacement Activities Not Started C 7 1 5d 11/21/24 11/27/24 11/21/24 8:00 AM 11/27/24 4:59 PM 1505 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.4.1 1 1569 Final Upgrade & Replacement Activities
1571 1.2 1.2.8.6.7.4.2 System Evaluation and Final Testing Not Started C 7 1 5d 11/27/24 12/04/24 11/27/24 8:00 AM 12/04/24 4:59 PM 1569FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.4.2 1 1570 System Evaluation and Final Testing
1572 1.2 1.2.8.6.7.5 Water Tanks & Handling Systems (VT & Submersible) Not Started P 6 1 9d 11/21/24 12/04/24 11/21/24 8:00 AM 12/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.5 1 1571 Water Tanks & Handling Systems (VT & Submersible)
1573 1.2 1.2.8.6.7.5.1 Mechanical Refit & Repairs (HPP) Not Started P 7 1 9d 11/21/24 12/04/24 11/21/24 8:00 AM 12/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.5.1 1 1572 Mechanical Refit & Repairs (HPP)
1574 1.2 1.2.8.6.7.5.1.1 Final Upgrade & Replacement Activities Not Started C 8 1 5d 11/21/24 11/27/24 11/21/24 8:00 AM 11/27/24 4:59 PM 1505 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.5.1.1 1 1573 Final Upgrade & Replacement Activities
1575 1.2 1.2.8.6.7.5.1.2 Pump Testing & System Evaluation Not Started C 8 1 5d 11/27/24 12/04/24 11/27/24 8:00 AM 12/04/24 4:59 PM 1573FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.5.1.2 1 1574 Pump Testing & System Evaluation
1576 1.2 1.2.8.6.7.5.2 Electrical/Controls Refit & Repairs (HPP) Not Started P 7 1 9d 11/21/24 12/04/24 11/21/24 8:00 AM 12/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.5.2 1 1575 Electrical/Controls Refit & Repairs (HPP)
1577 1.2 1.2.8.6.7.5.2.1 Final Upgrade & Replacement Activities Not Started C 8 1 5d 11/21/24 11/27/24 11/21/24 8:00 AM 11/27/24 4:59 PM 1505 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.5.2.1 1 1576 Final Upgrade & Replacement Activities
1578 1.2 1.2.8.6.7.5.2.2 System Evaluation and Final Testing Not Started C 8 1 5d 11/27/24 12/04/24 11/27/24 8:00 AM 12/04/24 4:59 PM 1573FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.5.2.2 1 1577 System Evaluation and Final Testing
1579 1.2 1.2.8.6.7.6 HPU2 Not Started P 6 1 12d 11/21/24 12/09/24 11/21/24 8:00 AM 12/09/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.6 1 1578 HPU2
1580 1.2 1.2.8.6.7.6.1 Relocate HPU2 to SES, Position Not Started C 7 1 1d 11/21/24 11/21/24 11/21/24 8:00 AM 11/21/24 4:59 PM 1498 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.6.1 1 1579 Relocate HPU2 to SES, Position
1581 1.2 1.2.8.6.7.6.2 Supply Power to HPU2, Warm Up Not Started C 7 1 1d 11/22/24 11/22/24 11/22/24 8:00 AM 11/22/24 4:59 PM 1505, 1579 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.6.2 1 1580 Supply Power to HPU2, Warm Up
1582 1.2 1.2.8.6.7.6.3 Initiate final Refit/Integration (HPU2) Not Started C 7 1 10d 11/25/24 12/09/24 11/25/24 8:00 AM 12/09/24 4:59 PM 1580 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.6.3 1 1581 Initiate final Refit/Integration (HPU2)
1583 1.2 1.2.8.6.7.7 Fuel Tower Not Started P 6 1 5d 12/02/24 12/06/24 12/02/24 8:00 AM 12/06/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.7 1 1582 Fuel Tower
1584 1.2 1.2.8.6.7.7.1 Install New Point I/O, connect to DCC, and configure/troubleshoot Not Started C 7 1 1d 12/02/24 12/02/24 12/02/24 8:00 AM 12/02/24 4:59 PM 1472FS +10d 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.7.1 1 1583 Install New Point I/O, connect to DCC, and configure/troubleshoot
1585 1.2 1.2.8.6.7.7.2 Fuel Tower: Commission - NPX Not Started C 7 1 4d 12/03/24 12/06/24 12/03/24 8:00 AM 12/06/24 4:59 PM 1583 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.7.2 1 1584 Fuel Tower: Commission - NPX
1586 1.2 1.2.8.6.7.8 Shops, MECC (SEW, TOW, OML) Not Started P 6 1 6d 11/14/24 11/21/24 11/14/24 8:00 AM 11/21/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.8 1 1585 Shops, MECC (SEW, TOW, OML)
1587 1.2 1.2.8.6.7.8.1 Final Upgrade/Retrofit Shops, MECC Not Started C 7 1 6d 11/14/24 11/21/24 11/14/24 8:00 AM 11/21/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.8.1 1 1586 Final Upgrade/Retrofit Shops, MECC
1588 1.2 1.2.8.6.7.9 Reels Not Started P 6 1 33d 12/09/24 01/24/25 12/09/24 8:00 AM 01/24/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9 1 1587 Reels
1589 1.2 1.2.8.6.7.9.1 Main Supply Hose Reel (MSHR) Not Started P 7 1 30d 12/12/24 01/24/25 12/12/24 8:00 AM 01/24/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.1 1 1588 Main Supply Hose Reel (MSHR)
1590 1.2 1.2.8.6.7.9.1.1 Install Inner Insulation Layer & RTDs Not Started C 8 2d 12/12/24 12/13/24 12/12/24 8:00 AM 12/13/24 4:59 PM 1498FS +14d 0% 0% Green 2 people x 2 days => ~36 hrs $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.1.1 1 1589 Install Inner Insulation Layer & RTDs
1591 1.2 1.2.8.6.7.9.1.2 Install Drill Hose on Reel Not Started C 8 5d 12/16/24 12/20/24 12/16/24 8:00 AM 12/20/24 4:59 PM 1589, 1477FS +5d 0% 0% Green 4 people x 5 days => ~180 hrs $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.1.2 1 1590 Install Drill Hose on Reel
1592 1.2 1.2.8.6.7.9.1.3 Final Upgrades & Testing (MSHR) Not Started C 8 1 2d 12/23/24 12/24/24 12/23/24 8:00 AM 12/24/24 4:59 PM 1590 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.1.3 1 1591 Final Upgrades & Testing (MSHR)
1593 1.2 1.2.8.6.7.9.1.4 Install Hose Heating Blankets & RTDs & Install Outer Cover Not Started C 8 2d 01/21/25 01/22/25 01/21/25 8:00 AM 01/22/25 4:59 PM 1650SS +2d 0% 0% Green 2 people x 3 days => ~54 hrs $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.1.4 1 1592 Install Hose Heating Blankets & RTDs & Install Outer Cover
1594 1.2 1.2.8.6.7.9.1.5 Install Hose Heating Controller, Connect to Power, & Test Not Started C 8 2d 01/23/25 01/24/25 01/23/25 8:00 AM 01/24/25 4:59 PM 1651, 1592 0% 0% Green 4 people x 5 days => ~180 hrs $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.1.5 1 1593 Install Hose Heating Controller, Connect to Power, & Test
1595 1.2 1.2.8.6.7.9.2 Return Water Hose Reel (RWHR) Not Started P 7 1 6d 12/09/24 12/16/24 12/09/24 8:00 AM 12/16/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.2 1 1594 Return Water Hose Reel (RWHR)
1596 1.2 1.2.8.6.7.9.2.1 Install Return Hose on Reel Not Started C 8 5d 12/09/24 12/13/24 12/09/24 8:00 AM 12/13/24 4:59 PM 1477FS +5d 0% 0% Green 4 people x 5 days => ~180 hrs $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.2.1 1 1595 Install Return Hose on Reel
1597 1.2 1.2.8.6.7.9.2.2 Final Upgrades & Testing Not Started C 8 1 5d 12/10/24 12/16/24 12/10/24 8:00 AM 12/16/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.2.2 1 1596 Final Upgrades & Testing
1598 1.2 1.2.8.6.7.9.3 Return Water Cable Reel (RWCR) Not Started P 7 1 5d 12/10/24 12/16/24 12/10/24 8:00 AM 12/16/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.3 1 1597 Return Water Cable Reel (RWCR)
1599 1.2 1.2.8.6.7.9.3.1 Final Upgrades & Testing Not Started C 8 1 5d 12/10/24 12/16/24 12/10/24 8:00 AM 12/16/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.3.1 1 1598 Final Upgrades & Testing
1600 1.2 1.2.8.6.7.9.4 Main Cable Reel (MCR) Not Started P 7 1 5d 12/10/24 12/16/24 12/10/24 8:00 AM 12/16/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.4 1 1599 Main Cable Reel (MCR)
1601 1.2 1.2.8.6.7.9.4.1 Final Upgrades & Testing Not Started C 8 1 5d 12/10/24 12/16/24 12/10/24 8:00 AM 12/16/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.9.4.1 1 1600 Final Upgrades & Testing
1602 1.2 1.2.8.6.7.10 Winches Not Started P 6 1 12d 12/15/24 12/31/24 12/15/24 8:00 AM 12/31/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.10 1 1601 Winches
1603 1.2 1.2.8.6.7.10.1 Winches Final Integration & Testing (TU-20, TU-15) Not Started C 7 1 12d 12/15/24 12/31/24 12/15/24 8:00 AM 12/31/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.10.1 1 1602 Winches Final Integration & Testing (TU-20, TU-15)
1604 1.2 1.2.8.6.7.11 TOS/Tower Not Started P 6 1 22d 11/22/24 12/24/24 11/22/24 8:00 AM 12/24/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.11 1 1603 TOS/Tower
1605 1.2 1.2.8.6.7.11.1 TOS1 - Core Controls Install, Commissioning & Check Out Not Started P 7 1 11d 11/22/24 12/09/24 11/22/24 8:00 AM 12/09/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.11.1 1 1604 TOS1 - Core Controls Install, Commissioning & Check Out
1606 1.2 1.2.8.6.7.11.1.1 TOS1 - Install Racks & Computing Equipment Not Started C 8 1 2d 11/22/24 11/25/24 11/22/24 8:00 AM 11/25/24 4:59 PM 1498FS +1d, 1472 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.11.1.1 1 1605 TOS1 - Install Racks & Computing Equipment
1607 1.2 1.2.8.6.7.11.1.2 TOS1 - Install Core PLC System Not Started C 8 1 1d 11/26/24 11/26/24 11/26/24 8:00 AM 11/26/24 4:59 PM 1605 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.11.1.2 1 1606 TOS1 - Install Core PLC System
1608 1.2 1.2.8.6.7.11.1.3 TOS1 - Connect & Configure I/O & Motor Drives Not Started C 8 1 2d 11/27/24 11/29/24 11/27/24 8:00 AM 11/29/24 4:59 PM 1606 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.11.1.3 1 1607 TOS1 - Connect & Configure I/O & Motor Drives
1609 1.2 1.2.8.6.7.11.1.4 TOS1 - Install & Commission Latest Software, SCADA Not Started C 8 1 2d 12/02/24 12/03/24 12/02/24 8:00 AM 12/03/24 4:59 PM 1607 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.11.1.4 1 1608 TOS1 - Install & Commission Latest Software, SCADA
1610 1.2 1.2.8.6.7.11.1.5 TOS1 - Connect Reels & Perform QA on Controls Not Started C 8 1 2d 12/04/24 12/05/24 12/04/24 8:00 AM 12/05/24 4:59 PM 1608 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.11.1.5 1 1609 TOS1 - Connect Reels & Perform QA on Controls
1611 1.2 1.2.8.6.7.11.1.6 TOS1 - Install Drill Head Power Supply Not Started C 8 1 1d 12/06/24 12/06/24 12/06/24 8:00 AM 12/06/24 4:59 PM 1609 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.11.1.6 1 1610 TOS1 - Install Drill Head Power Supply
1612 1.2 1.2.8.6.7.11.1.7 TOS1 - Test Drill Head Data Chain With Actual Drill Head Not Started C 8 1 1d 12/09/24 12/09/24 12/09/24 8:00 AM 12/09/24 4:59 PM 1610 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.11.1.7 1 1611 TOS1 - Test Drill Head Data Chain With Actual Drill Head
1613 1.2 1.2.8.6.7.11.1.8 TOS1 - TOS Control System Online Not Started C 8 1 1 0 12/09/24 12/09/24 12/09/24 4:59 PM 12/09/24 4:59 PM 1611 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.11.1.8 1 1612 TOS1 - TOS Control System Online
1614 1.2 1.2.8.6.7.11.2 TOS2 - Core Controls Install, Commissioning & Check Out Not Started P 7 1 11d 12/10/24 12/24/24 12/10/24 8:00 AM 12/24/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.11.2 1 1613 TOS2 - Core Controls Install, Commissioning & Check Out
1615 1.2 1.2.8.6.7.11.2.1 TOS2 - Install Racks & Computing Equipment Not Started C 8 1 2d 12/10/24 12/11/24 12/10/24 8:00 AM 12/11/24 4:59 PM 1498FS +1d, 1612, 1472 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.11.2.1 1 1614 TOS2 - Install Racks & Computing Equipment
1616 1.2 1.2.8.6.7.11.2.2 TOS2 - Install Core PLC System Not Started C 8 1 1d 12/12/24 12/12/24 12/12/24 8:00 AM 12/12/24 4:59 PM 1614 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.11.2.2 1 1615 TOS2 - Install Core PLC System
1617 1.2 1.2.8.6.7.11.2.3 TOS2 - Connect & Configure I/O & Motor Drives Not Started C 8 1 2d 12/13/24 12/16/24 12/13/24 8:00 AM 12/16/24 4:59 PM 1615 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.11.2.3 1 1616 TOS2 - Connect & Configure I/O & Motor Drives
1618 1.2 1.2.8.6.7.11.2.4 TOS2 - Install & Commission Latest Software, SCADA Not Started C 8 1 2d 12/17/24 12/18/24 12/17/24 8:00 AM 12/18/24 4:59 PM 1616 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.11.2.4 1 1617 TOS2 - Install & Commission Latest Software, SCADA
1619 1.2 1.2.8.6.7.11.2.5 TOS2 - Connect Reels & Perform QA on Controls Not Started C 8 1 2d 12/19/24 12/20/24 12/19/24 8:00 AM 12/20/24 4:59 PM 1617 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.11.2.5 1 1618 TOS2 - Connect Reels & Perform QA on Controls
1620 1.2 1.2.8.6.7.11.2.6 TOS2 - Install Drill Head Power Supply Not Started C 8 1 1d 12/23/24 12/23/24 12/23/24 8:00 AM 12/23/24 4:59 PM 1618 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.11.2.6 1 1619 TOS2 - Install Drill Head Power Supply
1621 1.2 1.2.8.6.7.11.2.7 TOS2 - Test Drill Head Data Chain With Actual Drill Head Not Started C 8 1 1d 12/24/24 12/24/24 12/24/24 8:00 AM 12/24/24 4:59 PM 1619 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.11.2.7 1 1620 TOS2 - Test Drill Head Data Chain With Actual Drill Head
1622 1.2 1.2.8.6.7.11.2.8 TOS2 - TOS Control System Online Not Started C 8 1 1 0 12/24/24 12/24/24 12/24/24 4:59 PM 12/24/24 4:59 PM 1620 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Flush heaters w epump to clean out debris, pressure test heaters with proof pump. 1.2.8.6.7.11.2.8 1 1621 TOS2 - TOS Control System Online
1623 1.2 1.2.8.6.7.12 Rodwell System (ARA) Not Started P 6 1 41d 11/22/24 01/22/25 11/22/24 8:00 AM 01/22/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.12 1 1622 Rodwell System (ARA)
1624 1.2 1.2.8.6.7.12.1 Commission Sled 1 - Generator Sled Not Started C 7 1 4d 11/22/24 11/27/24 11/22/24 8:00 AM 11/27/24 4:59 PM 1497FS +5d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.12.1 1 1623 Commission Sled 1 - Generator Sled
1625 1.2 1.2.8.6.7.12.2 Commission Sled 2 - Water Tank Sled Not Started C 7 1 4d 11/29/24 12/04/24 11/29/24 8:00 AM 12/04/24 4:59 PM 1623 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.12.2 1 1624 Commission Sled 2 - Water Tank Sled
1626 1.2 1.2.8.6.7.12.3 Commission Sled 3 - Heater/reel Sled Not Started C 7 1 4d 12/05/24 12/10/24 12/05/24 8:00 AM 12/10/24 4:59 PM 1624 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.12.3 1 1625 Commission Sled 3 - Heater/reel Sled
1627 1.2 1.2.8.6.7.12.4 System Commissioning and Checkout Not Started C 7 1 3d 12/11/24 12/13/24 12/11/24 8:00 AM 12/13/24 4:59 PM 1623, 1624, 1625 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.12.4 1 1626 System Commissioning and Checkout
1628 1.2 1.2.8.6.7.12.5 Fill System with Seed Water Not Started C 7 1 1d 12/11/24 12/11/24 12/11/24 8:00 AM 12/11/24 4:59 PM 1626SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.12.5 1 1627 Fill System with Seed Water
1629 1.2 1.2.8.6.7.12.6 Decommission & Store ARA Not Started C 7 1 3d 01/20/25 01/22/25 01/20/25 8:00 AM 01/22/25 4:59 PM 1650SS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.7.12.6 1 1628 Decommission & Store ARA
1630 1.2 1.2.8.6.8 Rodwell System (ARA) Ops - Condensate Bulbs Not Started P 5 1 20d 12/16/24 01/14/25 12/16/24 8:00 AM 01/14/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen Condensate will not be used for drilling operations. Filtered water will be delivered to bulb. 1.2.8.6.8 1 1629 Rodwell System (ARA) Ops - Condensate Bulbs
1631 1.2 1.2.8.6.8.1 Setup ARA System over mini FS2 Condensate Bulb Firn Hole Location Not Started C 6 1 1d 12/16/24 12/16/24 12/16/24 8:00 AM 12/16/24 4:59 PM 1626 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.8.1 1 1630 Setup ARA System over mini FS2 Condensate Bulb Firn Hole Location
1632 1.2 1.2.8.6.8.2 Drill Dry Pilot Hole, Develop, Pump Out (mini cond) Not Started C 6 1 2d 12/17/24 12/18/24 12/17/24 8:00 AM 12/18/24 4:59 PM 1630 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.8.2 1 1631 Drill Dry Pilot Hole, Develop, Pump Out (mini cond)
1633 1.2 1.2.8.6.8.3 Setup ARA System over main FS3 Condensate Bulb Hole Location Not Started C 6 1 1d 12/20/24 12/20/24 12/20/24 8:00 AM 12/20/24 4:59 PM 1631FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.8.3 1 1632 Setup ARA System over main FS3 Condensate Bulb Hole Location
1634 1.2 1.2.8.6.8.4 Drill Dry Pilot Hole (main cond) Not Started C 6 1 1d 12/23/24 12/23/24 12/23/24 8:00 AM 12/23/24 4:59 PM 1632 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.8.4 1 1633 Drill Dry Pilot Hole (main cond)
1635 1.2 1.2.8.6.8.5 Develop Bulb (main cond) Not Started C 6 1 4d 12/24/24 12/30/24 12/24/24 8:00 AM 12/30/24 4:59 PM 1633 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.8.5 1 1634 Develop Bulb (main cond)
1636 1.2 1.2.8.6.8.6 Maintain Bulb for Test, then Pump out Water (main cond) Not Started C 6 1 10d 12/31/24 01/14/25 12/31/24 8:00 AM 01/14/25 4:59 PM 1634 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.8.6 1 1635 Maintain Bulb for Test, then Pump out Water (main cond)
1637 1.2 1.2.8.6.9 Firn Drilling - Independent Firn Drill (IFD) Not Started P 5 1 40d 11/15/24 01/14/25 11/15/24 8:00 AM 01/14/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.9 1 1636 Firn Drilling - Independent Firn Drill (IFD)
1638 1.2 1.2.8.6.9.1 Deliver CRREL Gen and Firn Drill (USAP) Not Started C 6 1 1d 11/15/24 11/15/24 11/15/24 8:00 AM 11/15/24 4:59 PM 1497 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.9.1 1 1637 Deliver CRREL Gen and Firn Drill (USAP)
1639 1.2 1.2.8.6.9.2 Drill and CRREL Integration and Commissioning Not Started C 6 1 6d 11/18/24 11/25/24 11/18/24 8:00 AM 11/25/24 4:59 PM 1637 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.9.2 1 1638 Drill and CRREL Integration and Commissioning
1640 1.2 1.2.8.6.9.3 Excavation of 7 x Firn Hole Pits 4' x 4' x 2' (Set String Anchor in Each Hole) Not Started C 6 1 2d 11/18/24 11/19/24 11/18/24 8:00 AM 11/19/24 4:59 PM 1638SS 0 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.9.3 1 1639 Excavation of 7 x Firn Hole Pits 4' x 4' x 2' (Set String Anchor in Each Hole)
1641 1.2 1.2.8.6.9.4 Trenching for Setting the String Anchors for all the 7 x Firn Hole (USAP) Not Started C 6 1 2d 11/18/24 11/19/24 11/18/24 8:00 AM 11/19/24 4:59 PM 1639SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.9.4 1 1640 Trenching for Setting the String Anchors for all the 7 x Firn Hole (USAP)
1642 1.2 1.2.8.6.9.5 Drill 9 Firn Holes w/ Independent Firn Drill (IFD) Not Started C 6 1 25d 11/29/24 01/06/25 11/29/24 8:00 AM 01/06/25 4:59 PM 1638FS +2d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.9.5 1 1641 Drill 9 Firn Holes w/ Independent Firn Drill (IFD)
1643 1.2 1.2.8.6.9.6 Refueling Support - Firn Drilling (USAP) Not Started C 6 1 25d 11/29/24 01/06/25 11/29/24 8:00 AM 01/06/25 4:59 PM 1641SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.9.6 1 1642 Refueling Support - Firn Drilling (USAP)
1644 1.2 1.2.8.6.9.7 9 Holes Drilled, Covered and Flagged Not Started C 6 1 1 1 1 0 01/06/25 01/06/25 01/06/25 4:59 PM 01/06/25 4:59 PM 1641 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.9.7 1 1643 9 Holes Drilled, Covered and Flagged
1645 1.2 1.2.8.6.9.8 Winterize & Store IFD Not Started C 6 1 6d 01/07/25 01/14/25 01/07/25 8:00 AM 01/14/25 4:59 PM 1641 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.9.8 1 1644 Winterize & Store IFD
1646 1.2 1.2.8.6.10 EHWD: Full Systems Wet-Test Not Started P 5 1 32d 12/06/24 01/22/25 12/06/24 8:00 AM 01/22/25 4:59 PM 0.00% 0% Green Rep Note: change from partial to full system test $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.10 1 1645 EHWD: Full Systems Wet-Test
1647 1.2 1.2.8.6.10.1 Setup TOS, Tower, Reels over Rodwell Hole Location Not Started C 6 1 3d 12/06/24 12/10/24 12/06/24 8:00 AM 12/10/24 4:59 PM 1641SS +5d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.10.1 1 1646 Setup TOS, Tower, Reels over Rodwell Hole Location
1648 1.2 1.2.8.6.10.2 Phase 1: TOS Motion control testing and Tuning Not Started C 6 1 7d 12/26/24 01/06/25 12/26/24 8:00 AM 01/06/25 4:59 PM 1646FS +3d, 1590, 1621 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.10.2 1 1647 Phase 1: TOS Motion control testing and Tuning
1649 1.2 1.2.8.6.10.3 Readiness Review, Safety Refresher, Emergency & Safety Systems Tested Not Started C 6 1 1d 01/07/25 01/07/25 01/07/25 8:00 AM 01/07/25 4:59 PM 1647 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.10.3 1 1648 Readiness Review, Safety Refresher, Emergency & Safety Systems Tested
1650 1.2 1.2.8.6.10.4 Phase 2: Full System Wet-Test Not Started C 6 1 7d 01/08/25 01/16/25 01/08/25 8:00 AM 01/16/25 4:59 PM 1648, 1551, 1635SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.10.4 1 1649 Phase 2: Full System Wet-Test
1651 1.2 1.2.8.6.10.5 Blow Out Systems Not Started C 6 1 4d 01/17/25 01/22/25 01/17/25 8:00 AM 01/22/25 4:59 PM 1649 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.10.5 1 1650 Blow Out Systems
1652 1.2 1.2.8.6.10.6 Wet-Test Operations Complete Not Started C 6 1 1 1 0 01/22/25 01/22/25 01/22/25 4:59 PM 01/22/25 4:59 PM 1650 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.10.6 1 1651 Wet-Test Operations Complete
1653 1.2 1.2.8.6.11 Installation Support Activities Not Started P 5 1 9d 12/04/24 12/16/24 12/04/24 8:00 AM 12/16/24 4:59 PM 2038SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.11 1 1652 Installation Support Activities
1654 1.2 1.2.8.6.11.1 Sensor Handling Facility Construction Oversight Not Started C 6 1 9d 12/04/24 12/16/24 12/04/24 8:00 AM 12/16/24 4:59 PM 2038SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.11.1 1 1653 Sensor Handling Facility Construction Oversight
1655 1.2 1.2.8.6.12 Season Close-Out Work Not Started P 5 1 29d 12/24/24 02/04/25 12/24/24 8:00 AM 02/04/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.12 1 1654 Season Close-Out Work
1656 1.2 1.2.8.6.12.1 Document, Photograph Equip & Upgrade Work, Further Req's Not Started C 6 1 2d 12/24/24 12/26/24 12/24/24 8:00 AM 12/26/24 4:59 PM 1206SS, 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.12.1 1 1655 Document, Photograph Equip & Upgrade Work, Further Req's
1657 1.2 1.2.8.6.12.2 Collect Video Record of Condensate Bulb and Rodwell Not Started C 6 1 2d 01/23/25 01/24/25 01/23/25 8:00 AM 01/24/25 4:59 PM 1651 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.12.2 1 1656 Collect Video Record of Condensate Bulb and Rodwell
1658 1.2 1.2.8.6.12.3 Prepare Retrograde for Shipment Not Started C 6 1 7d 12/24/24 01/03/25 12/24/24 8:00 AM 01/03/25 4:59 PM 1655SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.12.3 1 1657 Prepare Retrograde for Shipment
1659 1.2 1.2.8.6.12.4 Demo Snow Ramp (USAP) Not Started C 6 1 1d 01/23/25 01/23/25 01/23/25 8:00 AM 01/23/25 4:59 PM 1651 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.12.4 1 1658 Demo Snow Ramp (USAP)
1660 1.2 1.2.8.6.12.5 Winterize EHWD Not Started P 6 1 10d 01/22/25 02/04/25 01/22/25 8:00 AM 02/04/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.12.5 1 1659 Winterize EHWD
1661 1.2 1.2.8.6.12.5.1 Remove DNF, Computer Equip, Drives, Capacitors, Etc Not Started C 7 1 4d 01/23/25 01/28/25 01/23/25 8:00 AM 01/28/25 4:59 PM 1651 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.12.5.1 1 1660 Remove DNF, Computer Equip, Drives, Capacitors, Etc
1662 1.2 1.2.8.6.12.5.2 Winterize SES & TOS, Disconnect All Cables Hoses, Connections Not Started C 7 1 6d 01/22/25 01/29/25 01/22/25 8:00 AM 01/29/25 4:59 PM 1660FS -5d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.12.5.2 1 1661 Winterize SES & TOS, Disconnect All Cables Hoses, Connections
1663 1.2 1.2.8.6.12.5.3 Winter Storage Support: Drill Hose Reel, TOS 1 & 2 (USAP) Not Started C 7 1 3d 01/30/25 02/03/25 01/30/25 8:00 AM 02/03/25 4:59 PM 1661 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.12.5.3 1 1662 Winter Storage Support: Drill Hose Reel, TOS 1 & 2 (USAP)
1664 1.2 1.2.8.6.12.5.4 All EHWD Equipment Winterized Not Started C 7 1 1d 02/04/25 02/04/25 02/04/25 8:00 AM 02/04/25 4:59 PM 1660, 1661, 1662 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.12.5.4 1 1663 All EHWD Equipment Winterized
1665 1.2 1.2.8.6.13 Other Field Activities (FS2) Not Started P 5 1 77d 10/15/25 02/03/26 10/15/25 8:00 AM 02/03/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.13 1 1664 Other Field Activities (FS2)
1666 1.2 1.2.8.6.13.1 Logistics Department Support - MCM & Pole (USAP) Not Started C 6 1 44d 10/15/25 12/16/25 10/15/25 8:00 AM 12/16/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.13.1 1 1665 Logistics Department Support - MCM & Pole (USAP)
1667 1.2 1.2.8.6.13.2 SPOT Support for Upgrade Cargo (USAP) Not Started C 6 1 65d 11/01/25 02/03/26 11/01/25 8:00 AM 02/03/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.6.13.2 1 1666 SPOT Support for Upgrade Cargo (USAP)
1668 1.2 1.2.8.6.14 ICU Field Team Redeployed Not Started C 5 1 1 1d 01/30/25 01/30/25 01/30/25 8:00 AM 01/30/25 4:59 PM 1660, 1661, 1657FS +2d 0 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.14 1 1667 ICU Field Team Redeployed
1669 1.2 1.2.8.6.15 On-ice Labor FS2 Not Started C 5 1 60d 11/08/24 02/04/25 11/08/24 8:00 AM 02/04/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.15 1 1668 On-ice Labor FS2
1670 1.2 1.2.8.6.16 END ICU NPX FS2 Season Not Started C 5 1 1 0 02/04/25 02/04/25 02/04/25 4:59 PM 02/04/25 4:59 PM 1663, 1667 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.16 1 1669 END ICU NPX FS2 Season
1671 1.2 1.2.8.7 USAP Field Season 3 (FY26) Not Started P 4 1 292d 01/15/25 03/03/26 01/15/25 8:00 AM 03/03/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7 1 1670 USAP Field Season 3 (FY26)
1672 1.2 1.2.8.7.1 FS3 Milestones Not Started P 5 1 202d 02/15/25 11/25/25 02/15/25 8:00 AM 11/25/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 1.2.8.7.1 1 1671 FS3 Milestones
1673 1.2 1.2.8.7.1.1 McM Mainbody Season Begins (USAP) Not Started C 6 1 1 0 10/01/25 10/01/25 10/01/25 8:00 AM 10/01/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.1.1 1 1672 McM Mainbody Season Begins (USAP)
1674 1.2 1.2.8.7.1.2 South Pole Season Begins (USAP) Not Started C 6 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.1.2 1 1673 South Pole Season Begins (USAP)
1675 1.2 1.2.8.7.1.3 ICU Team Arrivals [Headcount 29] Not Started P 6 1 10d 11/11/25 11/25/25 11/11/25 8:00 AM 11/25/25 8:00 AM 0 0% Green tentatively set to 16 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.1.3 1 1674 ICU Team Arrivals [Headcount 29]
1676 1.2 1.2.8.7.1.3.1 ICU Team Arrives - Wave I Not Started C 7 1 1 0 11/11/25 11/11/25 11/11/25 8:00 AM 11/11/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.1.3.1 1 1675 ICU Team Arrives - Wave I
1677 1.2 1.2.8.7.1.3.2 ICU Team Arrives - Wave II Not Started C 7 1 1 0 11/18/25 11/18/25 11/18/25 8:00 AM 11/18/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.1.3.2 1 1676 ICU Team Arrives - Wave II
1678 1.2 1.2.8.7.1.3.3 ICU Team Arrives - Wave III Not Started C 7 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.1.3.3 1 1677 ICU Team Arrives - Wave III
1679 1.2 1.2.8.7.1.4 Pole Season Ends (USAP) Not Started C 6 1 1 0 02/15/25 02/15/25 02/15/25 8:00 AM 02/15/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.1.4 1 1678 Pole Season Ends (USAP)
1680 1.2 1.2.8.7.1.5 MCM Season Ends (USAP) Not Started C 6 1 1 0 03/01/25 03/01/25 03/01/25 8:00 AM 03/01/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.1.5 1 1679 MCM Season Ends (USAP)
1681 1.2 1.2.8.7.2 PQ, ECW & Deployment Travel Costs (FS3) Not Started C 5 1 195d 06/01/25 03/03/26 06/01/25 8:00 AM 03/03/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Plan on Team of 30
- 3 days paid time during deployment
- 3 days paid time during redeployment
each driller, lead, etc

1-Dennis
10-Direct-Hire Drillers
15-Contributed Drillers
4-PSL Engineers

Travel Labor: 48 hrs/ea (Labor)
- 3 days paid time during deployment
- 3 days paid time during redeployment

Travel Cost: $1,200/ea (Travel)

PQ Cost: $950/ea (M&S)
1.2.8.7.2 1 1680 PQ, ECW & Deployment Travel Costs (FS3)
1682 1.2 1.2.8.7.3 USAP Cargo Movements (FY26) Not Started P 5 1 68d 11/01/25 02/06/26 11/01/25 8:00 AM 02/06/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3 1 1681 USAP Cargo Movements (FY26)
1683 1.2 1.2.8.7.3.1 Pole (USAP) Not Started P 6 1 53d 11/15/25 02/01/26 11/15/25 8:00 AM 02/01/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.1 1 1682 Pole (USAP)
1684 1.2 1.2.8.7.3.1.1 LC130 - Pole (USAP) Not Started P 7 1 30d 11/15/25 12/29/25 11/15/25 8:00 AM 12/29/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.1.1 1 1683 LC130 - Pole (USAP)
1685 1.2 1.2.8.7.3.1.1 Fuel 10,161 Gallons (USAP) Not Started C 8 1 30d 11/15/25 12/29/25 11/15/25 8:00 AM 12/29/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.1.1 1 1684 Fuel 10,161 Gallons (USAP)
1686 1.2 1.2.8.7.3.1.2 SPOT1 - Pole (USAP) Not Started C 7 1 1 0 12/01/25 12/01/25 12/01/25 8:00 AM 12/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.1.2 1 1685 SPOT1 - Pole (USAP)
1687 1.2 1.2.8.7.3.1.3 SPOT2 - Pole (USAP) Not Started C 7 1 1 0 01/01/26 01/01/26 01/01/26 8:00 AM 01/01/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.1.3 1 1686 SPOT2 - Pole (USAP)
1688 1.2 1.2.8.7.3.1.4 SPOT3 - Pole (USAP) Not Started C 7 1 1 0 02/01/26 02/01/26 02/01/26 8:00 AM 02/01/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.1.4 1 1687 SPOT3 - Pole (USAP)
1689 1.2 1.2.8.7.3.2 MCM (USAP) Not Started P 6 1 66d 11/01/25 02/05/26 11/01/25 8:00 AM 02/05/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.2 1 1688 MCM (USAP)
1690 1.2 1.2.8.7.3.2.1 SAAM - ComSur (USAP) Not Started P 7 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.2.1 1 1689 SAAM - ComSur (USAP)
1691 1.2 1.2.8.6.3.2.1.1 Driller Resupply/Refit Container (8' ISO) (USAP) Not Started C 8 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.2.1.1 1 1690 Driller Resupply/Refit Container (8' ISO) (USAP)
1692 1.2 1.2.8.6.3.2.1.2 Drill Refit Components Crate - DNF (USAP) Not Started C 8 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.6.3.2.1.2 1 1691 Drill Refit Components Crate - DNF (USAP)
1693 1.2 1.2.8.7.3.2.2 Vessel (USAP) Not Started P 7 1 1 0 02/05/26 02/05/26 02/05/26 8:00 AM 02/05/26 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.2.2 1 1692 Vessel (USAP)
1694 1.2 1.2.8.7.3.2.2.1 Placeholder Not Started C 8 1 1 0 02/05/26 02/05/26 02/05/26 8:00 AM 02/05/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.2.2.1 1 1693 Placeholder
1695 1.2 1.2.8.7.3.3 Retrograde (USAP) Not Started P 6 1 2d 01/15/26 01/16/26 01/15/26 8:00 AM 01/16/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.3 1 1694 Retrograde (USAP)
1696 1.2 1.2.8.7.3.3.1 Drill Hose - SPOT 3 (USAP) Not Started C 7 1 2d 01/15/26 01/16/26 01/15/26 8:00 AM 01/16/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.3.1 1 1695 Drill Hose - SPOT 3 (USAP)
1697 1.2 1.2.8.7.3.4 Cargo Storage Support Pole & MCM (USAP) Not Started C 6 1 58d 11/15/25 02/06/26 11/15/25 8:00 AM 02/06/26 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.3.4 1 1696 Cargo Storage Support Pole & MCM (USAP)
1698 1.2 1.2.8.7.4 Opening Activities & Seasonal Equipment Site (SES) Setup Not Started P 5 1 64d 11/07/25 02/09/26 11/07/25 8:00 AM 02/09/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4 1 1697 Opening Activities & Seasonal Equipment Site (SES) Setup
1699 1.2 1.2.8.7.4.1 Excavate Winter Storage Berms (USAP) Not Started C 6 1 8d 11/07/25 11/18/25 11/07/25 8:00 AM 11/18/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.1 1 1698 Excavate Winter Storage Berms (USAP)
1700 1.2 1.2.8.7.4.2 Excavate and Groom SES (USAP) Not Started C 6 1 8d 11/07/25 11/18/25 11/07/25 8:00 AM 11/18/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.2 1 1699 Excavate and Groom SES (USAP)
1701 1.2 1.2.8.7.4.3 SES Dig-out (Driller) Not Started C 6 1 3d 11/14/25 11/18/25 11/14/25 8:00 AM 11/18/25 4:59 PM #REF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.3 1 1700 SES Dig-out (Driller)
1702 1.2 1.2.8.7.4.4 Groom & Compact Roads/Drill Pad (USAP) Not Started C 6 1 2d 11/17/25 11/18/25 11/17/25 8:00 AM 11/18/25 4:59 PM 1700SS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.4 1 1701 Groom & Compact Roads/Drill Pad (USAP)
1703 1.2 1.2.8.7.4.5 Build Water Tank Ramp (USAP) Not Started C 6 1 2d 11/17/25 11/18/25 11/17/25 8:00 AM 11/18/25 4:59 PM 1700SS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.5 1 1702 Build Water Tank Ramp (USAP)
1704 1.2 1.2.8.7.4.6 Deliver TOS1, TOS2, Drill Towers, DCC (to SES), Main Hose Reel (ASC), Reels (TU-20, TU-15) Not Started C 6 1 3d 12/01/25 12/03/25 12/01/25 8:00 AM 12/03/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.6 1 1703 Deliver TOS1, TOS2, Drill Towers, DCC (to SES), Main Hose Reel (ASC), Reels (TU-20, TU-15)
1705 1.2 1.2.8.7.4.7 IT Integration Activities for SES (USAP) Not Started C 6 1 4d 11/18/25 11/21/25 11/18/25 8:00 AM 11/21/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.7 1 1704 IT Integration Activities for SES (USAP)
1706 1.2 1.2.8.7.4.8 SES & Drill Pad Excavated & Established Not Started C 6 1 1 0 11/15/25 11/15/25 11/15/25 8:00 AM 11/15/25 8:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.8 1 1705 SES & Drill Pad Excavated & Established
1707 1.2 1.2.8.7.4.9 Provide Heaters (PolarTherm) (USAP) Not Started C 6 1 59d 11/13/25 02/06/26 11/13/25 8:00 AM 02/06/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.9 1 1706 Provide Heaters (PolarTherm) (USAP)
1708 1.2 1.2.8.7.4.10 Provide Support Generators (CRREL / Onan Genset) (USAP) Not Started C 6 1 58d 11/13/25 02/05/26 11/13/25 8:00 AM 02/05/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.10 1 1707 Provide Support Generators (CRREL / Onan Genset) (USAP)
1709 1.2 1.2.8.7.4.11 Provide 953 Loader, 287B Skidsteer, Pax Van, & Snomo's (USAP) Not Started C 6 1 1d 11/13/25 11/13/25 11/13/25 8:00 AM 11/13/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.11 1 1708 Provide 953 Loader, 287B Skidsteer, Pax Van, & Snomo's (USAP)
1710 1.2 1.2.8.7.4.12 Begin Delivery - 5k Fuel Tanks (USAP) Not Started C 6 1 1d 11/20/25 11/20/25 11/20/25 8:00 AM 11/20/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.12 1 1709 Begin Delivery - 5k Fuel Tanks (USAP)
1711 1.2 1.2.8.7.4.13 Make Ready all SES Modules (DCC, PHS, MHPs, MECC, WTs, All) Not Started C 6 1 9d 11/17/25 11/28/25 11/17/25 8:00 AM 11/28/25 4:59 PM 1700SS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.13 1 1710 Make Ready all SES Modules (DCC, PHS, MHPs, MECC, WTs, All)
1712 1.2 1.2.8.7.4.14 Furnace Checkout & Fire Up (All modules) Not Started C 6 1 4d 11/17/25 11/20/25 11/17/25 8:00 AM 11/20/25 4:59 PM 1710SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.14 1 1711 Furnace Checkout & Fire Up (All modules)
1713 1.2 1.2.8.7.4.15 SES and Equipment Maintenance Activities Not Started C 6 1 51d 11/17/25 01/29/26 11/17/25 8:00 AM 01/29/26 4:59 PM 1711SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.15 1 1712 SES and Equipment Maintenance Activities
1714 1.2 1.2.8.7.4.16 SES IT Integration (USAP) Not Started C 6 1 4d 11/18/25 11/21/25 11/18/25 8:00 AM 11/21/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.16 1 1713 SES IT Integration (USAP)
1715 1.2 1.2.8.7.4.17 Drill Control Center Set-up, Integration, & Commissioning Not Started C 6 1 6d 11/18/25 11/25/25 11/18/25 8:00 AM 11/25/25 4:59 PM 1713SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.17 1 1714 Drill Control Center Set-up, Integration, & Commissioning
1716 1.2 1.2.8.7.4.18 Seed Water Delivery (3000 gallons) (USAP) Not Started C 6 1 1d 11/24/25 11/24/25 11/24/25 8:00 AM 11/24/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.18 1 1715 Seed Water Delivery (3000 gallons) (USAP)
1717 1.2 1.2.8.7.4.19 Deliver Compressor to SES (USAP) Not Started C 6 1 1d 12/01/25 12/01/25 12/01/25 8:00 AM 12/01/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.19 1 1716 Deliver Compressor to SES (USAP)
1718 1.2 1.2.8.7.4.20 Deliver & Warm Up Glycol Tank (USAP) Not Started C 6 1 1d 12/01/25 12/01/25 12/01/25 8:00 AM 12/01/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.20 1 1717 Deliver & Warm Up Glycol Tank (USAP)
1719 1.2 1.2.8.7.4.21 T&L Support - Cargo Deliveries (USAP) Not Started C 6 1 59d 11/15/25 02/09/26 11/15/25 8:00 AM 02/09/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.21 1 1718 T&L Support - Cargo Deliveries (USAP)
1720 1.2 1.2.8.7.4.22 Ready Antarctic Rodwell Apparatus (ARA) for Service Not Started C 6 1 5d 12/01/25 12/05/25 12/01/25 8:00 AM 12/05/25 4:59 PM 1711FS +5d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.22 1 1719 Ready Antarctic Rodwell Apparatus (ARA) for Service
1721 1.2 1.2.8.7.4.23 Create SES Snow Stockpile (USAP) Not Started C 6 1 36d 12/08/25 01/28/26 12/08/25 8:00 AM 01/28/26 4:59 PM 1719 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.23 1 1720 Create SES Snow Stockpile (USAP)
1722 1.2 1.2.8.7.4.24 Perform Emergency Incident Drill & Safety Training Not Started C 6 1 3d 11/26/25 12/01/25 11/26/25 8:00 AM 12/01/25 4:59 PM 1714 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.24 1 1721 Perform Emergency Incident Drill & Safety Training
1723 1.2 1.2.8.7.4.25 Perform Emergency Incident Drill & Safety Training Complete Not Started C 6 1 1 0 12/01/25 12/01/25 12/01/25 4:59 PM 12/01/25 4:59 PM 1721 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.25 1 1722 Perform Emergency Incident Drill & Safety Training Complete
1724 1.2 1.2.8.7.4.26 Final SES Readiness Assessment Not Started C 6 1 2d 12/08/25 12/09/25 12/08/25 8:00 AM 12/09/25 4:59 PM 1709, 1710, 1711, 1715, 1719, 1722 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.26 1 1723 Final SES Readiness Assessment
1725 1.2 1.2.8.7.4.27 SES Ready Not Started C 6 1 1 0 12/09/25 12/09/25 12/09/25 4:59 PM 12/09/25 4:59 PM 1723 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.4.27 1 1724 SES Ready
1726 1.2 1.2.8.7.5 Generators & PDM Not Started P 5 1 5d 11/18/25 11/24/25 11/18/25 8:00 AM 11/24/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.5 1 1725 Generators & PDM
1727 1.2 1.2.8.7.5.1 Generator & PDM: Commission - NPX Not Started C 6 1 5d 11/18/25 11/24/25 11/18/25 8:00 AM 11/24/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.5.1 1 1726 Generator & PDM: Commission - NPX
1728 1.2 1.2.8.7.5.2 Electrician Support for Power Generation (USAP) Not Started C 6 1 3d 11/19/25 11/21/25 11/19/25 8:00 AM 11/21/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.5.2 1 1727 Electrician Support for Power Generation (USAP)
1729 1.2 1.2.8.7.5.3 Generators Ready Not Started C 6 1 1 0 11/24/25 11/24/25 11/24/25 8:00 AM 11/24/25 8:00 AM 1726FS -1d, 1727FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.5.3 1 1728 Generators Ready
1730 1.2 1.2.8.7.5.4 Change from Temp Power to Generators (USAP) Not Started C 6 1 1 0 11/24/25 11/24/25 11/24/25 8:00 AM 11/24/25 8:00 AM 1728SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.5.4 1 1729 Change from Temp Power to Generators (USAP)
1731 1.2 1.2.8.7.6 TOS1 / Tower1 Setup Not Started P 5 1 16d 11/19/25 12/11/25 11/19/25 8:00 AM 12/11/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6 1 1730 TOS1 / Tower1 Setup
1732 1.2 1.2.8.7.6.1 Uncover Hole 1 / String 87 Not Started C 6 1 1h 11/19/25 11/19/25 11/19/25 8:00 AM 11/19/25 8:59 AM 1701 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.1 1 1731 Uncover Hole 1 / String 87
1733 1.2 1.2.8.7.6.2 Relocate TOS1 and Main Hose Reel to Hole 1 / String 87 Not Started C 6 1 1d 11/19/25 11/20/25 11/19/25 9:00 AM 11/20/25 8:59 AM 1731 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.2 1 1732 Relocate TOS1 and Main Hose Reel to Hole 1 / String 87
1734 1.2 1.2.8.7.6.3 Heavy Equipment Support for TOS1 and Main Hose Reel Relocation to Hole 1 / String 87 (USAP) Not Started C 6 1 1d 11/19/25 11/20/25 11/19/25 9:00 AM 11/20/25 8:59 AM 1732SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.3 1 1733 Heavy Equipment Support for TOS1 and Main Hose Reel Relocation to Hole 1 / String 87 (USAP)
1735 1.2 1.2.8.7.6.4 Position Sensor Handling Structure Not Started C 6 1 1d 11/20/25 11/21/25 11/20/25 9:00 AM 11/21/25 8:59 AM 1732 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.4 1 1734 Position Sensor Handling Structure
1736 1.2 1.2.8.7.6.5 Trench & Install Reel Anchors (Hole 1 & 2) Not Started C 6 1 1d 11/20/25 11/21/25 11/20/25 9:00 AM 11/21/25 8:59 AM 1732 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.5 1 1735 Trench & Install Reel Anchors (Hole 1 & 2)
1737 1.2 1.2.8.7.6.6 Position Hose & Cable Reels (Hole 1) Not Started C 6 1 2d 11/20/25 11/24/25 11/20/25 9:00 AM 11/24/25 8:59 AM 1735FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.6 1 1736 Position Hose & Cable Reels (Hole 1)
1738 1.2 1.2.8.7.6.7 Hose & Cable Delivery & Layout SES-TOS Not Started C 6 1 3d 11/24/25 11/28/25 11/24/25 9:00 AM 11/28/25 8:59 AM 1736 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.7 1 1737 Hose & Cable Delivery & Layout SES-TOS
1739 1.2 1.2.8.7.6.8 TOS1 Network/Comms Set-up Not Started C 6 1 3d 11/24/25 11/28/25 11/24/25 9:00 AM 11/28/25 8:59 AM 1736 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.8 1 1738 TOS1 Network/Comms Set-up
1740 1.2 1.2.8.7.6.9 Make TOS1 Operational, Deliver Fuel, Fire Furnace Not Started C 6 1 2d 11/28/25 12/02/25 11/28/25 9:00 AM 12/02/25 8:59 AM 1732, 1724FS -8d, 1738, 1737 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.9 1 1739 Make TOS1 Operational, Deliver Fuel, Fire Furnace
1741 1.2 1.2.8.7.6.10 Prepare MCA (Mount on TU20, test slip ring), Setup both TU20 (Hole 1 & 2) Not Started C 6 1 2d 12/04/25 12/05/25 12/04/25 8:00 AM 12/05/25 4:59 PM 1703 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.10 1 1740 Prepare MCA (Mount on TU20, test slip ring), Setup both TU20 (Hole 1 & 2)
1742 1.2 1.2.8.7.6.11 Connect Hose Loop & Circulate Water Not Started C 6 1 2d 12/01/25 12/03/25 12/01/25 9:00 AM 12/03/25 8:59 AM 1739FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.11 1 1741 Connect Hose Loop & Circulate Water
1743 1.2 1.2.8.7.6.12 Pull Drill Heads from ICL & Final Testing in TOS Not Started C 6 1 4d 12/08/25 12/11/25 12/08/25 8:00 AM 12/11/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.12 1 1742 Pull Drill Heads from ICL & Final Testing in TOS
1744 1.2 1.2.8.7.6.13 TOS1/Tower1 Site Ready for Drilling Not Started C 6 1 1 1 0 12/11/25 12/11/25 12/11/25 4:59 PM 12/11/25 4:59 PM 1742, 1741, 1739, 1738 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.6.13 1 1743 TOS1/Tower1 Site Ready for Drilling
1745 1.2 1.2.8.7.7 TOS2 / Tower2 Setup Not Started P 5 1 5.125d 11/19/25 11/26/25 11/19/25 8:00 AM 11/26/25 8:59 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.7 1 1744 TOS2 / Tower2 Setup
1746 1.2 1.2.8.7.7.1 Uncover Hole 2 / String 88 Not Started C 6 1 1h 11/19/25 11/19/25 11/19/25 8:00 AM 11/19/25 8:59 AM 1701 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.7.1 1 1745 Uncover Hole 2 / String 88
1747 1.2 1.2.8.7.7.2 Relocate TOS2 to Hole 2 / String 88 Not Started C 6 1 1d 11/19/25 11/20/25 11/19/25 9:00 AM 11/20/25 8:59 AM 1745 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.7.2 1 1746 Relocate TOS2 to Hole 2 / String 88
1748 1.2 1.2.8.7.7.3 Heavy Support for TOS2 Relocation to Hole 2 / String 88 (USAP) Not Started C 6 1 1d 11/19/25 11/20/25 11/19/25 9:00 AM 11/20/25 8:59 AM 1746SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.7.3 1 1747 Heavy Support for TOS2 Relocation to Hole 2 / String 88 (USAP)
1749 1.2 1.2.8.7.7.4 Cable Layout SES to TOS2 Not Started C 6 1 3d 11/20/25 11/25/25 11/20/25 9:00 AM 11/25/25 8:59 AM 1746 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.7.4 1 1748 Cable Layout SES to TOS2
1750 1.2 1.2.8.7.7.5 TOS2 Network/Comms Install Not Started C 6 1 3d 11/20/25 11/25/25 11/20/25 9:00 AM 11/25/25 8:59 AM 1748SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.7.5 1 1749 TOS2 Network/Comms Install
1751 1.2 1.2.8.7.7.6 Make TOS2 Operational, Deliver Fuel, Fire Furnace Not Started C 6 1 1d 11/25/25 11/26/25 11/25/25 9:00 AM 11/26/25 8:59 AM 1748 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.7.6 1 1750 Make TOS2 Operational, Deliver Fuel, Fire Furnace
1752 1.2 1.2.8.7.7.7 TOS2/Tower2 Site Ready for Drilling Not Started C 6 1 1 1 0 11/26/25 11/26/25 11/26/25 8:59 AM 11/26/25 8:59 AM 1750 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.7.7 1 1751 TOS2/Tower2 Site Ready for Drilling
1753 1.2 1.2.8.7.8 EHWD: Drill Commissioning Not Started P 5 1 14d 11/25/25 12/15/25 11/25/25 8:00 AM 12/15/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.8 1 1752 EHWD: Drill Commissioning
1754 1.2 1.2.8.7.8.1 Begin Circulation of Water & Fire Boilers Not Started C 6 1 5d 11/25/25 12/02/25 11/25/25 8:00 AM 12/02/25 4:59 PM 1715, 1709 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.8.1 1 1753 Begin Circulation of Water & Fire Boilers
1755 1.2 1.2.8.7.8.2 Develop & Establish Rodwell Not Started C 6 1 e14d 12/01/25 12/15/25 12/01/25 8:00 AM 12/15/25 7:59 AM 1753SS +3d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.8.2 1 1754 Develop & Establish Rodwell
1756 1.2 1.2.8.7.8.3 New Driller Training Not Started C 6 1 5d 12/03/25 12/09/25 12/03/25 8:00 AM 12/09/25 4:59 PM 1753, #REF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.8.3 1 1755 New Driller Training
1757 1.2 1.2.8.7.8.4 Emergency & Safety Systems Tests Not Started C 6 1 4d 12/03/25 12/08/25 12/03/25 8:00 AM 12/08/25 4:59 PM 1753 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.8.4 1 1756 Emergency & Safety Systems Tests
1758 1.2 1.2.8.7.8.5 Perform Complete Systems Testing (Wet-test & Comm) Not Started C 6 1 e4d 12/08/25 12/12/25 12/08/25 5:00 PM 12/12/25 4:59 PM 1756 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.8.5 1 1757 Perform Complete Systems Testing (Wet-test & Comm)
1759 1.2 1.2.8.7.8.6 Readiness Review/Safety Refresher Not Started C 6 1 e3d 12/12/25 12/15/25 12/12/25 5:00 PM 12/15/25 4:59 PM 1757 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.8.6 1 1758 Readiness Review/Safety Refresher
1760 1.2 1.2.8.7.8.7 EHWD System Ready for Drilling Not Started C 6 1 1 1 1 0 12/15/25 12/15/25 12/15/25 4:59 PM 12/15/25 4:59 PM 1758, 1757, 1756 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.8.7 1 1759 EHWD System Ready for Drilling
1761 1.2 1.2.8.7.9 Deep Drilling FS3 Not Started P 5 1 19d 12/15/25 01/13/26 12/15/25 5:00 PM 01/13/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9 1 1760 Deep Drilling FS3
1762 1.2 1.2.8.7.9.1 DRILL HOLE 1 / String 87 Not Started P 6 1 4d 12/15/25 12/20/25 12/15/25 5:00 PM 12/20/25 10:00 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.1 1 1761 DRILL HOLE 1 / String 87
1763 1.2 1.2.8.7.9.1.1 Drill Hole 1 / String 87 Not Started C 7 1 e52h 12/15/25 12/17/25 12/15/25 5:00 PM 12/17/25 8:59 PM 1759 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.1.1 1 1762 Drill Hole 1 / String 87
1764 1.2 1.2.8.7.9.1.2 Hole 1 Drilling Complete, Turn Over to Installation Team Not Started C 7 1 1 1 0 12/17/25 12/17/25 12/17/25 8:59 PM 12/17/25 8:59 PM 1762 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.1.2 1 1763 Hole 1 Drilling Complete, Turn Over to Installation Team
1765 1.2 1.2.8.7.9.1.3 Installation - Hole 1 / String 87 - Driller Supported Not Started C 7 1 e48h 12/17/25 12/19/25 12/17/25 9:00 PM 12/19/25 9:00 PM 2148FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.1.3 1 1764 Installation - Hole 1 / String 87 - Driller Supported
1766 1.2 1.2.8.7.9.1.4 Relocate Hose, Cable Reels to Hole 2 / String 88 Not Started C 7 1 e12h 12/17/25 12/18/25 12/17/25 9:00 PM 12/18/25 8:59 AM 1763, 1735 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.1.4 1 1765 Relocate Hose, Cable Reels to Hole 2 / String 88
1767 1.2 1.2.8.7.9.1.5 Heavy Support for Main Hose Reel Relocation (USAP) to Hole 2 / String 88 Not Started C 7 1 e4h 12/17/25 12/18/25 12/17/25 9:00 PM 12/18/25 12:59 AM 1765SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.7.9.1.5 1 1766 Heavy Support for Main Hose Reel Relocation (USAP) to Hole 2 / String 88
1768 1.2 1.2.8.7.9.1.6 Relocate Sensor Handling Structure to Hole 2 / String 88 Not Started C 7 1 e2h 12/19/25 12/19/25 12/19/25 8:00 PM 12/19/25 10:00 PM 2149FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.1.6 1 1767 Relocate Sensor Handling Structure to Hole 2 / String 88
1769 1.2 1.2.8.7.9.1.7 Uncover Hole 3 / String 89 Not Started C 7 1 e1h 12/20/25 12/20/25 12/20/25 9:00 AM 12/20/25 10:00 AM 1769SF 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.1.7 1 1768 Uncover Hole 3 / String 89
1770 1.2 1.2.8.7.9.1.8 Closeout & Relocate Tower & TOS-1 to Hole 3 / String 89 Not Started C 7 1 e8h 12/20/25 12/20/25 12/20/25 10:00 AM 12/20/25 6:00 PM 2151SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.1.8 1 1769 Closeout & Relocate Tower & TOS-1 to Hole 3 / String 89
1771 1.2 1.2.8.7.9.1.9 Heavy Support to Relocate Tower & TOS-1 to Hole 3 / String 89 (USAP) Not Started C 7 1 e2h 12/20/25 12/20/25 12/20/25 10:00 AM 12/20/25 12:00 PM 1769SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.7.9.1.9 1 1770 Heavy Support to Relocate Tower & TOS-1 to Hole 3 / String 89 (USAP)
1772 1.2 1.2.8.7.9.1.10 Trench & Install Reel Anchors at Hole 3 / String 89 Not Started C 7 1 e4h 12/20/25 12/20/25 12/20/25 12:00 PM 12/20/25 4:00 PM 1770 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.1.10 1 1771 Trench & Install Reel Anchors at Hole 3 / String 89
1773 1.2 1.2.8.7.9.1.11 Trenching Support at Hole 3 / String 89 (USAP) Not Started C 7 1 e4h 12/20/25 12/20/25 12/20/25 12:00 PM 12/20/25 4:00 PM 1771SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.7.9.1.11 1 1772 Trenching Support at Hole 3 / String 89 (USAP)
1774 1.2 1.2.8.7.9.1.12 Prepare MCA Cable (Mount on TU20, test slip ring) for Hole 3 / String 89 Not Started C 7 1 e8h 12/20/25 12/20/25 12/20/25 2:00 PM 12/20/25 10:00 PM 2151 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.1.12 1 1773 Prepare MCA Cable (Mount on TU20, test slip ring) for Hole 3 / String 89
1775 1.2 1.2.8.7.9.1.13 Heavy Support for Main Cable Loading (USAP) for Hole 3 / String 89 Not Started C 7 1 e2h 12/20/25 12/20/25 12/20/25 2:00 PM 12/20/25 4:00 PM 1773SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.7.9.1.13 1 1774 Heavy Support for Main Cable Loading (USAP) for Hole 3 / String 89
1776 1.2 1.2.8.7.9.2 Operational Debrief/Drill Maintenance Not Started C 6 1 e24h 12/20/25 12/21/25 12/20/25 6:00 PM 12/21/25 6:00 PM 1769 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.2 1 1775 Operational Debrief/Drill Maintenance
1777 1.2 1.2.8.7.9.3 DRILL HOLE 2 / String 88 Not Started P 6 1 3.125d 12/21/25 12/26/25 12/21/25 6:00 PM 12/26/25 9:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3 1 1776 DRILL HOLE 2 / String 88
1778 1.2 1.2.8.7.9.3.1 Drill Hole 2 / String 88 Not Started C 7 1 e52h 12/21/25 12/23/25 12/21/25 6:00 PM 12/23/25 10:00 PM 1775 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3.1 1 1777 Drill Hole 2 / String 88
1779 1.2 1.2.8.7.9.3.2 Hole 2 Drilling Complete, Turn Over to Installation Team Not Started C 7 1 1 1 0 12/23/25 12/23/25 12/23/25 10:00 PM 12/23/25 10:00 PM 1777 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3.2 1 1778 Hole 2 Drilling Complete, Turn Over to Installation Team
1780 1.2 1.2.8.7.9.3.3 Installation - Hole 2 / String 88 - Driller Supported Not Started C 7 1 e24h 12/23/25 12/24/25 12/23/25 10:00 PM 12/24/25 10:00 PM 2164FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3.3 1 1779 Installation - Hole 2 / String 88 - Driller Supported
1781 1.2 1.2.8.7.9.3.4 Relocate Hose, Cable Reels to Hole 3 / String 89 Not Started C 7 1 e12h 12/23/25 12/24/25 12/23/25 10:00 PM 12/24/25 10:00 AM 1778, 1771 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3.4 1 1780 Relocate Hose, Cable Reels to Hole 3 / String 89
1782 1.2 1.2.8.7.9.3.5 Heavy Support for Main Hose Reel Relocation to Hole 3 / String 89 (USAP) Not Started C 7 1 e4h 12/23/25 12/24/25 12/23/25 10:00 PM 12/24/25 2:00 AM 1780SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.7.9.3.5 1 1781 Heavy Support for Main Hose Reel Relocation to Hole 3 / String 89 (USAP)
1783 1.2 1.2.8.7.9.3.6 Relocate Sensor Handling Structure to Hole 3 / String 89 Not Started C 7 1 e2h 12/24/25 12/24/25 12/24/25 9:00 PM 12/24/25 11:00 PM 2165FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3.6 1 1782 Relocate Sensor Handling Structure to Hole 3 / String 89
1784 1.2 1.2.8.7.9.3.7 Uncover Hole 4 / String 90 Not Started C 7 1 1 e1h 12/25/25 12/25/25 12/25/25 10:00 PM 12/25/25 11:00 PM 1786SF 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3.7 1 1783 Uncover Hole 4 / String 90
1785 1.2 1.2.8.7.9.3.12 Prepare MCA (Mount on TU20, test slip ring) - Prep for Hole 4 / String 90 Not Started C 7 1 e8h 12/26/25 12/26/25 12/26/25 1:00 AM 12/26/25 9:00 AM 2168 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3.12 1 1784 Prepare MCA (Mount on TU20, test slip ring) - Prep for Hole 4 / String 90
1786 1.2 1.2.8.7.9.3.13 Heavy Support for Main Cable Loading - Hole 4 / String 90 (USAP) Not Started C 7 1 e2h 12/26/25 12/26/25 12/26/25 1:00 AM 12/26/25 3:00 AM 1784SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.8.7.9.3.13 1 1785 Heavy Support for Main Cable Loading - Hole 4 / String 90 (USAP)
1787 1.2 1.2.8.7.9.3.8 Closeout & Relocate Tower & TOS2 to Hole 4 / String 90 Not Started C 7 1 e8h 12/25/25 12/26/25 12/25/25 11:00 PM 12/26/25 7:00 AM 2167 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3.8 1 1786 Closeout & Relocate Tower & TOS2 to Hole 4 / String 90
1788 1.2 1.2.8.7.9.3.9 Heavy Support to Relocate Tower & TOS2 to Hole 4 / String 90 (USAP) Not Started C 7 1 e2h 12/25/25 12/26/25 12/25/25 11:00 PM 12/26/25 1:00 AM 1786SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3.9 1 1787 Heavy Support to Relocate Tower & TOS2 to Hole 4 / String 90 (USAP)
1789 1.2 1.2.8.7.9.3.10 Trench & Install Reel Anchors at Hole 4 / String 90 Not Started C 7 1 e4h 12/26/25 12/26/25 12/26/25 1:00 AM 12/26/25 5:00 AM 1787 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3.10 1 1788 Trench & Install Reel Anchors at Hole 4 / String 90
1790 1.2 1.2.8.7.9.3.11 Trenching Support at Hole 4 / String 90 (USAP) Not Started C 7 1 e4h 12/26/25 12/26/25 12/26/25 1:00 AM 12/26/25 5:00 AM 1788SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.3.11 1 1789 Trenching Support at Hole 4 / String 90 (USAP)
1791 1.2 1.2.8.7.9.4 DRILL HOLE 3 / String 89 Not Started P 6 1 1.75d 12/24/25 12/28/25 12/24/25 10:00 AM 12/28/25 3:00 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4 1 1790 DRILL HOLE 3 / String 89
1792 1.2 1.2.8.7.9.4.1 Drill Hole 3 / String 89 Not Started C 7 1 e52h 12/24/25 12/26/25 12/24/25 10:00 AM 12/26/25 2:00 PM 1780, 1769, 1772 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.1 1 1791 Drill Hole 3 / String 89
1793 1.2 1.2.8.7.9.4.2 Hole 3 Drilling Complete, Turn Over to Installation Team Not Started C 7 1 1 1 0 12/26/25 12/26/25 12/26/25 2:00 PM 12/26/25 2:00 PM 1791 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.2 1 1792 Hole 3 Drilling Complete, Turn Over to Installation Team
1794 1.2 1.2.8.7.9.4.3 Installation - Hole 3 / String 89 - Driller Supported Not Started C 7 1 e24h 12/26/25 12/27/25 12/26/25 2:00 PM 12/27/25 2:00 PM 2180FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.3 1 1793 Installation - Hole 3 / String 89 - Driller Supported
1795 1.2 1.2.8.7.9.4.4 Relocate Hose, Cable Reels to Hole 4 / String 90 Not Started C 7 1 e12h 12/26/25 12/27/25 12/26/25 2:00 PM 12/27/25 2:00 AM 1792, 1788 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.4 1 1794 Relocate Hose, Cable Reels to Hole 4 / String 90
1796 1.2 1.2.8.7.9.4.5 Heavy Support for Main Hose Reel Relocation to Hole 4 / String 90 (USAP) Not Started C 7 1 e4h 12/26/25 12/26/25 12/26/25 2:00 PM 12/26/25 6:00 PM 1794SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.5 1 1795 Heavy Support for Main Hose Reel Relocation to Hole 4 / String 90 (USAP)
1797 1.2 1.2.8.7.9.4.6 Relocate Sensor Handling Structure to Hole 4 / String 90 Not Started C 7 1 e2h 12/27/25 12/27/25 12/27/25 1:00 PM 12/27/25 3:00 PM 2182FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.6 1 1796 Relocate Sensor Handling Structure to Hole 4 / String 90
1798 1.2 1.2.8.7.9.4.12 Prepare MCA (Mount on TU20, test slip ring) - Prep for Hole 5 / String 91 Not Started C 7 1 e8h 12/28/25 12/28/25 12/28/25 7:00 AM 12/28/25 3:00 PM 2184 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.12 1 1797 Prepare MCA (Mount on TU20, test slip ring) - Prep for Hole 5 / String 91
1799 1.2 1.2.8.7.9.4.13 Heavy Support for Main Cable Loading - Hole 5 / String 91 (USAP) Not Started C 7 1 e2h 12/28/25 12/28/25 12/28/25 7:00 AM 12/28/25 9:00 AM 1797SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.13 1 1798 Heavy Support for Main Cable Loading - Hole 5 / String 91 (USAP)
1800 1.2 1.2.8.7.9.4.7 Uncover Hole 5 / String 91 Not Started C 7 1 e1h 12/28/25 12/28/25 12/28/25 2:00 AM 12/28/25 3:00 AM 1800SF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.7 1 1799 Uncover Hole 5 / String 91
1801 1.2 1.2.8.7.9.4.8 Closeout & Relocate Tower & TOS1 to Hole 5 / String 91 Not Started C 7 1 e8h 12/28/25 12/28/25 12/28/25 3:00 AM 12/28/25 11:00 AM 2184SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.8 1 1800 Closeout & Relocate Tower & TOS1 to Hole 5 / String 91
1802 1.2 1.2.8.7.9.4.9 Heavy Support to Relocate Tower & TOS1 to Hole 5 / String 91 (USAP) Not Started C 7 1 e2h 12/28/25 12/28/25 12/28/25 3:00 AM 12/28/25 5:00 AM 1800SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.9 1 1801 Heavy Support to Relocate Tower & TOS1 to Hole 5 / String 91 (USAP)
1803 1.2 1.2.8.7.9.4.10 Trench & Install Reel Anchors at Hole 5 / String 91 Not Started C 7 1 e4h 12/28/25 12/28/25 12/28/25 5:00 AM 12/28/25 9:00 AM 1801 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.10 1 1802 Trench & Install Reel Anchors at Hole 5 / String 91
1804 1.2 1.2.8.7.9.4.11 Trenching Support at at Hole 5 / String 91 (USAP) Not Started C 7 1 e4h 12/28/25 12/28/25 12/28/25 5:00 AM 12/28/25 9:00 AM 1802SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.4.11 1 1803 Trenching Support at at Hole 5 / String 91 (USAP)
1805 1.2 1.2.8.7.9.5 Operational Debrief / Drill Maintenance Not Started C 6 1 e24h 12/28/25 12/29/25 12/28/25 11:00 AM 12/29/25 11:00 AM 1789, 1794, 1800 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.5 1 1804 Operational Debrief / Drill Maintenance
1806 1.2 1.2.8.7.9.6 DRILL HOLE 4 / String 90 Not Started P 6 1 3.5d 12/29/25 01/02/26 12/29/25 11:00 AM 01/02/26 4:00 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6 1 1805 DRILL HOLE 4 / String 90
1807 1.2 1.2.8.7.9.6.1 Drill Hole 4 / String 90 Not Started C 7 1 e52h 12/29/25 12/31/25 12/29/25 11:00 AM 12/31/25 3:00 PM 1804 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.1 1 1806 Drill Hole 4 / String 90
1808 1.2 1.2.8.7.9.6.2 Hole 4 Drilling Complete, Turn Over to Installation Team Not Started C 7 1 1 1 0 12/31/25 12/31/25 12/31/25 3:00 PM 12/31/25 3:00 PM 1806 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.2 1 1807 Hole 4 Drilling Complete, Turn Over to Installation Team
1809 1.2 1.2.8.7.9.6.3 Installation - Hole 4 / String 90 - Driller Supported Not Started C 7 1 e24h 12/31/25 01/01/26 12/31/25 3:00 PM 01/01/26 3:00 PM 2197FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.3 1 1808 Installation - Hole 4 / String 90 - Driller Supported
1810 1.2 1.2.8.7.9.6.4 Relocate Hose, Cable Reels to Hole 5 / String 91 Not Started C 7 1 e12h 12/31/25 01/01/26 12/31/25 3:00 PM 01/01/26 3:00 AM 1807 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.4 1 1809 Relocate Hose, Cable Reels to Hole 5 / String 91
1811 1.2 1.2.8.7.9.6.5 Heavy Support for Main Hose Reel Relocation to Hole 5 / String 91 (USAP) Not Started C 7 1 e4h 12/31/25 12/31/25 12/31/25 3:00 PM 12/31/25 7:00 PM 1809SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.5 1 1810 Heavy Support for Main Hose Reel Relocation to Hole 5 / String 91 (USAP)
1812 1.2 1.2.8.7.9.6.6 Relocate Sensor Handling Structure to Hole 5 / String 91 Not Started C 7 1 e2h 01/01/26 01/01/26 01/01/26 2:00 PM 01/01/26 4:00 PM 2198FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.6 1 1811 Relocate Sensor Handling Structure to Hole 5 / String 91
1813 1.2 1.2.8.7.9.6.12 Prepare MCA Cable (Mount on TU20, test slip ring) - Prep for Hole 6 / String 92 Not Started C 7 1 e8h 01/02/26 01/02/26 01/02/26 8:00 AM 01/02/26 4:00 PM 2200 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.12 1 1812 Prepare MCA Cable (Mount on TU20, test slip ring) - Prep for Hole 6 / String 92
1814 1.2 1.2.8.7.9.6.13 Heavy Support for Main Cable Loading for Hole 6 / String 92 (USAP) Not Started C 7 1 e2h 01/02/26 01/02/26 01/02/26 8:00 AM 01/02/26 10:00 AM 1812SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.13 1 1813 Heavy Support for Main Cable Loading for Hole 6 / String 92 (USAP)
1815 1.2 1.2.8.7.9.6.7 Uncover Hole 6 / String 92 Not Started C 7 1 e1h 01/02/26 01/02/26 01/02/26 3:00 AM 01/02/26 4:00 AM 1815SF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.7 1 1814 Uncover Hole 6 / String 92
1816 1.2 1.2.8.7.9.6.8 Closeout & Relocate Tower & TOS2 for Hole 6 / String 92 Not Started C 7 1 e8h 01/02/26 01/02/26 01/02/26 4:00 AM 01/02/26 12:00 PM 2200SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.8 1 1815 Closeout & Relocate Tower & TOS2 for Hole 6 / String 92
1817 1.2 1.2.8.7.9.6.9 Heavy Support to Relocate Tower & TOS2 to Hole 6 / String 92 (USAP) Not Started C 7 1 e2h 01/02/26 01/02/26 01/02/26 4:00 AM 01/02/26 6:00 AM 1815SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.9 1 1816 Heavy Support to Relocate Tower & TOS2 to Hole 6 / String 92 (USAP)
1818 1.2 1.2.8.7.9.6.10 Trench & Install Reel Anchors at Hole 6 / String 92 Not Started C 7 1 e4h 01/02/26 01/02/26 01/02/26 6:00 AM 01/02/26 10:00 AM 1816 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.10 1 1817 Trench & Install Reel Anchors at Hole 6 / String 92
1819 1.2 1.2.8.7.9.6.11 Trenching Support at at Hole 6 / String 92 (USAP) Not Started C 7 1 e4h 01/02/26 01/02/26 01/02/26 6:00 AM 01/02/26 10:00 AM 1817SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.6.11 1 1818 Trenching Support at at Hole 6 / String 92 (USAP)
1820 1.2 1.2.8.7.9.7 DRILL HOLE 5 / String 91 Not Started P 6 1 2.001d 01/01/26 01/05/26 01/01/26 3:00 AM 01/05/26 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7 1 1819 DRILL HOLE 5 / String 91
1821 1.2 1.2.8.7.9.7.1 Drill Hole 5 / String 91 Not Started C 7 1 e52h 01/01/26 01/03/26 01/01/26 3:00 AM 01/03/26 7:00 AM 1801, 1803, 1809 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.1 1 1820 Drill Hole 5 / String 91
1822 1.2 1.2.8.7.9.7.2 Hole 5 Drilling Complete, Turn Over to Installation Team Not Started C 7 1 1 1 0 01/03/26 01/03/26 01/03/26 7:00 AM 01/03/26 7:00 AM 1820 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.2 1 1821 Hole 5 Drilling Complete, Turn Over to Installation Team
1823 1.2 1.2.8.7.9.7.3 Installation - Hole 5 / String 91 - Driller Supported Not Started C 7 1 e24h 01/03/26 01/04/26 01/03/26 7:00 AM 01/04/26 7:00 AM 2217FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.3 1 1822 Installation - Hole 5 / String 91 - Driller Supported
1824 1.2 1.2.8.7.9.7.4 Relocate Hose, Cable Reels to Hole 6 / String 92 Not Started C 7 1 e12h 01/03/26 01/03/26 01/03/26 7:00 AM 01/03/26 7:00 PM 1821 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.4 1 1823 Relocate Hose, Cable Reels to Hole 6 / String 92
1825 1.2 1.2.8.7.9.7.5 Heavy Support for Main Hose Reel Relocation to Hole 6 / String 92 (USAP) Not Started C 7 1 e4h 01/03/26 01/03/26 01/03/26 7:00 AM 01/03/26 11:00 AM 1823SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.5 1 1824 Heavy Support for Main Hose Reel Relocation to Hole 6 / String 92 (USAP)
1826 1.2 1.2.8.7.9.7.6 Relocate Sensor Handling Structure to Hole 6 / String 92 Not Started C 7 1 e2h 01/04/26 01/04/26 01/04/26 6:00 AM 01/04/26 8:00 AM 2218FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.6 1 1825 Relocate Sensor Handling Structure to Hole 6 / String 92
1827 1.2 1.2.8.7.9.7.7 Uncover Hole 7 / String 93 Not Started C 7 1 e1h 01/04/26 01/04/26 01/04/26 7:00 PM 01/04/26 8:00 PM 1830SF 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.7 1 1826 Uncover Hole 7 / String 93
1828 1.2 1.2.8.7.9.7.11 Trenching Support at at Hole 7 / String 93 (USAP) Not Started C 7 1 e4h 01/04/26 01/05/26 01/04/26 10:00 PM 01/05/26 2:00 AM 1832SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.11 1 1827 Trenching Support at at Hole 7 / String 93 (USAP)
1829 1.2 1.2.8.7.9.7.12 Prepare MCA Cable (Mount on TU20, test slip ring) - Prep for Hole 7 / String 93 Not Started C 7 1 e8h 01/05/26 01/05/26 01/05/26 12:00 AM 01/05/26 8:00 AM 2220 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.12 1 1828 Prepare MCA Cable (Mount on TU20, test slip ring) - Prep for Hole 7 / String 93
1830 1.2 1.2.8.7.9.7.13 Heavy Support for Main Cable Loading for Hole 7 / String 93 (USAP) Not Started C 7 1 e2h 01/05/26 01/05/26 01/05/26 12:00 AM 01/05/26 2:00 AM 1828SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.13 1 1829 Heavy Support for Main Cable Loading for Hole 7 / String 93 (USAP)
1831 1.2 1.2.8.7.9.7.8 Closeout & Relocate Tower & TOS1 to Hole 7 / String 93 Not Started C 7 1 e8h 01/04/26 01/05/26 01/04/26 8:00 PM 01/05/26 4:00 AM 2220SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.8 1 1830 Closeout & Relocate Tower & TOS1 to Hole 7 / String 93
1832 1.2 1.2.8.7.9.7.9 Heavy Support to Relocate Tower & TOS1 to Hole 7 / String 93 (USAP) Not Started C 7 1 e2h 01/04/26 01/04/26 01/04/26 8:00 PM 01/04/26 10:00 PM 1830SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.9 1 1831 Heavy Support to Relocate Tower & TOS1 to Hole 7 / String 93 (USAP)
1833 1.2 1.2.8.7.9.7.10 Trench & Install Reel Anchors at Hole 7 / String 93 Not Started C 7 1 e4h 01/04/26 01/05/26 01/04/26 10:00 PM 01/05/26 2:00 AM 1831 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.7.10 1 1832 Trench & Install Reel Anchors at Hole 7 / String 93
1834 1.2 1.2.8.7.9.8 Operational Debrief Not Started C 6 1 e1d 01/05/26 01/06/26 01/05/26 4:00 AM 01/06/26 4:00 AM 1832, 1823, 1830 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.8 1 1833 Operational Debrief
1835 1.2 1.2.8.7.9.9 DRILL HOLE 6 / String 92 Not Started P 6 1 4d 01/06/26 01/10/26 01/06/26 4:00 AM 01/10/26 5:00 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.9 1 1834 DRILL HOLE 6 / String 92
1836 1.2 1.2.8.7.9.9.1 Drill Hole 6 / String 92 Not Started C 7 1 e52h 01/06/26 01/08/26 01/06/26 4:00 AM 01/08/26 8:00 AM 1833 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.9.1 1 1835 Drill Hole 6 / String 92
1837 1.2 1.2.8.7.9.9.2 Hole 6 Drilling Complete, Turn Over to Installation Team Not Started C 7 1 1 1 0 01/08/26 01/08/26 01/08/26 8:00 AM 01/08/26 8:00 AM 1835 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.9.2 1 1836 Hole 6 Drilling Complete, Turn Over to Installation Team
1838 1.2 1.2.8.7.9.9.3 Driller Support for Dust Logging Activities Not Started C 7 1 e12h 01/08/26 01/08/26 01/08/26 8:00 AM 01/08/26 8:00 PM 2234FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.9.3 1 1837 Driller Support for Dust Logging Activities
1839 1.2 1.2.8.7.9.9.4 Installation - Hole 6 / String 92 - Driller Supported Not Started C 7 1 e24h 01/08/26 01/09/26 01/08/26 8:00 PM 01/09/26 8:00 PM 2236FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.9.4 1 1838 Installation - Hole 6 / String 92 - Driller Supported
1840 1.2 1.2.8.7.9.9.5 Relocate Hose & Cable Reels to Hole 7/ String 93 Not Started C 7 1 e12h 01/08/26 01/08/26 01/08/26 8:00 AM 01/08/26 8:00 PM 1836 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.9.5 1 1839 Relocate Hose & Cable Reels to Hole 7/ String 93
1841 1.2 1.2.8.7.9.9.6 Heavy Support for Main Hose Reel Relocation to Hole 6 / String 92 (USAP) Not Started C 7 1 e4h 01/08/26 01/08/26 01/08/26 8:00 AM 01/08/26 12:00 PM 1839SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.9.6 1 1840 Heavy Support for Main Hose Reel Relocation to Hole 6 / String 92 (USAP)
1842 1.2 1.2.8.7.9.9.7 Relocate Sensor Handling Structure to Hole 7 / String 93 Not Started C 7 1 e2h 01/09/26 01/09/26 01/09/26 9:00 PM 01/09/26 11:00 PM 2237 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.9.7 1 1841 Relocate Sensor Handling Structure to Hole 7 / String 93
1843 1.2 1.2.8.7.9.9.8 Closeout & Relocate Tower & TOS2 to Storage Not Started C 7 1 e8h 01/10/26 01/10/26 01/10/26 9:00 AM 01/10/26 5:00 PM 2239SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.9.8 1 1842 Closeout & Relocate Tower & TOS2 to Storage
1844 1.2 1.2.8.7.9.9.9 Heavy Support to Relocate Tower & TOS2 to Storage (USAP) Not Started C 7 1 e4h 01/10/26 01/10/26 01/10/26 9:00 AM 01/10/26 1:00 PM 1842SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.9.9 1 1843 Heavy Support to Relocate Tower & TOS2 to Storage (USAP)
1845 1.2 1.2.8.7.9.10 DRILL HOLE 7 / String 93 Not Started P 6 1 2d 01/08/26 01/13/26 01/08/26 8:00 PM 01/13/26 1:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.10 1 1844 DRILL HOLE 7 / String 93
1846 1.2 1.2.8.7.9.10.1 Drill Hole 7 / String 93 Not Started C 7 1 e52h 01/08/26 01/11/26 01/08/26 8:00 PM 01/11/26 12:00 AM 1830, 1832, 1839 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.10.1 1 1845 Drill Hole 7 / String 93
1847 1.2 1.2.8.7.9.10.2 Hole 7 Drilling Complete, Turn Over to Installation Team Not Started C 7 1 1 1 0 01/11/26 01/11/26 01/11/26 12:00 AM 01/11/26 12:00 AM 1845 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.10.2 1 1846 Hole 7 Drilling Complete, Turn Over to Installation Team
1848 1.2 1.2.8.7.9.10.3 Installation - Hole 7 / String 93 - Driller Supported Not Started C 7 1 e24h 01/11/26 01/12/26 01/11/26 12:00 AM 01/12/26 12:00 AM 2249FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.10.3 1 1847 Installation - Hole 7 / String 93 - Driller Supported
1849 1.2 1.2.8.7.9.10.4 Closeout & Relocate Tower & TOS1 to Storage Not Started C 7 1 e12h 01/12/26 01/13/26 01/12/26 1:00 PM 01/13/26 1:00 AM 2252SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.10.4 1 1848 Closeout & Relocate Tower & TOS1 to Storage
1850 1.2 1.2.8.7.9.10.5 Heavy Support to Relocate Main Hose Reel, Tower & TOS1 to Storage (USAP) Not Started C 7 1 e6h 01/12/26 01/12/26 01/12/26 1:00 PM 01/12/26 7:00 PM 1848SS 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.10.5 1 1849 Heavy Support to Relocate Main Hose Reel, Tower & TOS1 to Storage (USAP)
1851 1.2 1.2.8.7.9.11 Drilling & Installation Complete Not Started C 6 1 1 1 1 0 01/13/26 01/13/26 01/13/26 1:00 AM 01/13/26 1:00 AM 1848 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.11 1 1850 Drilling & Installation Complete
1852 1.2 1.2.8.7.9.12 Operational Debrief Not Started C 6 1 1d 01/13/26 01/13/26 01/13/26 8:00 AM 01/13/26 4:59 PM 1848 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.12 1 1851 Operational Debrief
1853 1.2 1.2.8.7.9.13 Drill and Safety Lessons Learned Complete Not Started C 6 1 1 1 0 01/13/26 01/13/26 01/13/26 1:00 AM 01/13/26 1:00 AM 1850 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.9.13 1 1852 Drill and Safety Lessons Learned Complete
1854 1.2 1.2.8.7.10 Decommission and Store EHWD Not Started P 5 1 264d 01/24/25 02/02/26 01/24/25 8:00 AM 02/02/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10 1 1853 Decommission and Store EHWD
1855 1.2 1.2.8.7.10.1 Create Storage Berms - End-of-the-World Site (USAP) Not Started C 6 1 22d 12/15/25 01/15/26 12/15/25 8:00 AM 01/15/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.1 1 1854 Create Storage Berms - End-of-the-World Site (USAP)
1856 1.2 1.2.8.7.10.2 Drain and Decommission EHWD Components Not Started C 6 1 4d 01/14/26 01/19/26 01/14/26 8:00 AM 01/19/26 4:59 PM 1852FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.2 1 1855 Drain and Decommission EHWD Components
1857 1.2 1.2.8.7.10.3 Remove & Retro/Store All DNF Not Started C 6 1 5d 01/14/26 01/20/26 01/14/26 8:00 AM 01/20/26 4:59 PM 1855SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.3 1 1856 Remove & Retro/Store All DNF
1858 1.2 1.2.8.7.10.4 Disconnect all Interconnect Cables & Hoses (All including SES to TOS) Not Started C 6 1 6d 01/14/26 01/21/26 01/14/26 8:00 AM 01/21/26 4:59 PM 1855SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.4 1 1857 Disconnect all Interconnect Cables & Hoses (All including SES to TOS)
1859 1.2 1.2.8.7.10.5 Decommission SES Not Started C 6 1 6d 01/14/26 01/21/26 01/14/26 8:00 AM 01/21/26 4:59 PM 1855SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.5 1 1858 Decommission SES
1860 1.2 1.2.8.7.10.6 Decommission TOS Not Started C 6 1 6d 01/15/26 01/22/26 01/15/26 8:00 AM 01/22/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.6 1 1859 Decommission TOS
1861 1.2 1.2.8.7.10.7 Winterize all EHWD Equipment Not Started C 6 1 5d 01/23/26 01/29/26 01/23/26 8:00 AM 01/29/26 4:59 PM 1859, 1858 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.7 1 1860 Winterize all EHWD Equipment
1862 1.2 1.2.8.7.10.8 Removal of Snow Ramp (USAP) Not Started C 6 1 2d 01/30/26 02/02/26 01/30/26 8:00 AM 02/02/26 4:59 PM 1860 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.8 1 1861 Removal of Snow Ramp (USAP)
1863 1.2 1.2.8.7.10.9 Tow and Place EHWD onto Berms for Long-Term Storage (USAP) Not Started C 6 1 2d 01/30/26 02/02/26 01/30/26 8:00 AM 02/02/26 4:59 PM 1861SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.9 1 1862 Tow and Place EHWD onto Berms for Long-Term Storage (USAP)
1864 1.2 1.2.8.7.10.10 Remove Drill Hose from MSHR, Respool & Ship to ZCM Not Started P 6 1 9d 01/16/26 01/28/26 01/16/26 8:00 AM 01/28/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.10 1 1863 Remove Drill Hose from MSHR, Respool & Ship to ZCM
1865 1.2 1.2.8.7.10.10.1 Remove Drill Hose from MSHR and Respool Individually Not Started C 7 1 4d 01/16/26 01/21/26 01/16/26 8:00 AM 01/21/26 4:59 PM 1855SS +2d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.10.1 1 1864 Remove Drill Hose from MSHR and Respool Individually
1866 1.2 1.2.8.7.10.10.2 Drill Hose Respooled Not Started C 7 1 1 0 01/21/26 01/21/26 01/21/26 4:59 PM 01/21/26 4:59 PM 1864 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.10.2 1 1865 Drill Hose Respooled
1867 1.2 1.2.8.7.10.10.3 Deliver to Cargo Yard and Prepare for Shipping (Driller & USAP) Not Started C 7 1 5d 01/22/26 01/28/26 01/22/26 8:00 AM 01/28/26 4:59 PM 1865 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.10.3 1 1866 Deliver to Cargo Yard and Prepare for Shipping (Driller & USAP)
1868 1.2 1.2.8.7.10.10.4 Drill Hose Shipped to McM (USAP) Not Started C 7 1 1 0 01/28/26 01/28/26 01/28/26 4:59 PM 01/28/26 4:59 PM 1866 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.10.4 1 1867 Drill Hose Shipped to McM (USAP)
1869 1.2 1.2.8.7.10.11 Winterization and Storage of EHWD Equipment Complete Not Started C 6 1 1 0 02/02/26 02/02/26 02/02/26 4:59 PM 02/02/26 4:59 PM 1867, 1862, 1860 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.11 1 1868 Winterization and Storage of EHWD Equipment Complete
1870 1.2 1.2.8.7.10.12 Inventory & Photograph EHWD, Document Repairs Needed Not Started C 6 1 3d 01/20/26 01/22/26 01/20/26 8:00 AM 01/22/26 4:59 PM 1856FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.12 1 1869 Inventory & Photograph EHWD, Document Repairs Needed
1871 1.2 1.2.8.7.10.13 UNL Equipment - Deliver to Cargo for Retro or Redistribution Not Started C 6 1 3d 01/22/26 01/26/26 01/22/26 8:00 AM 01/26/26 4:59 PM 1869FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.13 1 1870 UNL Equipment - Deliver to Cargo for Retro or Redistribution
1872 1.2 1.2.8.7.10.14 Crate and Deliver EHWD Equipment to Cargo for Retrograde or Redistribution Not Started C 6 1 5d 01/24/25 01/30/25 01/24/25 8:00 AM 01/30/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.14 1 1871 Crate and Deliver EHWD Equipment to Cargo for Retrograde or Redistribution
1873 1.2 1.2.8.7.10.15 Storage and Retrograde Complete Not Started C 6 1 1 0 01/31/25 01/31/25 01/31/25 4:59 PM 01/31/25 4:59 PM 1871FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.15 1 1872 Storage and Retrograde Complete
1874 1.2 1.2.8.7.10.16 Pole and MCM Cargo Retro Support (USAP) Not Started C 6 1 18d 01/24/25 02/18/25 01/24/25 8:00 AM 02/18/25 4:59 PM 1871SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.16 1 1873 Pole and MCM Cargo Retro Support (USAP)
1875 1.2 1.2.8.7.10.17 MCM Receive and Berm Drill Hose at the MCM (USAP) Not Started C 6 1 1 0 01/28/26 01/28/26 01/28/26 4:59 PM 01/28/26 4:59 PM 1867 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.10.17 1 1874 MCM Receive and Berm Drill Hose at the MCM (USAP)
1876 1.2 1.2.8.7.11 Other Field Activities (FS3 Season) Not Started P 5 1 276d 01/15/25 02/09/26 01/15/25 8:00 AM 02/09/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.11 1 1875 Other Field Activities (FS3 Season)
1877 1.2 1.2.8.7.11.1 MCM Field Logistics Rep (PSL) Not Started C 6 1 30d 11/11/25 12/23/25 11/11/25 8:00 AM 12/23/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.11.1 1 1876 MCM Field Logistics Rep (PSL)
1878 1.2 1.2.8.7.11.2 Electrician Support for Power Generation (USAP) Not Started C 6 1 3d 11/21/25 11/25/25 11/21/25 8:00 AM 11/25/25 4:59 PM 1700FS +2d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.11.2 1 1877 Electrician Support for Power Generation (USAP)
1879 1.2 1.2.8.7.11.3 MCM and Pole Logistics Support (USAP) Not Started C 6 1 44d 10/15/25 12/16/25 10/15/25 8:00 AM 12/16/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.11.3 1 1878 MCM and Pole Logistics Support (USAP)
1880 1.2 1.2.8.7.11.4 Equipment Ops Support - Moves, TU-20 Loading, Season Snow Removal, Road Maint. (USAP) Not Started C 6 1 59d 11/15/25 02/09/26 11/15/25 8:00 AM 02/09/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.11.4 1 1879 Equipment Ops Support - Moves, TU-20 Loading, Season Snow Removal, Road Maint. (USAP)
1881 1.2 1.2.8.7.11.5 Season Fuel Delivery - 5k Fuel Tanks (USAP) Not Started C 6 1 1d 11/20/25 11/20/25 11/20/25 8:00 AM 11/20/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.11.5 1 1880 Season Fuel Delivery - 5k Fuel Tanks (USAP)
1882 1.2 1.2.8.7.11.6 Survey Support for As-Built Drawing (USAP) Not Started C 6 1 6d 01/15/25 01/22/25 01/15/25 8:00 AM 01/22/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.11.6 1 1881 Survey Support for As-Built Drawing (USAP)
1883 1.2 1.2.8.7.12 ICU Field Team Redeployed Not Started C 5 1 1 0 02/03/26 02/03/26 02/03/26 4:59 PM 02/03/26 4:59 PM 1872, 1860, 1856, 1868FS +1d 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.12 1 1882 ICU Field Team Redeployed
1884 1.2 1.2.8.7.13 On-Ice Labor (FS3) Not Started C 5 1 64d 10/31/25 02/02/26 10/31/25 8:00 AM 02/02/26 4:59 PM 1868FF 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.13 1 1883 On-Ice Labor (FS3)
1885 1.2 1.2.8.7.14 NPX Activities Complete (FS3 Season) Not Started C 5 1 1 0 02/02/26 02/02/26 02/02/26 4:59 PM 02/02/26 4:59 PM 1868 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.8.7.14 1 1884 NPX Activities Complete (FS3 Season)
1886 1.2 1.2.9 Installation - Off-ice Should have Started P 3 1 864d 11/01/21 02/28/25 11/01/21 8:00 AM 02/28/25 4:59 PM 31.46% 0% Red $0.00 $0.00 $47,524.72 $151,083.63 31% delia.tosi@icecube.wisc.edu 1.2.9 1 1885 Installation - Off-ice
1887 1.2 1.2.9.1 Sensor Handling & Testing: Process & Equipment Should have Started P 4 1 656d 01/02/22 07/10/24 01/02/22 8:00 AM 07/10/24 4:59 PM 14.11% 0% Yellow $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.1 1 1886 Sensor Handling & Testing: Process & Equipment
1888 1.2 1.2.9.1.1 Finalize Sensor Handling Process Should have Started C 5 1 30d 01/02/22 02/10/22 01/02/22 8:00 AM 02/10/22 4:59 PM 74.30% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.1.1 1 1887 Finalize Sensor Handling Process
1889 1.2 1.2.9.1.2 South Pole Acceptance Testing (SPAT) Ready to be shipped from UW Not Started C 5 1 1 0 07/10/24 07/10/24 07/10/24 4:59 PM 07/10/24 4:59 PM 3415FS +7d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.1.2 1 1888 South Pole Acceptance Testing (SPAT) Ready to be shipped from UW
1890 1.2 1.2.9.1.3 Sensor Handling Equipment Not Started P 5 1 46d 08/15/22 10/17/22 08/15/22 8:00 AM 10/17/22 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.1.3 1 1889 Sensor Handling Equipment
1891 1.2 1.2.9.1.3.1 Spec Sensor Handling Equipment Not Started C 6 1 24d 08/15/22 09/15/22 08/15/22 8:00 AM 09/15/22 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Eng 1.2.9.1.3.1 1 1890 Spec Sensor Handling Equipment
1892 1.2 1.2.9.1.3.2 Procure Sensor Handling Equipment Not Started C 6 1 20d 09/16/22 10/13/22 09/16/22 8:00 AM 10/13/22 4:59 PM 1890 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.1.3.2 1 1891 Procure Sensor Handling Equipment
1893 1.2 1.2.9.1.3.3 Procure ESD Mitigation Equipment Not Started C 6 1 20d 09/20/22 10/17/22 09/20/22 8:00 AM 10/17/22 4:59 PM 1891SS +2d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.1.3.3 1 1892 Procure ESD Mitigation Equipment
1894 1.2 1.2.9.1.4 Sensor Handling Facility Should have Started P 5 1 168d 01/15/22 09/06/22 01/15/22 8:00 AM 09/06/22 4:59 PM 10.35% 0% Yellow $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.1.4 1 1893 Sensor Handling Facility
1895 1.2 1.2.9.1.4.1 Finalize Sensor Handling Facility Design Should have Started C 6 1 20d 01/15/22 02/10/22 01/15/22 8:00 AM 02/10/22 4:59 PM 62.10% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Eng, PSL drafter, Installation Lead 1.2.9.1.4.1 1 1894 Finalize Sensor Handling Facility Design
1896 1.2 1.2.9.1.4.2 Sensor Handling Facility Design Review Not Started C 6 1 1d 02/15/22 02/15/22 02/15/22 8:00 AM 02/15/22 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Eng, Installation Lead 1.2.9.1.4.2 1 1895 Sensor Handling Facility Design Review
1897 1.2 1.2.9.1.4.3 Sensor Handling Facility Design Complete Not Started C 6 1 1 0 02/24/22 02/24/22 02/24/22 4:59 PM 02/24/22 4:59 PM 1895FS +7d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.1.4.3 1 1896 Sensor Handling Facility Design Complete
1898 1.2 1.2.9.1.4.4 Procure Sensor Handling Facility Materials (or Administer Subcontract) Not Started C 6 1 60d 02/16/22 05/10/22 02/16/22 8:00 AM 05/10/22 4:59 PM 1895 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Eng, Installation Lead 1.2.9.1.4.4 1 1897 Procure Sensor Handling Facility Materials (or Administer Subcontract)
1899 1.2 1.2.9.1.4.5 Fabricate and Assemble Sensor Handling Structure at PSL and Verify Function Not Started C 6 1 75d 05/11/22 08/23/22 05/11/22 8:00 AM 08/23/22 4:59 PM 1897 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Tech, PSL Eng, Installation Lead 1.2.9.1.4.5 1 1898 Fabricate and Assemble Sensor Handling Structure at PSL and Verify Function
1900 1.2 1.2.9.1.4.6 Disassemble Sensor Handling Structure Marking for Reassembly Not Started C 6 1 7d 08/29/22 09/06/22 08/29/22 8:00 AM 09/06/22 4:59 PM 1898FS +3d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Tech, Installation Lead 1.2.9.1.4.6 1 1899 Disassemble Sensor Handling Structure Marking for Reassembly
1901 1.2 1.2.9.1.5 Sensor Sleds Not Started P 5 1 79d 02/11/22 06/01/22 02/11/22 8:00 AM 06/01/22 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.1.5 1 1900 Sensor Sleds
1902 1.2 1.2.9.1.5.1 Finalize Sensor Sled Design in Collaboration with USAP Contractor Not Started C 6 1 79d 02/11/22 06/01/22 02/11/22 8:00 AM 06/01/22 4:59 PM 1887 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.1.5.1 1 1901 Finalize Sensor Sled Design in Collaboration with USAP Contractor
1903 1.2 1.2.9.1.5.2 Sensor Sled Design Complete Not Started C 6 1 1 0 06/01/22 06/01/22 06/01/22 4:59 PM 06/01/22 4:59 PM 1901 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.1.5.2 1 1902 Sensor Sled Design Complete
1904 1.2 1.2.9.1.6 Sensor Testing Tent Not Started P 5 1 79d 02/11/22 06/01/22 02/11/22 8:00 AM 06/01/22 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.1.6 1 1903 Sensor Testing Tent
1905 1.2 1.2.9.1.6.1 Coordinate with USAP Contractor on Requirements, Tent Availability, and Sensor Staging Site Not Started C 6 1 79d 02/11/22 06/01/22 02/11/22 8:00 AM 06/01/22 4:59 PM 1887 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.1.6.1 1 1904 Coordinate with USAP Contractor on Requirements, Tent Availability, and Sensor Staging Site
1906 1.2 1.2.9.2 Rigging Hardware for String Installation Started P 4 1 427d 11/01/21 06/20/23 11/01/21 8:00 AM 06/20/23 4:59 PM 3.05% 2.00% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.2 1 1905 Rigging Hardware for String Installation
1907 1.2 1.2.9.2.1 Procure Installation Hardware Samples Should have Started C 5 1 196d 11/01/21 08/01/22 11/01/21 8:00 AM 08/01/22 4:59 PM 33.53% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.2.1 1 1906 Procure Installation Hardware Samples
1908 1.2 1.2.9.2.2 Preliminary Installation Hardware Sample Test Started C 5 1 67d 03/01/22 06/01/22 03/01/22 8:00 AM 06/01/22 4:59 PM 0.00% 17.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.2.2 1 1907 Preliminary Installation Hardware Sample Test
1909 1.2 1.2.9.2.3 Preliminary Installation Procedure Draft Not Started C 5 1 120d 03/01/22 08/15/22 03/01/22 8:00 AM 08/15/22 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.2.3 1 1908 Preliminary Installation Procedure Draft
1910 1.2 1.2.9.2.4 Preliminary Installation Procedure Test Not Started C 5 1 97d 04/01/22 08/15/22 04/01/22 8:00 AM 08/15/22 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead, PLS Eng, PSL Tech 1.2.9.2.4 1 1909 Preliminary Installation Procedure Test
1911 1.2 1.2.9.2.5 Installation Hardware and Procedure Review Started C 5 1 1d 09/15/22 09/15/22 09/15/22 8:00 AM 09/15/22 4:59 PM 0.00% 5% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.2.5 1 1910 Installation Hardware and Procedure Review
1912 1.2 1.2.9.2.6 Finalize Installation Hardware and Procedure Started C 5 1 21d 09/16/22 10/14/22 09/16/22 8:00 AM 10/14/22 4:59 PM 1910 0.00% 5% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.2.6 1 1911 Finalize Installation Hardware and Procedure
1913 1.2 1.2.9.2.7 Installation Hardware and Procedure Finalized Started C 5 1 1 0 10/14/22 10/14/22 10/14/22 4:59 PM 10/14/22 4:59 PM 1911 0.00% 5% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.2.7 1 1912 Installation Hardware and Procedure Finalized
1914 1.2 1.2.9.2.8 Procure Installation Hardware Started C 5 1 62d 11/04/22 01/30/23 11/04/22 8:00 AM 01/30/23 4:59 PM 1912FS +14d 0.00% 5% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.2.8 1 1913 Procure Installation Hardware
1915 1.2 1.2.9.2.9 Procure Installation Weights Not Started C 5 1 44d 11/04/22 01/04/23 11/04/22 8:00 AM 01/04/23 4:59 PM 1912FS +14d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.2.9 1 1914 Procure Installation Weights
1916 1.2 1.2.9.2.10 Receive, & Inspect Installation Materials Not Started C 5 1 20d 03/01/23 03/28/23 03/01/23 8:00 AM 03/28/23 4:59 PM 1914SS +83d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.2.10 1 1915 Receive, & Inspect Installation Materials
1917 1.2 1.2.9.2.11 Assemble Installation Kits Not Started C 5 1 60d 03/29/23 06/20/23 03/29/23 8:00 AM 06/20/23 4:59 PM 1915 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.2.11 1 1916 Assemble Installation Kits
1918 1.2 1.2.9.3 Installation Monitor Equipment: Depth Monitor & Handheld Connectivity Testers Not Started P 4 1 652d 04/01/22 10/03/24 04/01/22 8:00 AM 10/03/24 4:59 PM 31% 0% Red $0.00 $0.00 $47,524.72 $151,083.63 31% delia.tosi@icecube.wisc.edu 1.2.9.3 1 1917 Installation Monitor Equipment: Depth Monitor & Handheld Connectivity Testers
1919 1.2 1.2.9.3.1 IME TOS Connectivity Tester Not Started P 5 1 545d 06/01/22 07/05/24 06/01/22 8:00 AM 07/05/24 4:59 PM 0.16666667 0% Yellow $8,564.74 $51,388.43 $8,564.74 $51,388.43 17% delia.tosi@icecube.wisc.edu PSL Engineer, WIPAC Engineer 1.2.9.3.1 1 1918 IME TOS Connectivity Tester
1920 1.2 1.2.9.3.1.1 IME TOS Connectivity Tester Design & Initial Procurement for Prototype (2021-22) Not Started C 6 1 88d 06/01/22 09/30/22 06/01/22 8:00 AM 09/30/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Engineer, WIPAC Engineer 1.2.9.3.1.1 1 1919 IME TOS Connectivity Tester Design & Initial Procurement for Prototype (2021-22)
1921 1.2 1.2.9.3.1.2 IME TOS Connectivity Tester Development and System Integration (2022-23) Not Started C 6 1 261d 10/03/22 10/02/23 10/03/22 8:00 AM 10/02/23 4:59 PM 1919 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Engineer, WIPAC Engineer 1.2.9.3.1.2 1 1920 IME TOS Connectivity Tester Development and System Integration (2022-23)
1922 1.2 1.2.9.3.1.3 IME TOS Connectivity Tester Final Procurement and System Integration (2023-24) Not Started C 6 1 457d 10/03/22 07/05/24 10/03/22 8:00 AM 07/05/24 4:59 PM 1920SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Engineer, WIPAC Engineer PSL Engineering support for integration with the DCC - 20k for slip ring module for DOM connectivity, 4 k for hand held devices 1.2.9.3.1.3 1 1921 IME TOS Connectivity Tester Final Procurement and System Integration (2023-24)
1923 1.2 1.2.9.3.1.4 IME TOS Connectivity Tester Fabrication Complete Not Started C 6 1 1 0 07/05/24 07/05/24 07/05/24 4:59 PM 07/05/24 4:59 PM 1921 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.3.1.4 1 1922 IME TOS Connectivity Tester Fabrication Complete
1924 1.2 1.2.9.3.2 IME ICL Quad Connectivity Tester Design, Prototype, Production (2023-24) Not Started P 5 1 262d 10/01/23 10/03/24 10/01/23 8:00 AM 10/03/24 4:59 PM 0 0% Green $0.00 $2,879.96 $0.00 $2,879.96 0% delia.tosi@icecube.wisc.edu WIPAC Engineer LoE 1.2.9.3.2 1 1923 IME ICL Quad Connectivity Tester Design, Prototype, Production (2023-24)
1925 1.2 1.2.9.3.2.1 IME ICL Quad Connectivity Tester Design, Prototype, Production (2023-24) Not Started C 6 1 262d 10/01/23 10/03/24 10/01/23 8:00 AM 10/03/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu WIPAC Engineer LoE 1.2.9.3.2.1 1 1924 IME ICL Quad Connectivity Tester Design, Prototype, Production (2023-24)
1926 1.2 1.2.9.3.2.2 IME ICL Quad Connectivity Tester Fabrication Complete Not Started C 6 1 1 0 10/03/24 10/03/24 10/03/24 4:59 PM 10/03/24 4:59 PM 1924 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.3.2.2 1 1925 IME ICL Quad Connectivity Tester Fabrication Complete
1927 1.2 1.2.9.3.3 IME Depth Readout Not Started P 5 1 587d 04/01/22 07/04/24 04/01/22 8:00 AM 07/04/24 4:59 PM 0.40241581 0% Red $38,959.99 $96,815.25 $38,959.99 $96,815.25 40% delia.tosi@icecube.wisc.edu PSL Engineer 1.2.9.3.3 1 1926 IME Depth Readout
1928 1.2 1.2.9.3.3.1 IME Depth Readout Design & Initial Procurement for Prototype (2021-22) Not Started C 6 1 131d 04/01/22 09/30/22 04/01/22 8:00 AM 09/30/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Engineer 1.2.9.3.3.1 1 1927 IME Depth Readout Design & Initial Procurement for Prototype (2021-22)
1929 1.2 1.2.9.3.3.2 IME Depth Readout Development and System Integration (2022-23) Not Started C 6 1 261d 10/03/22 10/02/23 10/03/22 8:00 AM 10/02/23 4:59 PM 1927 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Engineer 1.2.9.3.3.2 1 1928 IME Depth Readout Development and System Integration (2022-23)
1930 1.2 1.2.9.3.3.3 IME Depth Readout System Final Integration (2023-24) Not Started C 6 1 197d 10/01/23 07/04/24 10/01/23 8:00 AM 07/04/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu PSL Engineer PSL Engineering support for integration with the DCC - 20k for slip ring module for DOM connectivity, 4 k for hand held devices 1.2.9.3.3.3 1 1929 IME Depth Readout System Final Integration (2023-24)
1931 1.2 1.2.9.3.3.4 IME Depth Readout Fabrication Complete Not Started C 6 1 1 0 07/04/24 07/04/24 07/04/24 4:59 PM 07/04/24 4:59 PM 1929 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.3.3.4 1 1930 IME Depth Readout Fabrication Complete
1932 1.2 1.2.9.3.3.5 Define Pressure Sensor Requirements Not Started C 6 1 20d 04/01/22 04/28/22 04/01/22 8:00 AM 04/28/22 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.3.3.5 1 1931 Define Pressure Sensor Requirements
1933 1.2 1.2.9.3.3.6 Procure Pressure Sensor Sample Not Started C 6 1 15d 04/29/22 05/19/22 04/29/22 8:00 AM 05/19/22 4:59 PM 1931 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.3.3.6 1 1932 Procure Pressure Sensor Sample
1934 1.2 1.2.9.3.3.7 Procure Pressure Sensors Not Started C 6 1 60d 02/01/24 04/24/24 02/01/24 8:00 AM 04/24/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.3.3.7 1 1933 Procure Pressure Sensors
1935 1.2 1.2.9.3.3.8 Pressure Sensors Received Not Started C 6 1 1 0 05/22/24 05/22/24 05/22/24 4:59 PM 05/22/24 4:59 PM 1933FS +20d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.3.3.8 1 1934 Pressure Sensors Received
1936 1.2 1.2.9.4 Logging & Calibration Support Not Started P 4 1 627d 03/01/22 07/29/24 03/01/22 8:00 AM 07/29/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.4 1 1935 Logging & Calibration Support
1937 1.2 1.2.9.4.1 Logging Coordination Not Started P 5 1 176d 03/01/22 11/01/22 03/01/22 8:00 AM 11/01/22 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.4.1 1 1936 Logging Coordination
1938 1.2 1.2.9.4.1.1 Coordinate IDP Winch Loan or Winch Procurement Not Started C 6 1 154d 03/01/22 09/30/22 03/01/22 8:00 AM 09/30/22 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.4.1.1 1 1937 Coordinate IDP Winch Loan or Winch Procurement
1939 1.2 1.2.9.4.1.2 IDP Winch Loan Secured Not Started C 6 1 1 0 09/30/22 09/30/22 09/30/22 4:59 PM 09/30/22 4:59 PM 1937 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.4.1.2 1 1938 IDP Winch Loan Secured
1940 1.2 1.2.9.4.1.3 Coordinate Winch Training Not Started C 6 1 22d 10/03/22 11/01/22 10/03/22 8:00 AM 11/01/22 4:59 PM 1938 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.4.1.3 1 1939 Coordinate Winch Training
1941 1.2 1.2.9.4.2 Logbook & Geometry Support Not Started P 5 1 141d 01/15/24 07/29/24 01/15/24 8:00 AM 07/29/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.9.4.2 1 1940 Logbook & Geometry Support
1942 1.2 1.2.9.4.2.1 Define Logbook Requirements Not Started C 6 1 22d 01/15/24 02/13/24 01/15/24 8:00 AM 02/13/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.4.2.1 1 1941 Define Logbook Requirements
1943 1.2 1.2.9.4.2.2 Develop Logbook Not Started C 6 1 60d 04/17/24 07/09/24 04/17/24 8:00 AM 07/09/24 4:59 PM 1941FS +45d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.4.2.2 1 1942 Develop Logbook
1944 1.2 1.2.9.4.2.3 Procure Logbook Tablets Not Started C 6 1 60d 04/17/24 07/09/24 04/17/24 8:00 AM 07/09/24 4:59 PM 1942SS 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.4.2.3 1 1943 Procure Logbook Tablets
1945 1.2 1.2.9.4.2.4 Logbook Complete Not Started C 6 1 1 0 07/29/24 07/29/24 07/29/24 4:59 PM 07/29/24 4:59 PM 1942FS +14d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.4.2.4 1 1944 Logbook Complete
1946 1.2 1.2.9.4.2.5 Procure Laser Rangers, Tape Measures, Shop Lights, Helmets for Installation Not Started C 6 1 90d 02/01/24 06/05/24 02/01/24 8:00 AM 06/05/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.4.2.5 1 1945 Procure Laser Rangers, Tape Measures, Shop Lights, Helmets for Installation
1947 1.2 1.2.9.5 Develop Installation Training Package Not Started C 4 1 33d 01/15/25 02/28/25 01/15/25 8:00 AM 02/28/25 4:59 PM 0.00% 0% Green Tosi LoE $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.9.5 1 1946 Develop Installation Training Package
1948 1.2 1.2.10 Installation Field Seasons - Antarctica Not Started P 3 1 962d 06/01/22 02/18/26 06/01/22 8:00 AM 02/18/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10 1 1947 Installation Field Seasons - Antarctica
1949 1.2 1.2.10.1 Seasonal Staffing & Training, Off-Ice Coordination Not Started P 4 1 565d 06/07/23 08/13/25 06/07/23 8:00 AM 08/13/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.1 1 1948 Seasonal Staffing & Training, Off-Ice Coordination
1950 1.2 1.2.10.1.1 FS1 Off-Ice Installation Training (Installers, including alternates) - Place Holder Not Started C 5 1 5d 06/07/23 06/13/23 06/07/23 8:00 AM 06/13/23 4:59 PM 995SS +5d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.1.1 1 1949 FS1 Off-Ice Installation Training (Installers, including alternates) - Place Holder
1951 1.2 1.2.10.1.2 FS2 Off-Ice Installation Training (Installers, including alternates) Not Started C 5 1 5d 06/07/24 06/13/24 06/07/24 8:00 AM 06/13/24 4:59 PM 996SS +5d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.1.2 1 1950 FS2 Off-Ice Installation Training (Installers, including alternates)
1952 1.2 1.2.10.1.3 FS3 Off-Ice Installation Training (Drillers, Installers, Management, including alternates) Not Started C 5 1 8d 08/04/25 08/13/25 08/04/25 8:00 AM 08/13/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.1.3 1 1951 FS3 Off-Ice Installation Training (Drillers, Installers, Management, including alternates)
1953 1.2 1.2.10.1.4 FS3 Off-Ice Logging Winch Training (Installation Manager) Not Started C 5 1 1d 05/27/25 05/27/25 05/27/25 8:00 AM 05/27/25 4:59 PM 997SS -1d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.10.1.4 1 1952 FS3 Off-Ice Logging Winch Training (Installation Manager)
1954 1.2 1.2.10.2 USAP Field Season 0 (FY23) Not Started P 4 1 186d 06/01/22 02/15/23 06/01/22 8:00 AM 02/15/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.2 1 1953 USAP Field Season 0 (FY23)
1955 1.2 1.2.10.2.1 Installation Team FS0 Arrives (Placeholder) Not Started C 5 1 1 0 11/15/22 11/15/22 11/15/22 8:00 AM 11/15/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.2.1 1 1954 Installation Team FS0 Arrives (Placeholder)
1956 1.2 1.2.10.2.2 PQ, ECW, Deployment Travel Costs Installation Team FS0 (Placeholder) Not Started C 5 1 186d 06/01/22 02/15/23 06/01/22 8:00 AM 02/15/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.2.2 1 1955 PQ, ECW, Deployment Travel Costs Installation Team FS0 (Placeholder)
1957 1.2 1.2.10.2.3 Cargo Movements (USAP) Not Started P 5 1 5d 02/06/23 02/10/23 02/06/23 8:00 AM 02/10/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.2.3 1 1956 Cargo Movements (USAP)
1958 1.2 1.2.10.2.3.1 Pole (USAP) PlaceHolder Not Started C 6 1 1 0 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.2.3.1 1 1957 Pole (USAP) PlaceHolder
1959 1.2 1.2.10.2.3.2 MCM (USAP) Not Started P 6 1 1 0 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.2.3.2 1 1958 MCM (USAP)
1960 1.2 1.2.10.2.3.2.1 MCM SAAM - ComSur (USAP) Not Started P 7 1 1 0 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.2.3.2.1 1 1959 MCM SAAM - ComSur (USAP)
1961 1.2 1.2.10.2.3.2.1.1 MCM SAAM - ComSur (USAP) Not Started C 8 1 1 0 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.2.3.2.1.1 1 1960 MCM SAAM - ComSur (USAP)
1962 1.2 1.2.10.2.3.2.2 Vessel FY23 (USAP) Not Started P 7 1 1 0 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.2.3.2.2 1 1961 Vessel FY23 (USAP)
1963 1.2 1.2.10.2.3.2.2.1 Surface Cables Assemblies (SCAs) Arrive (USAP) Not Started C 8 1 1 0 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.10.2.3.2.2.1 1 1962 Surface Cables Assemblies (SCAs) Arrive (USAP)
1964 1.2 1.2.10.2.3.2.2.2 SJBs Arrive (USAP) Not Started C 8 1 1 0 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.10.2.3.2.2.2 1 1963 SJBs Arrive (USAP)
1965 1.2 1.2.10.2.3.2.2.3 Sensor Handling Facility Arrives (USAP) Not Started C 8 1 1 0 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.10.2.3.2.2.3 1 1964 Sensor Handling Facility Arrives (USAP)
1966 1.2 1.2.10.2.3.3 Retrograde (USAP) Not Started C 6 1 1d 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.2.3.3 1 1965 Retrograde (USAP)
1967 1.2 1.2.10.2.3.4 Cargo Storage Support Pole & MCM (USAP) Not Started C 6 1 5d 02/06/23 02/10/23 02/06/23 8:00 AM 02/10/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.2.3.4 1 1966 Cargo Storage Support Pole & MCM (USAP)
1968 1.2 1.2.10.3 USAP Field Season 1 (FY24) Not Started P 4 1 269d 02/06/23 02/20/24 02/06/23 8:00 AM 02/20/24 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3 1 1967 USAP Field Season 1 (FY24)
1969 1.2 1.2.10.3.1 Installation Team FS1 Arrives (Placeholder) Not Started C 5 1 1 0 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3.1 1 1968 Installation Team FS1 Arrives (Placeholder)
1970 1.2 1.2.10.3.2 PQ, ECW, Deployment Travel Costs Installation Team FS1 (Placeholder) Not Started C 5 1 1 0 02/06/23 02/06/23 02/06/23 8:00 AM 02/06/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3.2 1 1969 PQ, ECW, Deployment Travel Costs Installation Team FS1 (Placeholder)
1971 1.2 1.2.10.3.3 Cargo Movements (USAP) Not Started P 5 1 67d 11/15/23 02/20/24 11/15/23 8:00 AM 02/20/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.3.3 1 1970 Cargo Movements (USAP)
1972 1.2 1.2.10.3.3.1 Pole (USAP) Not Started P 6 1 67d 11/15/23 02/20/24 11/15/23 8:00 AM 02/20/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.3.3.1 1 1971 Pole (USAP)
1973 1.2 1.2.10.3.3.1.1 SPoT 1 Not Started P 7 1 1 0 12/01/23 12/01/23 12/01/23 8:00 AM 12/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3.3.1.1 1 1972 SPoT 1
1974 1.2 1.2.10.3.3.1.1.1 Sensor Handling Facility Arrives - Pole (USAP) Not Started C 8 1 1 0 12/01/23 12/01/23 12/01/23 8:00 AM 12/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.3.3.1.1.1 1 1973 Sensor Handling Facility Arrives - Pole (USAP)
1975 1.2 1.2.10.3.3.1.1.2 SJBs Arrive - Pole (USAP) Not Started C 8 1 1 0 12/01/23 12/01/23 12/01/23 8:00 AM 12/01/23 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.3.3.1.1.2 1 1974 SJBs Arrive - Pole (USAP)
1976 1.2 1.2.10.3.3.1.2 SPoT 2 Not Started P 7 1 1 0 01/01/24 01/01/24 01/01/24 8:00 AM 01/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3.3.1.2 1 1975 SPoT 2
1977 1.2 1.2.10.3.3.1.2.1 Placeholder Not Started C 8 1 1 0 01/01/24 01/01/24 01/01/24 8:00 AM 01/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3.3.1.2.1 1 1976 Placeholder
1978 1.2 1.2.10.3.3.1.3 SPoT 3 Not Started P 7 1 1 0 02/01/24 02/01/24 02/01/24 8:00 AM 02/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3.3.1.3 1 1977 SPoT 3
1979 1.2 1.2.10.3.3.1.3.1 Placeholder Not Started C 8 1 1 0 02/01/24 02/01/24 02/01/24 8:00 AM 02/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3.3.1.3.1 1 1978 Placeholder
1980 1.2 1.2.10.3.3.1.4 LC-130 Not Started P 7 1 67d 11/15/23 02/20/24 11/15/23 8:00 AM 02/20/24 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3.3.1.4 1 1979 LC-130
1981 1.2 1.2.10.3.3.1.4.1 Placeholder Not Started C 8 1 67d 11/15/23 02/20/24 11/15/23 8:00 AM 02/20/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3.3.1.4.1 1 1980 Placeholder
1982 1.2 1.2.10.3.3.2 MCM (USAP) Not Started P 6 1 3d 02/06/24 02/08/24 02/06/24 8:00 AM 02/08/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.3.3.2 1 1981 MCM (USAP)
1983 1.2 1.2.10.3.3.2.1 MCM SAAM - ComSur (USAP) Not Started P 7 1 1d 02/08/24 02/08/24 02/08/24 8:00 AM 02/08/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3.3.2.1 1 1982 MCM SAAM - ComSur (USAP)
1984 1.2 1.2.10.3.3.2.1.1 Placeholder Not Started C 8 1 1 1d 02/08/24 02/08/24 02/08/24 8:00 AM 02/08/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.3.3.2.1.1 1 1983 Placeholder
1985 1.2 1.2.10.3.3.2.2 Vessel (USAP) Not Started P 7 1 1 0 02/06/24 02/06/24 02/06/24 8:00 AM 02/06/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.3.3.2.2 1 1984 Vessel (USAP)
1986 1.2 1.2.10.3.3.2.2.1 Installation Weights Arrive - MCM (USAP) Not Started C 8 1 1 0 02/06/24 02/06/24 02/06/24 8:00 AM 02/06/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.10.3.3.2.2.1 1 1985 Installation Weights Arrive - MCM (USAP)
1987 1.2 1.2.10.3.3.2.2.2 Installation Kits Arrive - MCM (USAP) Not Started C 8 1 1 0 02/06/24 02/06/24 02/06/24 8:00 AM 02/06/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen USAP Support 1.2.10.3.3.2.2.2 1 1986 Installation Kits Arrive - MCM (USAP)
1988 1.2 1.2.10.3.3.3 Retrograde (USAP) Not Started P 6 1 1d 02/09/24 02/09/24 02/09/24 8:00 AM 02/09/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.3.3.3 1 1987 Retrograde (USAP)
1989 1.2 1.2.10.3.3.3.1 Placeholder Not Started C 7 1 1 1d 02/09/24 02/09/24 02/09/24 8:00 AM 02/09/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.3.3.3.1 1 1988 Placeholder
1990 1.2 1.2.10.3.3.4 Cargo Storage Support Pole & MCM (USAP) Not Started C 6 1 4d 12/01/23 12/06/23 12/01/23 8:00 AM 12/06/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Installation Lead 1.2.10.3.3.4 1 1989 Cargo Storage Support Pole & MCM (USAP)
1991 1.2 1.2.10.4 USAP Field Season 2 (FY25) Not Started P 4 1 186d 06/01/24 02/19/25 06/01/24 8:00 AM 02/19/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4 1 1990 USAP Field Season 2 (FY25)
1992 1.2 1.2.10.4.1 Installation Team FS2 Arrives (Headcount 1) Not Started C 5 1 1 0 12/10/24 12/10/24 12/10/24 8:00 AM 12/10/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.1 1 1991 Installation Team FS2 Arrives (Headcount 1)
1993 1.2 1.2.10.4.2 PQ, ECW, Deployment Travel Costs Installation Team FS2 (Headcount 1) Not Started C 5 1 186d 06/01/24 02/19/25 06/01/24 8:00 AM 02/19/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.2 1 1992 PQ, ECW, Deployment Travel Costs Installation Team FS2 (Headcount 1)
1994 1.2 1.2.10.4.3 Cargo Movements (USAP) Not Started P 5 1 75d 11/01/24 02/18/25 11/01/24 8:00 AM 02/18/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.3 1 1993 Cargo Movements (USAP)
1995 1.2 1.2.10.4.3.1 Pole (USAP) Not Started P 6 1 54d 12/01/24 02/15/25 12/01/24 8:00 AM 02/15/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.4.3.1 1 1994 Pole (USAP)
1996 1.2 1.2.10.4.3.1.1 LC-130 (USAP) Not Started P 7 1 54d 12/01/24 02/15/25 12/01/24 8:00 AM 02/15/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.3.1.1 1 1995 LC-130 (USAP)
1997 1.2 1.2.10.4.3.1.1.1 ICL Power and Timing Electronics Arrive - Pole (USAP) Not Started C 8 1 1 0 12/01/24 12/01/24 12/01/24 8:00 AM 12/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.1 1 1996 ICL Power and Timing Electronics Arrive - Pole (USAP)
1998 1.2 1.2.10.4.3.1.1.2 ICL Patch Cables and Patch Panels Arrive - Pole (USAP) Not Started C 8 1 1 0 12/01/24 12/01/24 12/01/24 8:00 AM 12/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.2 1 1997 ICL Patch Cables and Patch Panels Arrive - Pole (USAP)
1999 1.2 1.2.10.4.3.1.1.3 Field Hub Electronics - Pole (USAP) Not Started C 8 1 1 0 12/01/24 12/01/24 12/01/24 8:00 AM 12/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.3 1 1998 Field Hub Electronics - Pole (USAP)
2000 1.2 1.2.10.4.3.1.1.4 Science Crate SF2 (SPAT, IME, Pressure Sensors, Laser Rangers) Equipment Arrives - Pole (USAP) Not Started C 8 1 1 0 12/01/24 12/01/24 12/01/24 8:00 AM 12/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.4 1 1999 Science Crate SF2 (SPAT, IME, Pressure Sensors, Laser Rangers) Equipment Arrives - Pole (USAP)
2001 1.2 1.2.10.4.3.1.1.5 String 87 & 88 Sensors Arrive (D-Eggs from Japan, mDOMs from Germany) - Pole (USAP) Not Started C 8 1 1 0 12/15/24 12/15/24 12/15/24 8:00 AM 12/15/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.5 1 2000 String 87 & 88 Sensors Arrive (D-Eggs from Japan, mDOMs from Germany) - Pole (USAP)
2002 1.2 1.2.10.4.3.1.1.6 String 87 & 88 Calibration Devices Arrive (Europe, USA) - Pole (USAP) Not Started C 8 1 1 0 12/15/24 12/15/24 12/15/24 8:00 AM 12/15/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.6 1 2001 String 87 & 88 Calibration Devices Arrive (Europe, USA) - Pole (USAP)
2003 1.2 1.2.10.4.3.1.1.7 String 87 & 88 Special Devices Arrive (Europe, USA) - Pole (USAP) Not Started C 8 1 1 0 12/15/24 12/15/24 12/15/24 8:00 AM 12/15/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.7 1 2002 String 87 & 88 Special Devices Arrive (Europe, USA) - Pole (USAP)
2004 1.2 1.2.10.4.3.1.1.8 String 87 & 88 BCAs Arrive - Pole (USAP) Not Started C 8 1 1 0 02/15/25 02/15/25 02/15/25 8:00 AM 02/15/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.8 1 2003 String 87 & 88 BCAs Arrive - Pole (USAP)
2005 1.2 1.2.10.4.3.1.2 SPOT 1 (USAP) Not Started P 7 1 1 0 12/01/24 12/01/24 12/01/24 8:00 AM 12/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.3.1.2 1 2004 SPOT 1 (USAP)
2006 1.2 1.2.10.4.3.1.2.1 SCA x7 Arrive - Pole (USAP) Not Started C 8 1 1 0 12/01/24 12/01/24 12/01/24 8:00 AM 12/01/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.2.1 1 2005 SCA x7 Arrive - Pole (USAP)
2007 1.2 1.2.10.4.3.1.3 SPOT 2 (USAP) Not Started P 7 1 1 0 01/01/25 01/01/25 01/01/25 8:00 AM 01/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.3.1.3 1 2006 SPOT 2 (USAP)
2008 1.2 1.2.10.4.3.1.3.1 Installation Kits Arrive - Pole (USAP) Not Started C 8 1 1 0 01/01/25 01/01/25 01/01/25 8:00 AM 01/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.3.1 1 2007 Installation Kits Arrive - Pole (USAP)
2009 1.2 1.2.10.4.3.1.3.2 Installation Weights Arrive - Pole (USAP) Not Started C 8 1 1 0 01/01/25 01/01/25 01/01/25 8:00 AM 01/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.3.2 1 2008 Installation Weights Arrive - Pole (USAP)
2010 1.2 1.2.10.4.3.1.4 SPOT 3 (USAP) Not Started P 7 1 1 0 02/01/25 02/01/25 02/01/25 8:00 AM 02/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.3.1.4 1 2009 SPOT 3 (USAP)
2011 1.2 1.2.10.4.3.1.4.1 Placeholder Not Started C 8 1 1 0 02/01/25 02/01/25 02/01/25 8:00 AM 02/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.3.1.4.1 1 2010 Placeholder
2012 1.2 1.2.10.4.3.2 MCM (USAP) Not Started P 6 1 66d 11/01/24 02/06/25 11/01/24 8:00 AM 02/06/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.3.2 1 2011 MCM (USAP)
2013 1.2 1.2.10.4.3.2.1 MCM SAAM - ComSur (USAP) Not Started P 7 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.3.2.1 1 2012 MCM SAAM - ComSur (USAP)
2014 1.2 1.2.10.4.3.1.1.1 ICL Power and Timing Electronics Arrive (USAP) Not Started C 8 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.1 1 2013 ICL Power and Timing Electronics Arrive (USAP)
2015 1.2 1.2.10.4.3.1.1.2 ICL Patch Cables and Patch Panels Arrive (USAP) Not Started C 8 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.2 1 2014 ICL Patch Cables and Patch Panels Arrive (USAP)
2016 1.2 1.2.10.4.3.1.1.3 Field Hub Electronics (USAP) Not Started C 8 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.3 1 2015 Field Hub Electronics (USAP)
2017 1.2 1.2.10.4.3.1.1.4 Science Crate SF2 (SPAT, IME, Pressure Sensors, Laser Rangers) Equipment (USAP) Not Started C 8 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.4 1 2016 Science Crate SF2 (SPAT, IME, Pressure Sensors, Laser Rangers) Equipment (USAP)
2018 1.2 1.2.10.4.3.1.1.5 String 87 & 88 Sensors Arrive (D-Eggs from Japan, mDOMs from Germany) (USAP) Not Started C 8 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.5 1 2017 String 87 & 88 Sensors Arrive (D-Eggs from Japan, mDOMs from Germany) (USAP)
2019 1.2 1.2.10.4.3.1.1.6 String 87 & 88 Calibration Devices Arrive (Europe, USA) (USAP) Not Started C 8 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.6 1 2018 String 87 & 88 Calibration Devices Arrive (Europe, USA) (USAP)
2020 1.2 1.2.10.4.3.1.1.7 String 87 & 88 Special Devices Arrive (Europe, USA) (USAP) Not Started C 8 1 1 0 11/01/24 11/01/24 11/01/24 8:00 AM 11/01/24 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.1.1.7 1 2019 String 87 & 88 Special Devices Arrive (Europe, USA) (USAP)
2021 1.2 1.2.10.4.3.2.2 Vessel (USAP) Not Started P 7 1 1 0 02/06/25 02/06/25 02/06/25 8:00 AM 02/06/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.3.2.2 1 2020 Vessel (USAP)
2022 1.2 1.2.10.4.3.2.2.1 Downhole MCAs - (USAP) Not Started C 8 1 1 0 02/06/25 02/06/25 02/06/25 8:00 AM 02/06/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.2.2.1 1 2021 Downhole MCAs - (USAP)
2023 1.2 1.2.10.4.3.2.2.2 Downhole Load Members ? - (USAP) Not Started C 8 1 1 0 02/06/25 02/06/25 02/06/25 8:00 AM 02/06/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.2.2.2 1 2022 Downhole Load Members ? - (USAP)
2024 1.2 1.2.10.4.3.2.2.3 String 87 & 88 BCAs - (USAP) Not Started C 8 1 1 0 02/06/25 02/06/25 02/06/25 8:00 AM 02/06/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.2.2.3 1 2023 String 87 & 88 BCAs - (USAP)
2025 1.2 1.2.10.4.3.2.2.4 String 89-93 BCAs (USAP) Not Started C 8 1 1 0 02/06/25 02/06/25 02/06/25 8:00 AM 02/06/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.2.2.4 1 2024 String 89-93 BCAs (USAP)
2026 1.2 1.2.10.4.3.3 Retrograde (USAP) Not Started C 6 1 1 0 02/06/25 02/06/25 02/06/25 8:00 AM 02/06/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.3.3 1 2025 Retrograde (USAP)
2027 1.2 1.2.10.4.3.4 Cargo Storage Support Pole & MCM (USAP) Not Started C 6 1 56d 12/01/24 02/18/25 12/01/24 8:00 AM 02/18/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.3.4 1 2026 Cargo Storage Support Pole & MCM (USAP)
2028 1.2 1.2.10.4.4 Sensor Sleds & Tent Not Started P 5 1 17d 12/01/24 12/24/24 12/01/24 8:00 AM 12/24/24 7:59 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.4 1 2027 Sensor Sleds & Tent
2029 1.2 1.2.10.4.4.1 Sensor Sleds Construction/Prep Oversight Not Started C 6 1 5d 12/01/24 12/05/24 12/01/24 8:00 AM 12/05/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.10.4.4.1 1 2028 Sensor Sleds Construction/Prep Oversight
2030 1.2 1.2.10.4.4.2 Sensor Sleds Construction/Prep Support (USAP) Not Started C 6 1 5d 12/02/24 12/06/24 12/02/24 8:00 AM 12/06/24 4:59 PM 2028SS, 2028FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.4.2 1 2029 Sensor Sleds Construction/Prep Support (USAP)
2031 1.2 1.2.10.4.4.3 Sensor Sleds Ready Not Started C 6 1 1 0 12/06/24 12/06/24 12/06/24 4:59 PM 12/06/24 4:59 PM 2029 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.4.3 1 2030 Sensor Sleds Ready
2032 1.2 1.2.10.4.4.4 Sensor Testing Tent Prep Oversight Not Started C 6 1 5d 12/01/24 12/05/24 12/01/24 8:00 AM 12/05/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.10.4.4.4 1 2031 Sensor Testing Tent Prep Oversight
2033 1.2 1.2.10.4.4.5 Sensor Testing Tent Prep Support (USAP) Not Started C 6 1 5d 12/02/24 12/06/24 12/02/24 8:00 AM 12/06/24 4:59 PM 2031SS, 2031FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.4.5 1 2032 Sensor Testing Tent Prep Support (USAP)
2034 1.2 1.2.10.4.4.6 Sensor Testing Tent Ready Not Started C 6 1 1 0 12/06/24 12/06/24 12/06/24 4:59 PM 12/06/24 4:59 PM 2032 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.4.6 1 2033 Sensor Testing Tent Ready
2035 1.2 1.2.10.4.4.7 Setup SPAT in tent Not Started C 6 1 e7d 12/17/24 12/24/24 12/17/24 8:00 AM 12/24/24 7:59 AM 1999FS +1d, 3416FS +1d 0% 0% Green support from 1.6 personnel $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead, 1.6 SPAT SME 1.2.10.4.4.7 1 2034 Setup SPAT in tent
2036 1.2 1.2.10.4.4.8 SPAT ready Not Started C 6 1 1 0 12/24/24 12/24/24 12/24/24 7:59 AM 12/24/24 7:59 AM 2034 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.4.8 1 2035 SPAT ready
2037 1.2 1.2.10.4.5 Sensor Handling Facility Assembly Not Started P 5 1 17d 12/04/24 12/27/24 12/04/24 8:00 AM 12/27/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.5 1 2036 Sensor Handling Facility Assembly
2038 1.2 1.2.10.4.5.1 Sensor Handling Facility Assembly Oversight Not Started C 6 1 14d 12/04/24 12/23/24 12/04/24 8:00 AM 12/23/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.10.4.5.1 1 2037 Sensor Handling Facility Assembly Oversight
2039 1.2 1.2.10.4.5.2 Sensor Handling Facility Assembly - Assemble Skis and Deck, Erect Walls, Construct Walls, Construct Roof (USAP) Not Started C 6 1 14d 12/04/24 12/23/24 12/04/24 8:00 AM 12/23/24 4:59 PM 2037SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.5.2 1 2038 Sensor Handling Facility Assembly - Assemble Skis and Deck, Erect Walls, Construct Walls, Construct Roof (USAP)
2040 1.2 1.2.10.4.5.3 Sensor Handling Facility Assembly Crane Support (USAP) Not Started C 6 1 14d 12/04/24 12/23/24 12/04/24 8:00 AM 12/23/24 4:59 PM 2037SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.5.3 1 2039 Sensor Handling Facility Assembly Crane Support (USAP)
2041 1.2 1.2.10.4.5.4 Sensor Handling Facility Construction Complete Not Started C 6 1 1 0 12/23/24 12/23/24 12/23/24 4:59 PM 12/23/24 4:59 PM 2039, 2038 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.5.4 1 2040 Sensor Handling Facility Construction Complete
2042 1.2 1.2.10.4.5.5 Position Sensor Handling Facility near Tower Not Started C 6 1 1d 12/24/24 12/24/24 12/24/24 8:00 AM 12/24/24 4:59 PM 2040 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.5.5 1 2041 Position Sensor Handling Facility near Tower
2043 1.2 1.2.10.4.5.6 Sensor Handling Dry Run Not Started C 6 1 2d 12/26/24 12/27/24 12/26/24 8:00 AM 12/27/24 4:59 PM 2041 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.5.6 1 2042 Sensor Handling Dry Run
2044 1.2 1.2.10.4.6 String Component Activities Not Started P 5 1 24d 12/15/24 01/20/25 12/15/24 8:00 AM 01/20/25 7:59 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.6 1 2043 String Component Activities
2045 1.2 1.2.10.4.6.1 Receive and Inspect Installation Kits & Weights Shipments Not Started C 6 1 3d 01/02/25 01/06/25 01/02/25 8:00 AM 01/06/25 4:59 PM 2008 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.10.4.6.1 1 2044 Receive and Inspect Installation Kits & Weights Shipments
2046 1.2 1.2.10.4.6.2 Receive and Inspect String 87 & 88 Sensors, Calibration & Special Devices Shipments Not Started C 6 1 e1d 12/15/24 12/16/24 12/15/24 8:00 AM 12/16/24 7:59 AM 2001 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Lead 1.2.10.4.6.2 1 2045 Receive and Inspect String 87 & 88 Sensors, Calibration & Special Devices Shipments
2047 1.2 1.2.10.4.6.3 Load String 87 Sensors on Sleds 1,2 for testing prior to storage Not Started C 6 1 e6h 12/26/24 12/26/24 12/26/24 8:00 AM 12/26/24 1:59 PM 2001FS +1d, 2035FS +1d, 2030FS +1d, 2033FS +1d, 2034 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.6 SPAT SME 1.2.10.4.6.3 1 2046 Load String 87 Sensors on Sleds 1,2 for testing prior to storage
2048 1.2 1.2.10.4.6.4 Load String 87 Sensors on Sleds 1,2 for testing prior to storage (USAP) Not Started C 6 1 e6h 12/26/24 12/26/24 12/26/24 8:00 AM 12/26/24 1:59 PM 2046SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.6 SPAT SME 1.2.10.4.6.4 1 2047 Load String 87 Sensors on Sleds 1,2 for testing prior to storage (USAP)
2049 1.2 1.2.10.4.6.5 Load String 88 Sensors on Sleds 3,4 for testing prior to storage Not Started C 6 1 e6h 12/27/24 12/27/24 12/27/24 2:00 PM 12/27/24 7:59 PM 2035FS +1d, 2030FS +1d, 2033FS +1d, 2047FS +1d 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.6 SPAT SME 1.2.10.4.6.5 1 2048 Load String 88 Sensors on Sleds 3,4 for testing prior to storage
2050 1.2 1.2.10.4.6.6 Load String 88 Sensors on Sleds 3,4 for testing prior to storage (USAP) Not Started C 6 1 e6h 12/27/24 12/27/24 12/27/24 2:00 PM 12/27/24 7:59 PM 2048SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.6 SPAT SME 1.2.10.4.6.6 1 2049 Load String 88 Sensors on Sleds 3,4 for testing prior to storage (USAP)
2051 1.2 1.2.10.4.6.7 Conduct South Pole Acceptance Testing (SPAT) String 87 Not Started C 6 1 e7d 12/26/24 01/02/25 12/26/24 8:00 AM 01/02/25 7:59 AM 2001FS +1d, 2035FS +1d, 2030FS +1d, 2033FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.6 SPAT SME 1.2.10.4.6.7 1 2050 Conduct South Pole Acceptance Testing (SPAT) String 87
2052 1.2 1.2.10.4.6.8 Conduct South Pole Acceptance Testing (SPAT) String 88 Not Started C 6 1 e7d 01/03/25 01/10/25 01/03/25 8:00 AM 01/10/25 7:59 AM 2049FS +1d, 2050FS +1d 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.6 SPAT SME 1.2.10.4.6.8 1 2051 Conduct South Pole Acceptance Testing (SPAT) String 88
2053 1.2 1.2.10.4.6.9 Conduct South Pole Acceptance Testing (SPAT) Special Devices String 87-88 Not Started C 6 1 e7d 01/13/25 01/20/25 01/13/25 8:00 AM 01/20/25 7:59 AM 2051FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.6 SPAT SME 1.2.10.4.6.9 1 2052 Conduct South Pole Acceptance Testing (SPAT) Special Devices String 87-88
2054 1.2 1.2.10.4.6.10 IME deployment and integration Not Started C 6 1 20d 12/18/24 01/16/25 12/18/24 8:00 AM 01/16/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu UW / PSL 1.2.10.4.6.10 1 2053 IME deployment and integration
2055 1.2 1.2.10.4.7 Surface Cable Activities (SJB to ICL) Not Started P 5 1 54d 11/10/24 01/27/25 11/10/24 8:00 AM 01/27/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.7 1 2054 Surface Cable Activities (SJB to ICL)
2056 1.2 1.2.10.4.7.1 Survey Trenches, Surface Junction Boxes and Holes (USAP) Not Started C 6 1 3d 11/10/24 11/12/24 11/10/24 8:00 AM 11/12/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.1 1 2055 Survey Trenches, Surface Junction Boxes and Holes (USAP)
2057 1.2 1.2.10.4.7.2 Prep & Compact Surface Near ICL for Cable Install (USAP) Not Started C 6 1 3d 12/01/24 12/03/24 12/01/24 8:00 AM 12/03/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.2 1 2056 Prep & Compact Surface Near ICL for Cable Install (USAP)
2058 1.2 1.2.10.4.7.3 Open and Modify Tower, Bridge & ICL for Cable Routing (USAP) Not Started C 6 1 4d 12/04/24 12/09/24 12/04/24 8:00 AM 12/09/24 4:59 PM 2056 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.3 1 2057 Open and Modify Tower, Bridge & ICL for Cable Routing (USAP)
2059 1.2 1.2.10.4.7.4 Excavate ICL Tower for Cable Entry & Routing (USAP) Not Started C 6 1 1d 12/10/24 12/10/24 12/10/24 8:00 AM 12/10/24 4:59 PM 2057 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.4 1 2058 Excavate ICL Tower for Cable Entry & Routing (USAP)
2060 1.2 1.2.10.4.7.5 Prep/Uncrate Cable Spools; Load on 953 Loader Not Started C 6 1 7d 12/17/24 12/26/24 12/17/24 8:00 AM 12/26/24 4:59 PM 2058, 3047FS +1d 0% 0% Green support from 1.4 personnel $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Team, 1.4 CPT (Cables, SBJs) 1.2.10.4.7.5 1 2059 Prep/Uncrate Cable Spools; Load on 953 Loader
2061 1.2 1.2.10.4.7.6 Prep/Uncrate Cable Spools; Load on 953 Loader (USAP) Not Started C 6 1 7d 12/11/24 12/19/24 12/11/24 8:00 AM 12/19/24 4:59 PM 2058 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.6 1 2060 Prep/Uncrate Cable Spools; Load on 953 Loader (USAP)
2062 1.2 1.2.10.4.7.7 Install 7 Surface Cables into ICL Tower, Across Bridge, into ICL Not Started C 6 1 7d 12/17/24 12/26/24 12/17/24 8:00 AM 12/26/24 4:59 PM 2059SS 0% 0% Green support from 1.4 personnel $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Team, 1.4 CPT (Cables, SBJs) 1.2.10.4.7.7 1 2061 Install 7 Surface Cables into ICL Tower, Across Bridge, into ICL
2063 1.2 1.2.10.4.7.8 Install 7 Surface Cables into ICL Tower, Across Bridge, into ICL (USAP) Not Started C 6 1 7d 12/17/24 12/26/24 12/17/24 8:00 AM 12/26/24 4:59 PM 2059SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.8 1 2062 Install 7 Surface Cables into ICL Tower, Across Bridge, into ICL (USAP)
2064 1.2 1.2.10.4.7.9 Close ICL Tower Bridge (USAP) Not Started C 6 1 1d 12/30/24 12/30/24 12/30/24 8:00 AM 12/30/24 4:59 PM 2062FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.9 1 2063 Close ICL Tower Bridge (USAP)
2065 1.2 1.2.10.4.7.10 Prep Cables & Attach to Grounding System in ICL Not Started C 6 1 2d 12/27/24 12/30/24 12/27/24 8:00 AM 12/30/24 4:59 PM 2062 0% 0% Green support from 1.4 personnel $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.4 CPT (Cables, SBJs) 1.2.10.4.7.10 1 2064 Prep Cables & Attach to Grounding System in ICL
2066 1.2 1.2.10.4.7.11 Prep Cables & Attach to Grounding System in ICL (USAP) Not Started C 6 1 2d 12/27/24 12/30/24 12/27/24 8:00 AM 12/30/24 4:59 PM 2062 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.11 1 2065 Prep Cables & Attach to Grounding System in ICL (USAP)
2067 1.2 1.2.10.4.7.12 Excavate Surface Junction Box Pits (USAP) Not Started C 6 1 1d 12/10/24 12/10/24 12/10/24 8:00 AM 12/10/24 4:59 PM 2058SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.12 1 2066 Excavate Surface Junction Box Pits (USAP)
2068 1.2 1.2.10.4.7.13 Trench (mechanical) from SJB to ICL Tower (USAP) Not Started C 6 1 2d 12/27/24 12/30/24 12/27/24 8:00 AM 12/30/24 4:59 PM 2061 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.13 1 2067 Trench (mechanical) from SJB to ICL Tower (USAP)
2069 1.2 1.2.10.4.7.14 Unspool & Lay Surface Cables from Tower to SJB Pits Not Started C 6 1 2d 12/30/24 12/31/24 12/30/24 8:00 AM 12/31/24 4:59 PM 2067FS -1d 0% 0% Green support from 1.4 personnel $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.4 CPT (Cables, SBJs) 1.2.10.4.7.14 1 2068 Unspool & Lay Surface Cables from Tower to SJB Pits
2070 1.2 1.2.10.4.7.15 Unspool & Lay Surface Cables from Tower to SJB Pits (USAP) Not Started C 6 1 2d 12/30/24 12/31/24 12/30/24 8:00 AM 12/31/24 4:59 PM 2067FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.15 1 2069 Unspool & Lay Surface Cables from Tower to SJB Pits (USAP)
2071 1.2 1.2.10.4.7.16 Install SJB's in Pits (2); Connect Cables Not Started C 6 1 2d 01/02/25 01/03/25 01/02/25 8:00 AM 01/03/25 4:59 PM 2069 0% 0% Green support from 1.4 personnel $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.4 CPT (Cables, SBJs) 1.2.10.4.7.16 1 2070 Install SJB's in Pits (2); Connect Cables
2072 1.2 1.2.10.4.7.17 Build & Install Temp-Vault w/Lid (8'x10'x4'h) (USAP) Not Started C 6 1 3d 01/02/25 01/06/25 01/02/25 8:00 AM 01/06/25 4:59 PM 2070SS 0% 0% Green 3 (where is a vault construction) $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.17 1 2071 Build & Install Temp-Vault w/Lid (8'x10'x4'h) (USAP)
2073 1.2 1.2.10.4.7.18 Survey (as built), Backfill, and Flag Pits & Trenches (USAP) Not Started C 6 1 3d 01/03/25 01/07/25 01/03/25 8:00 AM 01/07/25 4:59 PM 2070FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.18 1 2072 Survey (as built), Backfill, and Flag Pits & Trenches (USAP)
2074 1.2 1.2.10.4.7.19 Surface Cable Continuity Test Not Started C 6 1 2d 01/07/25 01/08/25 01/07/25 8:00 AM 01/08/25 4:59 PM 2070FS +1d 0% 0% Green support from 1.4 personnel $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.4 CPT (Cables, SBJs) 1.2.10.4.7.19 1 2073 Surface Cable Continuity Test
2075 1.2 1.2.10.4.7.20 Maintain access to SJBs (USAP) Not Started C 6 1 15d 01/07/25 01/27/25 01/07/25 8:00 AM 01/27/25 4:59 PM 2070FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.7.20 1 2074 Maintain access to SJBs (USAP)
2076 1.2 1.2.10.4.8 ICL Upgrade Activities Not Started P 5 1 24d 12/31/24 02/03/25 12/31/24 8:00 AM 02/03/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.4.8 1 2075 ICL Upgrade Activities
2077 1.2 1.2.10.4.8.1 ICL Upgrade Activities Not Started C 6 1 19d 01/08/25 02/03/25 01/08/25 8:00 AM 02/03/25 4:59 PM 3082SS, 3042FF 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.4.8.1 1 2076 ICL Upgrade Activities
2078 1.2 1.20.10.4.8.1 Field Hubs, timing system, patch panels and patch cables installation Not Started C 6 1 19d 12/31/24 01/27/25 12/31/24 8:00 AM 01/27/25 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.20.10.4.8.1 1 2077 Field Hubs, timing system, patch panels and patch cables installation
2079 1.2 1.2.10.4.9 End of NPX Season Installation Close-Out Work Not Started P 5 1 19d 12/31/24 01/27/25 12/31/24 8:00 AM 01/27/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.4.9 1 2078 End of NPX Season Installation Close-Out Work
2080 1.2 1.2.10.4.9.1 Store Sensor Handling Facility for Winter (USAP) Not Started C 6 1 3d 12/31/24 01/03/25 12/31/24 8:00 AM 01/03/25 4:59 PM 2042FS +1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.9.1 1 2079 Store Sensor Handling Facility for Winter (USAP)
2081 1.2 1.2.10.4.9.2 Sensor Sleds Winter Storage (USAP) Not Started C 6 1 5d 01/21/25 01/27/25 01/21/25 8:00 AM 01/27/25 4:59 PM 2081 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.9.2 1 2080 Sensor Sleds Winter Storage (USAP)
2082 1.2 1.2.10.4.9.3 Store 87 & 88 Sensors in Cryo Helium Bay for Winter Not Started C 6 1 3d 01/16/25 01/20/25 01/16/25 8:00 AM 01/20/25 4:59 PM 2053FS -1d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.9.3 1 2081 Store 87 & 88 Sensors in Cryo Helium Bay for Winter
2083 1.2 1.2.10.4.9.4 Support Storage 87 & 88 Sensors in Cryo Helium Bay for Winter (USAP) Not Started C 6 1 3d 01/16/25 01/20/25 01/16/25 8:00 AM 01/20/25 4:59 PM 2081SS 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.9.4 1 2082 Support Storage 87 & 88 Sensors in Cryo Helium Bay for Winter (USAP)
2084 1.2 1.2.10.4.9.5 Store 87 & 88 Special Devices and BCAs in ICL for Winter Not Started C 6 1 3d 01/16/25 01/20/25 01/16/25 8:00 AM 01/20/25 4:59 PM 2053FS -1d 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.4.9.5 1 2083 Store 87 & 88 Special Devices and BCAs in ICL for Winter
2085 1.2 1.2.10.4.9.6 Clean up Testing Tent & Store SPAT Not Started C 6 1 3d 01/21/25 01/23/25 01/21/25 8:00 AM 01/23/25 4:59 PM 2052FS +1d 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.9.6 1 2084 Clean up Testing Tent & Store SPAT
2086 1.2 1.2.10.4.9.7 Clean up Testing Tent & Store SPAT (USAP) Not Started C 6 1 3d 01/21/25 01/23/25 01/21/25 8:00 AM 01/23/25 4:59 PM 2084SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.4.9.7 1 2085 Clean up Testing Tent & Store SPAT (USAP)
2087 1.2 1.2.10.4.10 Installation: On-Ice Labor (FS2) Not Started C 5 1 40d 12/10/24 02/05/25 12/10/24 8:00 AM 02/05/25 4:59 PM 1991SS, 2087FF 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Installation Lead 1.2.10.4.10 1 2086 Installation: On-Ice Labor (FS2)
2088 1.2 1.2.10.4.11 END NPX Installation FS2 Season Not Started C 5 1 1 0 02/05/25 02/05/25 02/05/25 8:00 AM 02/05/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.4.11 1 2087 END NPX Installation FS2 Season
2089 1.2 1.2.10.5 USAP Field Season 3 (FY26) Not Started P 4 1 267d 02/06/25 02/18/26 02/06/25 8:00 AM 02/18/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5 1 2088 USAP Field Season 3 (FY26)
2090 1.2 1.2.10.5.1 Installation Team Arrives Not Started P 5 1 11d 11/20/25 12/08/25 11/20/25 8:00 AM 12/08/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.1 1 2089 Installation Team Arrives
2091 1.2 1.2.10.5.1.1 Installation Team I arrives (1 + 1 In-kind) Not Started C 6 1 1 0 11/20/25 11/20/25 11/20/25 8:00 AM 11/20/25 8:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead, Install Night Shift Lead 1.2.10.5.1.1 1 2090 Installation Team I arrives (1 + 1 In-kind)
2092 1.2 1.2.10.5.1.2 Installation Team II arrives (8 all in kind) Not Started C 6 1 1 0 12/08/25 12/08/25 12/08/25 8:00 AM 12/08/25 8:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 8 Installers, In-kind 1.2.10.5.1.2 1 2091 Installation Team II arrives (8 all in kind)
2093 1.2 1.2.10.5.2 PQ, ECW, Deployment Travel Costs Install FS2 Installation Team Not Started C 5 1 186d 06/01/25 02/18/26 06/01/25 8:00 AM 02/18/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.2 1 2092 PQ, ECW, Deployment Travel Costs Install FS2 Installation Team
2094 1.2 1.2.10.5.3 Cargo Movements (USAP) Not Started P 5 1 263d 02/06/25 02/12/26 02/06/25 8:00 AM 02/12/26 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3 1 2093 Cargo Movements (USAP)
2095 1.2 1.2.10.5.3.1 Pole (USAP) Not Started P 6 1 3d 11/25/25 12/01/25 11/25/25 8:00 AM 12/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.1 1 2094 Pole (USAP)
2096 1.2 1.2.10.5.3.1.1 LC-130 (USAP) Not Started P 7 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.1.1 1 2095 LC-130 (USAP)
2097 1.2 1.2.10.5.3.1.1.1 89-93 BCAs Arrive - Pole (USAP) Not Started C 8 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.1.1.1 1 2096 89-93 BCAs Arrive - Pole (USAP)
2098 1.2 1.2.10.5.3.1.1.2 Science Crate FS3 Arrive - Pole (USAP) Not Started C 8 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.1.1.2 1 2097 Science Crate FS3 Arrive - Pole (USAP)
2099 1.2 1.2.10.5.3.1.1.3 String 89-93 BCAs Arrive (McMurdo) - Pole (USAP) Not Started C 8 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.1.1.3 1 2098 String 89-93 BCAs Arrive (McMurdo) - Pole (USAP)
2100 1.2 1.2.10.5.3.1.1.4 String 89-93 Sensors Arrive (Japan, USA, Europe) - Pole (USAP) Not Started C 8 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.1.1.4 1 2099 String 89-93 Sensors Arrive (Japan, USA, Europe) - Pole (USAP)
2101 1.2 1.2.10.5.3.1.1.5 String 89-93 Special Devices (Germany, USA) Arrive Pole (USAP) Not Started C 8 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.1.1.5 1 2100 String 89-93 Special Devices (Germany, USA) Arrive Pole (USAP)
2102 1.2 1.2.10.5.3.1.1.6 String 89-93 Calibration Devices (Europe, USA) Arrive Pole (USAP) Not Started C 8 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.1.1.6 1 2101 String 89-93 Calibration Devices (Europe, USA) Arrive Pole (USAP)
2103 1.2 1.2.10.5.3.1.1.7 Dust Logger and Dust Logger Winch Arrives Pole (USAP) Not Started C 8 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.1.1.7 1 2102 Dust Logger and Dust Logger Winch Arrives Pole (USAP)
2104 1.2 1.2.10.5.3.1.1.8 DM-Ice (USAP) Not Started C 8 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.1.1.8 1 2103 DM-Ice (USAP)
2105 1.2 1.2.10.5.3.1.2 SPOT 1 (USAP) Not Started P 7 1 1 0 12/01/25 12/01/25 12/01/25 8:00 AM 12/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.1.2 1 2104 SPOT 1 (USAP)
2106 1.2 1.2.10.5.3.1.2.1 MCAs Arrive - Pole (USAP) Not Started C 8 1 1 0 12/01/25 12/01/25 12/01/25 8:00 AM 12/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.1.2.1 1 2105 MCAs Arrive - Pole (USAP)
2107 1.2 1.2.10.5.3.1.2.2 Load Members Arrive - Pole (USAP) Not Started C 8 1 1 0 12/01/25 12/01/25 12/01/25 8:00 AM 12/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.1.2.2 1 2106 Load Members Arrive - Pole (USAP)
2108 1.2 1.2.10.5.3.1.3 SPOT 2 (USAP) Not Started P 7 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.1.3 1 2107 SPOT 2 (USAP)
2109 1.2 1.2.10.5.3.1.3.1 Placeholder Not Started C 8 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.1.3.1 1 2108 Placeholder
2110 1.2 1.2.10.5.3.1.4 SPOT 3 (USAP) Not Started P 7 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.1.4 1 2109 SPOT 3 (USAP)
2111 1.2 1.2.10.5.3.1.4.1 Placeholder Not Started C 8 1 1 0 11/25/25 11/25/25 11/25/25 8:00 AM 11/25/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.1.4.1 1 2110 Placeholder
2112 1.2 1.2.10.5.3.2 MCM (USAP) Not Started P 6 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.2 1 2111 MCM (USAP)
2113 1.2 1.2.10.5.3.2.1 MCM SAAM - ComSur (USAP) Not Started P 7 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.2.1 1 2112 MCM SAAM - ComSur (USAP)
2114 1.2 1.2.10.5.3.2.1.1 Science Crate FS3 Arrive - (USAP) Not Started C 8 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.2.1.1 1 2113 Science Crate FS3 Arrive - (USAP)
2115 1.2 1.2.10.5.3.2.1.2 String 89-93 BCAs Arrive (McMurdo) - (USAP) Not Started C 8 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.2.1.2 1 2114 String 89-93 BCAs Arrive (McMurdo) - (USAP)
2116 1.2 1.2.10.5.3.2.1.3 String 89-93 Sensors Arrive (Japan, USA, Europe) - (USAP) Not Started C 8 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.2.1.3 1 2115 String 89-93 Sensors Arrive (Japan, USA, Europe) - (USAP)
2117 1.2 1.2.10.5.3.2.1.4 String 89-93 Special Devices (Germany, USA) Arrive Pole - (USAP) Not Started C 8 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.2.1.4 1 2116 String 89-93 Special Devices (Germany, USA) Arrive Pole - (USAP)
2118 1.2 1.2.10.5.3.2.1.5 String 89-93 Calibration Devices (Europe, USA) - (USAP) Not Started C 8 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.2.1.5 1 2117 String 89-93 Calibration Devices (Europe, USA) - (USAP)
2119 1.2 1.2.10.5.3.2.1.6 Dust Logger and Dust Logger Winch - (USAP) Not Started C 8 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.2.1.6 1 2118 Dust Logger and Dust Logger Winch - (USAP)
2120 1.2 1.2.10.5.3.2.1.7 DM-Ice (USAP) Not Started C 8 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.2.1.7 1 2119 DM-Ice (USAP)
2121 1.2 1.2.10.5.3.2.2 Vessel (USAP) Not Started P 7 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.2.2 1 2120 Vessel (USAP)
2122 1.2 1.2.10.5.3.2.2.1 Placeholder Not Started C 8 1 1 0 11/01/25 11/01/25 11/01/25 8:00 AM 11/01/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.2.2.1 1 2121 Placeholder
2123 1.2 1.2.10.5.3.3 Retrograde (USAP) Not Started C 6 1 1 0 02/06/25 02/06/25 02/06/25 8:00 AM 02/06/25 8:00 AM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.3.3 1 2122 Retrograde (USAP)
2124 1.2 1.2.10.5.3.4 Cargo Storage Support Pole & MCM (USAP) Not Started C 6 1 52d 12/01/25 02/12/26 12/01/25 8:00 AM 02/12/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.3.4 1 2123 Cargo Storage Support Pole & MCM (USAP)
2125 1.2 1.2.10.5.4 Pre-Installation Activities Not Started P 5 1 16d 11/21/25 12/15/25 11/21/25 8:00 AM 12/15/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.4 1 2124 Pre-Installation Activities
2126 1.2 1.2.10.5.4.1 Prep Sensor Testing Tent for SPAT & De-Berm Sleds Not Started C 6 1 3d 11/21/25 11/25/25 11/21/25 8:00 AM 11/25/25 4:59 PM 2090FS +1d, 2131SF -1d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead 1.2.10.5.4.1 1 2125 Prep Sensor Testing Tent for SPAT & De-Berm Sleds
2127 1.2 1.2.10.5.4.2 Prep Sensor Testing Tent for SPAT & De-Berm Sleds (USAP) Not Started C 6 1 3d 11/21/25 11/25/25 11/21/25 8:00 AM 11/25/25 4:59 PM 2125SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.4.2 1 2126 Prep Sensor Testing Tent for SPAT & De-Berm Sleds (USAP)
2128 1.2 1.2.10.5.4.3 Prep Sensor Handling Facility Not Started C 6 1 3d 11/21/25 11/25/25 11/21/25 8:00 AM 11/25/25 4:59 PM 2090FS +1d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME, Install Shift 1 1.2.10.5.4.3 1 2127 Prep Sensor Handling Facility
2129 1.2 1.2.10.5.4.4 On-ice Sensor Handling Training Not Started C 6 1 1d 12/10/25 12/10/25 12/10/25 8:00 AM 12/10/25 4:59 PM 2127, 2091FS +2d, 1734 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead, Install Shift 1, Install Night Shift Lead, Install Shift 2 1.2.10.5.4.4 1 2128 On-ice Sensor Handling Training
2130 1.2 1.2.10.5.4.5 Receive and Inspect MCAs & load members Not Started C 6 1 3d 12/01/25 12/03/25 12/01/25 8:00 AM 12/03/25 4:59 PM 2105, 3123 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME (Cables/SJBs), Install Lead 1.2.10.5.4.5 1 2129 Receive and Inspect MCAs & load members
2131 1.2 1.2.10.5.4.6 Receive and Inspect BCAs & String 89-93 Sensors Not Started C 6 1 2d 11/25/25 11/26/25 11/25/25 8:00 AM 11/26/25 4:59 PM 2098, 2099 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead, Install Night Shift Lead 1.2.10.5.4.6 1 2130 Receive and Inspect BCAs & String 89-93 Sensors
2132 1.2 1.2.10.5.4.7 Take out String 87 Sensors from Storage; Load sensor String 87 on sleds 1 & 2 Not Started C 6 1 e12h 11/21/25 11/21/25 11/21/25 8:00 AM 11/21/25 7:59 PM 3418FS +1d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME, Install Lead 1.2.10.5.4.7 1 2131 Take out String 87 Sensors from Storage; Load sensor String 87 on sleds 1 & 2
2133 1.2 1.2.10.5.4.8 Take out String 87 Sensors from Storage; Load sensor String 87 on sleds 1 & 2 (USAP) Not Started C 6 1 e12h 11/21/25 11/21/25 11/21/25 8:00 AM 11/21/25 7:59 PM 2131SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.4.8 1 2132 Take out String 87 Sensors from Storage; Load sensor String 87 on sleds 1 & 2 (USAP)
2134 1.2 1.2.10.5.4.9 SPAT String 87 Not Started C 6 1 e7d 11/26/25 12/03/25 11/26/25 7:59 AM 12/03/25 7:59 AM 2131, 2136SF -1d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME, Install Lead 1.2.10.5.4.9 1 2133 SPAT String 87
2135 1.2 1.2.10.5.4.10 Take out String 88 Sensors from Storage; Load sensor String 88 on sleds 3 & 4 Not Started C 6 1 e12h 11/21/25 11/22/25 11/21/25 8:00 PM 11/22/25 7:59 AM 2131 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME, Install Lead 1.2.10.5.4.10 1 2134 Take out String 88 Sensors from Storage; Load sensor String 88 on sleds 3 & 4
2136 1.2 1.2.10.5.4.11 Take out String 88 Sensors from Storage; Load sensor String 88 on sleds 3 & 4 (USAP) Not Started C 6 1 e12h 11/21/25 11/22/25 11/21/25 8:00 PM 11/22/25 7:59 AM 2134SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.4.11 1 2135 Take out String 88 Sensors from Storage; Load sensor String 88 on sleds 3 & 4 (USAP)
2137 1.2 1.2.10.5.4.12 SPAT String 88 Not Started C 6 1 e7d 12/05/25 12/12/25 12/05/25 7:59 AM 12/12/25 7:59 AM 2135, 1762SF -2d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME, Install Lead 1.2.10.5.4.12 1 2136 SPAT String 88
2138 1.2 1.2.10.5.4.13 Excavation Pit #1 Not Started C 6 1 3d 12/11/25 12/15/25 12/11/25 8:00 AM 12/15/25 4:59 PM 1762FF -2d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME (Cables/SJBs), Install Lead 1.2.10.5.4.13 1 2137 Excavation Pit #1
2139 1.2 1.2.10.5.4.14 Excavation Pit #1 (USAP) Not Started C 6 1 3d 12/11/25 12/15/25 12/11/25 8:00 AM 12/15/25 4:59 PM 2137SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.4.14 1 2138 Excavation Pit #1 (USAP)
2140 1.2 1.2.10.5.4.15 Dust Logger / Dust Logger Winch On-ice Test Not Started C 6 1 5d 11/21/25 12/01/25 11/21/25 9:00 AM 12/01/25 8:59 AM 2102SF +1d, 2090FS +1d, 1732FS +1d 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead, PSL Driller 1.2.10.5.4.15 1 2139 Dust Logger / Dust Logger Winch On-ice Test
2141 1.2 1.2.10.5.4.16 Installation Team On Ice Training and Installation Preparation Not Started C 6 1 5d 12/08/25 12/12/25 12/08/25 8:00 AM 12/12/25 4:59 PM 2091 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead, Install Night Shift Lead, Install Shift 1, Install Shift 2 1.2.10.5.4.16 1 2140 Installation Team On Ice Training and Installation Preparation
2142 1.2 1.2.10.5.4.17 On-Ice Readiness Review for 1st Hole Drill/Deployment Not Started C 6 1 1d 12/15/25 12/15/25 12/15/25 8:00 AM 12/15/25 4:59 PM 1758FF 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead, Install Night Shift Lead, Install Shift 1, Install Shift 2 1.2.10.5.4.17 1 2141 On-Ice Readiness Review for 1st Hole Drill/Deployment
2143 1.2 1.2.10.5.4.18 Installation Team Ready for Deployment Not Started C 6 1 1 0 12/12/25 12/12/25 12/12/25 4:59 PM 12/12/25 4:59 PM 2140 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.4.18 1 2142 Installation Team Ready for Deployment
2144 1.2 1.2.10.5.5 String Installation Field Activities Not Started P 5 1 27.501d 12/03/25 01/13/26 12/03/25 7:59 AM 01/13/26 1:00 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5 1 2143 String Installation Field Activities
2145 1.2 1.2.10.5.5.1 Installation - String 87 - Hole 1 Not Started P 6 1 13d 12/03/25 12/21/25 12/03/25 7:59 AM 12/21/25 6:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.1 1 2144 Installation - String 87 - Hole 1
2146 1.2 1.2.10.5.5.1.1 Load String 87 Sensors in Sensor Handling Facility Not Started C 7 1 e12h 12/03/25 12/03/25 12/03/25 7:59 AM 12/03/25 7:59 PM 1734, 2133 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Night Shift Lead, Install Shift 2 1.2.10.5.5.1.1 1 2145 Load String 87 Sensors in Sensor Handling Facility
2147 1.2 1.2.10.5.5.1.2 Load String 87 Special/Calibration Devices, Rigging Hardware and BCAs in Sensor Handling Facility Not Started C 7 1 e12h 12/03/25 12/04/25 12/03/25 7:59 PM 12/04/25 7:59 AM 2145 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead, Install Shift 1 1.2.10.5.5.1.2 1 2146 Load String 87 Special/Calibration Devices, Rigging Hardware and BCAs in Sensor Handling Facility
2148 1.2 1.2.10.5.5.1.3 Install String 87 / Hole 1 Not Started C 7 1 e48h 12/17/25 12/19/25 12/17/25 9:00 PM 12/19/25 8:59 PM 1763 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead, Install Shift 1, Install Night Shift Lead, Install Shift 2 1.2.10.5.5.1.3 1 2147 Install String 87 / Hole 1
2149 1.2 1.2.10.5.5.1.4 Install String 87 / Hole 1 Complete Not Started C 7 1 1 1 e5s 12/19/25 12/19/25 12/19/25 9:00 PM 12/19/25 9:00 PM 2147 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.1.4 1 2148 Install String 87 / Hole 1 Complete
2150 1.2 1.2.10.5.5.1.5 Anchor String 87 / Hole 1 Not Started C 7 1 e1h 12/19/25 12/19/25 12/19/25 9:00 PM 12/19/25 10:00 PM 2148 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead 1.2.10.5.5.1.5 1 2149 Anchor String 87 / Hole 1
2151 1.2 1.2.10.5.5.1.6 TOS Clean Up - Wait 12 hours for Anchor to Set Not Started C 7 1 e12h 12/19/25 12/20/25 12/19/25 10:00 PM 12/20/25 10:00 AM 2149 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.1.6 1 2150 TOS Clean Up - Wait 12 hours for Anchor to Set
2152 1.2 1.2.10.5.5.1.7 String 87 / Hole 1 Cable drag Not Started C 7 1 e4h 12/20/25 12/20/25 12/20/25 10:00 AM 12/20/25 2:00 PM 2150 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.1.7 1 2151 String 87 / Hole 1 Cable drag
2153 1.2 1.2.10.5.5.1.8 Trench Hole 1 / String 87 to Pit #1 Not Started C 7 1 e4h 12/20/25 12/20/25 12/20/25 6:00 PM 12/20/25 10:00 PM 1769 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME (Cables/SJBs) 1.2.10.5.5.1.8 1 2152 Trench Hole 1 / String 87 to Pit #1
2154 1.2 1.2.10.5.5.1.9 Trench Hole 1 / String 87 to Pit #1 (USAP) Not Started C 7 1 e4h 12/20/25 12/20/25 12/20/25 6:00 PM 12/20/25 10:00 PM 2152SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.1.9 1 2153 Trench Hole 1 / String 87 to Pit #1 (USAP)
2155 1.2 1.2.10.5.5.1.10 Connect in-ice Cable to SJB 87 in Pit #1 Not Started C 7 1 e4h 12/20/25 12/21/25 12/20/25 10:00 PM 12/21/25 2:00 AM 2153 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME (Cables/SJBs) 1.2.10.5.5.1.10 1 2154 Connect in-ice Cable to SJB 87 in Pit #1
2156 1.2 1.2.10.5.5.1.11 Backfill Hole 1 / String 87 to Pit #1 Not Started C 7 1 e4h 12/21/25 12/21/25 12/21/25 2:00 AM 12/21/25 6:00 AM 2154 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME (Cables/SJBs) 1.2.10.5.5.1.11 1 2155 Backfill Hole 1 / String 87 to Pit #1
2157 1.2 1.2.10.5.5.1.12 Backfill Hole 1 / String 87 to Pit #1 (USAP) Not Started C 7 1 e4h 12/21/25 12/21/25 12/21/25 2:00 AM 12/21/25 6:00 AM 2155SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.1.12 1 2156 Backfill Hole 1 / String 87 to Pit #1 (USAP)
2158 1.2 1.2.10.5.5.1.13 Load Sensor String 89 (Hole 3) on Sleds 1 & 2 Not Started C 7 1 e4h 12/17/25 12/18/25 12/17/25 9:00 PM 12/18/25 12:59 AM 2147SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME 1.2.10.5.5.1.13 1 2157 Load Sensor String 89 (Hole 3) on Sleds 1 & 2
2159 1.2 1.2.10.5.5.1.14 Load Sensor String 89 (Hole 3) on Sleds 1 & 2 (USAP) Not Started C 7 1 e4h 12/17/25 12/18/25 12/17/25 9:00 PM 12/18/25 12:59 AM 2157SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.1.14 1 2158 Load Sensor String 89 (Hole 3) on Sleds 1 & 2 (USAP)
2160 1.2 1.2.10.5.5.1.15 SPAT String 89 Not Started C 7 1 e72h 12/18/25 12/21/25 12/18/25 1:00 AM 12/21/25 12:59 AM 2158 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME 1.2.10.5.5.1.15 1 2159 SPAT String 89
2161 1.2 1.2.10.5.5.2 Installation - String 88 - Hole 2 Not Started P 6 1 4d 12/19/25 12/27/25 12/19/25 10:00 PM 12/27/25 2:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.2 1 2160 Installation - String 88 - Hole 2
2162 1.2 1.2.10.5.5.2.1 Load String 88 Sensors in Sensor Handling Facility Not Started C 7 1 e12h 12/19/25 12/20/25 12/19/25 10:00 PM 12/20/25 10:00 AM 1767, 2136 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead, Install Shift 1 1.2.10.5.5.2.1 1 2161 Load String 88 Sensors in Sensor Handling Facility
2163 1.2 1.2.10.5.5.2.2 Load String 88 Calibration/Special Devices & BCAs in Sensor Handling Facility Not Started C 7 1 e12h 12/20/25 12/20/25 12/20/25 10:00 AM 12/20/25 10:00 PM 2161 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Night Shift Lead, Install Shift 2 1.2.10.5.5.2.2 1 2162 Load String 88 Calibration/Special Devices & BCAs in Sensor Handling Facility
2164 1.2 1.2.10.5.5.2.3 Install String 88 / Hole 2 Not Started C 7 1 e24h 12/23/25 12/24/25 12/23/25 10:00 PM 12/24/25 10:00 PM 1778 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead, Install Shift 1, Install Night Shift Lead, Install Shift 2 1.2.10.5.5.2.3 1 2163 Install String 88 / Hole 2
2165 1.2 1.2.10.5.5.2.4 Install String 88 / Hole 2 Complete Not Started C 7 1 1 1 e5s 12/24/25 12/24/25 12/24/25 10:00 PM 12/24/25 10:00 PM 2163 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.2.4 1 2164 Install String 88 / Hole 2 Complete
2166 1.2 1.2.10.5.5.2.5 Anchor String 88 / Hole 2 Not Started C 7 1 e1h 12/24/25 12/24/25 12/24/25 10:00 PM 12/24/25 11:00 PM 2164 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead 1.2.10.5.5.2.5 1 2165 Anchor String 88 / Hole 2
2167 1.2 1.2.10.5.5.2.6 TOS Clean Up - Wait 12 hours for Anchor to Set Not Started C 7 1 e12h 12/24/25 12/25/25 12/24/25 11:00 PM 12/25/25 11:00 AM 2165 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.2.6 1 2166 TOS Clean Up - Wait 12 hours for Anchor to Set
2168 1.2 1.2.10.5.5.2.7 Christmas Break Not Started C 7 1 e24h 12/24/25 12/25/25 12/24/25 11:00 PM 12/25/25 11:00 PM 2166SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.2.7 1 2167 Christmas Break
2169 1.2 1.2.10.5.5.2.8 String 88 / Hole 2 Cable drag Not Started C 7 1 e2h 12/25/25 12/26/25 12/25/25 11:00 PM 12/26/25 1:00 AM 2167 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.2.8 1 2168 String 88 / Hole 2 Cable drag
2170 1.2 1.2.10.5.5.2.9 Trench Hole 2 / String 88 to Pit #1 Not Started C 7 1 e4h 12/26/25 12/26/25 12/26/25 7:00 AM 12/26/25 11:00 AM 1786 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME (Cables/SJBs) 1.2.10.5.5.2.9 1 2169 Trench Hole 2 / String 88 to Pit #1
2171 1.2 1.2.10.5.5.2.10 Trench Hole 2 / String 88 to Pit #1 (USAP) Not Started C 7 1 e4h 12/26/25 12/26/25 12/26/25 7:00 AM 12/26/25 11:00 AM 2169SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.2.10 1 2170 Trench Hole 2 / String 88 to Pit #1 (USAP)
2172 1.2 1.2.10.5.5.2.11 Connect in-ice Cable to SJB 88 in Pit #1 Not Started C 7 1 e4h 12/26/25 12/26/25 12/26/25 11:00 AM 12/26/25 3:00 PM 2170 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME (Cables/SJBs) 1.2.10.5.5.2.11 1 2171 Connect in-ice Cable to SJB 88 in Pit #1
2173 1.2 1.2.10.5.5.2.12 Backfill Hole 2 / String 88 to Pit #1 Not Started C 7 1 e4h 12/26/25 12/26/25 12/26/25 3:00 PM 12/26/25 7:00 PM 2171 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME (Cables/SJBs) 1.2.10.5.5.2.12 1 2172 Backfill Hole 2 / String 88 to Pit #1
2174 1.2 1.2.10.5.5.2.13 Backfill Hole 2 / String 88 to Pit #1 (USAP) Not Started C 7 1 e4h 12/26/25 12/26/25 12/26/25 3:00 PM 12/26/25 7:00 PM 2172SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.2.13 1 2173 Backfill Hole 2 / String 88 to Pit #1 (USAP)
2175 1.2 1.2.10.5.5.2.14 Load sensor String 90 (Hole 4) on sleds 3,4 Not Started C 7 1 e4h 12/23/25 12/24/25 12/23/25 10:00 PM 12/24/25 2:00 AM 2163SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME 1.2.10.5.5.2.14 1 2174 Load sensor String 90 (Hole 4) on sleds 3,4
2176 1.2 1.2.10.5.5.2.15 Load sensor String 90 (Hole 4) on sleds 3,4 (USAP) Not Started C 7 1 e4h 12/23/25 12/24/25 12/23/25 10:00 PM 12/24/25 2:00 AM 2174SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.2.15 1 2175 Load sensor String 90 (Hole 4) on sleds 3,4 (USAP)
2177 1.2 1.2.10.5.5.2.16 SPAT String 90 Not Started C 7 1 e72h 12/24/25 12/27/25 12/24/25 2:00 AM 12/27/25 2:00 AM 2175 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME 1.2.10.5.5.2.16 1 2176 SPAT String 90
2178 1.2 1.2.10.5.5.3 Installation - String 89 - Hole 3 Not Started P 6 1 2d 12/24/25 12/29/25 12/24/25 11:00 PM 12/29/25 6:00 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.3 1 2177 Installation - String 89 - Hole 3
2179 1.2 1.2.10.5.5.3.1 Load String 89 (Hole 3) Sensors in Sensor Handling Facility Not Started C 7 1 e12h 12/24/25 12/25/25 12/24/25 11:00 PM 12/25/25 11:00 AM 1782, 2159 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Team 1.2.10.5.5.3.1 1 2178 Load String 89 (Hole 3) Sensors in Sensor Handling Facility
2180 1.2 1.2.10.5.5.3.2 Load String 89 (Hole 3) Calibration/Special Devices & BCAs in Sensor Handling Facility Not Started C 7 1 e12h 12/25/25 12/25/25 12/25/25 11:00 AM 12/25/25 11:00 PM 2178 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Night Shift Lead, Install Shift 2 1.2.10.5.5.3.2 1 2179 Load String 89 (Hole 3) Calibration/Special Devices & BCAs in Sensor Handling Facility
2181 1.2 1.2.10.5.5.3.3 Install String 89 / Hole 3 Not Started C 7 1 e24h 12/26/25 12/27/25 12/26/25 2:00 PM 12/27/25 2:00 PM 1792 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Team 1.2.10.5.5.3.3 1 2180 Install String 89 / Hole 3
2182 1.2 1.2.10.5.5.3.4 Install String 89 / Hole 3 Complete Not Started C 7 1 1 1 e5s 12/27/25 12/27/25 12/27/25 2:00 PM 12/27/25 2:00 PM 2180 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.3.4 1 2181 Install String 89 / Hole 3 Complete
2183 1.2 1.2.10.5.5.3.5 Anchor String 89 / Hole 3 Not Started C 7 1 e1h 12/27/25 12/27/25 12/27/25 2:00 PM 12/27/25 3:00 PM 2181 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Team 1.2.10.5.5.3.5 1 2182 Anchor String 89 / Hole 3
2184 1.2 1.2.10.5.5.3.6 TOS Clean Up - Wait 12 hours for Anchor to Set Not Started C 7 1 e12h 12/27/25 12/28/25 12/27/25 3:00 PM 12/28/25 3:00 AM 2182 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.3.6 1 2183 TOS Clean Up - Wait 12 hours for Anchor to Set
2185 1.2 1.2.10.5.5.3.7 String 89 / Hole 3 Cable drag Not Started C 7 1 e4h 12/28/25 12/28/25 12/28/25 3:00 AM 12/28/25 7:00 AM 2183 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.3.7 1 2184 String 89 / Hole 3 Cable drag
2186 1.2 1.2.10.5.5.3.8 Trench Hole 3 / String 89 to Pit #1 Not Started C 7 1 e4h 12/28/25 12/28/25 12/28/25 11:00 AM 12/28/25 3:00 PM 1800 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME 1.2.10.5.5.3.8 1 2185 Trench Hole 3 / String 89 to Pit #1
2187 1.2 1.2.10.5.5.3.9 Trench Hole 3 / String 89 to Pit #1 (USAP) Not Started C 7 1 e4h 12/28/25 12/28/25 12/28/25 11:00 AM 12/28/25 3:00 PM 2185SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.3.9 1 2186 Trench Hole 3 / String 89 to Pit #1 (USAP)
2188 1.2 1.2.10.5.5.3.10 Connect in-ice cable to SJB 89 in Pit #1 Not Started C 7 1 e4h 12/28/25 12/28/25 12/28/25 3:00 PM 12/28/25 7:00 PM 2186 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.3.10 1 2187 Connect in-ice cable to SJB 89 in Pit #1
2189 1.2 1.2.10.5.5.3.11 Backfill Hole 3 / String 89 to Pit #1 Not Started C 7 1 e4h 12/28/25 12/28/25 12/28/25 7:00 PM 12/28/25 11:00 PM 2187 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.3.11 1 2188 Backfill Hole 3 / String 89 to Pit #1
2190 1.2 1.2.10.5.5.3.12 Backfill Hole 3 / String 89 to Pit #1 (USAP) Not Started C 7 1 e4h 12/28/25 12/28/25 12/28/25 7:00 PM 12/28/25 11:00 PM 2188SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.3.12 1 2189 Backfill Hole 3 / String 89 to Pit #1 (USAP)
2191 1.2 1.2.10.5.5.3.13 Load sensor String 91 (Hole 5) on sleds 1 & 2 Not Started C 7 1 e4h 12/26/25 12/26/25 12/26/25 2:00 PM 12/26/25 6:00 PM 2180SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME 1.2.10.5.5.3.13 1 2190 Load sensor String 91 (Hole 5) on sleds 1 & 2
2192 1.2 1.2.10.5.5.3.14 Load sensor String 91 (Hole 5) on sleds 1 & 2 (USAP) Not Started C 7 1 e4h 12/26/25 12/26/25 12/26/25 2:00 PM 12/26/25 6:00 PM 2190SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.3.14 1 2191 Load sensor String 91 (Hole 5) on sleds 1 & 2 (USAP)
2193 1.2 1.2.10.5.5.3.15 SPAT String 91 Not Started C 7 1 e72h 12/26/25 12/29/25 12/26/25 6:00 PM 12/29/25 6:00 PM 2190 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME 1.2.10.5.5.3.15 1 2192 SPAT String 91
2194 1.2 1.2.10.5.5.4 Installation - String 90 - Hole 4 Not Started P 6 1 4.25d 12/27/25 01/03/26 12/27/25 3:00 PM 01/03/26 7:00 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.4 1 2193 Installation - String 90 - Hole 4
2195 1.2 1.2.10.5.5.4.1 Load String 90 (Hole 4) Sensors in Sensor Handling Facility Not Started C 7 1 e12h 12/27/25 12/28/25 12/27/25 3:00 PM 12/28/25 3:00 AM 1796, 2176 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.4.1 1 2194 Load String 90 (Hole 4) Sensors in Sensor Handling Facility
2196 1.2 1.2.10.5.5.4.2 Load String 90 (Hole 4) Calibration/Special Devices & BCAs in Sensor Handling Facility Not Started C 7 1 e12h 12/28/25 12/28/25 12/28/25 3:00 AM 12/28/25 3:00 PM 2194 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Night Shift Lead, Install Shift 2 1.2.10.5.5.4.2 1 2195 Load String 90 (Hole 4) Calibration/Special Devices & BCAs in Sensor Handling Facility
2197 1.2 1.2.10.5.5.4.3 Install String 90 Not Started C 7 1 e24h 12/31/25 01/01/26 12/31/25 3:00 PM 01/01/26 3:00 PM 1807 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.4.3 1 2196 Install String 90
2198 1.2 1.2.10.5.5.4.4 Install String 90 / Hole 4 Complete Not Started C 7 1 1 1 e5s 01/01/26 01/01/26 01/01/26 3:00 PM 01/01/26 3:00 PM 2196 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.4.4 1 2197 Install String 90 / Hole 4 Complete
2199 1.2 1.2.10.5.5.4.5 Anchor String 90 / Hole 4 Not Started C 7 1 e1h 01/01/26 01/01/26 01/01/26 3:00 PM 01/01/26 4:00 PM 2197 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.4.5 1 2198 Anchor String 90 / Hole 4
2200 1.2 1.2.10.5.5.4.6 TOS Clean Up - Wait 12 hours for Anchor to Set Not Started C 7 1 e12h 01/01/26 01/02/26 01/01/26 4:00 PM 01/02/26 4:00 AM 2198 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.4.6 1 2199 TOS Clean Up - Wait 12 hours for Anchor to Set
2201 1.2 1.2.10.5.5.4.7 String 90 / Hole 4 Cable drag Not Started C 7 1 e4h 01/02/26 01/02/26 01/02/26 4:00 AM 01/02/26 8:00 AM 2199 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.4.7 1 2200 String 90 / Hole 4 Cable drag
2202 1.2 1.2.10.5.5.4.8 Trench Hole 4 / String 90 to Pit #1 Not Started C 7 1 e4h 01/02/26 01/02/26 01/02/26 12:00 PM 01/02/26 4:00 PM 1815 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME 1.2.10.5.5.4.8 1 2201 Trench Hole 4 / String 90 to Pit #1
2203 1.2 1.2.10.5.5.4.9 Trench Hole 4 / String 90 to Pit #1 (USAP) Not Started C 7 1 e4h 01/02/26 01/02/26 01/02/26 12:00 PM 01/02/26 4:00 PM 2201SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.4.9 1 2202 Trench Hole 4 / String 90 to Pit #1 (USAP)
2204 1.2 1.2.10.5.5.4.10 Connect in-ice cable to SJB 90 in Pit #1 Not Started C 7 1 e4h 01/02/26 01/02/26 01/02/26 4:00 PM 01/02/26 8:00 PM 2201 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME 1.2.10.5.5.4.10 1 2203 Connect in-ice cable to SJB 90 in Pit #1
2205 1.2 1.2.10.5.5.4.11 Backfill Hole 4 / String 90 to Pit #1 Not Started C 7 1 e4h 01/02/26 01/03/26 01/02/26 8:00 PM 01/03/26 12:00 AM 2203 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME 1.2.10.5.5.4.11 1 2204 Backfill Hole 4 / String 90 to Pit #1
2206 1.2 1.2.10.5.5.4.12 Backfill Hole 4 / String 90 to Pit #1 (USAP) Not Started C 7 1 e4h 01/02/26 01/03/26 01/02/26 8:00 PM 01/03/26 12:00 AM 2204SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.4.12 1 2205 Backfill Hole 4 / String 90 to Pit #1 (USAP)
2207 1.2 1.2.10.5.5.4.13 Backfill, Remove Temp Vault, Flag and Survey Pit #1 Not Started C 7 1 e4h 01/02/26 01/03/26 01/02/26 8:00 PM 01/03/26 12:00 AM 2204SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME 1.2.10.5.5.4.13 1 2206 Backfill, Remove Temp Vault, Flag and Survey Pit #1
2208 1.2 1.2.10.5.5.4.14 Backfill, Remove Temp Vault, Flag and Survey Pit #1 (USAP) Not Started C 7 1 e4h 01/02/26 01/03/26 01/02/26 8:00 PM 01/03/26 12:00 AM 2206SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.4.14 1 2207 Backfill, Remove Temp Vault, Flag and Survey Pit #1 (USAP)
2209 1.2 1.2.10.5.5.4.15 Load Sensor String 92 (Hole 6) on Sleds 3 & 4 Not Started C 7 1 e4h 12/31/25 12/31/25 12/31/25 3:00 PM 12/31/25 7:00 PM 2196SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME 1.2.10.5.5.4.15 1 2208 Load Sensor String 92 (Hole 6) on Sleds 3 & 4
2210 1.2 1.2.10.5.5.4.16 Load Sensor String 92 (Hole 6) on sleds 3 & 4 (USAP) Not Started C 7 1 e4h 12/31/25 12/31/25 12/31/25 3:00 PM 12/31/25 7:00 PM 2208SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.4.16 1 2209 Load Sensor String 92 (Hole 6) on sleds 3 & 4 (USAP)
2211 1.2 1.2.10.5.5.4.17 SPAT String 92 Not Started C 7 1 e72h 12/31/25 01/03/26 12/31/25 7:00 PM 01/03/26 7:00 PM 2209 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu SPAT SME 1.2.10.5.5.4.17 1 2210 SPAT String 92
2212 1.2 1.2.10.5.5.5 Installation - String 91 - Hole 5 Not Started P 6 1 2.5d 01/01/26 01/06/26 01/01/26 4:00 PM 01/06/26 11:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.5 1 2211 Installation - String 91 - Hole 5
2213 1.2 1.2.10.5.5.5.1 Excavation Pit #2 (Assist) Not Started C 7 1 e8h 01/03/26 01/03/26 01/03/26 12:00 AM 01/03/26 8:00 AM 2207 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.5.1 1 2212 Excavation Pit #2 (Assist)
2214 1.2 1.2.10.5.5.5.2 Excavation Pit #2 (USAP) Not Started C 7 1 e8h 01/03/26 01/03/26 01/03/26 12:00 AM 01/03/26 8:00 AM 2212SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.5.2 1 2213 Excavation Pit #2 (USAP)
2215 1.2 1.2.10.5.5.5.3 Load String 91 (Hole 5) Sensors in Sensor Handling Facility Not Started C 7 1 e12h 01/01/26 01/02/26 01/01/26 4:00 PM 01/02/26 4:00 AM 1811, 2192 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.5.3 1 2214 Load String 91 (Hole 5) Sensors in Sensor Handling Facility
2216 1.2 1.2.10.5.5.5.4 Load String 91 (Hole 5) Calibration/Special Devices & BCAs in Sensor Handling Facility Not Started C 7 1 e12h 01/02/26 01/02/26 01/02/26 4:00 AM 01/02/26 4:00 PM 2214 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Night Shift Lead, Install Shift 2 1.2.10.5.5.5.4 1 2215 Load String 91 (Hole 5) Calibration/Special Devices & BCAs in Sensor Handling Facility
2217 1.2 1.2.10.5.5.5.5 Install String 91 / Hole 5 Not Started C 7 1 e24h 01/03/26 01/04/26 01/03/26 7:00 AM 01/04/26 7:00 AM 1821 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.5.5 1 2216 Install String 91 / Hole 5
2218 1.2 1.2.10.5.5.5.6 Install String 91 / Hole 5 Complete Not Started C 7 1 1 1 e5s 01/04/26 01/04/26 01/04/26 7:00 AM 01/04/26 7:00 AM 2216 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.5.6 1 2217 Install String 91 / Hole 5 Complete
2219 1.2 1.2.10.5.5.5.7 Anchor String 91 / Hole 5 Not Started C 7 1 e1h 01/04/26 01/04/26 01/04/26 7:00 AM 01/04/26 8:00 AM 2217 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.5.7 1 2218 Anchor String 91 / Hole 5
2220 1.2 1.2.10.5.5.5.8 TOS Clean Up - Wait 12 hours for Anchor to Set Not Started C 7 1 e12h 01/04/26 01/04/26 01/04/26 8:00 AM 01/04/26 8:00 PM 2218 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.5.8 1 2219 TOS Clean Up - Wait 12 hours for Anchor to Set
2221 1.2 1.2.10.5.5.5.9 String 91 / Hole 5 Cable drag Not Started C 7 1 e4h 01/04/26 01/05/26 01/04/26 8:00 PM 01/05/26 12:00 AM 2219 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.5.9 1 2220 String 91 / Hole 5 Cable drag
2222 1.2 1.2.10.5.5.5.10 Trench Hole 5 / String 91 to Pit #2 Not Started C 7 1 e4h 01/05/26 01/05/26 01/05/26 4:00 AM 01/05/26 8:00 AM 1830 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.4 CPT (Cables, SJBs), Installation Personnel 1.2.10.5.5.5.10 1 2221 Trench Hole 5 / String 91 to Pit #2
2223 1.2 1.2.10.5.5.5.11 Trench Hole 5 / String 91 to Pit #2 (USAP) Not Started C 7 1 e4h 01/05/26 01/05/26 01/05/26 4:00 AM 01/05/26 8:00 AM 2221SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.5.11 1 2222 Trench Hole 5 / String 91 to Pit #2 (USAP)
2224 1.2 1.2.10.5.5.5.12 Connect in-ice Cable to SJB 91 in Pit #2 Not Started C 7 1 e4h 01/05/26 01/05/26 01/05/26 8:00 AM 01/05/26 12:00 PM 2221 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.4 CPT (Cables, SJBs) 1.2.10.5.5.5.12 1 2223 Connect in-ice Cable to SJB 91 in Pit #2
2225 1.2 1.2.10.5.5.5.13 Backfill Hole 5 / String 91 to Pit #2 Not Started C 7 1 e4h 01/05/26 01/05/26 01/05/26 12:00 PM 01/05/26 4:00 PM 2223 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.4 CPT (Cables, SJBs), Installation Personnel 1.2.10.5.5.5.13 1 2224 Backfill Hole 5 / String 91 to Pit #2
2226 1.2 1.2.10.5.5.5.14 Backfill Hole 5 / String 91 to Pit #2 (USAP) Not Started C 7 1 e4h 01/05/26 01/05/26 01/05/26 12:00 PM 01/05/26 4:00 PM 2224SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.5.14 1 2225 Backfill Hole 5 / String 91 to Pit #2 (USAP)
2227 1.2 1.2.10.5.5.5.15 Load Sensor String 93 (Hole 7) on Sleds 3 & 4 Not Started C 7 1 e4h 01/03/26 01/03/26 01/03/26 7:00 AM 01/03/26 11:00 AM 2216SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.6 SPAT SME, Installation Personnel 1.2.10.5.5.5.15 1 2226 Load Sensor String 93 (Hole 7) on Sleds 3 & 4
2228 1.2 1.2.10.5.5.5.16 Load Sensor String 93 (Hole 7) on Sleds 3 & 4 (USAP) Not Started C 7 1 e4h 01/03/26 01/03/26 01/03/26 7:00 AM 01/03/26 11:00 AM 2226SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.5.16 1 2227 Load Sensor String 93 (Hole 7) on Sleds 3 & 4 (USAP)
2229 1.2 1.2.10.5.5.5.17 SPAT String 93 Not Started C 7 1 e72h 01/03/26 01/06/26 01/03/26 11:00 AM 01/06/26 11:00 AM 2226 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.6 SPAT SME, Installation Personnel 1.2.10.5.5.5.17 1 2228 SPAT String 93
2230 1.2 1.2.10.5.5.6 Installation - String 92 - Hole 6 Not Started P 6 1 5.999d 01/04/26 01/11/26 01/04/26 8:00 AM 01/11/26 5:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.6 1 2229 Installation - String 92 - Hole 6
2231 1.2 1.2.10.5.5.6.1 Load String 92 (Hole 6) Sensors in Sensor Handling Facility Not Started C 7 1 e12h 01/04/26 01/04/26 01/04/26 8:00 AM 01/04/26 8:00 PM 1825, 2210 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.6.1 1 2230 Load String 92 (Hole 6) Sensors in Sensor Handling Facility
2232 1.2 1.2.10.5.5.6.2 Load String 92 (Hole 6) Calibration/Special Devices & BCAs in Sensor Handling Facility Not Started C 7 1 e12h 01/04/26 01/05/26 01/04/26 8:00 PM 01/05/26 8:00 AM 2230 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Night Shift Lead, Install Shift 2 1.2.10.5.5.6.2 1 2231 Load String 92 (Hole 6) Calibration/Special Devices & BCAs in Sensor Handling Facility
2233 1.2 1.2.10.5.5.6.3 Set-up Logging Winch Not Started C 7 1 e4h 01/08/26 01/08/26 01/08/26 4:00 AM 01/08/26 8:00 AM 1836FF 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.6.3 1 2232 Set-up Logging Winch
2234 1.2 1.2.10.5.5.6.4 Dust Logging Not Started C 7 1 e12h 01/08/26 01/08/26 01/08/26 8:00 AM 01/08/26 8:00 PM 1836 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.6.4 1 2233 Dust Logging
2235 1.2 1.2.10.5.5.6.5 Dust Logging Complete Not Started C 7 1 1 1 e5s 01/08/26 01/08/26 01/08/26 8:00 PM 01/08/26 8:00 PM 2233 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.6.5 1 2234 Dust Logging Complete
2236 1.2 1.2.10.5.5.6.6 Install String 92 / Hole 6 Not Started C 7 1 e24h 01/08/26 01/09/26 01/08/26 8:00 PM 01/09/26 8:00 PM 2234 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.6.6 1 2235 Install String 92 / Hole 6
2237 1.2 1.2.10.5.5.6.7 Install String 92 / Hole 6 Complete Not Started C 7 1 1 1 e5s 01/09/26 01/09/26 01/09/26 8:00 PM 01/09/26 8:00 PM 2235 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.6.7 1 2236 Install String 92 / Hole 6 Complete
2238 1.2 1.2.10.5.5.6.8 Anchor String 92 / Hole 6 Not Started C 7 1 e1h 01/09/26 01/09/26 01/09/26 8:00 PM 01/09/26 9:00 PM 2236 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.6.8 1 2237 Anchor String 92 / Hole 6
2239 1.2 1.2.10.5.5.6.9 TOS Clean Up - Wait 12 hours for Anchor to Set Not Started C 7 1 e12h 01/09/26 01/10/26 01/09/26 9:00 PM 01/10/26 9:00 AM 2237 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.6.9 1 2238 TOS Clean Up - Wait 12 hours for Anchor to Set
2240 1.2 1.2.10.5.5.6.10 String 92 / Hole 6 Cable drag Not Started C 7 1 e4h 01/10/26 01/10/26 01/10/26 9:00 AM 01/10/26 1:00 PM 2238 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.6.10 1 2239 String 92 / Hole 6 Cable drag
2241 1.2 1.2.10.5.5.6.11 Trench Hole 6 / String 92 to Pit #2 Not Started C 7 1 e4h 01/10/26 01/10/26 01/10/26 5:00 PM 01/10/26 9:00 PM 1842 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME 1.2.10.5.5.6.11 1 2240 Trench Hole 6 / String 92 to Pit #2
2242 1.2 1.2.10.5.5.6.12 Trench Hole 6 / String 92 to Pit #2 (USAP) Not Started C 7 1 e4h 01/10/26 01/10/26 01/10/26 5:00 PM 01/10/26 9:00 PM 2240SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.6.12 1 2241 Trench Hole 6 / String 92 to Pit #2 (USAP)
2243 1.2 1.2.10.5.5.6.13 Connect in-ice Cable to SJB 92 in Pit #2 Not Started C 7 1 e4h 01/10/26 01/11/26 01/10/26 9:00 PM 01/11/26 1:00 AM 2240 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME 1.2.10.5.5.6.13 1 2242 Connect in-ice Cable to SJB 92 in Pit #2
2244 1.2 1.2.10.5.5.6.14 Backfill Hole 6 / String 92 to Pit #2 Not Started C 7 1 e4h 01/11/26 01/11/26 01/11/26 1:00 AM 01/11/26 5:00 AM 2242 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu CPT SME 1.2.10.5.5.6.14 1 2243 Backfill Hole 6 / String 92 to Pit #2
2245 1.2 1.2.10.5.5.6.15 Backfill Hole 6 / String 92 to Pit #2 (USAP) Not Started C 7 1 e4h 01/11/26 01/11/26 01/11/26 1:00 AM 01/11/26 5:00 AM 2243SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.6.15 1 2244 Backfill Hole 6 / String 92 to Pit #2 (USAP)
2246 1.2 1.2.10.5.5.7 Installation - String 93 - Hole 7 Not Started P 6 1 1.501d 01/09/26 01/13/26 01/09/26 11:00 PM 01/13/26 1:00 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.7 1 2245 Installation - String 93 - Hole 7
2247 1.2 1.2.10.5.5.7.1 Load String 93 (Hole 7) Sensors into Sensor Handling Facility Not Started C 7 1 e12h 01/09/26 01/10/26 01/09/26 11:00 PM 01/10/26 11:00 AM 1841, 2228 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Lead, Install Shift 1 1.2.10.5.5.7.1 1 2246 Load String 93 (Hole 7) Sensors into Sensor Handling Facility
2248 1.2 1.2.10.5.5.7.2 Load String 93 (Hole 7) Calibration/Special Devices & BCAs in Sensor Handling Facility Not Started C 7 1 e12h 01/10/26 01/10/26 01/10/26 11:00 AM 01/10/26 11:00 PM 2246 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Night Shift Lead, Install Shift 2 1.2.10.5.5.7.2 1 2247 Load String 93 (Hole 7) Calibration/Special Devices & BCAs in Sensor Handling Facility
2249 1.2 1.2.10.5.5.7.3 Install String 93 / Hole 7 Not Started C 7 1 e24h 01/11/26 01/12/26 01/11/26 12:00 AM 01/12/26 12:00 AM 1846 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.7.3 1 2248 Install String 93 / Hole 7
2250 1.2 1.2.10.5.5.7.4 Install String 93 / Hole 7 Complete Not Started C 7 1 1 1 e5s 01/12/26 01/12/26 01/12/26 12:00 AM 01/12/26 12:00 AM 2248 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.5.7.4 1 2249 Install String 93 / Hole 7 Complete
2251 1.2 1.2.10.5.5.7.5 Anchor String 93 / Hole 7 Not Started C 7 1 e1h 01/12/26 01/12/26 01/12/26 12:00 AM 01/12/26 1:00 AM 2249 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Tosi 1.2.10.5.5.7.5 1 2250 Anchor String 93 / Hole 7
2252 1.2 1.2.10.5.5.7.6 TOS Clean Up - Wait 12 hours for Anchor to Set Not Started C 7 1 e12h 01/12/26 01/12/26 01/12/26 1:00 AM 01/12/26 1:00 PM 2250 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 2 1.2.10.5.5.7.6 1 2251 TOS Clean Up - Wait 12 hours for Anchor to Set
2253 1.2 1.2.10.5.5.7.7 String 93 / Hole 7 Cable drag Not Started C 7 1 e4h 01/12/26 01/12/26 01/12/26 1:00 PM 01/12/26 5:00 PM 2251 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Install Shift 1 1.2.10.5.5.7.7 1 2252 String 93 / Hole 7 Cable drag
2254 1.2 1.2.10.5.5.7.8 Trench Hole 7 / String 93 to Pit #2 Not Started C 7 1 e4h 01/13/26 01/13/26 01/13/26 1:00 AM 01/13/26 5:00 AM 1848 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.4 CPT (Cables, SJBs), Installation Personnel 1.2.10.5.5.7.8 1 2253 Trench Hole 7 / String 93 to Pit #2
2255 1.2 1.2.10.5.5.7.9 Trench Hole 7 / String 93 to Pit #2 (USAP) Not Started C 7 1 e4h 01/13/26 01/13/26 01/13/26 1:00 AM 01/13/26 5:00 AM 2253SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.7.9 1 2254 Trench Hole 7 / String 93 to Pit #2 (USAP)
2256 1.2 1.2.10.5.5.7.10 Connect in-ice Cable to SJB 93 in Pit #2 Not Started C 7 1 e4h 01/13/26 01/13/26 01/13/26 5:00 AM 01/13/26 9:00 AM 2253 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.4 CPT (Cables, SJBs) 1.2.10.5.5.7.10 1 2255 Connect in-ice Cable to SJB 93 in Pit #2
2257 1.2 1.2.10.5.5.7.11 Backfill Hole 7 / String 93 to Pit #2 Not Started C 7 1 e4h 01/13/26 01/13/26 01/13/26 9:00 AM 01/13/26 1:00 PM 2255 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.5.7.11 1 2256 Backfill Hole 7 / String 93 to Pit #2
2258 1.2 1.2.10.5.5.7.12 Backfill Hole 7 / String 93 to Pit #2 (USAP) Not Started C 7 1 e4h 01/13/26 01/13/26 01/13/26 9:00 AM 01/13/26 1:00 PM 2256SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.7.12 1 2257 Backfill Hole 7 / String 93 to Pit #2 (USAP)
2259 1.2 1.2.10.5.5.7.13 Backfill, Remove Temp Vault, Flag and Survey Pit #2 Not Started C 7 1 e4h 01/13/26 01/13/26 01/13/26 9:00 AM 01/13/26 1:00 PM 2256SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.4 CPT (Cables, SJBs), Installation Personnel 1.2.10.5.5.7.13 1 2258 Backfill, Remove Temp Vault, Flag and Survey Pit #2
2260 1.2 1.2.10.5.5.7.14 Backfill, Remove Temp Vault, Flag and Survey Pit #2 (USAP) Not Started C 7 1 e4h 01/13/26 01/13/26 01/13/26 9:00 AM 01/13/26 1:00 PM 2258SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu USAP Support 1.2.10.5.5.7.14 1 2259 Backfill, Remove Temp Vault, Flag and Survey Pit #2 (USAP)
2261 1.2 1.2.10.5.6 String Installation ICL Activities Not Started P 5 1 33d 12/05/25 01/22/26 12/05/25 8:00 AM 01/22/26 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6 1 2260 String Installation ICL Activities
2262 1.2 1.2.10.5.6.1 M&O/Upgrade liaison [ongoing] Not Started C 6 1 31d 12/07/25 01/20/26 12/07/25 8:00 AM 01/20/26 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.1 1 2261 M&O/Upgrade liaison [ongoing]
2263 1.2 1.2.10.5.6.2 Update CPT installation firmware, software (pre-deployment) [1.5 days] Not Started C 6 1 1.5d 12/17/25 12/18/25 12/17/25 7:59 AM 12/18/25 11:59 AM 2263SF 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.2 1 2262 Update CPT installation firmware, software (pre-deployment) [1.5 days]
2264 1.2 1.2.10.5.6.3 Final DOM power system configuration (pre-deployment) [0.5 day] Not Started C 6 1 0.5d 12/18/25 12/18/25 12/18/25 12:59 PM 12/18/25 4:59 PM 2264SF 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.3 1 2263 Final DOM power system configuration (pre-deployment) [0.5 day]
2265 1.2 1.2.10.5.6.4 CPT final pre-deployment checkout [1 day] Not Started C 6 1 1d 12/19/25 12/19/25 12/19/25 7:59 AM 12/19/25 4:59 PM 2148SF 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.4 1 2264 CPT final pre-deployment checkout [1 day]
2266 1.2 1.2.10.5.6.5 Low-level Communications and Timing Commissioning: String 87 Not Started C 6 1 3d 12/22/25 12/24/25 12/22/25 8:00 AM 12/24/25 4:59 PM 2148 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.5 1 2265 Low-level Communications and Timing Commissioning: String 87
2267 1.2 1.2.10.5.6.6 Low-level Communications and Timing Commissioning: String 88 Not Started C 6 1 1d 12/26/25 12/26/25 12/26/25 8:00 AM 12/26/25 4:59 PM 2164 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.6 1 2266 Low-level Communications and Timing Commissioning: String 88
2268 1.2 1.2.10.5.6.7 Low-level Communications and Timing Commissioning: String 89 Not Started C 6 1 1d 12/29/25 12/29/25 12/29/25 8:00 AM 12/29/25 4:59 PM 2181 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.7 1 2267 Low-level Communications and Timing Commissioning: String 89
2269 1.2 1.2.10.5.6.8 Low-level Communications and Timing Commissioning: String 90 Not Started C 6 1 1d 01/02/26 01/02/26 01/02/26 8:00 AM 01/02/26 4:59 PM 2197 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.8 1 2268 Low-level Communications and Timing Commissioning: String 90
2270 1.2 1.2.10.5.6.9 Low-level Communications and Timing Commissioning: String 91 Not Started C 6 1 1d 01/05/26 01/05/26 01/05/26 8:00 AM 01/05/26 4:59 PM 2217 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.9 1 2269 Low-level Communications and Timing Commissioning: String 91
2271 1.2 1.2.10.5.6.10 Low-level Communications and Timing Commissioning: String 92 Not Started C 6 1 1d 01/12/26 01/12/26 01/12/26 8:00 AM 01/12/26 4:59 PM 2236 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.10 1 2270 Low-level Communications and Timing Commissioning: String 92
2272 1.2 1.2.10.5.6.11 Low-level Communications and Timing Commissioning: String 93 Not Started C 6 1 1d 01/12/26 01/12/26 01/12/26 8:00 AM 01/12/26 4:59 PM 2249 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.11 1 2271 Low-level Communications and Timing Commissioning: String 93
2273 1.2 1.2.10.5.6.12 ICL patch cabling / surface cabling / SJB debug support [ongoing] Not Started C 6 1 31d 12/05/25 01/20/26 12/05/25 8:00 AM 01/20/26 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.12 1 2272 ICL patch cabling / surface cabling / SJB debug support [ongoing]
2274 1.2 1.2.10.5.6.13 FieldHub / DAQ software integration support [ongoing] Not Started C 6 1 31d 12/09/25 01/22/26 12/09/25 8:00 AM 01/22/26 4:59 PM 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.13 1 2273 FieldHub / DAQ software integration support [ongoing]
2275 1.2 1.2.10.5.6.14 Enable FieldHub and power supply monitoring [1 day] Not Started C 6 1 1d 01/13/26 01/13/26 01/13/26 8:00 AM 01/13/26 4:59 PM 2271 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.6.14 1 2274 Enable FieldHub and power supply monitoring [1 day]
2276 1.2 1.2.10.5.7 Installation Closeout Not Started P 5 1 5d 01/13/26 01/20/26 01/13/26 9:00 AM 01/20/26 9:00 AM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu 1.2.10.5.7 1 2275 Installation Closeout
2277 1.2 1.2.10.5.7.1 Operational Debrief - String & Cable Installation Not Started C 6 1 1d 01/13/26 01/14/26 01/13/26 9:00 AM 01/14/26 9:00 AM 2255 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.7.1 1 2276 Operational Debrief - String & Cable Installation
2278 1.2 1.2.10.5.7.2 Installation and Safety Lessons Learned Complete Not Started C 6 1 1 1 0 01/14/26 01/14/26 01/14/26 9:00 AM 01/14/26 9:00 AM 2276FF 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.7.2 1 2277 Installation and Safety Lessons Learned Complete
2279 1.2 1.2.10.5.7.3 Breakdown Sensor Packaging for Entrance into USAP Waste Stream Not Started C 6 1 2d 01/14/26 01/16/26 01/14/26 9:00 AM 01/16/26 9:00 AM 2277 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.7.3 1 2278 Breakdown Sensor Packaging for Entrance into USAP Waste Stream
2280 1.2 1.2.10.5.7.4 Stow Installation Equipment Not Started C 6 1 2d 01/14/26 01/16/26 01/14/26 9:00 AM 01/16/26 9:00 AM 2277 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.7.4 1 2279 Stow Installation Equipment
2281 1.2 1.2.10.5.7.5 Crate Installation Retrograde and Deliver to Cargo Not Started C 6 1 2d 01/16/26 01/20/26 01/16/26 9:00 AM 01/20/26 9:00 AM 2279 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.7.5 1 2280 Crate Installation Retrograde and Deliver to Cargo
2282 1.2 1.2.10.5.7.6 Store SPAT Equipment Not Started C 6 1 2d 01/14/26 01/16/26 01/14/26 9:00 AM 01/16/26 9:00 AM 2277 0 0% Green $0.00 $0.00 $0.00 $0.00 delia.tosi@icecube.wisc.edu Installation Personnel 1.2.10.5.7.6 1 2281 Store SPAT Equipment
2283 1.2 1.2.10.5.8 Installation: On-Ice Labor (FS3) Not Started C 5 1 54d 11/20/25 02/06/26 11/20/25 8:00 AM 02/06/26 4:59 PM 2090SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen Team 2 shifts each of: 5 in-kind personnel + 3 drillers (drillers cost absorbed in 1.2.8)

Travel Labor: 0 hrs/ea (In Kind Labor)
- 3 days paid time during deployment
- 3 days paid time during redeployment

Travel Cost: $1,800/ea (Travel) - Covered by Institution for in-kind labor

PQ Cost: $950/ea (M&S) - Also covered by Institution
1.2.10.5.8 1 2282 Installation: On-Ice Labor (FS3)
2284 1.2 1.2.10.5.9 END NPX Installation FS3 Season Not Started C 5 1 1 1d 01/20/26 01/21/26 01/20/26 9:00 AM 01/21/26 9:00 AM 2280 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Ian McEwen 1.2.10.5.9 1 2283 END NPX Installation FS3 Season
2285 1.3 1.3 Sensors Started P 2 1 1980d 10/01/18 05/14/26 10/01/18 8:00 AM 05/14/26 4:59 PM 16.11% 50.0% Green $0.00 $0.00 $27,123.55 $168,383.82 16% Timo Karg 1.3 1 2284 Sensors
2286 1.3 1.3.1 mDOM Started P 3 1818d 10/01/18 09/25/25 10/01/18 8:00 AM 09/25/25 4:59 PM 100% 67.00% Red $0.00 $0.00 $6,496.61 $6,496.61 100% Timo Karg 1.3.1 1 2285 mDOM
2287 1.3 1.3.1.1 mDOM DAQ Electronics Started P 4 1140d 10/01/18 02/10/23 10/01/18 8:00 AM 02/10/23 4:59 PM 100% 66.00% Red $0.00 $0.00 $3,453.88 $3,453.88 100% Timo Karg 1.3.1.1 1 2286 mDOM DAQ Electronics
2288 1.3 1.3.1.1.1 Preliminary design phase Complete P 5 261d 10/01/18 09/30/19 10/01/18 8:00 AM 09/30/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.1 1 2287 Preliminary design phase
2289 1.3 1.3.1.1.1.1 Mainboard conceptual design Complete C 6 55d 10/01/18 12/14/18 10/01/18 8:00 AM 12/14/18 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.1.1 1 2288 Mainboard conceptual design
2290 1.3 1.3.1.1.1.2 Schematic development Complete C 6 60d 12/17/18 03/08/19 12/17/18 8:00 AM 03/08/19 4:59 PM 2288 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Removed 1.3.1.1.1.2 1 2289 Schematic development
2291 1.3 1.3.1.1.1.3 mDOM DAQ schematic ready Complete C 6 1 1d 03/11/19 03/11/19 03/11/19 8:00 AM 03/11/19 4:59 PM 2289 100% 100% Gray Need to update schedule due to the introduction of an additional revision of the mDOM mainboard. First articles of the intermediate revision have been delivered and will be characterized and reviewed at the mDOM electronics PDR in August 2019 $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Removed 1.3.1.1.1.3 1 2290 mDOM DAQ schematic ready
2292 1.3 1.3.1.1.1.4 Build 4 ch. analog-front end (AFE) demonstrator board Complete C 6 50d 12/17/18 02/22/19 12/17/18 8:00 AM 02/22/19 4:59 PM 2288 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.1.4 1 2291 Build 4 ch. analog-front end (AFE) demonstrator board
2293 1.3 1.3.1.1.1.5 Characterization of AFE performance Complete C 6 20d 02/25/19 03/22/19 02/25/19 8:00 AM 03/22/19 4:59 PM 2291 99% 100% Gray Will be finished in time for the mDOM electronics PDR scheduled for August 26, 2019 $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.1.5 1 2292 Characterization of AFE performance
2294 1.3 1.3.1.1.1.6 Test Mainboard (mDOT) schematic development Complete C 6 80d 12/17/18 04/05/19 12/17/18 8:00 AM 04/05/19 4:59 PM 2288 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.1.1.6 1 2293 Test Mainboard (mDOT) schematic development
2295 1.3 1.3.1.1.1.7 Test Mainboard (mDOT) layout Complete C 6 30d 04/08/19 05/17/19 04/08/19 8:00 AM 05/17/19 4:59 PM 2293 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.1.1.7 1 2294 Test Mainboard (mDOT) layout
2296 1.3 1.3.1.1.1.8 Test mainboard (mDOT) production Complete C 6 20d 05/20/19 06/14/19 05/20/19 8:00 AM 06/14/19 4:59 PM 2294 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.1.1.8 1 2295 Test mainboard (mDOT) production
2297 1.3 1.3.1.1.1.9 Test mainboard (mDOT) shipment to PSU Complete C 6 10d 06/17/19 06/28/19 06/17/19 8:00 AM 06/28/19 4:59 PM 2295 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.1.1.9 1 2296 Test mainboard (mDOT) shipment to PSU
2298 1.3 1.3.1.1.1.10 Test mainboard (mDOT) firmware development Complete C 6 20d 07/01/19 07/26/19 07/01/19 8:00 AM 07/26/19 4:59 PM 2296 99% 100% Gray Delayed in favor of D-Egg mainboard firmware development $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.1.1.10 1 2297 Test mainboard (mDOT) firmware development
2299 1.3 1.3.1.1.1.11 Test mainboard (mDOT) characterization Complete C 6 46d 07/29/19 09/30/19 07/29/19 8:00 AM 09/30/19 4:59 PM 2297 99% 100% Gray Catching up to complete this in time for WBS 1.3.1.1.2.7 $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.1.1.11 1 2298 Test mainboard (mDOT) characterization
2300 1.3 1.3.1.1.2 Final design phase Started P 5 879d 10/01/19 02/10/23 10/01/19 8:00 AM 02/10/23 4:59 PM 100% 64.00% Red $0.00 $0.00 $3,453.88 $3,453.88 100% Timo Karg 1.3.1.1.2 1 2299 Final design phase
2301 1.3 1.3.1.1.2.1 mDOM Mainboard Rev1 Complete P 6 319d 10/01/19 12/18/20 10/01/19 8:00 AM 12/18/20 4:59 PM 99% 100% Gray Delayed due to priorization of mini-Field Hub work $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.1.1.2.1 1 2300 mDOM Mainboard Rev1
2302 1.3 1.3.1.1.2.1.1 Mainboard layout Complete C 7 20d 12/24/19 01/20/20 12/24/19 8:00 AM 01/20/20 4:59 PM 2304 99% 100% Gray Delayed due to priorization of mini-Field Hub work $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.1.1.2.1.1 1 2301 Mainboard layout
2303 1.3 1.3.1.1.2.1.2 Commissioning Complete C 7 20d 02/18/20 03/16/20 02/18/20 8:00 AM 03/16/20 4:59 PM 2303 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.1.2 1 2302 Commissioning
2304 1.3 1.3.1.1.2.1.4 Mainboard production Complete C 7 20d 01/21/20 02/17/20 01/21/20 8:00 AM 02/17/20 4:59 PM 2301 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.1.1.2.1.4 1 2303 Mainboard production
2305 1.3 1.3.1.1.2.1.5 Mainboard schematic development Complete C 7 60d 10/01/19 12/23/19 10/01/19 8:00 AM 12/23/19 4:59 PM 100% 100% Gray Delayed due to priorization of mini-Field Hub work $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.1.2.1.5 1 2304 Mainboard schematic development
2306 1.3 1.3.1.1.2.1.6 Ship Rev1 Mainboards to WIPAC and PSU Complete C 7 10d 12/07/20 12/18/20 12/07/20 8:00 AM 12/18/20 4:59 PM 2302FS +189d 97% 100% Gray Delayed due to priorization of mini-Field Hub work $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.1.2.1.6 1 2305 Ship Rev1 Mainboards to WIPAC and PSU
2307 1.3 1.3.1.1.2.2 mDOM Mainboard Rev2 Started P 6 300d 01/25/21 03/18/22 01/25/21 8:00 AM 03/18/22 4:59 PM 100% 85.00% Yellow $0.00 $0.00 $3,453.88 $3,453.88 100% Timo Karg 1.3.1.1.2.2 1 2306 mDOM Mainboard Rev2
2308 1.3 1.3.1.1.2.2.1 Schematic changes Complete C 7 5d 01/25/21 01/29/21 01/25/21 8:00 AM 01/29/21 4:59 PM 93% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.2.1 1 2307 Schematic changes
2309 1.3 1.3.1.1.2.2.2 Layout changes Complete C 7 5d 02/01/21 02/05/21 02/01/21 8:00 AM 02/05/21 4:59 PM 2307 93% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.2.2 1 2308 Layout changes
2310 1.3 1.3.1.1.2.2.3 Production and assembly of 15 PCBs Complete C 7 20d 02/08/21 03/05/21 02/08/21 8:00 AM 03/05/21 4:59 PM 2308 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.2.3 1 2309 Production and assembly of 15 PCBs
2311 1.3 1.3.1.1.2.2.4 Comissioning Complete C 7 10d 03/08/21 03/19/21 03/08/21 8:00 AM 03/19/21 4:59 PM 2309 100% 100% Gray $3,453.88 $3,453.88 $3,453.88 $3,453.88 100% $3,453.88 Timo Karg 1.3.1.1.2.2.4 1 2310 Comissioning
2312 1.3 1.3.1.1.2.2.5 (14) Rev. 2 Mainboards available for testing Complete C 7 1 0 09/20/21 09/20/21 09/20/21 8:00 AM 09/20/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.2.5 1 2311 (14) Rev. 2 Mainboards available for testing
2313 1.3 1.3.1.1.2.2.6 Rev. 2 Mainboard design verification Complete C 7 15d 09/20/21 10/08/21 09/20/21 8:00 AM 10/08/21 4:59 PM 2311 98% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.2.6 1 2312 Rev. 2 Mainboard design verification
2314 1.3 1.3.1.1.2.2.7 Ship remaining parts to DESY HH for test production Complete C 7 10d 11/01/21 11/12/21 11/01/21 8:00 AM 11/12/21 4:59 PM 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.2.7 1 2313 Ship remaining parts to DESY HH for test production
2315 1.3 1.3.1.1.2.2.8 Test production of (8) Rev. 2 Mainboards at DESY HH, pt. 1 Complete C 7 30d 12/13/21 01/21/22 12/13/21 8:00 AM 01/21/22 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.2.8 1 2314 Test production of (8) Rev. 2 Mainboards at DESY HH, pt. 1
2316 1.3 1.3.1.1.2.2.9 Setting up automated impedance testing and testing of (8) Rev. 2 Mainboards Complete C 7 20d 01/24/22 02/18/22 01/24/22 8:00 AM 02/18/22 4:59 PM 2314 30% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.2.9 1 2315 Setting up automated impedance testing and testing of (8) Rev. 2 Mainboards
2317 1.3 1.3.1.1.2.2.10 Ship (2) HH Mainboards to WIPAC for HALT Not Started C 7 10d 02/21/22 03/04/22 02/21/22 8:00 AM 03/04/22 4:59 PM 2315 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.2.10 1 2316 Ship (2) HH Mainboards to WIPAC for HALT
2318 1.3 1.3.1.1.2.2.11 mDOM Mainboard HALT Not Started C 7 10d 03/07/22 03/18/22 03/07/22 8:00 AM 03/18/22 4:59 PM 2316 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.2.11 1 2317 mDOM Mainboard HALT
2319 1.3 1.3.1.1.2.3 mDOM Mainboard Rev3 Started P 6 470d 04/26/21 02/10/23 04/26/21 8:00 AM 02/10/23 4:59 PM 64% 27.00% Red $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3 1 2318 mDOM Mainboard Rev3
2320 1.3 1.3.1.1.2.3.1 Schematic changes Complete C 7 5d 04/26/21 04/30/21 04/26/21 8:00 AM 04/30/21 4:59 PM 93% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.1 1 2319 Schematic changes
2321 1.3 1.3.1.1.2.3.2 Layout changes Complete C 7 5d 05/03/21 05/07/21 05/03/21 8:00 AM 05/07/21 4:59 PM 2319 93% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.2 1 2320 Layout changes
2322 1.3 1.3.1.1.2.3.3 Production and assembly of test series Complete C 7 20d 05/10/21 06/04/21 05/10/21 8:00 AM 06/04/21 4:59 PM 2320 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.3 1 2321 Production and assembly of test series
2323 1.3 1.3.1.1.2.3.4 Comissioning and final design verification Complete C 7 20d 06/07/21 07/02/21 06/07/21 8:00 AM 07/02/21 4:59 PM 2321 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.4 1 2322 Comissioning and final design verification
2324 1.3 1.3.1.1.2.3.5 Production and testing of 450 mDOM Mainboards Started P 7 265d 01/10/22 01/13/23 01/10/22 8:00 AM 01/13/23 4:59 PM 2% 15.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.5 1 2323 Production and testing of 450 mDOM Mainboards
2325 1.3 1.3.1.1.2.3.5.1 Production of (40) Mainboards with available parts Not Started C 8 20d 02/28/22 03/25/22 02/28/22 8:00 AM 03/25/22 4:59 PM 0% 0% Green POs for all parts for (40) MBs have been placed throughout 2021; not all parts received, yet $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.5.1 1 2324 Production of (40) Mainboards with available parts
2326 1.3 1.3.1.1.2.3.5.2 Tender and procurement of parts for main production run Started C 8 1 130d 01/10/22 07/08/22 01/10/22 8:00 AM 07/08/22 4:59 PM 12% 33% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.5.2 1 2325 Tender and procurement of parts for main production run
2327 1.3 1.3.1.1.2.3.5.3 Parts delivery Not Started C 8 1 100d 07/11/22 11/25/22 07/11/22 8:00 AM 11/25/22 4:59 PM 2325 0% 0% Green All the uncertainty about worldwide supply chains lives in this activity. Uncertainty is very high! $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.5.3 1 2326 Parts delivery
2328 1.3 1.3.1.1.2.3.5.4 All components for mDOM Mainboard production available Not Started C 8 1 1 0 11/25/22 11/25/22 11/25/22 4:59 PM 11/25/22 4:59 PM 2326 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.3.1.1.2.3.5.4 1 2327 All components for mDOM Mainboard production available
2329 1.3 1.3.1.1.2.3.5.5 Production and burn-in of mainboards (rate: (60) / week), pt. 1 Not Started C 8 1 20d 11/28/22 12/23/22 11/28/22 8:00 AM 12/23/22 4:59 PM 2327 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.5.5 1 2328 Production and burn-in of mainboards (rate: (60) / week), pt. 1
2330 1.3 1.3.1.1.2.3.5.6 Holiday Break Not Started C 8 5d 12/26/22 12/30/22 12/26/22 8:00 AM 12/30/22 4:59 PM 2328 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.5.6 1 2329 Holiday Break
2331 1.3 1.3.1.1.2.3.5.7 Production and burn-in of mainboards (rate: (60) / week), pt. 2 Not Started C 8 1 10d 01/02/23 01/13/23 01/02/23 8:00 AM 01/13/23 4:59 PM 2329 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.5.7 1 2330 Production and burn-in of mainboards (rate: (60) / week), pt. 2
2332 1.3 1.3.1.1.2.3.6 Ship mainboards to MSU Not Started C 7 20d 01/16/23 02/10/23 01/16/23 8:00 AM 02/10/23 4:59 PM 2330 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.3.6 1 2331 Ship mainboards to MSU
2333 1.3 1.3.1.1.2.4 Design of mDOM Mainboard burn-in and acceptance testing Complete C 6 40d 01/04/21 02/26/21 01/04/21 8:00 AM 02/26/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.4 1 2332 Design of mDOM Mainboard burn-in and acceptance testing
2334 1.3 1.3.1.1.2.5 Construction and commissioning of mDOM Mainboard burn-in and acceptance testing Started C 6 60d 03/01/21 05/21/21 03/01/21 8:00 AM 05/21/21 4:59 PM 2332 100% 33.00% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.2.5 1 2333 Construction and commissioning of mDOM Mainboard burn-in and acceptance testing
2335 1.3 1.3.1.1.3 mDOM Mainboard firmware development Complete C 5 456d 01/02/20 09/30/21 01/02/20 8:00 AM 09/30/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.3 1 2334 mDOM Mainboard firmware development
2336 1.3 1.3.1.1.4 Tender and procurement (test production) Started C 5 120d 04/22/20 10/06/20 04/22/20 8:00 AM 10/06/20 4:59 PM 100% 75.00% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.4 1 2335 Tender and procurement (test production)
2337 1.3 1.3.1.1.5 Tender and procurement (series production) Should have Started C 5 200d 04/22/20 01/26/21 04/22/20 8:00 AM 01/26/21 4:59 PM 2335SS 100% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.5 1 2336 Tender and procurement (series production)
2338 1.3 1.3.1.1.6 mDOM Adapter Board (mDAB) Started P 5 180d 01/31/22 10/07/22 01/31/22 8:00 AM 10/07/22 4:59 PM 1% 6% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.6 1 2337 mDOM Adapter Board (mDAB)
2339 1.3 1.3.1.1.6.1 Procurement of parts for (40) mDABs Started C 6 20d 01/31/22 02/25/22 01/31/22 8:00 AM 02/25/22 4:59 PM 4% 50% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.6.1 1 2338 Procurement of parts for (40) mDABs
2340 1.3 1.3.1.1.6.2 Production of (40) mDABs in the DESY Zeuthen workshop Not Started C 6 20d 02/28/22 03/25/22 02/28/22 8:00 AM 03/25/22 4:59 PM 2338 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.6.2 1 2339 Production of (40) mDABs in the DESY Zeuthen workshop
2341 1.3 1.3.1.1.6.3 Procurement of parts for mDAB main production run Not Started C 6 60d 03/28/22 06/17/22 03/28/22 8:00 AM 06/17/22 4:59 PM 2339 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.6.3 1 2340 Procurement of parts for mDAB main production run
2342 1.3 1.3.1.1.6.4 All components for mDAB production available Not Started C 6 1 0 06/17/22 06/17/22 06/17/22 4:59 PM 06/17/22 4:59 PM 2340 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.3.1.1.6.4 1 2341 All components for mDAB production available
2343 1.3 1.3.1.1.6.5 Series production of mDABs in the DESY Zeuthen workshop Not Started C 6 80d 06/20/22 10/07/22 06/20/22 8:00 AM 10/07/22 4:59 PM 2341 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.1.6.5 1 2342 Series production of mDABs in the DESY Zeuthen workshop
2344 1.3 1.3.1.2 mDOM PMT Started P 4 1047d 10/01/18 10/04/22 10/01/18 8:00 AM 10/04/22 4:59 PM 89% 88.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2 1 2343 mDOM PMT
2345 1.3 1.3.1.2.1 Preliminary design phase Complete P 5 40d 10/01/18 11/23/18 10/01/18 8:00 AM 11/23/18 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.1 1 2344 Preliminary design phase
2346 1.3 1.3.1.2.1.1 Qualification of Hamamatsu R12199 Complete C 6 40d 10/01/18 11/23/18 10/01/18 8:00 AM 11/23/18 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.1.1 1 2345 Qualification of Hamamatsu R12199
2347 1.3 1.3.1.2.2 Final design phase Complete P 5 61d 11/26/18 02/18/19 11/26/18 8:00 AM 02/18/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.2 1 2346 Final design phase
2348 1.3 1.3.1.2.2.1 Delivery of 48 HZC PMTs Complete C 6 1 1d 11/26/18 11/26/18 11/26/18 8:00 AM 11/26/18 4:59 PM 2345 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.2.1 1 2347 Delivery of 48 HZC PMTs
2349 1.3 1.3.1.2.2.2 Qualification of HZC PMTs Complete C 6 60d 11/26/18 02/15/19 11/26/18 8:00 AM 02/15/19 4:59 PM 2347SS 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.2.2 1 2348 Qualification of HZC PMTs
2350 1.3 1.3.1.2.2.3 Decision on baseline PMT Complete C 6 1 1d 02/18/19 02/18/19 02/18/19 8:00 AM 02/18/19 4:59 PM 2348 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.2.3 1 2349 Decision on baseline PMT
2351 1.3 1.3.1.2.3 Procurement of PMTs for DVT Complete C 5 60d 10/01/19 12/23/19 10/01/19 8:00 AM 12/23/19 4:59 PM 100% 100% Gray Vendor specifications have been submitted to Hamamatsu and HZC Photonics $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.3 1 2350 Procurement of PMTs for DVT
2352 1.3 1.3.1.2.5 Tender and procurement (series production) Complete P 5 340d 09/02/19 12/18/20 09/02/19 8:00 AM 12/18/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.1.2.5 1 2351 Tender and procurement (series production)
2353 1.3 1.3.1.2.5.1 Publish tender Complete C 6 49d 09/02/19 11/07/19 09/02/19 8:00 AM 11/07/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.5.1 1 2352 Publish tender
2354 1.3 1.3.1.2.5.2 PMT Purchase Order placed Complete C 6 1 1d 11/08/19 11/08/19 11/08/19 8:00 AM 11/08/19 4:59 PM 2352 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.5.2 1 2353 PMT Purchase Order placed
2355 1.3 1.3.1.2.5.3 Production preparation by manufacturer Complete C 6 120d 11/08/19 04/23/20 11/08/19 8:00 AM 04/23/20 4:59 PM 2353SS 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.5.3 1 2354 Production preparation by manufacturer
2356 1.3 1.3.1.2.5.4 PMT Production Batch #1 (Qty. 1250) Complete C 6 19d 04/24/20 05/20/20 04/24/20 8:00 AM 05/20/20 4:59 PM 2354 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.5.4 1 2355 PMT Production Batch #1 (Qty. 1250)
2357 1.3 1.3.1.2.5.5 PMT Production Batch #2 (Qty. 1250) Complete C 6 22d 05/21/20 06/19/20 05/21/20 8:00 AM 06/19/20 4:59 PM 2355 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.5.5 1 2356 PMT Production Batch #2 (Qty. 1250)
2358 1.3 1.3.1.2.5.6 PMT Production Batch #3 (Qty. 1375) Complete C 6 21d 06/22/20 07/20/20 06/22/20 8:00 AM 07/20/20 4:59 PM 2356 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.5.6 1 2357 PMT Production Batch #3 (Qty. 1375)
2359 1.3 1.3.1.2.5.7 PMT Production Batch #4 (Qty. 1375) Complete C 6 23d 07/21/20 08/20/20 07/21/20 8:00 AM 08/20/20 4:59 PM 2357 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.5.7 1 2358 PMT Production Batch #4 (Qty. 1375)
2360 1.3 1.3.1.2.5.8 PMT Production Batch #5 (Qty. 1375) Complete C 6 21d 08/21/20 09/18/20 08/21/20 8:00 AM 09/18/20 4:59 PM 2358 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.5.8 1 2359 PMT Production Batch #5 (Qty. 1375)
2361 1.3 1.3.1.2.5.9 PMT Production Batch #6 (Qty. 1375) Complete C 6 22d 09/21/20 10/20/20 09/21/20 8:00 AM 10/20/20 4:59 PM 2359 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.5.9 1 2360 PMT Production Batch #6 (Qty. 1375)
2362 1.3 1.3.1.2.5.10 PMT Production Batch #7 (Qty. 2000) Complete C 6 23d 10/21/20 11/20/20 10/21/20 8:00 AM 11/20/20 4:59 PM 2360 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.5.10 1 2361 PMT Production Batch #7 (Qty. 2000)
2363 1.3 1.3.1.2.5.11 PMT Production Batch #8 (Qty. 500) Complete C 6 20d 11/23/20 12/18/20 11/23/20 8:00 AM 12/18/20 4:59 PM 2361 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.5.11 1 2362 PMT Production Batch #8 (Qty. 500)
2364 1.3 1.3.1.2.6 Production of PMT+Base assembly Complete P 5 300d 11/08/19 12/31/20 11/08/19 8:00 AM 12/31/20 4:59 PM 98% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.6 1 2363 Production of PMT+Base assembly
2365 1.3 1.3.1.2.6.1 Preparation of soldering of PMT Base PCAs with PMT manufacturer Complete C 6 120d 11/08/19 04/23/20 11/08/19 8:00 AM 04/23/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.6.1 1 2364 Preparation of soldering of PMT Base PCAs with PMT manufacturer
2366 1.3 1.3.1.2.6.2 PMT+Base Assy. Production Batch #1 (Qty. 1250) Complete C 6 10d 06/03/20 06/16/20 06/03/20 8:00 AM 06/16/20 4:59 PM 2364FS +28d 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.6.2 1 2365 PMT+Base Assy. Production Batch #1 (Qty. 1250)
2367 1.3 1.3.1.2.6.3 PMT+Base Assy. Production Batch #2 (Qty. 1250) Complete C 6 10d 06/17/20 06/30/20 06/17/20 8:00 AM 06/30/20 4:59 PM 2365 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.6.3 1 2366 PMT+Base Assy. Production Batch #2 (Qty. 1250)
2368 1.3 1.3.1.2.6.4 PMT+Base Assy. Production Batch #3 (Qty. 1375) Complete C 6 10d 07/01/20 07/14/20 07/01/20 8:00 AM 07/14/20 4:59 PM 2366 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.6.4 1 2367 PMT+Base Assy. Production Batch #3 (Qty. 1375)
2369 1.3 1.3.1.2.6.5 PMT+Base Assy. Production Batch #4 (Qty. 1375) Complete C 6 10d 07/24/20 08/06/20 07/24/20 8:00 AM 08/06/20 4:59 PM 2367FS +7d 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.6.5 1 2368 PMT+Base Assy. Production Batch #4 (Qty. 1375)
2370 1.3 1.3.1.2.6.6 PMT+Base Assy. Production Batch #5 (Qty. 1375) Complete C 6 10d 08/27/20 09/09/20 08/27/20 8:00 AM 09/09/20 4:59 PM 2368FS +14d 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.6.6 1 2369 PMT+Base Assy. Production Batch #5 (Qty. 1375)
2371 1.3 1.3.1.2.6.7 PMT+Base Assy. Production Batch #6 (Qty. 1375) Complete C 6 10d 10/09/20 10/22/20 10/09/20 8:00 AM 10/22/20 4:59 PM 2369FS +21d 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.6.7 1 2370 PMT+Base Assy. Production Batch #6 (Qty. 1375)
2372 1.3 1.3.1.2.6.8 PMT+Base Assy. Production Batch #7 (Qty. 2000) Complete C 6 10d 11/18/20 12/01/20 11/18/20 8:00 AM 12/01/20 4:59 PM 2370FS +18d 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.6.8 1 2371 PMT+Base Assy. Production Batch #7 (Qty. 2000)
2373 1.3 1.3.1.2.6.9 PMT+Base Assy. Production Batch #8 (Qty. 500) Complete C 6 10d 12/18/20 12/31/20 12/18/20 8:00 AM 12/31/20 4:59 PM 2371FS +12d 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.6.9 1 2372 PMT+Base Assy. Production Batch #8 (Qty. 500)
2374 1.3 1.3.1.2.7 Acceptance testing and calibration of incoming PMT+Base assemblies Complete P 5 567d 01/01/19 03/03/21 01/01/19 8:00 AM 03/03/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.7 1 2373 Acceptance testing and calibration of incoming PMT+Base assemblies
2375 1.3 1.3.1.2.7.1 Development and construction of test facilities Complete C 6 360d 01/01/19 05/18/20 01/01/19 8:00 AM 05/18/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.7.1 1 2374 Development and construction of test facilities
2376 1.3 1.3.1.2.7.2 Incoming PMT+Base Test Batch #1 (Qty. 1250) Complete C 6 20d 07/01/20 07/28/20 07/01/20 8:00 AM 07/28/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.7.2 1 2375 Incoming PMT+Base Test Batch #1 (Qty. 1250)
2377 1.3 1.3.1.2.7.3 Incoming PMT+Base Test Batch #2 (Qty. 1250) Complete C 6 20d 07/29/20 08/25/20 07/29/20 8:00 AM 08/25/20 4:59 PM 2375 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.7.3 1 2376 Incoming PMT+Base Test Batch #2 (Qty. 1250)
2378 1.3 1.3.1.2.7.4 Incoming PMT+Base Test Batch #3 (Qty. 1375) Complete C 6 20d 08/26/20 09/22/20 08/26/20 8:00 AM 09/22/20 4:59 PM 2376 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.7.4 1 2377 Incoming PMT+Base Test Batch #3 (Qty. 1375)
2379 1.3 1.3.1.2.7.5 Incoming PMT+Base Test Batch #4 (Qty. 1375) Complete C 6 20d 09/23/20 10/20/20 09/23/20 8:00 AM 10/20/20 4:59 PM 2377 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.7.5 1 2378 Incoming PMT+Base Test Batch #4 (Qty. 1375)
2380 1.3 1.3.1.2.7.6 Incoming PMT+Base Test Batch #5 (Qty. 1375) Complete C 6 20d 11/02/20 11/27/20 11/02/20 8:00 AM 11/27/20 4:59 PM 2378FS +8d 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.7.6 1 2379 Incoming PMT+Base Test Batch #5 (Qty. 1375)
2381 1.3 1.3.1.2.7.7 Incoming PMT+Base Test Batch #6 (Qty. 1375) Complete C 6 20d 12/02/20 12/29/20 12/02/20 8:00 AM 12/29/20 4:59 PM 2379FS +2d 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.7.7 1 2380 Incoming PMT+Base Test Batch #6 (Qty. 1375)
2382 1.3 1.3.1.2.7.8 Incoming PMT+Base Test Batch #7 (Qty. 2000) Complete C 6 20d 01/01/21 01/28/21 01/01/21 8:00 AM 01/28/21 4:59 PM 2380FS +2d 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.7.8 1 2381 Incoming PMT+Base Test Batch #7 (Qty. 2000)
2383 1.3 1.3.1.2.7.9 Incoming PMT+Base Test Batch #8 (Qty. 500) Complete C 6 20d 02/04/21 03/03/21 02/04/21 8:00 AM 03/03/21 4:59 PM 2381FS +4d 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.2.7.9 1 2382 Incoming PMT+Base Test Batch #8 (Qty. 500)
2384 1.3 1.3.1.2.8 Incoming PMT+uBase Testing Started P 5 312d 07/26/21 10/04/22 07/26/21 8:00 AM 10/04/22 4:59 PM 30% 35.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8 1 2383 Incoming PMT+uBase Testing
2385 1.3 1.3.1.2.8.1 Aachen Site Started P 6 312d 07/26/21 10/04/22 07/26/21 8:00 AM 10/04/22 4:59 PM 21% 35.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1 1 2384 Aachen Site
2386 1.3 1.3.1.2.8.1.1 (5600) PMT Assemblies available in Aachen Complete C 7 1 0 07/26/21 07/26/21 07/26/21 8:00 AM 07/26/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.1 1 2385 (5600) PMT Assemblies available in Aachen
2387 1.3 1.3.1.2.8.1.2 (4) Rev. 1 mDOM Mainboard available in Aachen Complete C 7 1 0 09/20/21 09/20/21 09/20/21 8:00 AM 09/20/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.2 1 2386 (4) Rev. 1 mDOM Mainboard available in Aachen
2388 1.3 1.3.1.2.8.1.3 Commissioning of Aachen test stand Complete C 7 55d 09/20/21 12/03/21 09/20/21 8:00 AM 12/03/21 4:59 PM 2386 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.3 1 2387 Commissioning of Aachen test stand
2389 1.3 1.3.1.2.8.1.4 Screening of high-dark count rate PMTs Complete C 7 40d 12/06/21 01/28/22 12/06/21 8:00 AM 01/28/22 4:59 PM 2387 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.4 1 2388 Screening of high-dark count rate PMTs
2390 1.3 1.3.1.2.8.1.5 Optimization of Aachen test stand Started C 7 40d 01/31/22 03/25/22 01/31/22 8:00 AM 03/25/22 4:59 PM 2388 2% 2% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.5 1 2389 Optimization of Aachen test stand
2391 1.3 1.3.1.2.8.1.6 Aachen test stand ready for production Not Started C 7 1 0 03/25/22 03/25/22 03/25/22 4:59 PM 03/25/22 4:59 PM 2389 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.6 1 2390 Aachen test stand ready for production
2392 1.3 1.3.1.2.8.1.7 Test of (500) PMT Assemblies Not Started C 7 20d 03/28/22 04/22/22 03/28/22 8:00 AM 04/22/22 4:59 PM 2390 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.7 1 2391 Test of (500) PMT Assemblies
2393 1.3 1.3.1.2.8.1.8 Test of (500) PMT Assemblies Not Started C 7 20d 04/25/22 05/20/22 04/25/22 8:00 AM 05/20/22 4:59 PM 2391 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.8 1 2392 Test of (500) PMT Assemblies
2394 1.3 1.3.1.2.8.1.9 Test of (500) PMT Assemblies Not Started C 7 15d 05/23/22 06/10/22 05/23/22 8:00 AM 06/10/22 4:59 PM 2392 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.9 1 2393 Test of (500) PMT Assemblies
2395 1.3 1.3.1.2.8.1.10 Test of (500) PMT Assemblies Not Started C 7 10d 06/13/22 06/24/22 06/13/22 8:00 AM 06/24/22 4:59 PM 2393 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.10 1 2394 Test of (500) PMT Assemblies
2396 1.3 1.3.1.2.8.1.11 Test of (500) PMT Assemblies Not Started C 7 10d 06/27/22 07/08/22 06/27/22 8:00 AM 07/08/22 4:59 PM 2394 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.11 1 2395 Test of (500) PMT Assemblies
2397 1.3 1.3.1.2.8.1.12 Test of (500) PMT Assemblies Not Started C 7 10d 07/11/22 07/22/22 07/11/22 8:00 AM 07/22/22 4:59 PM 2395 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.12 1 2396 Test of (500) PMT Assemblies
2398 1.3 1.3.1.2.8.1.13 Test of (500) PMT Assemblies Not Started C 7 10d 07/25/22 08/05/22 07/25/22 8:00 AM 08/05/22 4:59 PM 2396 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.13 1 2397 Test of (500) PMT Assemblies
2399 1.3 1.3.1.2.8.1.14 Test of (500) PMT Assemblies Not Started C 7 10d 08/08/22 08/19/22 08/08/22 8:00 AM 08/19/22 4:59 PM 2397 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.14 1 2398 Test of (500) PMT Assemblies
2400 1.3 1.3.1.2.8.1.15 Test of (500) PMT Assemblies Not Started C 7 10d 08/22/22 09/02/22 08/22/22 8:00 AM 09/02/22 4:59 PM 2398 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.15 1 2399 Test of (500) PMT Assemblies
2401 1.3 1.3.1.2.8.1.16 Test of (500) PMT Assemblies Not Started C 7 10d 09/05/22 09/16/22 09/05/22 8:00 AM 09/16/22 4:59 PM 2399 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.16 1 2400 Test of (500) PMT Assemblies
2402 1.3 1.3.1.2.8.1.17 Test of (500) PMT Assemblies Not Started C 7 10d 09/19/22 09/30/22 09/19/22 8:00 AM 09/30/22 4:59 PM 2400 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.17 1 2401 Test of (500) PMT Assemblies
2403 1.3 1.3.1.2.8.1.18 Test of (100) PMT Assemblies Not Started C 7 2d 10/03/22 10/04/22 10/03/22 8:00 AM 10/04/22 4:59 PM 2401 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.18 1 2402 Test of (100) PMT Assemblies
2404 1.3 1.3.1.2.8.1.19 PMT Testing in Aachen complete Not Started C 7 1 0 10/04/22 10/04/22 10/04/22 4:59 PM 10/04/22 4:59 PM 2402 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.1.19 1 2403 PMT Testing in Aachen complete
2405 1.3 1.3.1.2.8.2 Dortmund Site Started P 6 261d 08/30/21 08/29/22 08/30/21 8:00 AM 08/29/22 4:59 PM 38% 35.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2 1 2404 Dortmund Site
2406 1.3 1.3.1.2.8.2.1 (4) Rev. 1 mDOM Mainboard available in Dortmund Complete C 7 1 0 10/11/21 10/11/21 10/11/21 8:00 AM 10/11/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.1 1 2405 (4) Rev. 1 mDOM Mainboard available in Dortmund
2407 1.3 1.3.1.2.8.2.2 Reference PMTs available in Dortmund Complete C 7 1 0 09/27/21 09/27/21 09/27/21 8:00 AM 09/27/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.2 1 2406 Reference PMTs available in Dortmund
2408 1.3 1.3.1.2.8.2.3 Arrival of (720) PMT Assemblies in Dortmund Complete C 7 1 0 08/30/21 08/30/21 08/30/21 8:00 AM 08/30/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.3 1 2407 Arrival of (720) PMT Assemblies in Dortmund
2409 1.3 1.3.1.2.8.2.4 Arrival of (720) PMT Assemblies in Dortmund Complete C 7 1 0 10/01/21 10/01/21 10/01/21 8:00 AM 10/01/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.4 1 2408 Arrival of (720) PMT Assemblies in Dortmund
2410 1.3 1.3.1.2.8.2.5 Arrival of (1620) PMT Assemblies in Dortmund Complete C 7 1 0 11/01/21 11/01/21 11/01/21 8:00 AM 11/01/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.5 1 2409 Arrival of (1620) PMT Assemblies in Dortmund
2411 1.3 1.3.1.2.8.2.6 Arrival of (1720) PMT Assemblies in Dortmund Complete C 7 1 0 12/01/21 12/01/21 12/01/21 8:00 AM 12/01/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.6 1 2410 Arrival of (1720) PMT Assemblies in Dortmund
2412 1.3 1.3.1.2.8.2.7 Commissioning of Dortmund test stand Complete C 7 40d 10/11/21 12/03/21 10/11/21 8:00 AM 12/03/21 4:59 PM 2405, 2406 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.7 1 2411 Commissioning of Dortmund test stand
2413 1.3 1.3.1.2.8.2.8 Screening of high-dark count rate PMTs Complete C 7 40d 12/06/21 01/28/22 12/06/21 8:00 AM 01/28/22 4:59 PM 2411 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.8 1 2412 Screening of high-dark count rate PMTs
2414 1.3 1.3.1.2.8.2.9 Optimization of Dortmund test stand Started C 7 40d 01/31/22 03/25/22 01/31/22 8:00 AM 03/25/22 4:59 PM 2412 2% 2% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.9 1 2413 Optimization of Dortmund test stand
2415 1.3 1.3.1.2.8.2.10 Dortmund test stand ready for production Not Started C 7 1 0 03/25/22 03/25/22 03/25/22 4:59 PM 03/25/22 4:59 PM 2413 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.10 1 2414 Dortmund test stand ready for production
2416 1.3 1.3.1.2.8.2.11 Test of (500) PMT Assemblies Not Started C 7 20d 03/28/22 04/22/22 03/28/22 8:00 AM 04/22/22 4:59 PM 2407, 2414 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.11 1 2415 Test of (500) PMT Assemblies
2417 1.3 1.3.1.2.8.2.12 Test of (500) PMT Assemblies Not Started C 7 15d 04/25/22 05/13/22 04/25/22 8:00 AM 05/13/22 4:59 PM 2408, 2415 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.12 1 2416 Test of (500) PMT Assemblies
2418 1.3 1.3.1.2.8.2.13 Test of (500) PMT Assemblies Not Started C 7 10d 05/16/22 05/27/22 05/16/22 8:00 AM 05/27/22 4:59 PM 2409, 2416 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.13 1 2417 Test of (500) PMT Assemblies
2419 1.3 1.3.1.2.8.2.14 Test of (500) PMT Assemblies Not Started C 7 10d 05/30/22 06/10/22 05/30/22 8:00 AM 06/10/22 4:59 PM 2409, 2417 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.14 1 2418 Test of (500) PMT Assemblies
2420 1.3 1.3.1.2.8.2.15 Test of (500) PMT Assemblies Not Started C 7 10d 06/13/22 06/24/22 06/13/22 8:00 AM 06/24/22 4:59 PM 2409, 2418 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.15 1 2419 Test of (500) PMT Assemblies
2421 1.3 1.3.1.2.8.2.16 Test of (500) PMT Assemblies Not Started C 7 10d 06/27/22 07/08/22 06/27/22 8:00 AM 07/08/22 4:59 PM 194, 2419 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.16 1 2420 Test of (500) PMT Assemblies
2422 1.3 1.3.1.2.8.2.17 Test of (500) PMT Assemblies Not Started C 7 10d 07/11/22 07/22/22 07/11/22 8:00 AM 07/22/22 4:59 PM 2410, 2420 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.17 1 2421 Test of (500) PMT Assemblies
2423 1.3 1.3.1.2.8.2.18 Test of (500) PMT Assemblies Not Started C 7 10d 07/25/22 08/05/22 07/25/22 8:00 AM 08/05/22 4:59 PM 2410, 2421 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.18 1 2422 Test of (500) PMT Assemblies
2424 1.3 1.3.1.2.8.2.19 Test of (500) PMT Assemblies Not Started C 7 10d 08/08/22 08/19/22 08/08/22 8:00 AM 08/19/22 4:59 PM 2410, 2422 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.19 1 2423 Test of (500) PMT Assemblies
2425 1.3 1.3.1.2.8.2.20 Test of (280) PMT Assemblies Not Started C 7 6d 08/22/22 08/29/22 08/22/22 8:00 AM 08/29/22 4:59 PM 2410, 2423 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.20 1 2424 Test of (280) PMT Assemblies
2426 1.3 1.3.1.2.8.2.21 PMT Testing in Dortmund complete Not Started C 7 1 0 08/29/22 08/29/22 08/29/22 4:59 PM 08/29/22 4:59 PM 2424 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.2.8.2.21 1 2425 PMT Testing in Dortmund complete
2427 1.3 1.3.1.3 mDOM High Voltage Subsystem Complete P 4 1 546d 10/01/18 11/02/20 10/01/18 8:00 AM 11/02/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.3 1 2426 mDOM High Voltage Subsystem
2428 1.3 1.3.1.3.1 Preliminary design phase Complete C 5 1 120d 10/01/18 03/15/19 10/01/18 8:00 AM 03/15/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.3.1 1 2427 Preliminary design phase
2429 1.3 1.3.1.3.2 Final design phase Complete C 5 1 210d 02/18/19 12/06/19 02/18/19 8:00 AM 12/06/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.3.2 1 2428 Final design phase
2430 1.3 1.3.1.3.4 Tender and procurement Complete P 5 285d 10/01/19 11/02/20 10/01/19 8:00 AM 11/02/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.1.3.4 1 2429 Tender and procurement
2431 1.3 1.3.1.3.4.1 Identification of contract manufacturer for PMT Base PCA Complete C 6 60d 10/01/19 12/23/19 10/01/19 8:00 AM 12/23/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.4.1 1 2430 Identification of contract manufacturer for PMT Base PCA
2432 1.3 1.3.1.3.4.2 Development and construction of test station for PMT Base PCA Complete C 6 60d 10/01/19 12/23/19 10/01/19 8:00 AM 12/23/19 4:59 PM 2430SS 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.4.2 1 2431 Development and construction of test station for PMT Base PCA
2433 1.3 1.3.1.3.4.3 Production and test of 50 PMT Base PCAs Complete C 6 40d 12/31/19 02/24/20 12/31/19 8:00 AM 02/24/20 4:59 PM 2431FS +5d 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.4.3 1 2432 Production and test of 50 PMT Base PCAs
2434 1.3 1.3.1.3.4.4 PMT Base PCA Production Batch #1 (Qty. 3000) Complete C 6 60d 02/25/20 05/18/20 02/25/20 8:00 AM 05/18/20 4:59 PM 2432 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.4.4 1 2433 PMT Base PCA Production Batch #1 (Qty. 3000)
2435 1.3 1.3.1.3.4.5 Shipment of Batch #1 to PMT Manufacturer Complete C 6 10d 05/19/20 06/01/20 05/19/20 8:00 AM 06/01/20 4:59 PM 2433 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.4.5 1 2434 Shipment of Batch #1 to PMT Manufacturer
2436 1.3 1.3.1.3.4.6 PMT Base PCA Production Batch #2 (Qty. 3000) Complete C 6 40d 05/19/20 07/13/20 05/19/20 8:00 AM 07/13/20 4:59 PM 2434SS 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.4.6 1 2435 PMT Base PCA Production Batch #2 (Qty. 3000)
2437 1.3 1.3.1.3.4.7 Shipment of Batch #2 to PMT Manufacturer Complete C 6 10d 07/14/20 07/27/20 07/14/20 8:00 AM 07/27/20 4:59 PM 2435 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.4.7 1 2436 Shipment of Batch #2 to PMT Manufacturer
2438 1.3 1.3.1.3.4.8 PMT Base PCA Production Batch #3 (Qty. 3000) Complete C 6 40d 07/14/20 09/07/20 07/14/20 8:00 AM 09/07/20 4:59 PM 2436SS 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.4.8 1 2437 PMT Base PCA Production Batch #3 (Qty. 3000)
2439 1.3 1.3.1.3.4.9 Shipment of Batch #3 to PMT Manufacturer Complete C 6 10d 09/08/20 09/21/20 09/08/20 8:00 AM 09/21/20 4:59 PM 2437 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.4.9 1 2438 Shipment of Batch #3 to PMT Manufacturer
2440 1.3 1.3.1.3.4.10 PMT Base PCA Production Batch #4 (Qty. 2000) Complete C 6 30d 09/08/20 10/19/20 09/08/20 8:00 AM 10/19/20 4:59 PM 2438SS 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.4.10 1 2439 PMT Base PCA Production Batch #4 (Qty. 2000)
2441 1.3 1.3.1.3.4.11 Shipment of Batch #4 to PMT Manufacturer Complete C 6 10d 10/20/20 11/02/20 10/20/20 8:00 AM 11/02/20 4:59 PM 2439 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.4.11 1 2440 Shipment of Batch #4 to PMT Manufacturer
2442 1.3 1.3.1.3.5 mDOM High Voltage Subsystem Final Design Review Complete C 5 1 1d 12/23/19 12/23/19 12/23/19 8:00 AM 12/23/19 4:59 PM 2431FF 100% 100% Gray Informal internal review held on 2019-12-17 $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.3.5 1 2441 mDOM High Voltage Subsystem Final Design Review
2443 1.3 1.3.1.4 mDOM Pressure Vessel Complete P 4 607d 10/01/18 01/26/21 10/01/18 8:00 AM 01/26/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.4 1 2442 mDOM Pressure Vessel
2444 1.3 1.3.1.4.1 Preliminary design phase Complete P 5 40d 10/01/18 11/23/18 10/01/18 8:00 AM 11/23/18 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.4.1 1 2443 Preliminary design phase
2445 1.3 1.3.1.4.1.1 Qualification of Nautilus pressure vessels Complete C 6 40d 10/01/18 11/23/18 10/01/18 8:00 AM 11/23/18 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.4.1.1 1 2444 Qualification of Nautilus pressure vessels
2446 1.3 1.3.1.4.2 Final design phase Complete C 5 180d 11/26/18 08/02/19 11/26/18 8:00 AM 08/02/19 4:59 PM 2444 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.4.2 1 2445 Final design phase
2447 1.3 1.3.1.4.3 Procurement of pressure vessels for DVT Complete C 5 60d 08/05/19 10/25/19 08/05/19 8:00 AM 10/25/19 4:59 PM 2445 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.4.3 1 2446 Procurement of pressure vessels for DVT
2448 1.3 1.3.1.4.4 Tender and procurement (test production) Complete C 5 120d 04/22/20 10/06/20 04/22/20 8:00 AM 10/06/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.4.4 1 2447 Tender and procurement (test production)
2449 1.3 1.3.1.4.5 Tender and procurement (series production) Complete C 5 200d 04/22/20 01/26/21 04/22/20 8:00 AM 01/26/21 4:59 PM 2447SS 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.4.5 1 2448 Tender and procurement (series production)
2450 1.3 1.3.1.5 mDOM PMT Support Structure and Reflector Rings Started P 4 1195d 10/01/18 04/28/23 10/01/18 8:00 AM 04/28/23 4:59 PM 58% 23.00% Red $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5 1 2449 mDOM PMT Support Structure and Reflector Rings
2451 1.3 1.3.1.5.1 Preliminary design phase Complete C 5 40d 10/01/18 11/23/18 10/01/18 8:00 AM 11/23/18 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.1 1 2450 Preliminary design phase
2452 1.3 1.3.1.5.2 Final design phase Started C 5 180d 11/26/18 08/02/19 11/26/18 8:00 AM 08/02/19 4:59 PM 2450 100% 90.0% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.2 1 2451 Final design phase
2453 1.3 1.3.1.5.3 Procurement of PMT support structures for DVT Complete C 5 60d 08/05/19 10/25/19 08/05/19 8:00 AM 10/25/19 4:59 PM 2451 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.3 1 2452 Procurement of PMT support structures for DVT
2454 1.3 1.3.1.5.4 Procurement of reflector rings for DVT Complete C 5 20d 08/05/19 08/30/19 08/05/19 8:00 AM 08/30/19 4:59 PM 2452SS 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.4 1 2453 Procurement of reflector rings for DVT
2455 1.3 1.3.1.5.5 Tender and procurement of support structures (test production) Should have Started C 5 120d 04/22/20 10/06/20 04/22/20 8:00 AM 10/06/20 4:59 PM 100% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.5 1 2454 Tender and procurement of support structures (test production)
2456 1.3 1.3.1.5.6 Procurement of reflector rings (test production) Started C 5 20d 09/09/20 10/06/20 09/09/20 8:00 AM 10/06/20 4:59 PM 2454FF 99% 66.00% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.6 1 2455 Procurement of reflector rings (test production)
2457 1.3 1.3.1.5.7 Tender and procurement of support structures (series production) Should have Started C 5 200d 04/22/20 01/26/21 04/22/20 8:00 AM 01/26/21 4:59 PM 2454SS, 2448FF 100% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.7 1 2456 Tender and procurement of support structures (series production)
2458 1.3 1.3.1.5.8 Procurement of reflector rings (series production) Should have Started C 5 40d 12/02/20 01/26/21 12/02/20 8:00 AM 01/26/21 4:59 PM 2456FF 99% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.8 1 2457 Procurement of reflector rings (series production)
2459 1.3 1.3.1.5.9 Decision on Support Structure design for series production Complete C 5 1 0 01/10/22 01/10/22 01/10/22 8:00 AM 01/10/22 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.9 1 2458 Decision on Support Structure design for series production
2460 1.3 1.3.1.5.10 EU-wide tender for PMT Support Structures Started C 5 40d 01/10/22 03/04/22 01/10/22 8:00 AM 03/04/22 4:59 PM 2458 40% 33% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.10 1 2459 EU-wide tender for PMT Support Structures
2461 1.3 1.3.1.5.11 Purchase order for support structures signed Not Started C 5 1 0 03/04/22 03/04/22 03/04/22 4:59 PM 03/04/22 4:59 PM 2459 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.11 1 2460 Purchase order for support structures signed
2462 1.3 1.3.1.5.12 Preparation of production at manufacturer Not Started C 5 10d 03/07/22 03/18/22 03/07/22 8:00 AM 03/18/22 4:59 PM 2460 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.12 1 2461 Preparation of production at manufacturer
2463 1.3 1.3.1.5.13 Production of PMT Support Structures (expected rate: 18 hemispheres / week) Not Started P 5 270d 03/21/22 03/31/23 03/21/22 8:00 AM 03/31/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13 1 2462 Production of PMT Support Structures (expected rate: 18 hemispheres / week)
2464 1.3 1.3.1.5.13.1 Pre-series production of support structure (20 mDOMs, expected rate: 18 hemispheres / week) Not Started C 6 15d 03/21/22 04/08/22 03/21/22 8:00 AM 04/08/22 4:59 PM 2461 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.1 1 2463 Pre-series production of support structure (20 mDOMs, expected rate: 18 hemispheres / week)
2465 1.3 1.3.1.5.13.2 Production of (54) support structures (Batch #1) Not Started C 6 15d 05/09/22 05/27/22 05/09/22 8:00 AM 05/27/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.2 1 2464 Production of (54) support structures (Batch #1)
2466 1.3 1.3.1.5.13.3 Production of (54) support structures (Batch #2) Not Started C 6 15d 05/30/22 06/17/22 05/30/22 8:00 AM 06/17/22 4:59 PM 2464 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.3 1 2465 Production of (54) support structures (Batch #2)
2467 1.3 1.3.1.5.13.4 Production of (54) support structures (Batch #3) Not Started C 6 15d 06/20/22 07/08/22 06/20/22 8:00 AM 07/08/22 4:59 PM 2465 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.4 1 2466 Production of (54) support structures (Batch #3)
2468 1.3 1.3.1.5.13.5 Production of (54) support structures (Batch #4) Not Started C 6 15d 07/11/22 07/29/22 07/11/22 8:00 AM 07/29/22 4:59 PM 2466 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.5 1 2467 Production of (54) support structures (Batch #4)
2469 1.3 1.3.1.5.13.6 Production of (54) support structures (Batch #5) Not Started C 6 15d 08/01/22 08/19/22 08/01/22 8:00 AM 08/19/22 4:59 PM 2467 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.6 1 2468 Production of (54) support structures (Batch #5)
2470 1.3 1.3.1.5.13.7 Production of (54) support structures (Batch #6) Not Started C 6 15d 08/22/22 09/09/22 08/22/22 8:00 AM 09/09/22 4:59 PM 2468 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.7 1 2469 Production of (54) support structures (Batch #6)
2471 1.3 1.3.1.5.13.8 Production of (54) support structures (Batch #7) Not Started C 6 15d 09/12/22 09/30/22 09/12/22 8:00 AM 09/30/22 4:59 PM 2469 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.8 1 2470 Production of (54) support structures (Batch #7)
2472 1.3 1.3.1.5.13.9 Production of (54) support structures (Batch #8) Not Started C 6 15d 10/03/22 10/21/22 10/03/22 8:00 AM 10/21/22 4:59 PM 2470 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.9 1 2471 Production of (54) support structures (Batch #8)
2473 1.3 1.3.1.5.13.10 Production of (54) support structures (Batch #9) Not Started C 6 15d 10/24/22 11/11/22 10/24/22 8:00 AM 11/11/22 4:59 PM 2471 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.10 1 2472 Production of (54) support structures (Batch #9)
2474 1.3 1.3.1.5.13.11 Production of (54) support structures (Batch #10) Not Started C 6 15d 11/14/22 12/02/22 11/14/22 8:00 AM 12/02/22 4:59 PM 2472 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.11 1 2473 Production of (54) support structures (Batch #10)
2475 1.3 1.3.1.5.13.12 Production of (54) support structures (Batch #11) Not Started C 6 15d 12/05/22 12/23/22 12/05/22 8:00 AM 12/23/22 4:59 PM 2473 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.12 1 2474 Production of (54) support structures (Batch #11)
2476 1.3 1.3.1.5.13.13 Production of (54) support structures (Batch #12) Not Started C 6 15d 12/26/22 01/13/23 12/26/22 8:00 AM 01/13/23 4:59 PM 2474 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.13 1 2475 Production of (54) support structures (Batch #12)
2477 1.3 1.3.1.5.13.14 Production of (54) support structures (Batch #13) Not Started C 6 15d 01/16/23 02/03/23 01/16/23 8:00 AM 02/03/23 4:59 PM 2475 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.14 1 2476 Production of (54) support structures (Batch #13)
2478 1.3 1.3.1.5.13.15 Production of (54) support structures (Batch #14) Not Started C 6 15d 02/06/23 02/24/23 02/06/23 8:00 AM 02/24/23 4:59 PM 2476 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.15 1 2477 Production of (54) support structures (Batch #14)
2479 1.3 1.3.1.5.13.16 Production of (54) support structures (Batch #15) Not Started C 6 15d 02/27/23 03/17/23 02/27/23 8:00 AM 03/17/23 4:59 PM 2477 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.16 1 2478 Production of (54) support structures (Batch #15)
2480 1.3 1.3.1.5.13.17 Production of (30) support structures (Batch #16) Not Started C 6 10d 03/20/23 03/31/23 03/20/23 8:00 AM 03/31/23 4:59 PM 2478 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.13.17 1 2479 Production of (30) support structures (Batch #16)
2481 1.3 1.3.1.5.13.18 Production of PMT Support Structures completed Not Started C 6 1 0 03/31/23 03/31/23 03/31/23 4:59 PM 03/31/23 4:59 PM 2479 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.3.1.5.13.18 1 2480 Production of PMT Support Structures completed
2482 1.3 1.3.1.5.14 Procurement of Reflector Rings for Batch #0 Not Started C 5 20d 02/28/22 03/25/22 02/28/22 8:00 AM 03/25/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.14 1 2481 Procurement of Reflector Rings for Batch #0
2483 1.3 1.3.1.5.15 Tender and Procurement for Reflector Rings Not Started C 5 40d 03/28/22 05/20/22 03/28/22 8:00 AM 05/20/22 4:59 PM 2481 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.15 1 2482 Tender and Procurement for Reflector Rings
2484 1.3 1.3.1.5.16 Pre-assembly of PMT Support Structures in Münster (expected rate: 18 hemispheres / week) Not Started P 5 280d 04/04/22 04/28/23 04/04/22 8:00 AM 04/28/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16 1 2483 Pre-assembly of PMT Support Structures in Münster (expected rate: 18 hemispheres / week)
2485 1.3 1.3.1.5.16.1 Pre-assembly of (40) support structures (pre-series) Not Started C 6 15d 04/04/22 04/22/22 04/04/22 8:00 AM 04/22/22 4:59 PM 2463SS +10d, 2481 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.1 1 2484 Pre-assembly of (40) support structures (pre-series)
2486 1.3 1.3.1.5.16.2 Pre-assembly of (54) support structures (Batch #1) Not Started C 6 20d 05/23/22 06/17/22 05/23/22 8:00 AM 06/17/22 4:59 PM 2464SS +10d, 2482 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.2 1 2485 Pre-assembly of (54) support structures (Batch #1)
2487 1.3 1.3.1.5.16.3 Pre-assembly of (54) support structures (Batch #2) Not Started C 6 20d 06/20/22 07/15/22 06/20/22 8:00 AM 07/15/22 4:59 PM 2465SS +10d, 2485 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.3 1 2486 Pre-assembly of (54) support structures (Batch #2)
2488 1.3 1.3.1.5.16.4 Pre-assembly of (54) support structures (Batch #3) Not Started C 6 15d 07/18/22 08/05/22 07/18/22 8:00 AM 08/05/22 4:59 PM 2466SS +10d, 2486 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.4 1 2487 Pre-assembly of (54) support structures (Batch #3)
2489 1.3 1.3.1.5.16.5 Pre-assembly of (54) support structures (Batch #4) Not Started C 6 15d 08/08/22 08/26/22 08/08/22 8:00 AM 08/26/22 4:59 PM 2467SS +10d, 2487 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.5 1 2488 Pre-assembly of (54) support structures (Batch #4)
2490 1.3 1.3.1.5.16.6 Pre-assembly of (54) support structures (Batch #5) Not Started C 6 15d 08/29/22 09/16/22 08/29/22 8:00 AM 09/16/22 4:59 PM 2468SS +10d, 2488 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.6 1 2489 Pre-assembly of (54) support structures (Batch #5)
2491 1.3 1.3.1.5.16.7 Pre-assembly of (54) support structures (Batch #6) Not Started C 6 15d 09/19/22 10/07/22 09/19/22 8:00 AM 10/07/22 4:59 PM 2469SS +10d, 2489 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.7 1 2490 Pre-assembly of (54) support structures (Batch #6)
2492 1.3 1.3.1.5.16.8 Pre-assembly of (54) support structures (Batch #7) Not Started C 6 15d 10/10/22 10/28/22 10/10/22 8:00 AM 10/28/22 4:59 PM 2470SS +10d, 2490 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.8 1 2491 Pre-assembly of (54) support structures (Batch #7)
2493 1.3 1.3.1.5.16.9 Pre-assembly of (54) support structures (Batch #8) Not Started C 6 15d 10/31/22 11/18/22 10/31/22 8:00 AM 11/18/22 4:59 PM 2471SS +10d, 2491 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.9 1 2492 Pre-assembly of (54) support structures (Batch #8)
2494 1.3 1.3.1.5.16.10 Pre-assembly of (54) support structures (Batch #9) Not Started C 6 15d 11/21/22 12/09/22 11/21/22 8:00 AM 12/09/22 4:59 PM 2472SS +10d, 2492 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.10 1 2493 Pre-assembly of (54) support structures (Batch #9)
2495 1.3 1.3.1.5.16.11 Pre-assembly of (54) support structures (Batch #10) Not Started C 6 15d 12/12/22 12/30/22 12/12/22 8:00 AM 12/30/22 4:59 PM 2473SS +10d, 2493 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.11 1 2494 Pre-assembly of (54) support structures (Batch #10)
2496 1.3 1.3.1.5.16.12 Pre-assembly of (54) support structures (Batch #11) Not Started C 6 15d 01/02/23 01/20/23 01/02/23 8:00 AM 01/20/23 4:59 PM 2474SS +10d, 2494 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.12 1 2495 Pre-assembly of (54) support structures (Batch #11)
2497 1.3 1.3.1.5.16.13 Ship pre-assembled support structures to MSU Not Started C 6 30d 01/23/23 03/03/23 01/23/23 8:00 AM 03/03/23 4:59 PM 2489, 2490, 2491, 2492, 2493, 2494, 2495 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.13 1 2496 Ship pre-assembled support structures to MSU
2498 1.3 1.3.1.5.16.14 Pre-assembly of (54) support structures (Batch #12) Not Started C 6 15d 01/23/23 02/10/23 01/23/23 8:00 AM 02/10/23 4:59 PM 2475SS +10d, 2495 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.14 1 2497 Pre-assembly of (54) support structures (Batch #12)
2499 1.3 1.3.1.5.16.15 Pre-assembly of (54) support structures (Batch #13) Not Started C 6 15d 02/13/23 03/03/23 02/13/23 8:00 AM 03/03/23 4:59 PM 2476SS +10d, 2497 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.15 1 2498 Pre-assembly of (54) support structures (Batch #13)
2500 1.3 1.3.1.5.16.16 Pre-assembly of (54) support structures (Batch #14) Not Started C 6 15d 03/06/23 03/24/23 03/06/23 8:00 AM 03/24/23 4:59 PM 2477SS +10d, 2498 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.16 1 2499 Pre-assembly of (54) support structures (Batch #14)
2501 1.3 1.3.1.5.16.17 Pre-assembly of (54) support structures (Batch #15) Not Started C 6 15d 03/27/23 04/14/23 03/27/23 8:00 AM 04/14/23 4:59 PM 2478SS +10d, 2499 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.17 1 2500 Pre-assembly of (54) support structures (Batch #15)
2502 1.3 1.3.1.5.16.18 Pre-assembly of (30) support structures (Batch #16) Not Started C 6 10d 04/17/23 04/28/23 04/17/23 8:00 AM 04/28/23 4:59 PM 2479SS +10d, 2500 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.5.16.18 1 2501 Pre-assembly of (30) support structures (Batch #16)
2503 1.3 1.3.1.5.16.19 Pre-assembly of PMT Support Structures completed Not Started C 6 1 0 04/28/23 04/28/23 04/28/23 4:59 PM 04/28/23 4:59 PM 2501 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.3.1.5.16.19 1 2502 Pre-assembly of PMT Support Structures completed
2504 1.3 1.3.1.6 mDOM Optical Gel Complete P 4 607d 10/01/18 01/26/21 10/01/18 8:00 AM 01/26/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.6 1 2503 mDOM Optical Gel
2505 1.3 1.3.1.6.1 Preliminary design phase Complete C 5 40d 10/01/18 11/23/18 10/01/18 8:00 AM 11/23/18 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.6.1 1 2504 Preliminary design phase
2506 1.3 1.3.1.6.2 Final design phase Complete C 5 180d 11/26/18 08/02/19 11/26/18 8:00 AM 08/02/19 4:59 PM 2504 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.6.2 1 2505 Final design phase
2507 1.3 1.3.1.6.3 Procurement of optical gel for DVT Complete C 5 60d 12/23/19 03/13/20 12/23/19 8:00 AM 03/13/20 4:59 PM 2505FS +100d 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.6.3 1 2506 Procurement of optical gel for DVT
2508 1.3 1.3.1.6.4 Tender and procurement (test production) Complete C 5 120d 04/13/20 09/25/20 04/13/20 8:00 AM 09/25/20 4:59 PM 2506FS +20d 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.6.4 1 2507 Tender and procurement (test production)
2509 1.3 1.3.1.6.5 Tender and procurement (series production) Complete C 5 200d 04/22/20 01/26/21 04/22/20 8:00 AM 01/26/21 4:59 PM 2507SS, 2456FF 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.6.5 1 2508 Tender and procurement (series production)
2510 1.3 1.3.1.7 mDOM Harness Started P 4 1050d 10/01/18 10/07/22 10/01/18 8:00 AM 10/07/22 4:59 PM 86% 77.00% Yellow $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7 1 2509 mDOM Harness
2511 1.3 1.3.1.7.1 Preliminary design phase Complete C 5 40d 10/01/18 11/23/18 10/01/18 8:00 AM 11/23/18 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.1 1 2510 Preliminary design phase
2512 1.3 1.3.1.7.2 Final design phase Complete C 5 240d 11/26/18 10/25/19 11/26/18 8:00 AM 10/25/19 4:59 PM 2510 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.2 1 2511 Final design phase
2513 1.3 1.3.1.7.3 Tender and procurement (test production) Complete C 5 120d 04/22/20 10/06/20 04/22/20 8:00 AM 10/06/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.3 1 2512 Tender and procurement (test production)
2514 1.3 1.3.1.7.4 Tender and procurement (series production) Complete C 5 200d 04/22/20 01/26/21 04/22/20 8:00 AM 01/26/21 4:59 PM 2512SS, 2508FF 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.4 1 2513 Tender and procurement (series production)
2515 1.3 1.3.1.7.5 Production in Wuppertal Started P 5 266d 10/01/21 10/07/22 10/01/21 8:00 AM 10/07/22 4:59 PM 30% 25% Yellow $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.5 1 2514 Production in Wuppertal
2516 1.3 1.3.1.7.5.1 Welding stand construction Complete C 6 30d 10/01/21 11/11/21 10/01/21 8:00 AM 11/11/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.5.1 1 2515 Welding stand construction
2517 1.3 1.3.1.7.5.2 Hire personnel Complete C 6 30d 12/01/21 01/11/22 12/01/21 8:00 AM 01/11/22 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.5.2 1 2516 Hire personnel
2518 1.3 1.3.1.7.5.3 Start of mDOM Harness production Complete C 6 1 0 01/31/22 01/31/22 01/31/22 8:00 AM 01/31/22 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 1.3.1.7.5.3 1 2517 Start of mDOM Harness production
2519 1.3 1.3.1.7.5.4 Production of 50 harnesses Started C 6 30d 01/31/22 03/11/22 01/31/22 8:00 AM 03/11/22 4:59 PM 2517 2% 2% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.5.4 1 2518 Production of 50 harnesses
2520 1.3 1.3.1.7.5.5 Production of 50 harnesses Not Started C 6 30d 03/14/22 04/22/22 03/14/22 8:00 AM 04/22/22 4:59 PM 2518 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.5.5 1 2519 Production of 50 harnesses
2521 1.3 1.3.1.7.5.6 Production of 100 harnesses Not Started C 6 30d 04/25/22 06/03/22 04/25/22 8:00 AM 06/03/22 4:59 PM 2519 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.5.6 1 2520 Production of 100 harnesses
2522 1.3 1.3.1.7.5.7 Production of 100 harnesses Not Started C 6 30d 06/06/22 07/15/22 06/06/22 8:00 AM 07/15/22 4:59 PM 2520 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.5.7 1 2521 Production of 100 harnesses
2523 1.3 1.3.1.7.5.8 Production of 100 harnesses Not Started C 6 30d 07/18/22 08/26/22 07/18/22 8:00 AM 08/26/22 4:59 PM 2521 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.5.8 1 2522 Production of 100 harnesses
2524 1.3 1.3.1.7.5.9 Production of 50 harnesses Not Started C 6 30d 08/29/22 10/07/22 08/29/22 8:00 AM 10/07/22 4:59 PM 2522 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.7.5.9 1 2523 Production of 50 harnesses
2525 1.3 1.3.1.7.5.10 mDOM Harness production completed Not Started C 6 1 0 10/07/22 10/07/22 10/07/22 4:59 PM 10/07/22 4:59 PM 2523 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.3.1.7.5.10 1 2524 mDOM Harness production completed
2526 1.3 1.3.1.8 Integrated mDOM Started P 4 970d 10/01/18 06/17/22 10/01/18 8:00 AM 06/17/22 4:59 PM 100% 78.00% Red $0.00 $0.00 $3,042.74 $3,042.74 100% Timo Karg 1.3.1.8 1 2525 Integrated mDOM
2527 1.3 1.3.1.8.1 Integrated module design Started P 5 310d 10/01/18 12/06/19 10/01/18 8:00 AM 12/06/19 4:59 PM 100% 93.00% Yellow $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.1 1 2526 Integrated module design
2528 1.3 1.3.1.8.1.1 Preliminary design phase Complete C 6 100d 10/01/18 02/15/19 10/01/18 8:00 AM 02/15/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.1.1 1 2527 Preliminary design phase
2529 1.3 1.3.1.8.1.2 Final design phase Started C 6 210d 02/18/19 12/06/19 02/18/19 8:00 AM 12/06/19 4:59 PM 2527 100% 90.0% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.1.2 1 2528 Final design phase
2530 1.3 1.3.1.8.2 Packaging and shipping tools and procedures Complete C 5 120d 11/06/19 04/21/20 11/06/19 8:00 AM 04/21/20 4:59 PM 2528FS -23d 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.2 1 2529 Packaging and shipping tools and procedures
2531 1.3 1.3.1.8.3 Deployment tools and procedures Complete C 5 120d 11/06/19 04/21/20 11/06/19 8:00 AM 04/21/20 4:59 PM 2529SS 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.3 1 2530 Deployment tools and procedures
2532 1.3 1.3.1.8.4 Build 10 modules for DVT Started C 5 20d 01/20/21 02/16/21 01/20/21 8:00 AM 02/16/21 4:59 PM 2530FS +188d, 2513FS -5d 99% 60.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.4 1 2531 Build 10 modules for DVT
2533 1.3 1.3.1.8.5 DVT preparation using Rev. 1 Mainboard Complete C 5 30d 02/17/21 03/30/21 02/17/21 8:00 AM 03/30/21 4:59 PM 2531 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.5 1 2532 DVT preparation using Rev. 1 Mainboard
2534 1.3 1.3.1.8.6 Install Rev. 2 Mainboard in DVT mDOMs Complete C 5 5d 03/31/21 04/06/21 03/31/21 8:00 AM 04/06/21 4:59 PM 2532 95% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.6 1 2533 Install Rev. 2 Mainboard in DVT mDOMs
2535 1.3 1.3.1.8.7 Design Verification Testing Started C 5 253d 04/07/21 03/25/22 04/07/21 8:00 AM 03/25/22 4:59 PM 2533 85% 50.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.7 1 2534 Design Verification Testing
2536 1.3 1.3.1.8.8 mDOM Final Design Review Not Started C 5 1 1 0 03/25/22 03/25/22 03/25/22 4:59 PM 03/25/22 4:59 PM 2534 100% 0% Red $3,042.74 $3,042.74 $3,042.74 $3,042.74 100% $0.00 Timo Karg 1.3.1.8.8 1 2535 mDOM Final Design Review
2537 1.3 1.3.1.8.9 Ship DVT modules to NTS Not Started C 5 10d 03/28/22 04/08/22 03/28/22 8:00 AM 04/08/22 4:59 PM 2535 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.9 1 2536 Ship DVT modules to NTS
2538 1.3 1.3.1.8.10 uBase UART Cable (ribbon cable) Started P 5 150d 08/19/21 03/16/22 08/19/21 8:00 AM 03/16/22 4:59 PM 45% 85% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.10 1 2537 uBase UART Cable (ribbon cable)
2539 1.3 1.3.1.8.10.1 Purchase order signed Complete C 6 1 0 08/19/21 08/19/21 08/19/21 8:00 AM 08/19/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.10.1 1 2538 Purchase order signed
2540 1.3 1.3.1.8.10.2 Production of ribbon cables Started C 6 150d 08/19/21 03/16/22 08/19/21 8:00 AM 03/16/22 4:59 PM 2538 79% 85% Green 30 weeks lead time due to non-availability of 3M connectors $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.10.2 1 2539 Production of ribbon cables
2541 1.3 1.3.1.8.10.3 Delivery of ribbon cables for 40 mDOMs Complete C 6 1 0 03/16/22 03/16/22 03/16/22 8:00 AM 03/16/22 8:00 AM 0% 100% Gray We reduced the initial production of flasher cables to get some uBase UART cables early $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.10.3 1 2540 Delivery of ribbon cables for 40 mDOMs
2542 1.3 1.3.1.8.10.4 Delivery of ribbon cables for 440 mDOMs Not Started C 6 1 0 03/16/22 03/16/22 03/16/22 4:59 PM 03/16/22 4:59 PM 2539 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.10.4 1 2541 Delivery of ribbon cables for 440 mDOMs
2543 1.3 1.3.1.8.11 uBase Signal Cable (coaxial cable) Started P 5 185d 10/04/21 06/17/22 10/04/21 8:00 AM 06/17/22 4:59 PM 53% 61% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.11 1 2542 uBase Signal Cable (coaxial cable)
2544 1.3 1.3.1.8.11.1 Decision of 50-ohm vs. 75-ohm cables Complete C 6 1 0 10/04/21 10/04/21 10/04/21 8:00 AM 10/04/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.11.1 1 2543 Decision of 50-ohm vs. 75-ohm cables
2545 1.3 1.3.1.8.11.2 Vendor qualification Complete C 6 60d 10/04/21 12/24/21 10/04/21 8:00 AM 12/24/21 4:59 PM 2543 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.11.2 1 2544 Vendor qualification
2546 1.3 1.3.1.8.11.3 Holiday Break Complete C 6 5d 12/27/21 12/31/21 12/27/21 8:00 AM 12/31/21 4:59 PM 2544 93% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.11.3 1 2545 Holiday Break
2547 1.3 1.3.1.8.11.4 Tender for coaxial cables Started C 6 80d 01/03/22 04/22/22 01/03/22 8:00 AM 04/22/22 4:59 PM 2545 26% 35% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.11.4 1 2546 Tender for coaxial cables
2548 1.3 1.3.1.8.11.5 Production of coaxial cables Started C 6 40d 04/25/22 06/17/22 04/25/22 8:00 AM 06/17/22 4:59 PM 2546 0% 50% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.11.5 1 2547 Production of coaxial cables
2549 1.3 1.3.1.8.11.6 Delivery of coaxial cables Not Started C 6 1 0 06/17/22 06/17/22 06/17/22 4:59 PM 06/17/22 4:59 PM 2547 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.8.11.6 1 2548 Delivery of coaxial cables
2550 1.3 1.3.1.9 mDOM Production Facilities Started P 4 965d 02/18/19 10/28/22 02/18/19 8:00 AM 10/28/22 4:59 PM 19% 77.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9 1 2549 mDOM Production Facilities
2551 1.3 1.3.1.9.1 DESY Production Facility Started P 5 915d 02/18/19 08/19/22 02/18/19 8:00 AM 08/19/22 4:59 PM 29% 81.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1 1 2550 DESY Production Facility
2552 1.3 1.3.1.9.1.1 Set up facilities and hire personel Started P 6 910d 02/18/19 08/12/22 02/18/19 8:00 AM 08/12/22 4:59 PM 52% 87.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1 1 2551 Set up facilities and hire personel
2553 1.3 1.3.1.9.1.1.1 Production facilities Started P 7 720d 02/18/19 11/19/21 02/18/19 8:00 AM 11/19/21 4:59 PM 99% 94.00% Yellow $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.1 1 2552 Production facilities
2554 1.3 1.3.1.9.1.1.1.1 Development of assembly procedures and tools Complete C 8 180d 02/18/19 10/25/19 02/18/19 8:00 AM 10/25/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.1.1 1 2553 Development of assembly procedures and tools
2555 1.3 1.3.1.9.1.1.1.2 Tendering for HVAC Complete C 8 23d 10/27/20 11/26/20 10/27/20 8:00 AM 11/26/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.1.2 1 2554 Tendering for HVAC
2556 1.3 1.3.1.9.1.1.1.3 Installation of HVAC in Schoenefeld Complete C 8 85d 01/04/21 04/30/21 01/04/21 8:00 AM 04/30/21 4:59 PM 100% 100% Gray Construction of facility in newly rented hall has commenced $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.1.3 1 2555 Installation of HVAC in Schoenefeld
2557 1.3 1.3.1.9.1.1.1.4 Production site installation Started C 8 20d 10/25/21 11/19/21 10/25/21 8:00 AM 11/19/21 4:59 PM 99% 66.00% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.1.4 1 2556 Production site installation
2558 1.3 1.3.1.9.1.1.1.5 DESY production site ready Should have Started C 8 1 0 11/19/21 11/19/21 11/19/21 4:59 PM 11/19/21 4:59 PM 2556 100% 0% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.1.5 1 2557 DESY production site ready
2559 1.3 1.3.1.9.1.1.1.6 Development of logistics and packaging to transport mDOMs between production and FAT sites Started C 8 60d 01/04/21 03/26/21 01/04/21 8:00 AM 03/26/21 4:59 PM 100% 75.00% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.1.6 1 2558 Development of logistics and packaging to transport mDOMs between production and FAT sites
2560 1.3 1.3.1.9.1.1.2 FAT facilities Started P 7 130d 01/03/22 07/01/22 01/03/22 8:00 AM 07/01/22 4:59 PM 7% 23.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.2 1 2559 FAT facilities
2561 1.3 1.3.1.9.1.1.2.1 Design room temperature FAT Started C 8 50d 01/03/22 03/11/22 01/03/22 8:00 AM 03/11/22 4:59 PM 42% 60.0% Green Identified resources at universities Mainz and Erlangen to work on this in the context of the German university funding $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.2.1 1 2560 Design room temperature FAT
2562 1.3 1.3.1.9.1.1.2.2 Construction of room temperature FAT setup Not Started C 8 20d 03/14/22 04/08/22 03/14/22 8:00 AM 04/08/22 4:59 PM 2560 0% 0% Green Identified resources at universities Mainz and Erlangen to work on this in the context of the German university funding $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.2.2 1 2561 Construction of room temperature FAT setup
2563 1.3 1.3.1.9.1.1.2.3 Commissioning of room temperature FAT setup Not Started C 8 15d 04/11/22 04/29/22 04/11/22 8:00 AM 04/29/22 4:59 PM 2561 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.2.3 1 2562 Commissioning of room temperature FAT setup
2564 1.3 1.3.1.9.1.1.2.4 DFL Commissioning Phase 1 Not Started C 8 40d 03/14/22 05/06/22 03/14/22 8:00 AM 05/06/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.2.4 1 2563 DFL Commissioning Phase 1
2565 1.3 1.3.1.9.1.1.2.5 DFL Commissioning Phase 2 Not Started C 8 5d 06/27/22 07/01/22 06/27/22 8:00 AM 07/01/22 4:59 PM 2568 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.3.1.9.1.1.2.5 1 2564 DFL Commissioning Phase 2
2566 1.3 1.3.1.9.1.1.2.6 DESY DFL fully commissioned Not Started C 8 1 0 07/01/22 07/01/22 07/01/22 4:59 PM 07/01/22 4:59 PM 2562, 2564 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.2.6 1 2565 DESY DFL fully commissioned
2567 1.3 1.3.1.9.1.1.3 Personnel Complete C 7 240d 08/01/19 07/01/20 08/01/19 8:00 AM 07/01/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.3 1 2566 Personnel
2568 1.3 1.3.1.9.1.1.4 mDOM Production Readiness Review (in Germany) Not Started C 7 1 1 0 08/12/22 08/12/22 08/12/22 4:59 PM 08/12/22 4:59 PM 2569 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.1.4 1 2567 mDOM Production Readiness Review (in Germany)
2569 1.3 1.3.1.9.1.2 Test production (Batch #0, Qty. 20) Not Started C 6 30d 05/16/22 06/24/22 05/16/22 8:00 AM 06/24/22 4:59 PM 0% 0% Green Key personnel not available earlier $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.2 1 2568 Test production (Batch #0, Qty. 20)
2570 1.3 1.3.1.9.1.3 FAT Test Production Not Started C 6 30d 07/04/22 08/12/22 07/04/22 8:00 AM 08/12/22 4:59 PM 2564 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.3 1 2569 FAT Test Production
2571 1.3 1.3.1.9.1.4 Packing Test Production Not Started C 6 5d 08/15/22 08/19/22 08/15/22 8:00 AM 08/19/22 4:59 PM 2569 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.4 1 2570 Packing Test Production
2572 1.3 1.3.1.9.1.5 Transfer equipment from temporary production site to Schoenefeld Complete C 6 5d 07/26/21 07/30/21 07/26/21 8:00 AM 07/30/21 4:59 PM 93% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.1.5 1 2571 Transfer equipment from temporary production site to Schoenefeld
2573 1.3 1.3.1.9.2 MSU Production Facility Started P 5 847d 08/01/19 10/28/22 08/01/19 8:00 AM 10/28/22 4:59 PM 10% 72.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2 1 2572 MSU Production Facility
2574 1.3 1.3.1.9.2.1 Set up facilities and hire personel Started P 6 842d 08/01/19 10/21/22 08/01/19 8:00 AM 10/21/22 4:59 PM 50% 81.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.1 1 2573 Set up facilities and hire personel
2575 1.3 1.3.1.9.2.1.1 Production Facilities Complete C 7 170d 08/01/19 03/25/20 08/01/19 8:00 AM 03/25/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.1.1 1 2574 Production Facilities
2576 1.3 1.3.1.9.2.1.2 FAT Facilities Started P 7 115d 02/07/22 07/15/22 02/07/22 8:00 AM 07/15/22 4:59 PM 0% 14.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.1.2 1 2575 FAT Facilities
2577 1.3 1.3.1.9.2.1.2.1 Optical FAT construction Not Started C 8 15d 06/06/22 06/24/22 06/06/22 8:00 AM 06/24/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.1.2.1 1 2576 Optical FAT construction
2578 1.3 1.3.1.9.2.1.2.2 Optical FAT comissioning Not Started C 8 15d 06/27/22 07/15/22 06/27/22 8:00 AM 07/15/22 4:59 PM 2576 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.1.2.2 1 2577 Optical FAT comissioning
2579 1.3 1.3.1.9.2.1.2.3 DFL comissioning Complete C 8 5d 02/07/22 02/11/22 02/07/22 8:00 AM 02/11/22 4:59 PM 0% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.1.2.3 1 2578 DFL comissioning
2580 1.3 1.3.1.9.2.1.3 Personnel Complete C 7 240d 08/01/19 07/01/20 08/01/19 8:00 AM 07/01/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.1.3 1 2579 Personnel
2581 1.3 1.3.1.9.2.1.4 mDOM Production Readiness Review (in US at MSU) Not Started C 7 1 1 0 10/21/22 10/21/22 10/21/22 4:59 PM 10/21/22 4:59 PM 2582 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.1.4 1 2580 mDOM Production Readiness Review (in US at MSU)
2582 1.3 1.3.1.9.2.2 Test production (Batch #0, Qty. 20) Not Started C 6 30d 08/01/22 09/09/22 08/01/22 8:00 AM 09/09/22 4:59 PM 2584 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.2 1 2581 Test production (Batch #0, Qty. 20)
2583 1.3 1.3.1.9.2.3 FAT Test Production Not Started C 6 30d 09/12/22 10/21/22 09/12/22 8:00 AM 10/21/22 4:59 PM 2581 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.3 1 2582 FAT Test Production
2584 1.3 1.3.1.9.2.4 Packing Test Production Not Started C 6 5d 10/24/22 10/28/22 10/24/22 8:00 AM 10/28/22 4:59 PM 2582 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.4 1 2583 Packing Test Production
2585 1.3 1.3.1.9.2.5 Shipping of mDOM components from DESY to MSU Not Started C 6 40d 06/06/22 07/29/22 06/06/22 8:00 AM 07/29/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.9.2.5 1 2584 Shipping of mDOM components from DESY to MSU
2586 1.3 1.3.1.10 mDOM Series Production Not Started P 4 843d 06/24/22 09/25/25 06/24/22 4:59 PM 09/25/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10 1 2585 mDOM Series Production
2587 1.3 1.3.1.10.1 Series Production Not Started P 5 320d 06/24/22 09/15/23 06/24/22 4:59 PM 09/15/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1 1 2586 Series Production
2588 1.3 1.3.1.10.1.1 DESY Production Facility Not Started P 6 295d 06/24/22 08/11/23 06/24/22 4:59 PM 08/11/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1 1 2587 DESY Production Facility
2589 1.3 1.3.1.10.1.1.1 Start of mDOM series production at DESY Not Started C 7 1 0 06/24/22 06/24/22 06/24/22 4:59 PM 06/24/22 4:59 PM 2485SS +15d, 2568 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.3.1.10.1.1.1 1 2588 Start of mDOM series production at DESY
2590 1.3 1.3.1.10.1.1.2 Integration of (54) half-mDOMs (Batch #1) Not Started C 7 1 30d 06/27/22 08/05/22 06/27/22 8:00 AM 08/05/22 4:59 PM 2588 0% 0% Green Seal (1) mDOM / week to check for bubbles or delaminations (Q: Do half-modules need to be stored at 500 mbar to avoid bubbles?). Need storage space for half-mDOMs/ $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.2 1 2589 Integration of (54) half-mDOMs (Batch #1)
2591 1.3 1.3.1.10.1.1.3 Integration of (54) half-mDOMs (Batch #2) Not Started C 7 1 20d 08/08/22 09/02/22 08/08/22 8:00 AM 09/02/22 4:59 PM 2486, 2589 0% 0% Green Seal (1) mDOM / week to check for bubbles or delaminations (Q: Do half-modules need to be stored at 500 mbar to avoid bubbles?). Need storage space for half-mDOMs/ $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.3 1 2590 Integration of (54) half-mDOMs (Batch #2)
2592 1.3 1.3.1.10.1.1.4 Integration of (54) half-mDOMs (Batch #3) Not Started C 7 1 20d 09/05/22 09/30/22 09/05/22 8:00 AM 09/30/22 4:59 PM 2487, 2590 0% 0% Green Seal (1) mDOM / week to check for bubbles or delaminations (Q: Do half-modules need to be stored at 500 mbar to avoid bubbles?). Need storage space for half-mDOMs/ $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.4 1 2591 Integration of (54) half-mDOMs (Batch #3)
2593 1.3 1.3.1.10.1.1.5 Integration of (54) half-mDOMs (Batch #4) Not Started C 7 1 15d 10/03/22 10/21/22 10/03/22 8:00 AM 10/21/22 4:59 PM 2488, 2591 0% 0% Green Seal (1) mDOM / week to check for bubbles or delaminations (Q: Do half-modules need to be stored at 500 mbar to avoid bubbles?). Need storage space for half-mDOMs/ $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.5 1 2592 Integration of (54) half-mDOMs (Batch #4)
2594 1.3 1.3.1.10.1.1.6 Mainboard integration and sealing Batch #1, pt. 1 Not Started C 7 1 5d 12/19/22 12/23/22 12/19/22 8:00 AM 12/23/22 4:59 PM 2328SS +15d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.6 1 2593 Mainboard integration and sealing Batch #1, pt. 1
2595 1.3 1.3.1.10.1.1.7 Holiday Break Not Started C 7 1 5d 12/26/22 12/30/22 12/26/22 8:00 AM 12/30/22 4:59 PM 2593 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.7 1 2594 Holiday Break
2596 1.3 1.3.1.10.1.1.8 Mainboard integration and sealing Batch #1, pt. 2 Not Started C 7 1 10d 01/02/23 01/13/23 01/02/23 8:00 AM 01/13/23 4:59 PM 2594 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.8 1 2595 Mainboard integration and sealing Batch #1, pt. 2
2597 1.3 1.3.1.10.1.1.9 FAT Batch #1 Not Started C 7 1 30d 01/16/23 02/24/23 01/16/23 8:00 AM 02/24/23 4:59 PM 2595 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.9 1 2596 FAT Batch #1
2598 1.3 1.3.1.10.1.1.10 Mounting of harness wires and packing (Batch #1) Not Started C 7 1 5d 02/27/23 03/03/23 02/27/23 8:00 AM 03/03/23 4:59 PM 2596 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.10 1 2597 Mounting of harness wires and packing (Batch #1)
2599 1.3 1.3.1.10.1.1.11 Mainboard integration and sealing Batch #2 Not Started C 7 1 10d 01/16/23 01/27/23 01/16/23 8:00 AM 01/27/23 4:59 PM 2590, 2595 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.11 1 2598 Mainboard integration and sealing Batch #2
2600 1.3 1.3.1.10.1.1.12 FAT Batch #2 Not Started C 7 1 20d 02/27/23 03/24/23 02/27/23 8:00 AM 03/24/23 4:59 PM 2596, 2598 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.12 1 2599 FAT Batch #2
2601 1.3 1.3.1.10.1.1.13 Mounting of harness wires and packing (Batch #2) Not Started C 7 1 5d 03/27/23 03/31/23 03/27/23 8:00 AM 03/31/23 4:59 PM 2599 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.13 1 2600 Mounting of harness wires and packing (Batch #2)
2602 1.3 1.3.1.10.1.1.14 Mainboard integration and sealing Batch #3 Not Started C 7 1 10d 01/30/23 02/10/23 01/30/23 8:00 AM 02/10/23 4:59 PM 2591, 2598 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.14 1 2601 Mainboard integration and sealing Batch #3
2603 1.3 1.3.1.10.1.1.15 FAT Batch #3 Not Started C 7 1 20d 03/27/23 04/21/23 03/27/23 8:00 AM 04/21/23 4:59 PM 2599, 2601 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.15 1 2602 FAT Batch #3
2604 1.3 1.3.1.10.1.1.16 Mounting of harness wires and packing (Batch #3) Not Started C 7 1 5d 04/24/23 04/28/23 04/24/23 8:00 AM 04/28/23 4:59 PM 2602 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.16 1 2603 Mounting of harness wires and packing (Batch #3)
2605 1.3 1.3.1.10.1.1.17 Mainboard integration and sealing Batch #4 Not Started C 7 1 10d 02/13/23 02/24/23 02/13/23 8:00 AM 02/24/23 4:59 PM 2592, 2601 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.17 1 2604 Mainboard integration and sealing Batch #4
2606 1.3 1.3.1.10.1.1.18 FAT Batch #4 Not Started C 7 1 15d 04/24/23 05/12/23 04/24/23 8:00 AM 05/12/23 4:59 PM 2602, 2604 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.18 1 2605 FAT Batch #4
2607 1.3 1.3.1.10.1.1.19 Mounting of harness wires and packing (Batch #4) Not Started C 7 1 5d 05/15/23 05/19/23 05/15/23 8:00 AM 05/19/23 4:59 PM 2605 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.19 1 2606 Mounting of harness wires and packing (Batch #4)
2608 1.3 1.3.1.10.1.1.20 128 mDOMs for Strings 87-88 ready to ship to CHC Not Started C 7 1 1 1 0 05/19/23 05/19/23 05/19/23 4:59 PM 05/19/23 4:59 PM 2606 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.20 1 2607 128 mDOMs for Strings 87-88 ready to ship to CHC
2609 1.3 1.3.1.10.1.1.21 Production Batch #5 (Qty. 27) Not Started C 7 15d 03/06/23 03/24/23 03/06/23 8:00 AM 03/24/23 4:59 PM 2497FS +15d, 2604 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.21 1 2608 Production Batch #5 (Qty. 27)
2610 1.3 1.3.1.10.1.1.22 FAT Batch #5 Not Started C 7 15d 05/15/23 06/02/23 05/15/23 8:00 AM 06/02/23 4:59 PM 2605, 2608 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.22 1 2609 FAT Batch #5
2611 1.3 1.3.1.10.1.1.23 Mounting of harness wires and packing (Batch #5) Not Started C 7 5d 06/05/23 06/09/23 06/05/23 8:00 AM 06/09/23 4:59 PM 2609 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.23 1 2610 Mounting of harness wires and packing (Batch #5)
2612 1.3 1.3.1.10.1.1.24 Production Batch #6 (Qty. 27) Not Started C 7 15d 03/27/23 04/14/23 03/27/23 8:00 AM 04/14/23 4:59 PM 2498, 2608 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.24 1 2611 Production Batch #6 (Qty. 27)
2613 1.3 1.3.1.10.1.1.25 FAT Batch #6 Not Started C 7 15d 06/05/23 06/23/23 06/05/23 8:00 AM 06/23/23 4:59 PM 2609, 2611 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.25 1 2612 FAT Batch #6
2614 1.3 1.3.1.10.1.1.26 Mounting of harness wires and packing (Batch #6) Not Started C 7 5d 06/26/23 06/30/23 06/26/23 8:00 AM 06/30/23 4:59 PM 2612 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.1.10.1.1.26 1 2613 Mounting of harness wires and packing (Batch #6)
2615 1.3 1.3.1.10.1.1.27 Production Batch #7 (Qty. 27) Not Started C 7 15d 04/17/23 05/05/23 04/17/23 8:00 AM 05/05/23 4:59 PM 2499, 2611 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.10.1.1.27 1 2614 Production Batch #7 (Qty. 27)
2616 1.3 1.3.1.10.1.1.28 FAT Batch #7 Not Started C 7 15d 06/26/23 07/14/23 06/26/23 8:00 AM 07/14/23 4:59 PM 2612, 2614 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.10.1.1.28 1 2615 FAT Batch #7
2617 1.3 1.3.1.10.1.1.29 Mounting of harness wires and packing (Batch #7) Not Started C 7 5d 07/17/23 07/21/23 07/17/23 8:00 AM 07/21/23 4:59 PM 2615 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.29 1 2616 Mounting of harness wires and packing (Batch #7)
2618 1.3 1.3.1.10.1.1.30 Production Batch #8 (Qty. 16) Not Started C 7 15d 04/17/23 05/05/23 04/17/23 8:00 AM 05/05/23 4:59 PM 2500, 2611 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.30 1 2617 Production Batch #8 (Qty. 16)
2619 1.3 1.3.1.10.1.1.31 FAT Batch #8 Not Started C 7 15d 07/17/23 08/04/23 07/17/23 8:00 AM 08/04/23 4:59 PM 2615, 2617 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.31 1 2618 FAT Batch #8
2620 1.3 1.3.1.10.1.1.32 Mounting of harness wires and packing (Batch #8) Not Started C 7 5d 08/07/23 08/11/23 08/07/23 8:00 AM 08/11/23 4:59 PM 2618 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.32 1 2619 Mounting of harness wires and packing (Batch #8)
2621 1.3 1.3.1.10.1.1.33 96 mDOMs for Strings 89-93 ready to ship to CHC Not Started C 7 1 1 1 0 08/11/23 08/11/23 08/11/23 4:59 PM 08/11/23 4:59 PM 2619 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.1.33 1 2620 96 mDOMs for Strings 89-93 ready to ship to CHC
2622 1.3 1.3.1.10.1.2 MSU Production Facility Not Started P 6 140d 03/03/23 09/15/23 03/03/23 4:59 PM 09/15/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2 1 2621 MSU Production Facility
2623 1.3 1.3.1.10.1.2.1 Start of mDOM series production at MSU Not Started C 7 1 0 03/03/23 03/03/23 03/03/23 4:59 PM 03/03/23 4:59 PM 2496 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.3.1.10.1.2.1 1 2622 Start of mDOM series production at MSU
2624 1.3 1.3.1.10.1.2.2 Production Batch #1 (Qty. 27) Not Started C 7 20d 03/06/23 03/31/23 03/06/23 8:00 AM 03/31/23 4:59 PM 2622 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.2 1 2623 Production Batch #1 (Qty. 27)
2625 1.3 1.3.1.10.1.2.3 FAT Batch #1 Not Started C 7 20d 04/03/23 04/28/23 04/03/23 8:00 AM 04/28/23 4:59 PM 2623 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.3 1 2624 FAT Batch #1
2626 1.3 1.3.1.10.1.2.4 Mounting of harness wires and packing (Batch #1) Not Started C 7 5d 05/01/23 05/05/23 05/01/23 8:00 AM 05/05/23 4:59 PM 2624 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.4 1 2625 Mounting of harness wires and packing (Batch #1)
2627 1.3 1.3.1.10.1.2.5 Production Batch #2 (Qty. 27) Not Started C 7 20d 04/03/23 04/28/23 04/03/23 8:00 AM 04/28/23 4:59 PM 2623 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.5 1 2626 Production Batch #2 (Qty. 27)
2628 1.3 1.3.1.10.1.2.6 FAT Batch #2 Not Started C 7 20d 05/01/23 05/26/23 05/01/23 8:00 AM 05/26/23 4:59 PM 2624, 2626 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.6 1 2627 FAT Batch #2
2629 1.3 1.3.1.10.1.2.7 Mounting of harness wires and packing (Batch #2) Not Started C 7 5d 05/29/23 06/02/23 05/29/23 8:00 AM 06/02/23 4:59 PM 2627 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.7 1 2628 Mounting of harness wires and packing (Batch #2)
2630 1.3 1.3.1.10.1.2.8 Production Batch #3 (Qty. 27) Not Started C 7 15d 05/01/23 05/19/23 05/01/23 8:00 AM 05/19/23 4:59 PM 2626 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.8 1 2629 Production Batch #3 (Qty. 27)
2631 1.3 1.3.1.10.1.2.9 FAT Batch #3 Not Started C 7 15d 05/29/23 06/16/23 05/29/23 8:00 AM 06/16/23 4:59 PM 2627, 2629 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.9 1 2630 FAT Batch #3
2632 1.3 1.3.1.10.1.2.10 Mounting of harness wires and packing (Batch #3) Not Started C 7 5d 06/19/23 06/23/23 06/19/23 8:00 AM 06/23/23 4:59 PM 2630 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.10 1 2631 Mounting of harness wires and packing (Batch #3)
2633 1.3 1.3.1.10.1.2.11 Production Batch #4 (Qty. 27) Not Started C 7 15d 05/22/23 06/09/23 05/22/23 8:00 AM 06/09/23 4:59 PM 2629 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.11 1 2632 Production Batch #4 (Qty. 27)
2634 1.3 1.3.1.10.1.2.12 FAT Batch #4 Not Started C 7 15d 06/19/23 07/07/23 06/19/23 8:00 AM 07/07/23 4:59 PM 2630, 2632 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.12 1 2633 FAT Batch #4
2635 1.3 1.3.1.10.1.2.13 Mounting of harness wires and packing (Batch #4) Not Started C 7 5d 07/10/23 07/14/23 07/10/23 8:00 AM 07/14/23 4:59 PM 2633 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.13 1 2634 Mounting of harness wires and packing (Batch #4)
2636 1.3 1.3.1.10.1.2.14 Production Batch #5 (Qty. 27) Not Started C 7 15d 06/12/23 06/30/23 06/12/23 8:00 AM 06/30/23 4:59 PM 2632 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.14 1 2635 Production Batch #5 (Qty. 27)
2637 1.3 1.3.1.10.1.2.15 FAT Batch #5 Not Started C 7 15d 07/10/23 07/28/23 07/10/23 8:00 AM 07/28/23 4:59 PM 2633, 2635 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.15 1 2636 FAT Batch #5
2638 1.3 1.3.1.10.1.2.16 Mounting of harness wires and packing (Batch #5) Not Started C 7 5d 07/31/23 08/04/23 07/31/23 8:00 AM 08/04/23 4:59 PM 2636 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.16 1 2637 Mounting of harness wires and packing (Batch #5)
2639 1.3 1.3.1.10.1.2.17 Production Batch #6 (Qty. 27) Not Started C 7 15d 07/03/23 07/21/23 07/03/23 8:00 AM 07/21/23 4:59 PM 2635 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.17 1 2638 Production Batch #6 (Qty. 27)
2640 1.3 1.3.1.10.1.2.18 FAT Batch #6 Not Started C 7 15d 07/31/23 08/18/23 07/31/23 8:00 AM 08/18/23 4:59 PM 2636, 2638 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.1.10.1.2.18 1 2639 FAT Batch #6
2641 1.3 1.3.1.10.1.2.19 Mounting of harness wires and packing (Batch #6) Not Started C 7 5d 08/21/23 08/25/23 08/21/23 8:00 AM 08/25/23 4:59 PM 2639 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.1.10.1.2.19 1 2640 Mounting of harness wires and packing (Batch #6)
2642 1.3 1.3.1.10.1.2.20 Production Batch #7 (Qty. 23) Not Started C 7 15d 07/24/23 08/11/23 07/24/23 8:00 AM 08/11/23 4:59 PM 2638 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.20 1 2641 Production Batch #7 (Qty. 23)
2643 1.3 1.3.1.10.1.2.21 FAT Batch #7 Not Started C 7 15d 08/21/23 09/08/23 08/21/23 8:00 AM 09/08/23 4:59 PM 2639, 2641 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.21 1 2642 FAT Batch #7
2644 1.3 1.3.1.10.1.2.22 Mounting of harness wires and packing (Batch #7) Not Started C 7 5d 09/11/23 09/15/23 09/11/23 8:00 AM 09/15/23 4:59 PM 2642 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.22 1 2643 Mounting of harness wires and packing (Batch #7)
2645 1.3 1.3.1.10.1.2.23 200 mDOMs for Strings 89-93 ready to ship to Pt. Hueneme Not Started C 7 1 1 1 0 09/15/23 09/15/23 09/15/23 4:59 PM 09/15/23 4:59 PM 2643 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.1.2.23 1 2644 200 mDOMs for Strings 89-93 ready to ship to Pt. Hueneme
2646 1.3 1.3.1.10.2 Ship 116 + 12 spare mDOMs for Strings 87-88 from DESY to CHC Not Started C 5 1 40d 08/01/24 09/25/24 08/01/24 8:00 AM 09/25/24 4:59 PM 2607FS +310d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.2 1 2645 Ship 116 + 12 spare mDOMs for Strings 87-88 from DESY to CHC
2647 1.3 1.3.1.10.3 Ship 96 mDOMs for Strings 89-93 from DESY to CHC Not Started C 5 1 40d 08/01/25 09/25/25 08/01/25 8:00 AM 09/25/25 4:59 PM 2620FS +508d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.3 1 2646 Ship 96 mDOMs for Strings 89-93 from DESY to CHC
2648 1.3 1.3.1.10.4 Ship 190 + 10 spare mDOMs for Strings 89-93 from MSU to Pt. Hueneme Not Started C 5 1 20d 08/01/25 08/28/25 08/01/25 8:00 AM 08/28/25 4:59 PM 2644FS +483d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.1.10.4 1 2647 Ship 190 + 10 spare mDOMs for Strings 89-93 from MSU to Pt. Hueneme
2649 1.3 1.3.2 D-Egg Started P 3 1838d 10/01/18 10/23/25 10/01/18 8:00 AM 10/23/25 4:59 PM 90% 84.00% Yellow $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2 1 2648 D-Egg
2650 1.3 1.3.2.1 D-Egg DAQ Electronics Complete P 4 653d 10/01/18 03/31/21 10/01/18 8:00 AM 03/31/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.1 1 2649 D-Egg DAQ Electronics
2651 1.3 1.3.2.1.1 Preliminary design phase Complete P 5 251d 10/01/18 09/16/19 10/01/18 8:00 AM 09/16/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.1.1 1 2650 Preliminary design phase
2652 1.3 1.3.2.1.1.1 Rev. 2 mainboard schematics and layout Complete C 6 175d 10/01/18 05/31/19 10/01/18 8:00 AM 05/31/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.1.1.1 1 2651 Rev. 2 mainboard schematics and layout
2653 1.3 1.3.2.1.1.2 Rev. 2 mainboard production Complete C 6 15d 06/03/19 06/21/19 06/03/19 8:00 AM 06/21/19 4:59 PM 2651 98% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.1.1.2 1 2652 Rev. 2 mainboard production
2654 1.3 1.3.2.1.1.3 Rev. 2 mainboard prototypes available Complete C 6 1 1d 06/24/19 06/24/19 06/24/19 8:00 AM 06/24/19 4:59 PM 2652 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.1.1.3 1 2653 Rev. 2 mainboard prototypes available
2655 1.3 1.3.2.1.1.4 Rev. 2 mainboard testing Complete C 6 60d 06/25/19 09/16/19 06/25/19 8:00 AM 09/16/19 4:59 PM 2653 100% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.1.1.4 1 2654 Rev. 2 mainboard testing
2656 1.3 1.3.2.1.1.5 Rev. 2 mainboard communication tests Complete C 6 10d 08/20/19 09/02/19 08/20/19 8:00 AM 09/02/19 4:59 PM 2654FF -10d 97% 100% Gray Scheduled for 2020-01-10 $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.1.1.5 1 2655 Rev. 2 mainboard communication tests
2657 1.3 1.3.2.1.2 Final design phase Complete P 5 501d 05/01/19 03/31/21 05/01/19 8:00 AM 03/31/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.1.2 1 2656 Final design phase
2658 1.3 1.3.2.1.2.1 Rev. 3 mainboard design Complete C 6 40d 07/08/19 08/30/19 07/08/19 8:00 AM 08/30/19 4:59 PM 99% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.1.2.1 1 2657 Rev. 3 mainboard design
2659 1.3 1.3.2.1.2.2 Firmware development Complete C 6 501d 05/01/19 03/31/21 05/01/19 8:00 AM 03/31/21 4:59 PM 100% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.1.2.2 1 2658 Firmware development
2660 1.3 1.3.2.1.2.3 Production of 15 Rev. 3 mainboards for DVT Complete C 6 25d 09/02/19 10/04/19 09/02/19 8:00 AM 10/04/19 4:59 PM 2657 99% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.1.2.3 1 2659 Production of 15 Rev. 3 mainboards for DVT
2661 1.3 1.3.2.1.2.4 Commissioning and Design Verification Complete C 6 20d 10/07/19 11/01/19 10/07/19 8:00 AM 11/01/19 4:59 PM 2659 99% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.1.2.4 1 2660 Commissioning and Design Verification
2662 1.3 1.3.2.1.3 Production Complete C 5 80d 10/21/19 02/07/20 10/21/19 8:00 AM 02/07/20 4:59 PM 2660FS -10d 100% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.1.3 1 2661 Production
2663 1.3 1.3.2.1.4 Testing Complete C 5 50d 12/09/19 02/14/20 12/09/19 8:00 AM 02/14/20 4:59 PM 2661SS +35d 99% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.1.4 1 2662 Testing
2664 1.3 1.3.2.2 D-Egg PMT Complete P 4 1 281d 10/01/18 10/28/19 10/01/18 8:00 AM 10/28/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.2 1 2663 D-Egg PMT
2665 1.3 1.3.2.2.1 PMT Production Complete P 5 1 281d 10/01/18 10/28/19 10/01/18 8:00 AM 10/28/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.2.1 1 2664 PMT Production
2666 1.3 1.3.2.2.1.1 PMT Batch #1 (Qty. 300) Complete C 6 80d 10/01/18 01/18/19 10/01/18 8:00 AM 01/18/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.2.1.1 1 2665 PMT Batch #1 (Qty. 300)
2667 1.3 1.3.2.2.1.2 PMT Batch #2 (Qty. 300) Complete C 6 120d 04/01/19 09/13/19 04/01/19 8:00 AM 09/13/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.2.1.2 1 2666 PMT Batch #2 (Qty. 300)
2668 1.3 1.3.2.2.1.3 PMT Spares (Qty. 15) Complete C 6 20d 10/01/19 10/28/19 10/01/19 8:00 AM 10/28/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.2.1.3 1 2667 PMT Spares (Qty. 15)
2669 1.3 1.3.2.3 D-Egg High Voltage Subsystem Complete P 4 330d 10/01/18 01/03/20 10/01/18 8:00 AM 01/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.3 1 2668 D-Egg High Voltage Subsystem
2670 1.3 1.3.2.3.1 Preliminary design phase Complete C 5 120d 10/01/18 03/15/19 10/01/18 8:00 AM 03/15/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.3.1 1 2669 Preliminary design phase
2671 1.3 1.3.2.3.2 Final design phase Complete C 5 100d 04/01/19 08/16/19 04/01/19 8:00 AM 08/16/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.3.2 1 2670 Final design phase
2672 1.3 1.3.2.3.3 Tender and procurement Complete P 5 1 310d 10/01/18 12/06/19 10/01/18 8:00 AM 12/06/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.3.3 1 2671 Tender and procurement
2673 1.3 1.3.2.3.3.1 Ferrite core (Qty. 600) Complete C 6 20d 10/01/18 10/26/18 10/01/18 8:00 AM 10/26/18 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.3.3.1 1 2672 Ferrite core (Qty. 600)
2674 1.3 1.3.2.3.3.2 HV generator (Qty. 600) Complete C 6 60d 09/04/19 11/26/19 09/04/19 8:00 AM 11/26/19 4:59 PM 100% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.3.3.2 1 2673 HV generator (Qty. 600)
2675 1.3 1.3.2.3.3.3 HV board (Qty. 600) Complete C 6 60d 09/16/19 12/06/19 09/16/19 8:00 AM 12/06/19 4:59 PM 100% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.3.3.3 1 2674 HV board (Qty. 600)
2676 1.3 1.3.2.3.4 Acceptance testing Complete C 5 60d 10/14/19 01/03/20 10/14/19 8:00 AM 01/03/20 4:59 PM 100% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.3.4 1 2675 Acceptance testing
2677 1.3 1.3.2.4 D-Egg Pressure Vessel Complete P 4 1 673d 10/01/18 04/28/21 10/01/18 8:00 AM 04/28/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.4 1 2676 D-Egg Pressure Vessel
2678 1.3 1.3.2.4.1 Pressure Vessel production Complete P 5 1 673d 10/01/18 04/28/21 10/01/18 8:00 AM 04/28/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.4.1 1 2677 Pressure Vessel production
2679 1.3 1.3.2.4.1.1 PV Batch #1 (Qty. 40) Complete C 6 40d 10/01/18 11/23/18 10/01/18 8:00 AM 11/23/18 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.4.1.1 1 2678 PV Batch #1 (Qty. 40)
2680 1.3 1.3.2.4.1.2 PV Batch #2 (Qty. 130) Complete C 6 60d 04/01/19 06/21/19 04/01/19 8:00 AM 06/21/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.4.1.2 1 2679 PV Batch #2 (Qty. 130)
2681 1.3 1.3.2.4.1.3 PV Batch #3 (Qty. 130) Complete C 6 60d 04/01/20 06/23/20 04/01/20 8:00 AM 06/23/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.4.1.3 1 2680 PV Batch #3 (Qty. 130)
2682 1.3 1.3.2.4.1.4 PV Spare Complete C 6 20d 04/01/21 04/28/21 04/01/21 8:00 AM 04/28/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.4.1.4 1 2681 PV Spare
2683 1.3 1.3.2.5 D-Egg Optical Gel Complete P 4 1 323d 10/01/18 12/25/19 10/01/18 8:00 AM 12/25/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.5 1 2682 D-Egg Optical Gel
2684 1.3 1.3.2.5.1 Final design phase Complete C 5 120d 10/01/18 03/15/19 10/01/18 8:00 AM 03/15/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.5.1 1 2683 Final design phase
2685 1.3 1.3.2.5.2 Procurement of optical gel for DVT Complete C 5 60d 03/18/19 06/07/19 03/18/19 8:00 AM 06/07/19 4:59 PM 2683 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.5.2 1 2684 Procurement of optical gel for DVT
2686 1.3 1.3.2.5.3 Tender and procurement Complete C 5 39d 11/01/19 12/25/19 11/01/19 8:00 AM 12/25/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.5.3 1 2685 Tender and procurement
2687 1.3 1.3.2.6 D-Egg Harness Complete P 4 398d 10/04/18 04/13/20 10/04/18 8:00 AM 04/13/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.6 1 2686 D-Egg Harness
2688 1.3 1.3.2.6.1 Final design phase Complete C 5 180d 10/04/18 06/12/19 10/04/18 8:00 AM 06/12/19 4:59 PM 100% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.6.1 1 2687 Final design phase
2689 1.3 1.3.2.6.2 Construction of production tools Complete C 5 60d 10/01/19 12/23/19 10/01/19 8:00 AM 12/23/19 4:59 PM 100% 100% Gray Delays in development. Dates are driven by Japanese funding agency, not the project needs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.6.2 1 2688 Construction of production tools
2690 1.3 1.3.2.6.3 Production of harnesses for DVT Complete C 5 20d 12/24/19 01/20/20 12/24/19 8:00 AM 01/20/20 4:59 PM 2688 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.6.3 1 2689 Production of harnesses for DVT
2691 1.3 1.3.2.6.4 Tender and procurement Complete C 5 60d 01/21/20 04/13/20 01/21/20 8:00 AM 04/13/20 4:59 PM 2689 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.6.4 1 2690 Tender and procurement
2692 1.3 1.3.2.7 Integrated D-Egg Started P 4 670d 10/01/18 04/23/21 10/01/18 8:00 AM 04/23/21 4:59 PM 99% 98.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7 1 2691 Integrated D-Egg
2693 1.3 1.3.2.7.1 Integrated module design Complete P 5 220d 10/01/18 08/02/19 10/01/18 8:00 AM 08/02/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.1 1 2692 Integrated module design
2694 1.3 1.3.2.7.1.1 Preliminary design phase Complete C 6 120d 10/01/18 03/15/19 10/01/18 8:00 AM 03/15/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.1.1 1 2693 Preliminary design phase
2695 1.3 1.3.2.7.1.2 Final design phase Complete C 6 20d 03/18/19 04/12/19 03/18/19 8:00 AM 04/12/19 4:59 PM 2693 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.1.2 1 2694 Final design phase
2696 1.3 1.3.2.7.1.3 Construction of production tools for internal structure Complete C 6 20d 04/15/19 05/10/19 04/15/19 8:00 AM 05/10/19 4:59 PM 2694 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.1.3 1 2695 Construction of production tools for internal structure
2697 1.3 1.3.2.7.1.4 Production of internal structures for DVT Complete C 6 20d 05/13/19 06/07/19 05/13/19 8:00 AM 06/07/19 4:59 PM 2695 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.1.4 1 2696 Production of internal structures for DVT
2698 1.3 1.3.2.7.1.5 Tender and procurement of internal structures Complete C 6 40d 06/10/19 08/02/19 06/10/19 8:00 AM 08/02/19 4:59 PM 2696 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.1.5 1 2697 Tender and procurement of internal structures
2699 1.3 1.3.2.7.2 Packaging and shipping tools and procedures Complete C 5 120d 11/09/20 04/23/21 11/09/20 8:00 AM 04/23/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.2 1 2698 Packaging and shipping tools and procedures
2700 1.3 1.3.2.7.3 Deployment tools and and procedures Complete C 5 120d 11/09/20 04/23/21 11/09/20 8:00 AM 04/23/21 4:59 PM 2698SS 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.3 1 2699 Deployment tools and and procedures
2701 1.3 1.3.2.7.4 Build 10 modules for DVT Complete C 5 15d 10/21/19 11/08/19 10/21/19 8:00 AM 11/08/19 4:59 PM 98% 100% Gray Scheduled for Jan. 2020 $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.4 1 2700 Build 10 modules for DVT
2702 1.3 1.3.2.7.5 Design Verification Test Complete C 5 40d 11/26/19 01/20/20 11/26/19 8:00 AM 01/20/20 4:59 PM 2700, 2702 99% 100% Gray Scheduled for Jan./Feb. 2020 $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.5 1 2701 Design Verification Test
2703 1.3 1.3.2.7.6 Integrated D-Egg Final Design Review Complete C 5 1 1 1d 11/25/19 11/25/19 11/25/19 8:00 AM 11/25/19 4:59 PM 100% 100% Gray Scheduled for 2020-02-13+14 $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.6 1 2702 Integrated D-Egg Final Design Review
2704 1.3 1.3.2.7.7 Ship DVT modules to NTS Started C 5 10d 01/21/20 02/03/20 01/21/20 8:00 AM 02/03/20 4:59 PM 2701 97% 20.0% Red $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.7.7 1 2703 Ship DVT modules to NTS
2705 1.3 1.3.2.8 D-Egg Production Facility Complete P 4 656d 10/01/18 04/05/21 10/01/18 8:00 AM 04/05/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.8 1 2704 D-Egg Production Facility
2706 1.3 1.3.2.8.1 Set up facilities and hire personel Complete C 5 60d 10/01/18 12/21/18 10/01/18 8:00 AM 12/21/18 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.8.1 1 2705 Set up facilities and hire personel
2707 1.3 1.3.2.8.2 Test Production (Qty. 40 half-D-Eggs) Complete C 5 40d 12/24/18 02/15/19 12/24/18 8:00 AM 02/15/19 4:59 PM 2705 99% 100% Gray Qty. has been reduced $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.8.2 1 2706 Test Production (Qty. 40 half-D-Eggs)
2708 1.3 1.3.2.8.3 Improve production site and procedures Complete C 5 60d 04/23/19 07/15/19 04/23/19 8:00 AM 07/15/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.8.3 1 2707 Improve production site and procedures
2709 1.3 1.3.2.8.4 Production facility audit for assembly, handling, and shipping Complete C 5 1 1d 09/20/19 09/20/19 09/20/19 8:00 AM 09/20/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.2.8.4 1 2708 Production facility audit for assembly, handling, and shipping
2710 1.3 1.3.2.8.5 D-Egg Production Readiness Review Complete C 5 1 1 1d 04/05/21 04/05/21 04/05/21 8:00 AM 04/05/21 4:59 PM 100% 100% Gray Delayed until after initial test production of 50 D-Eggs $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.2.8.5 1 2709 D-Egg Production Readiness Review
2711 1.3 1.3.2.9 D-Egg Series Production Started P 4 1487d 02/04/20 10/23/25 02/04/20 8:00 AM 10/23/25 4:59 PM 12% 41.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.9 1 2710 D-Egg Series Production
2712 1.3 1.3.2.9.1 Series production Started P 5 854d 02/04/20 05/12/23 02/04/20 8:00 AM 05/12/23 4:59 PM 37% 47.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.9.1 1 2711 Series production
2713 1.3 1.3.2.9.1.1 FAT rehearsal Complete P 6 65d 12/07/20 03/05/21 12/07/20 8:00 AM 03/05/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Removed 1.3.2.9.1.1 1 2712 FAT rehearsal
2714 1.3 1.3.2.9.1.1.1 Preparation, debugging Complete C 7 50d 12/07/20 02/12/21 12/07/20 8:00 AM 02/12/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Removed 1.3.2.9.1.1.1 1 2713 Preparation, debugging
2715 1.3 1.3.2.9.1.1.2 Dry-run with to be re-sealed D-Eggs Complete C 7 15d 02/15/21 03/05/21 02/15/21 8:00 AM 03/05/21 4:59 PM 2713 98% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Removed 1.3.2.9.1.1.2 1 2714 Dry-run with to be re-sealed D-Eggs
2716 1.3 1.3.2.9.1.2 D-Egg Batch #1 (Qty. 50) Started P 6 599d 02/04/20 05/20/22 02/04/20 8:00 AM 05/20/22 4:59 PM 59% 52.00% Yellow $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.9.1.2 1 2715 D-Egg Batch #1 (Qty. 50)
2717 1.3 1.3.2.9.1.2.1 PMT potting, camera / flasher installation Complete C 7 40d 02/04/20 03/30/20 02/04/20 8:00 AM 03/30/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg pending confirmation from Erik 1.3.2.9.1.2.1 1 2716 PMT potting, camera / flasher installation
2718 1.3 1.3.2.9.1.2.2 Camera installation (Qty. 36) Complete C 7 9d 09/10/20 09/22/20 09/10/20 8:00 AM 09/22/20 4:59 PM 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg pending confirmation from Erik 1.3.2.9.1.2.2 1 2717 Camera installation (Qty. 36)
2719 1.3 1.3.2.9.1.2.3 MB / PCA installation, sealing Complete C 7 16d 04/05/21 04/26/21 04/05/21 8:00 AM 04/26/21 4:59 PM 98% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg pending confirmation from Erik 1.3.2.9.1.2.3 1 2718 MB / PCA installation, sealing
2720 1.3 1.3.2.9.1.2.4 Start of D-Egg Final Acceptance Testing Not Started C 7 1 0 02/28/22 02/28/22 02/28/22 8:00 AM 02/28/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.3.2.9.1.2.4 1 2719 Start of D-Egg Final Acceptance Testing
2721 1.3 1.3.2.9.1.2.5 FAT Not Started C 7 1 60d 02/28/22 05/20/22 02/28/22 8:00 AM 05/20/22 4:59 PM 2719 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg pending confirmation from Erik 1.3.2.9.1.2.5 1 2720 FAT
2722 1.3 1.3.2.9.1.3 D-Egg Batch #2 (Qty. 110) Started P 6 480d 12/14/20 10/14/22 12/14/20 8:00 AM 10/14/22 4:59 PM 50% 42.00% Yellow $0.00 $0.00 $0.00 $0.00 Timo Karg pending confirmation from Erik 1.3.2.9.1.3 1 2721 D-Egg Batch #2 (Qty. 110)
2723 1.3 1.3.2.9.1.3.1 Integration at NME Complete C 7 75d 12/14/20 03/26/21 12/14/20 8:00 AM 03/26/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.9.1.3.1 1 2722 Integration at NME
2724 1.3 1.3.2.9.1.3.2 FAT Not Started C 7 1 105d 05/23/22 10/14/22 05/23/22 8:00 AM 10/14/22 4:59 PM 2720 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.9.1.3.2 1 2723 FAT
2725 1.3 1.3.2.9.1.4 D-Egg Batch #3 (Qty. 150) Started P 6 527d 05/06/21 05/12/23 05/06/21 8:00 AM 05/12/23 4:59 PM 50% 39.00% Yellow $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.9.1.4 1 2724 D-Egg Batch #3 (Qty. 150)
2726 1.3 1.3.2.9.1.4.1 Integration at NME Complete C 7 97d 05/06/21 09/17/21 05/06/21 8:00 AM 09/17/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.9.1.4.1 1 2725 Integration at NME
2727 1.3 1.3.2.9.1.4.2 FAT Not Started C 7 1 150d 10/17/22 05/12/23 10/17/22 8:00 AM 05/12/23 4:59 PM 2723 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.9.1.4.2 1 2726 FAT
2728 1.3 1.3.2.9.1.5 78 + 18 spares D-Eggs for Strings 87-88 ready to ship to CHC Not Started C 6 1 1 1 0 07/25/22 07/25/22 07/25/22 8:00 AM 07/25/22 8:00 AM 2723SS +45d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg pending confirmation from Erik 1.3.2.9.1.5 1 2727 78 + 18 spares D-Eggs for Strings 87-88 ready to ship to CHC
2729 1.3 1.3.2.9.1.6 197 + 11 spare D-Eggs for Strings 89-93 ready to ship to CHC Not Started C 6 1 1 1 0 05/12/23 05/12/23 05/12/23 4:59 PM 05/12/23 4:59 PM 2726 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.9.1.6 1 2728 197 + 11 spare D-Eggs for Strings 89-93 ready to ship to CHC
2730 1.3 1.3.2.9.1.7 Production of 310 D-Eggs completed Not Started C 6 1 0 05/12/23 05/12/23 05/12/23 4:59 PM 05/12/23 4:59 PM 2728 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.2.9.1.7 1 2729 Production of 310 D-Eggs completed
2731 1.3 1.3.2.9.2 Ship 78 + 18 spare D-Eggs for Strings 87-88 to CHC Not Started C 5 1 60d 08/01/24 10/23/24 08/01/24 8:00 AM 10/23/24 4:59 PM 2727FS +525d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.9.2 1 2730 Ship 78 + 18 spare D-Eggs for Strings 87-88 to CHC
2732 1.3 1.3.2.9.3 Ship 197 + 11 spare D-Eggs for Strings 89-93 to CHC Not Started C 5 1 60d 08/01/25 10/23/25 08/01/25 8:00 AM 10/23/25 4:59 PM 2728FS +573d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.2.9.3 1 2731 Ship 197 + 11 spare D-Eggs for Strings 89-93 to CHC
2733 1.3 1.3.3 PDOM Started P 3 1 1683d 03/11/19 08/28/25 03/11/19 8:00 AM 08/28/25 4:59 PM 13% 47.00% Green $0.00 $0.00 $20,626.94 $161,887.20 13% Timo Karg 1.3.3 1 2732 PDOM
2734 1.3 1.3.3.1 PDOM DAQ Electronics Started P 4 1 940d 03/11/19 10/14/22 03/11/19 8:00 AM 10/14/22 4:59 PM 29% 87.00% Green $0.00 $0.00 $20,626.94 $71,703.88 29% Timo Karg 1.3.3.1 1 2733 PDOM DAQ Electronics
2735 1.3 1.3.3.1.1 PDOM Rev2 Mainboard Complete P 5 1 175d 03/11/19 11/08/19 03/11/19 8:00 AM 11/08/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.1.1 1 2734 PDOM Rev2 Mainboard
2736 1.3 1.3.3.1.1.1 Update schematics Complete C 6 1 25d 04/01/19 05/03/19 04/01/19 8:00 AM 05/03/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.1.1.1 1 2735 Update schematics
2737 1.3 1.3.3.1.1.2 Layout Complete C 6 1 30d 05/06/19 06/14/19 05/06/19 8:00 AM 06/14/19 4:59 PM 2735 99% 100% Gray Delays in development due to unification of PDOM and D-Egg mainboards $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.1.1.2 1 2736 Layout
2738 1.3 1.3.3.1.1.3 PDOM Rev2 Mainboard production (Qty. 10) Complete C 6 1 30d 06/17/19 07/26/19 06/17/19 8:00 AM 07/26/19 4:59 PM 2736 99% 100% Gray Delays in development due to unification of PDOM and D-Egg mainboards $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.1.1.3 1 2737 PDOM Rev2 Mainboard production (Qty. 10)
2739 1.3 1.3.3.1.1.4 Firmware Complete C 6 1 100d 03/11/19 07/26/19 03/11/19 8:00 AM 07/26/19 4:59 PM 2737FF 100% 100% Gray Delays in development due to unification of PDOM and D-Egg mainboards $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.1.1.4 1 2738 Firmware
2740 1.3 1.3.3.1.1.5 Testing Complete C 6 1 75d 07/29/19 11/08/19 07/29/19 8:00 AM 11/08/19 4:59 PM 2738 100% 100% Gray Delays in development due to unification of PDOM and D-Egg mainboards $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.1.1.5 1 2739 Testing
2741 1.3 1.3.3.1.2 PDOM Rev3 Mainboard Started P 5 1 641d 05/01/20 10/14/22 05/01/20 8:00 AM 10/14/22 4:59 PM 29% 83.00% Green $0.00 $0.00 $20,626.94 $71,703.88 29% Timo Karg 1.3.3.1.2 1 2740 PDOM Rev3 Mainboard
2742 1.3 1.3.3.1.2.1 Update schematics Complete C 6 1 20d 05/01/20 05/28/20 05/01/20 8:00 AM 05/28/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.1.2.1 1 2741 Update schematics
2743 1.3 1.3.3.1.2.2 Layout Complete C 6 1 30d 05/29/20 07/09/20 05/29/20 8:00 AM 07/09/20 4:59 PM 2741 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.1.2.2 1 2742 Layout
2744 1.3 1.3.3.1.2.3 PDOM Rev3 Mainboard production (Qty. 8) Complete C 6 1 30d 09/27/21 11/05/21 09/27/21 8:00 AM 11/05/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.1.2.3 1 2743 PDOM Rev3 Mainboard production (Qty. 8)
2745 1.3 1.3.3.1.2.6 Adapt D-Egg Firmware to PDOM Mainboard and verify design Started C 6 1 205d 09/27/21 07/08/22 09/27/21 8:00 AM 07/08/22 4:59 PM 2743SS 45% 95.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.1.2.6 1 2744 Adapt D-Egg Firmware to PDOM Mainboard and verify design
2746 1.3 1.3.3.1.2.4 Testing Started C 6 1 30d 04/04/22 05/13/22 04/04/22 8:00 AM 05/13/22 4:59 PM 90% 33.00% Red $20,626.94 $22,953.88 $20,626.94 $22,953.88 90% $7,574.78 Timo Karg 1.3.3.1.2.4 1 2745 Testing
2747 1.3 1.3.3.1.2.5 PDOM Rev3 Mainboard production (Qty. 27) Not Started C 6 1 30d 09/05/22 10/14/22 09/05/22 8:00 AM 10/14/22 4:59 PM 2755 0% 0% Green $0.00 $48,750.00 $0.00 $48,750.00 0% $0.00 Timo Karg 1.3.3.1.2.5 1 2746 PDOM Rev3 Mainboard production (Qty. 27)
2748 1.3 1.3.3.2 PDOM High Voltage Subsystem Started P 4 1 903d 05/01/19 10/14/22 05/01/19 8:00 AM 10/14/22 4:59 PM 0% 54.00% Green $0.00 $0.00 $0.00 $12,250.00 0% Timo Karg 1.3.3.2 1 2747 PDOM High Voltage Subsystem
2749 1.3 1.3.3.2.1 PDOM HV System Preliminary Design Complete C 5 1 120d 05/01/19 10/15/19 05/01/19 8:00 AM 10/15/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.2.1 1 2748 PDOM HV System Preliminary Design
2750 1.3 1.3.3.2.2 PDOM HV System Final Design Started P 5 1 359d 06/01/21 10/14/22 06/01/21 8:00 AM 10/14/22 4:59 PM 0% 38.00% Green $0.00 $0.00 $0.00 $12,250.00 0% Timo Karg 1.3.3.2.2 1 2749 PDOM HV System Final Design
2751 1.3 1.3.3.2.2.1 Update schematics Complete C 6 1 20d 06/01/21 06/28/21 06/01/21 8:00 AM 06/28/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.2.2.1 1 2750 Update schematics
2752 1.3 1.3.3.2.2.2 Layout Complete C 6 1 30d 01/17/22 02/25/22 01/17/22 8:00 AM 02/25/22 4:59 PM 37% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.2.2.2 1 2751 Layout
2753 1.3 1.3.3.2.2.3 PDOM HV System production (Qty. 8) Not Started C 6 1 30d 02/28/22 04/08/22 02/28/22 8:00 AM 04/08/22 4:59 PM 2751 0% 0% Green $0.00 $3,500.00 $0.00 $3,500.00 0% $0.00 Timo Karg 1.3.3.2.2.3 1 2752 PDOM HV System production (Qty. 8)
2754 1.3 1.3.3.2.2.4 Testing Not Started C 6 1 20d 04/11/22 05/06/22 04/11/22 8:00 AM 05/06/22 4:59 PM 2752 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.2.2.4 1 2753 Testing
2755 1.3 1.3.3.2.2.5 PDOM HV system production (Qty. 27) Not Started C 6 1 30d 09/05/22 10/14/22 09/05/22 8:00 AM 10/14/22 4:59 PM 2755 0% 0% Green $0.00 $8,750.00 $0.00 $8,750.00 0% $0.00 Timo Karg 1.3.3.2.2.5 1 2754 PDOM HV system production (Qty. 27)
2756 1.3 1.3.3.3 PDOM Final Design Review Not Started C 4 1 1 1 0 09/02/22 09/02/22 09/02/22 4:59 PM 09/02/22 4:59 PM 2758 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.3 1 2755 PDOM Final Design Review
2757 1.3 1.3.3.4 IceCube DOM Refurbishment Not Started P 4 1 923d 02/07/22 08/28/25 02/07/22 8:00 AM 08/28/25 4:59 PM 0% 0% Green $0.00 $16,100.00 $0.00 $77,933.32 0% $0.00 Timo Karg 1.3.3.4 1 2756 IceCube DOM Refurbishment
2758 1.3 1.3.3.4.1 Refurbish 10 IceCube DOMs Not Started C 5 1 20d 06/13/22 07/08/22 06/13/22 8:00 AM 07/08/22 4:59 PM 2745, 2753, 2777, 2782, 2787 0% 0% Green $0.00 $13,641.59 $0.00 $13,641.59 0% $0.00 Timo Karg 1.3.3.4.1 1 2757 Refurbish 10 IceCube DOMs
2759 1.3 1.3.3.4.2 Design Verification Test Not Started C 5 1 40d 07/11/22 09/02/22 07/11/22 8:00 AM 09/02/22 4:59 PM 2757 0% 0% Green $0.00 $18,006.84 $0.00 $18,006.84 0% $0.00 Timo Karg 1.3.3.4.2 1 2758 Design Verification Test
2760 1.3 1.3.3.4.3 Ship DVT modules to NTS Not Started C 5 1 10d 09/05/22 09/16/22 09/05/22 8:00 AM 09/16/22 4:59 PM 2758 0% 0% Green $0.00 $1,000.00 $0.00 $1,000.00 0% $0.00 Timo Karg 1.3.3.4.3 1 2759 Ship DVT modules to NTS
2761 1.3 1.3.3.4.4 Facilities Not Started P 5 1 60d 02/07/22 04/29/22 02/07/22 8:00 AM 04/29/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.4.4 1 2760 Facilities
2762 1.3 1.3.3.4.4.1 Set up refurbishment Facility Not Started C 6 1 60d 02/07/22 04/29/22 02/07/22 8:00 AM 04/29/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.4.4.1 1 2761 Set up refurbishment Facility
2763 1.3 1.3.3.4.4.2 DOM Refurbishment Facilities Ready Not Started C 6 1 1 0 04/29/22 04/29/22 04/29/22 4:59 PM 04/29/22 4:59 PM 2761 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.4.4.2 1 2762 DOM Refurbishment Facilities Ready
2764 1.3 1.3.3.4.5 Refurbish 20 IceCube DOMs with Rev3 Mainboards Not Started P 5 1 65d 10/17/22 01/13/23 10/17/22 8:00 AM 01/13/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $29,184.89 0% Timo Karg 1.3.3.4.5 1 2763 Refurbish 20 IceCube DOMs with Rev3 Mainboards
2765 1.3 1.3.3.4.5.1 Refurbishment Batch #1 (Qty. 20) Not Started C 6 1 30d 10/17/22 11/25/22 10/17/22 8:00 AM 11/25/22 4:59 PM 2746, 2754, 2762 0% 0% Green $0.00 $27,283.18 $0.00 $27,283.18 0% $0.00 Timo Karg 1.3.3.4.5.1 1 2764 Refurbishment Batch #1 (Qty. 20)
2766 1.3 1.3.3.4.5.2 FAT Batch #1 Not Started C 6 1 30d 11/28/22 01/06/23 11/28/22 8:00 AM 01/06/23 4:59 PM 2764 0% 0% Green $0.00 $1,901.71 $0.00 $1,901.71 0% $0.00 Timo Karg 1.3.3.4.5.2 1 2765 FAT Batch #1
2767 1.3 1.3.3.4.5.3 Packing Batch #1 Not Started C 6 1 5d 01/09/23 01/13/23 01/09/23 8:00 AM 01/13/23 4:59 PM 2765 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.4.5.3 1 2766 Packing Batch #1
2768 1.3 1.3.3.4.5.4 2 + 2 spare PDOMs for Strings 87-88 ready to ship to Pt. Hueneme Not Started C 6 1 1 0 01/13/23 01/13/23 01/13/23 4:59 PM 01/13/23 4:59 PM 2766 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.3.4.5.4 1 2767 2 + 2 spare PDOMs for Strings 87-88 ready to ship to Pt. Hueneme
2769 1.3 1.3.3.4.5.5 12 + 4 spare PDOMs for Strings 89-93 ready to ship to Pt. Hueneme Not Started C 6 1 1 0 01/13/23 01/13/23 01/13/23 4:59 PM 01/13/23 4:59 PM 2766 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.3.4.5.5 1 2768 12 + 4 spare PDOMs for Strings 89-93 ready to ship to Pt. Hueneme
2770 1.3 1.3.3.4.5.6 Refurbishment of 20 PDOMs completed Not Started C 6 1 0 01/13/23 01/13/23 01/13/23 4:59 PM 01/13/23 4:59 PM 2768 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg New Activity 1.3.3.4.5.6 1 2769 Refurbishment of 20 PDOMs completed
2771 1.3 1.3.3.4.6 Ship 2 + 1 spare PDOMs for Strings 87-88 to Pt. Hueneme Not Started C 5 1 1 20d 08/01/24 08/28/24 08/01/24 8:00 AM 08/28/24 4:59 PM 2767FS +400d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.3.4.6 1 2770 Ship 2 + 1 spare PDOMs for Strings 87-88 to Pt. Hueneme
2772 1.3 1.3.3.4.7 Ship 12 + 1 spare PDOMs for Strings 89-93 to Pt. Hueneme Not Started C 5 1 1 20d 08/01/25 08/28/25 08/01/25 8:00 AM 08/28/25 4:59 PM 2768FS +658d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.3.4.7 1 2771 Ship 12 + 1 spare PDOMs for Strings 89-93 to Pt. Hueneme
2773 1.3 1.3.3.5 PDOM Calibration Subsystem Started P 4 115d 01/03/22 06/10/22 01/03/22 8:00 AM 06/10/22 4:59 PM 3% 36.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5 1 2772 PDOM Calibration Subsystem
2774 1.3 1.3.3.5.1 PDOM Calibration Board Started P 5 115d 01/03/22 06/10/22 01/03/22 8:00 AM 06/10/22 4:59 PM 8% 43.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.1 1 2773 PDOM Calibration Board
2775 1.3 1.3.3.5.1.1 PDOM Calibration Board Design Started C 6 70d 01/03/22 04/08/22 01/03/22 8:00 AM 04/08/22 4:59 PM 30% 70.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.1.1 1 2774 PDOM Calibration Board Design
2776 1.3 1.3.3.5.1.2 PDOM Calibration Board Implementation Not Started C 6 25d 04/11/22 05/13/22 04/11/22 8:00 AM 05/13/22 4:59 PM 2774 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.1.2 1 2775 PDOM Calibration Board Implementation
2777 1.3 1.3.3.5.1.3 PDOM Calibration Board Testing Not Started C 6 20d 05/16/22 06/10/22 05/16/22 8:00 AM 06/10/22 4:59 PM 2775 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.1.3 1 2776 PDOM Calibration Board Testing
2778 1.3 1.3.3.5.1.4 PDOM Calibration Board production ready Not Started C 6 1 0 06/10/22 06/10/22 06/10/22 4:59 PM 06/10/22 4:59 PM 2776 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.3.3.5.1.4 1 2777 PDOM Calibration Board production ready
2779 1.3 1.3.3.5.2 PDOM Camera Illuminators Started P 5 70d 01/31/22 05/06/22 01/31/22 8:00 AM 05/06/22 4:59 PM 1% 39.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.2 1 2778 PDOM Camera Illuminators
2780 1.3 1.3.3.5.2.1 PDOM Camera Illuminators Design Started C 6 30d 01/31/22 03/11/22 01/31/22 8:00 AM 03/11/22 4:59 PM 2% 90.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.2.1 1 2779 PDOM Camera Illuminators Design
2781 1.3 1.3.3.5.2.2 PDOM Camera Illuminators Implementation Not Started C 6 20d 03/14/22 04/08/22 03/14/22 8:00 AM 04/08/22 4:59 PM 2779 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.2.2 1 2780 PDOM Camera Illuminators Implementation
2782 1.3 1.3.3.5.2.3 PDOM Camera Illuminators Testing Not Started C 6 20d 04/11/22 05/06/22 04/11/22 8:00 AM 05/06/22 4:59 PM 2780 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.2.3 1 2781 PDOM Camera Illuminators Testing
2783 1.3 1.3.3.5.2.4 PDOM Camera Illuminators production ready Not Started C 6 1 0 05/06/22 05/06/22 05/06/22 4:59 PM 05/06/22 4:59 PM 2781 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.3.3.5.2.4 1 2782 PDOM Camera Illuminators production ready
2784 1.3 1.3.3.5.3 Acoustic Receiver Integration Started P 5 70d 02/28/22 06/03/22 02/28/22 8:00 AM 06/03/22 4:59 PM 0% 21.00% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.3 1 2783 Acoustic Receiver Integration
2785 1.3 1.3.3.5.3.1 Acoustic Receiver Integration Design Started C 6 30d 02/28/22 04/08/22 02/28/22 8:00 AM 04/08/22 4:59 PM 0% 50.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.3.1 1 2784 Acoustic Receiver Integration Design
2786 1.3 1.3.3.5.3.2 Acoustic Receiver Integration Implementation Not Started C 6 20d 04/11/22 05/06/22 04/11/22 8:00 AM 05/06/22 4:59 PM 2784 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.3.2 1 2785 Acoustic Receiver Integration Implementation
2787 1.3 1.3.3.5.3.3 Acoustic Receiver Integration Testing Not Started C 6 20d 05/09/22 06/03/22 05/09/22 8:00 AM 06/03/22 4:59 PM 2785 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.3.5.3.3 1 2786 Acoustic Receiver Integration Testing
2788 1.3 PDOM Acoustic Receiver Integration design complete Not Started C 6 1 0 06/03/22 06/03/22 06/03/22 4:59 PM 06/03/22 4:59 PM 2786 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1 2787 PDOM Acoustic Receiver Integration design complete
2789 1.3 1.3.4 Ice Comms Module Started P 3 1891d 02/01/19 05/14/26 02/01/19 8:00 AM 05/14/26 4:59 PM 88% 42.00% Red $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4 1 2788 Ice Comms Module
2790 1.3 1.3.4.1 ICM Electronics Complete P 4 664d 02/01/19 08/18/21 02/01/19 8:00 AM 08/18/21 4:59 PM 98% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1 1 2789 ICM Electronics
2791 1.3 1.3.4.1.1 Interface of ICM to DOM mainboard defined Complete C 5 1d 02/01/19 02/01/19 02/01/19 8:00 AM 02/01/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.1 1 2790 Interface of ICM to DOM mainboard defined
2792 1.3 1.3.4.1.2 Schematic / BOM development Complete C 5 1 20d 02/04/19 03/01/19 02/04/19 8:00 AM 03/01/19 4:59 PM 2790 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.2 1 2791 Schematic / BOM development
2793 1.3 1.3.4.1.3 Conceptual design available Complete C 5 2d 03/04/19 03/05/19 03/04/19 8:00 AM 03/05/19 4:59 PM 2791 84% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.3 1 2792 Conceptual design available
2794 1.3 1.3.4.1.4 Preliminary design phase Complete C 5 1 40d 03/04/19 04/26/19 03/04/19 8:00 AM 04/26/19 4:59 PM 2792SS 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.4 1 2793 Preliminary design phase
2795 1.3 1.3.4.1.5 First working prototype available Complete C 5 1d 04/29/19 04/29/19 04/29/19 8:00 AM 04/29/19 4:59 PM 2793 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.5 1 2794 First working prototype available
2796 1.3 1.3.4.1.6 Production of Stand-alone PCBs for Cable Verification Complete C 5 50d 04/29/19 07/05/19 04/29/19 8:00 AM 07/05/19 4:59 PM 2794SS 99% 100% Gray Cable verification has been done at DESY $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.6 1 2795 Production of Stand-alone PCBs for Cable Verification
2797 1.3 1.3.4.1.7 Shipping to NTS Complete C 5 10d 07/08/19 07/19/19 07/08/19 8:00 AM 07/19/19 4:59 PM 2795 97% 100% Gray Printed circuit assemblies of the final design are available; firmware development is ongoing, but firmware will be required for design verification $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.7 1 2796 Shipping to NTS
2798 1.3 1.3.4.1.8 Final design phase Complete C 5 1 87d 04/26/19 08/26/19 04/26/19 8:00 AM 08/26/19 4:59 PM 100% 100% Gray Printed circuit assemblies of the final design are available; firmware development is ongoing, but firmware will be required for design verification $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.4.1.8 1 2797 Final design phase
2799 1.3 1.3.4.1.9 Ice Comms Module FDR Complete C 5 1d 08/27/19 08/27/19 08/27/19 8:00 AM 08/27/19 4:59 PM 2797 100% 100% Gray Printed circuit assemblies of the final design are available; firmware development is ongoing, but firmware will be required for design verification $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.4.1.9 1 2798 Ice Comms Module FDR
2800 1.3 1.3.4.1.10 Production of 15 ICMs for D-Egg DVT Complete C 5 29d 08/27/19 10/04/19 08/27/19 8:00 AM 10/04/19 4:59 PM 2798SS 99% 100% Gray Printed circuit assemblies of the final design are available; firmware development is ongoing, but firmware will be required for design verification $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.10 1 2799 Production of 15 ICMs for D-Egg DVT
2801 1.3 1.3.4.1.11 Tender and Procurement (series production) Complete C 5 80d 06/17/19 10/04/19 06/17/19 8:00 AM 10/04/19 4:59 PM 2799FF 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.11 1 2800 Tender and Procurement (series production)
2802 1.3 1.3.4.1.12 Production of 900 ICMs for in-ice modules Complete P 5 1 488d 10/07/19 08/18/21 10/07/19 8:00 AM 08/18/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.12 1 2801 Production of 900 ICMs for in-ice modules
2803 1.3 1.3.4.1.12.1 Production Batch #1 (Qty. 72) Complete C 6 40d 10/07/19 11/29/19 10/07/19 8:00 AM 11/29/19 4:59 PM 2800 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.12.1 1 2802 Production Batch #1 (Qty. 72)
2804 1.3 1.3.4.1.12.2 Production Batch #2 (Qty. 264) Complete C 6 60d 08/03/20 10/23/20 08/03/20 8:00 AM 10/23/20 4:59 PM 100% 100% Gray Cable verification has been done at DESY $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.12.2 1 2803 Production Batch #2 (Qty. 264)
2805 1.3 1.3.4.1.12.3 Production Batch #3 (Qty. 500) Complete C 6 15d 03/08/21 03/26/21 03/08/21 8:00 AM 03/26/21 4:59 PM 98% 100% Gray Printed circuit assemblies of the final design are available; firmware development is ongoing, but firmware will be required for design verification $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.12.3 1 2804 Production Batch #3 (Qty. 500)
2806 1.3 1.3.4.1.12.4 Testing Batch #3 (Qty. 500) Complete C 6 1 30d 03/29/21 05/07/21 03/29/21 8:00 AM 05/07/21 4:59 PM 2804 99% 100% Gray Printed circuit assemblies of the final design are available; firmware development is ongoing, but firmware will be required for design verification $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.4.1.12.4 1 2805 Testing Batch #3 (Qty. 500)
2807 1.3 1.3.4.1.12.5 Production Batch #4 (Qty. 200) Complete C 6 15d 07/01/21 07/21/21 07/01/21 8:00 AM 07/21/21 4:59 PM 98% 100% Gray Printed circuit assemblies of the final design are available; firmware development is ongoing, but firmware will be required for design verification $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.4.1.12.5 1 2806 Production Batch #4 (Qty. 200)
2808 1.3 1.3.4.1.12.6 Testing Batch #4 (Qty. 200) Complete C 6 20d 07/22/21 08/18/21 07/22/21 8:00 AM 08/18/21 4:59 PM 2806 99% 100% Gray Printed circuit assemblies of the final design are available; firmware development is ongoing, but firmware will be required for design verification $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.1.12.6 1 2807 Testing Batch #4 (Qty. 200)
2809 1.3 1.3.4.2 ICM Firmware Started P 4 1415d 11/30/20 05/14/26 11/30/20 8:00 AM 05/14/26 4:59 PM 65% 10.0% Red $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.2 1 2808 ICM Firmware
2810 1.3 1.3.4.2.1 Parallel communication to multiple devices Complete C 5 10d 11/30/20 12/11/20 11/30/20 8:00 AM 12/11/20 4:59 PM 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.2.1 1 2809 Parallel communication to multiple devices
2811 1.3 1.3.4.2.3 RAPCAL Firmware Started P 5 1405d 12/14/20 05/14/26 12/14/20 8:00 AM 05/14/26 4:59 PM 34% 9.00% Red $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.2.3 1 2810 RAPCAL Firmware
2812 1.3 1.3.4.2.3.1 Implementation Complete P 6 25d 12/14/20 01/15/21 12/14/20 8:00 AM 01/15/21 4:59 PM 95% 100% Gray $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.2.3.1 1 2811 Implementation
2813 1.3 1.3.4.2.3.1.1 Part 1 (before holidays) Complete C 7 5d 12/14/20 12/18/20 12/14/20 8:00 AM 12/18/20 4:59 PM 2809 93% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.4.2.3.1.1 1 2812 Part 1 (before holidays)
2814 1.3 1.3.4.2.3.1.2 Part 2 (after holidays) Complete C 7 10d 01/04/21 01/15/21 01/04/21 8:00 AM 01/15/21 4:59 PM 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg Activity Renamed 1.3.4.2.3.1.2 1 2813 Part 2 (after holidays)
2815 1.3 1.3.4.2.3.2 Debugging Complete C 6 20d 01/18/21 02/12/21 01/18/21 8:00 AM 02/12/21 4:59 PM 2813 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.2.3.2 1 2814 Debugging
2816 1.3 1.3.4.2.3.3 Firmware support during D-Egg FAT Not Started C 6 1 315d 02/28/22 05/12/23 02/28/22 8:00 AM 05/12/23 4:59 PM 2720SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.2.3.3 1 2815 Firmware support during D-Egg FAT
2817 1.3 1.3.4.2.3.4 Firmware preparation for mDOM FAT Not Started C 6 1 30d 06/27/22 08/05/22 06/27/22 8:00 AM 08/05/22 4:59 PM 0% 0% Green hen $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.2.3.4 1 2816 Firmware preparation for mDOM FAT
2818 1.3 1.3.4.2.3.5 Firmware support during mDOM FAT Not Started C 6 1 175d 01/16/23 09/15/23 01/16/23 8:00 AM 09/15/23 4:59 PM 0% 0% Green Parallel to mDOM FAT at DESY and MSU $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.2.3.5 1 2817 Firmware support during mDOM FAT
2819 1.3 1.3.4.2.3.6 Firmware support during development of Calibration Devices, Special Devices, system integration, and commissioning Started C 6 1 1217d 09/02/21 05/14/26 09/02/21 8:00 AM 05/14/26 4:59 PM 2843SS 9% 9.00% Green Activity should run until end-of-project, whenever that is $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.2.3.6 1 2818 Firmware support during development of Calibration Devices, Special Devices, system integration, and commissioning
2820 1.3 1.3.4.3 mini-FieldHub ICM Firmware Complete C 4 120d 08/31/20 02/12/21 08/31/20 8:00 AM 02/12/21 4:59 PM 2814FF 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.4.3 1 2819 mini-FieldHub ICM Firmware
2821 1.3 1.3.5 Special Devices Started P 3 1733d 01/01/19 08/29/25 01/01/19 8:00 AM 08/29/25 4:59 PM 43% 9.00% Red $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5 1 2820 Special Devices
2822 1.3 1.3.5.1 R&D module registration Complete C 4 349d 01/01/19 05/01/20 01/01/19 8:00 AM 05/01/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.1 1 2821 R&D module registration
2823 1.3 1.3.5.2 R&D module mission review Complete C 4 1d 05/04/20 05/04/20 05/04/20 8:00 AM 05/04/20 4:59 PM 2821 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.2 1 2822 R&D module mission review
2824 1.3 1.3.5.3 Allocation of R&D module resources Complete C 4 260d 01/04/21 12/31/21 01/04/21 8:00 AM 12/31/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.3 1 2823 Allocation of R&D module resources
2825 1.3 1.3.5.4 R&D modules deployment readiness review Should have Started C 4 100% Red Has been replaced by reviews for individual devices (WBS 1.3.5.5 to 1.3.5.11) $0.00 $0.00 $0.00 $0.00 $0.00 1.3.5.4 1 2824 R&D modules deployment readiness review
2826 1.3 1.3.5.5 DM-Ice Not Started P 4 911d 02/24/22 08/29/25 02/24/22 8:00 AM 08/29/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.5 1 2825 DM-Ice
2827 1.3 1.3.5.5.1 DM-Ice Preliminary Design Review Not Started C 5 1 0 02/24/22 02/24/22 02/24/22 8:00 AM 02/24/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.5.1 1 2826 DM-Ice Preliminary Design Review
2828 1.3 1.3.5.5.2 DM-Ice Final Design Review Not Started C 5 1 0 05/01/24 05/01/24 05/01/24 8:00 AM 05/01/24 8:00 AM 2828SF -195d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.5.2 1 2827 DM-Ice Final Design Review
2829 1.3 1.3.5.5.3 DM-Ice Deployment Readiness Review Not Started C 5 1 0 02/03/25 02/03/25 02/03/25 8:00 AM 02/03/25 8:00 AM 2829SF -130d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.5.3 1 2828 DM-Ice Deployment Readiness Review
2830 1.3 1.3.5.5.4 Ship 2 DM-Ice modules from Yale to Pt. Hueneme Not Started C 5 20d 08/04/25 08/29/25 08/04/25 8:00 AM 08/29/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.5.4 1 2829 Ship 2 DM-Ice modules from Yale to Pt. Hueneme
2831 1.3 1.3.5.6 Fiber-Optic Module (FOM) Not Started P 4 883d 04/04/22 08/28/25 04/04/22 8:00 AM 08/28/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.6 1 2830 Fiber-Optic Module (FOM)
2832 1.3 1.3.5.6.1 FOM Preliminary Design Review Not Started C 5 1 0 04/04/22 04/04/22 04/04/22 8:00 AM 04/04/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.6.1 1 2831 FOM Preliminary Design Review
2833 1.3 1.3.5.6.2 FOM Final Design Review Not Started C 5 1 0 05/01/23 05/01/23 05/01/23 8:00 AM 05/01/23 8:00 AM 2833SF -195d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.6.2 1 2832 FOM Final Design Review
2834 1.3 1.3.5.6.3 FOM Deployment Readiness Review Not Started C 5 1 0 02/01/24 02/01/24 02/01/24 8:00 AM 02/01/24 8:00 AM 2834SF -130d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.6.3 1 2833 FOM Deployment Readiness Review
2835 1.3 1.3.5.6.4 Ship 4 FOMs from UW to Pt. Hueneme Not Started C 5 20d 08/01/24 08/28/24 08/01/24 8:00 AM 08/28/24 4:59 PM 2770SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.6.4 1 2834 Ship 4 FOMs from UW to Pt. Hueneme
2836 1.3 1.3.5.6.5 Ship 5 FOMs from UW to Pt. Hueneme Not Started C 5 20d 08/01/25 08/28/25 08/01/25 8:00 AM 08/28/25 4:59 PM 2771SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.6.5 1 2835 Ship 5 FOMs from UW to Pt. Hueneme
2837 1.3 1.3.5.7 eLongated Optical Module (LOM) Should have Started P 4 962d 12/14/21 08/28/25 12/14/21 8:00 AM 08/28/25 4:59 PM 20% 0% Yellow $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.7 1 2836 eLongated Optical Module (LOM)
2838 1.3 1.3.5.7.1 LOM Preliminary Design Review Complete C 5 1 0 12/14/21 12/14/21 12/14/21 8:00 AM 12/14/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.7.1 1 2837 LOM Preliminary Design Review
2839 1.3 1.3.5.7.2 LOM Final Design Review Not Started C 5 1 0 05/01/23 05/01/23 05/01/23 8:00 AM 05/01/23 8:00 AM 2839SF -195d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.7.2 1 2838 LOM Final Design Review
2840 1.3 1.3.5.7.3 LOM Deployment Readiness Review Not Started C 5 1 0 02/01/24 02/01/24 02/01/24 8:00 AM 02/01/24 8:00 AM 2840SF -130d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.7.3 1 2839 LOM Deployment Readiness Review
2841 1.3 1.3.5.7.4 Ship 2 LOMs from UW to Pt. Hueneme Not Started C 5 20d 08/01/24 08/28/24 08/01/24 8:00 AM 08/28/24 4:59 PM 2770SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.7.4 1 2840 Ship 2 LOMs from UW to Pt. Hueneme
2842 1.3 1.3.5.7.5 Ship 12 LOMs from UW to Pt. Hueneme Not Started C 5 20d 08/01/25 08/28/25 08/01/25 8:00 AM 08/28/25 4:59 PM 2771SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.7.5 1 2841 Ship 12 LOMs from UW to Pt. Hueneme
2843 1.3 1.3.5.8 Radio Pulser (RP) Should have Started P 4 777d 09/02/21 08/28/24 09/02/21 8:00 AM 08/28/24 4:59 PM 25% 0% Red $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.8 1 2842 Radio Pulser (RP)
2844 1.3 1.3.5.8.1 RP Preliminary Design Review Complete C 5 1 0 09/02/21 09/02/21 09/02/21 8:00 AM 09/02/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.8.1 1 2843 RP Preliminary Design Review
2845 1.3 1.3.5.8.2 RP Final Design Review Not Started C 5 1 0 05/01/23 05/01/23 05/01/23 8:00 AM 05/01/23 8:00 AM 2845SF -195d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.8.2 1 2844 RP Final Design Review
2846 1.3 1.3.5.8.3 RP Deployment Readiness Review Not Started C 5 1 0 02/01/24 02/01/24 02/01/24 8:00 AM 02/01/24 8:00 AM 2846SF -130d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.8.3 1 2845 RP Deployment Readiness Review
2847 1.3 1.3.5.8.4 Ship 5 RPs from UW to Pt. Hueneme Not Started C 5 20d 08/01/24 08/28/24 08/01/24 8:00 AM 08/28/24 4:59 PM 2770SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.8.4 1 2846 Ship 5 RPs from UW to Pt. Hueneme
2848 1.3 1.3.5.9 Radio Receiver (RR) Not Started P 4 863d 05/02/22 08/28/25 05/02/22 8:00 AM 08/28/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.9 1 2847 Radio Receiver (RR)
2849 1.3 1.3.5.9.1 RR Preliminary Design Review Not Started C 5 1 0 05/02/22 05/02/22 05/02/22 8:00 AM 05/02/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.9.1 1 2848 RR Preliminary Design Review
2850 1.3 1.3.5.9.2 RR Final Design Review Not Started C 5 1 0 05/01/23 05/01/23 05/01/23 8:00 AM 05/01/23 8:00 AM 2850FS -195d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.9.2 1 2849 RR Final Design Review
2851 1.3 1.3.5.9.3 RR Deployment Readiness Review Not Started C 5 1 0 02/01/24 02/01/24 02/01/24 8:00 AM 02/01/24 8:00 AM 2851SF -130d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.9.3 1 2850 RR Deployment Readiness Review
2852 1.3 1.3.5.9.4 Ship 2 RRs from UW to Pt. Hueneme Not Started C 5 20d 08/01/24 08/28/24 08/01/24 8:00 AM 08/28/24 4:59 PM 2770SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.9.4 1 2851 Ship 2 RRs from UW to Pt. Hueneme
2853 1.3 1.3.5.9.5 Ship 3 RRs from UW to Pt. Hueneme Not Started C 5 20d 08/01/25 08/28/25 08/01/25 8:00 AM 08/28/25 4:59 PM 2771SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.9.5 1 2852 Ship 3 RRs from UW to Pt. Hueneme
2854 1.3 1.3.5.10 Very Broadband Seismograph (SMG) Not Started P 4 818d 07/04/22 08/28/25 07/04/22 8:00 AM 08/28/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.10 1 2853 Very Broadband Seismograph (SMG)
2855 1.3 1.3.5.10.1 SMG Preliminary Design Review Not Started C 5 1 0 07/04/22 07/04/22 07/04/22 8:00 AM 07/04/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.10.1 1 2854 SMG Preliminary Design Review
2856 1.3 1.3.5.10.2 SMG Final Design Review Not Started C 5 1 0 05/28/24 05/28/24 05/28/24 8:00 AM 05/28/24 8:00 AM 2856FS -195d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.10.2 1 2855 SMG Final Design Review
2857 1.3 1.3.5.10.3 SMG Deployment Readiness Review Not Started C 5 1 0 02/28/25 02/28/25 02/28/25 8:00 AM 02/28/25 8:00 AM 2857FS -130d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.10.3 1 2856 SMG Deployment Readiness Review
2858 1.3 1.3.5.10.4 Ship SMG from UW to Pt. Hueneme Not Started C 5 20d 08/01/25 08/28/25 08/01/25 8:00 AM 08/28/25 4:59 PM 2771SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.10.4 1 2857 Ship SMG from UW to Pt. Hueneme
2859 1.3 1.3.5.11 Wavelength-shifting Optical Module (WOM) Should have Started P 4 728d 12/10/21 09/27/24 12/10/21 8:00 AM 09/27/24 4:59 PM 25% 0% Red $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.11 1 2858 Wavelength-shifting Optical Module (WOM)
2860 1.3 1.3.5.11.1 WOM Preliminary Design Review Complete C 5 1 0 12/10/21 12/10/21 12/10/21 8:00 AM 12/10/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.11.1 1 2859 WOM Preliminary Design Review
2861 1.3 1.3.5.11.2 WOM Final Design Review Not Started C 5 1 0 05/03/23 05/03/23 05/03/23 8:00 AM 05/03/23 8:00 AM 2861SF -195d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.11.2 1 2860 WOM Final Design Review
2862 1.3 1.3.5.11.3 WOM Deployment Readiness Review Not Started C 5 1 0 02/05/24 02/05/24 02/05/24 8:00 AM 02/05/24 8:00 AM 2862SF -130d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.11.3 1 2861 WOM Deployment Readiness Review
2863 1.3 1.3.5.11.4 Ship 16 WOMs from DESY to CHC Not Started C 5 40d 08/05/24 09/27/24 08/05/24 8:00 AM 09/27/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Timo Karg 1.3.5.11.4 1 2862 Ship 16 WOMs from DESY to CHC
2864 1.4 1.4 CPT Started P 2 1 1920d 11/14/18 04/06/26 11/14/18 8:00 AM 04/06/26 4:59 PM 11.76% 18.00% Green $1,925.00 $26,007.70 $85,518.39 $727,464.77 12% $4,681.39 Tyce Deyoung 1.4 1 2863 CPT
2865 1.4 1.4.1 Downhole Cables Started P 3 1 1888d 11/14/18 02/19/26 11/14/18 8:00 AM 02/19/26 4:59 PM 7.31% 27.00% Green $0.00 $0.00 $30,967.24 $423,853.61 7% Tyce Deyoung 1.4.1 1 2864 Downhole Cables
2866 1.4 1.4.1.1 Main Cable Assembly Started P 4 1 1303d 11/14/18 11/10/23 11/14/18 8:00 AM 11/10/23 4:59 PM 1.39% 34.00% Green $125.00 $500.00 $1,377.15 $99,190.06 1% $170.00 Tyce Deyoung 1.4.1.1 1 2865 Main Cable Assembly
2867 1.4 1.4.1.1.1 Main Cables Started P 5 1 1201d 11/14/18 06/21/23 11/14/18 8:00 AM 06/21/23 4:59 PM 1.76% 59.00% Green $0.00 $0.00 $1,252.15 $71,142.65 2% Tyce Deyoung 1.4.1.1.1 1 2866 Main Cables
2868 1.4 1.4.1.1.1.1 Main cable preliminary design phase Complete P 6 1 860d 11/14/18 03/01/22 11/14/18 8:00 AM 03/01/22 4:59 PM 0.00% 100% Gray $0.00 $0.00 $0.00 $2,504.31 0% Tyce Deyoung 1.4.1.1.1.1 1 2867 Main cable preliminary design phase
2869 1.4 1.4.1.1.1.1.1 Main Cable RFI Complete C 7 1 2d 11/14/18 11/15/18 11/14/18 8:00 AM 11/15/18 4:59 PM 84.21% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.1.1 1 2868 Main Cable RFI
2870 1.4 1.4.1.1.1.1.2 Site visits to potential vendors Complete C 7 1 91d 11/16/18 03/22/19 11/16/18 8:00 AM 03/22/19 4:59 PM 2868 99.71% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.1.2 1 2869 Site visits to potential vendors
2871 1.4 1.4.1.1.1.1.3 Procurement of sample quads Complete C 7 1 216d 01/01/21 10/29/21 01/01/21 8:00 AM 10/29/21 4:59 PM 99.88% 100% Gray Hexatronic triplet received $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.1.3 1 2870 Procurement of sample quads
2872 1.4 1.4.1.1.1.1.4 Evaluation of sample quads Complete C 7 1 262d 03/01/21 03/01/22 03/01/21 8:00 AM 03/01/22 4:59 PM 0.00% 100% Gray Hexatronic triplet tested $0.00 $2,504.31 $0.00 $2,504.31 0% $2,504.31 Tyce Deyoung 1.4.1.1.1.1.4 1 2871 Evaluation of sample quads
2873 1.4 1.4.1.1.1.2 Main Cable Final Design Phase Should have Started P 6 1 186d 11/01/21 07/18/22 11/01/21 8:00 AM 07/18/22 4:59 PM 3.39% 0% Green $0.00 $0.00 $1,252.15 $36,943.09 3% Tyce Deyoung 1.4.1.1.1.2 1 2872 Main Cable Final Design Phase
2874 1.4 1.4.1.1.1.2.1 Main cable final design Should have Started P 7 1 131d 11/01/21 05/02/22 11/01/21 8:00 AM 05/02/22 4:59 PM 0.00% Green $0.00 $7,512.93 $0.00 $7,512.93 0% $0.00 Tyce Deyoung 1.4.1.1.1.2.1 1 2873 Main cable final design
2875 1.4 1.4.1.1.1.2.1.1 Develop electrical properties measurement system Not Started P 8 1 45d 03/01/22 05/02/22 03/01/22 8:00 AM 05/02/22 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.1.1 1 2874 Develop electrical properties measurement system
2876 1.4 1.4.1.1.1.2.1.1.1 Assess crosstalk measurement board requirements Not Started C 9 1 10d 03/01/22 03/14/22 03/01/22 8:00 AM 03/14/22 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.1.1.1 1 2875 Assess crosstalk measurement board requirements
2877 1.4 1.4.1.1.1.2.1.1.2 Design crosstalk measurement board Not Started C 9 1 15d 03/15/22 04/04/22 03/15/22 8:00 AM 04/04/22 4:59 PM 2875 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.1.1.2 1 2876 Design crosstalk measurement board
2878 1.4 1.4.1.1.1.2.1.1.3 Order crosstalk measurement board Not Started C 9 1 15d 04/05/22 04/25/22 04/05/22 8:00 AM 04/25/22 4:59 PM 2876 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.1.1.3 1 2877 Order crosstalk measurement board
2879 1.4 1.4.1.1.1.2.1.1.4 Populate and test crosstalk measurement board Not Started C 9 1 5d 04/26/22 05/02/22 04/26/22 8:00 AM 05/02/22 4:59 PM 2877 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.1.1.4 1 2878 Populate and test crosstalk measurement board
2880 1.4 1.4.1.1.1.2.1.1.5 Crosstalk measurement board ready for use Not Started C 9 1 1 0 05/02/22 05/02/22 05/02/22 4:59 PM 05/02/22 4:59 PM 2878 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.1.1.5 1 2879 Crosstalk measurement board ready for use
2881 1.4 1.4.1.1.1.2.1.2 Develop mechanical test plan for composite cable Should have Started C 8 1 80d 11/01/21 02/18/22 11/01/21 8:00 AM 02/18/22 4:59 PM 83.35% Red $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.1.2 1 2880 Develop mechanical test plan for composite cable
2882 1.4 1.4.1.1.1.2.2 Hexatronic prototype testing Should have Started P 7 1 135d 12/10/21 06/16/22 12/10/21 8:00 AM 06/16/22 4:59 PM 50.00% 0% Red $1,252.15 $2,504.31 $1,252.15 $2,504.31 50% $0.00 Tyce Deyoung 1.4.1.1.1.2.2 1 2881 Hexatronic prototype testing
2883 1.4 1.4.1.1.1.2.2.1 Hexatronic prototype main cable production Should have Started C 8 1 58d 12/10/21 03/01/22 12/10/21 8:00 AM 03/01/22 4:59 PM 64.34% Red $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.2.1 1 2882 Hexatronic prototype main cable production
2884 1.4 1.4.1.1.1.2.2.2 Hexatronic prototype main cable pull test Not Started C 8 1 22d 03/02/22 03/31/22 03/02/22 8:00 AM 03/31/22 4:59 PM 2882, 2880 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.2.2 1 2883 Hexatronic prototype main cable pull test
2885 1.4 1.4.1.1.1.2.2.3 Hexatronic prototype main cable shipping to PSL Not Started C 8 1 8w 04/01/22 05/26/22 04/01/22 8:00 AM 05/26/22 4:59 PM 2883 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.2.3 1 2884 Hexatronic prototype main cable shipping to PSL
2886 1.4 1.4.1.1.1.2.2.4 Hexatronic prototype main cable mechanical testing at PSL Not Started C 8 1 3w 05/27/22 06/16/22 05/27/22 8:00 AM 06/16/22 4:59 PM 2884 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.2.4 1 2885 Hexatronic prototype main cable mechanical testing at PSL
2887 1.4 1.4.1.1.1.2.2.5 Hexatronic prototype main cable mechanical testing complete Not Started C 8 1 1 0 06/16/22 06/16/22 06/16/22 4:59 PM 06/16/22 4:59 PM 2885 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.2.5 1 2886 Hexatronic prototype main cable mechanical testing complete
2888 1.4 1.4.1.1.1.2.2.6 Hexatronic prototype main cable shipping to breakout suppliers Not Started C 8 1 8w 04/01/22 05/26/22 04/01/22 8:00 AM 05/26/22 4:59 PM 2883 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.2.6 1 2887 Hexatronic prototype main cable shipping to breakout suppliers
2889 1.4 1.4.1.1.1.2.3 Fibron prototype testing Should have Started P 7 1 146d 12/20/21 07/11/22 12/20/21 8:00 AM 07/11/22 4:59 PM 0.00% Green $0.00 $14,412.93 $0.00 $14,412.93 0% $0.00 Tyce Deyoung 1.4.1.1.1.2.3 1 2888 Fibron prototype testing
2890 1.4 1.4.1.1.1.2.3.1 Fibron prototype main cable production Should have Started C 8 1 19w 12/20/21 04/29/22 12/20/21 8:00 AM 04/29/22 4:59 PM 32.73% Red $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.3.1 1 2889 Fibron prototype main cable production
2891 1.4 1.4.1.1.1.2.3.2 Fibron prototype main cable shipping to MSU Not Started C 8 1 6w 05/03/22 06/13/22 05/03/22 8:00 AM 06/13/22 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.3.2 1 2890 Fibron prototype main cable shipping to MSU
2892 1.4 1.4.1.1.1.2.3.3 Fibron prototype main cable electrical testing Not Started C 8 1 3w 06/14/22 07/04/22 06/14/22 8:00 AM 07/04/22 4:59 PM 2879, 2890 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.3.3 1 2891 Fibron prototype main cable electrical testing
2893 1.4 1.4.1.1.1.2.3.4 Fibron prototype main cable communications testing Not Started C 8 1 1w 07/05/22 07/11/22 07/05/22 8:00 AM 07/11/22 4:59 PM 2891 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.3.4 1 2892 Fibron prototype main cable communications testing
2894 1.4 1.4.1.1.1.2.3.5 Fibron prototype main cable testing complete Not Started C 8 1 1 0 07/11/22 07/11/22 07/11/22 4:59 PM 07/11/22 4:59 PM 2892 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.2.3.5 1 2893 Fibron prototype main cable testing complete
2895 1.4 1.4.1.1.1.2.4 Hexatronic main cable final design review / decision Not Started C 7 1 22d 06/17/22 07/18/22 06/17/22 8:00 AM 07/18/22 4:59 PM 2886 0.00% Green $0.00 $5,008.62 $0.00 $5,008.62 0% $0.00 Tyce Deyoung 1.4.1.1.1.2.4 1 2894 Hexatronic main cable final design review / decision
2896 1.4 1.4.1.1.1.2.5 Main cable final design review complete Not Started C 7 1 1 1 0 07/18/22 07/18/22 07/18/22 4:59 PM 07/18/22 4:59 PM 2894 0.00% Green $0.00 $7,504.31 $0.00 $7,504.31 0% $0.00 Tyce Deyoung 1.4.1.1.1.2.5 1 2895 Main cable final design review complete
2897 1.4 1.4.1.1.1.3 Main Cable Production Started P 6 1 558d 05/03/21 06/21/23 05/03/21 8:00 AM 06/21/23 4:59 PM 0.00% 15.00% Green $0.00 $0.00 $0.00 $31,695.25 0% Tyce Deyoung 1.4.1.1.1.3 1 2896 Main Cable Production
2898 1.4 1.4.1.1.1.3.1 Main cable procurement Started C 7 1 346d 05/03/21 08/29/22 05/03/21 8:00 AM 08/29/22 4:59 PM 2895FF +30d 0.00% 25.00% Green $0.00 $2,504.31 $0.00 $2,504.31 0% $626.08 Tyce Deyoung 1.4.1.1.1.3.1 1 2897 Main cable procurement
2899 1.4 1.4.1.1.1.3.2 Production of first article Not Started P 7 1 120d 08/30/22 02/13/23 08/30/22 8:00 AM 02/13/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $19,173.70 0% Tyce Deyoung 1.4.1.1.1.3.2 1 2898 Production of first article
2900 1.4 1.4.1.1.1.3.2.1 Fabrication Not Started C 8 1 16w 08/30/22 12/19/22 08/30/22 8:00 AM 12/19/22 4:59 PM 2897 0.00% 0% Green $0.00 $8,765.08 $0.00 $8,765.08 0% $0.00 Tyce Deyoung 1.4.1.1.1.3.2.1 1 2899 Fabrication
2901 1.4 1.4.1.1.1.3.2.2 Acceptance testing Not Started C 8 1 3w 12/20/22 01/09/23 12/20/22 8:00 AM 01/09/23 4:59 PM 2899 0.00% 0% Green $0.00 $9,156.46 $0.00 $9,156.46 0% $0.00 Tyce Deyoung 1.4.1.1.1.3.2.2 1 2900 Acceptance testing
2902 1.4 1.4.1.1.1.3.2.4 First article shipping to breakout installation facility Not Started C 8 1 5w 01/10/23 02/13/23 01/10/23 8:00 AM 02/13/23 4:59 PM 2900 0.00% 0% Green $0.00 $1,252.15 $0.00 $1,252.15 0% $0.00 Tyce Deyoung 1.4.1.1.1.3.2.4 1 2901 First article shipping to breakout installation facility
2903 1.4 1.4.1.1.1.3.3 Production readiness review Not Started C 7 1 17d 01/10/23 02/01/23 01/10/23 8:00 AM 02/01/23 4:59 PM 2900 0.00% 0% Green $0.00 $7,512.93 $0.00 $7,512.93 0% $0.00 Tyce Deyoung 1.4.1.1.1.3.3 1 2902 Production readiness review
2904 1.4 1.4.1.1.1.3.3.1 Production readiness review complete Not Started C 7 1 1 1 0 02/01/23 02/01/23 02/01/23 4:59 PM 02/01/23 4:59 PM 2902 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.3.3.1 1 2903 Production readiness review complete
2905 1.4 1.4.1.1.1.3.4 Production of final six main cables Not Started C 7 1 12w 02/02/23 04/26/23 02/02/23 8:00 AM 04/26/23 4:59 PM 2902 0.00% 0% Green $0.00 $2,504.31 $0.00 $2,504.31 0% $0.00 Tyce Deyoung 1.4.1.1.1.3.4 1 2904 Production of final six main cables
2906 1.4 1.4.1.1.1.3.5 Main Cable Production Complete Not Started C 7 1 1 1 0 04/26/23 04/26/23 04/26/23 4:59 PM 04/26/23 4:59 PM 2904 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.3.5 1 2905 Main Cable Production Complete
2907 1.4 1.4.1.1.1.3.6 Production main cable shipping to breakout installation facility Not Started C 7 1 8w 04/27/23 06/21/23 04/27/23 8:00 AM 06/21/23 4:59 PM 2904 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.1.3.6 1 2906 Production main cable shipping to breakout installation facility
2908 1.4 1.4.1.1.2 Breakout connections Started P 5 1 462d 03/25/21 12/30/22 03/25/21 8:00 AM 12/30/22 4:59 PM 0.00% 15.00% Green $0.00 $0.00 $0.00 $27,547.40 0% Tyce Deyoung 1.4.1.1.2 1 2907 Breakout connections
2909 1.4 1.4.1.1.2.1 Breakout preliminary design phase Started P 6 1 358d 03/25/21 08/08/22 03/25/21 8:00 AM 08/08/22 4:59 PM 0.00% 19.00% Green $0.00 $0.00 $0.00 $13,773.70 0% Tyce Deyoung 1.4.1.1.2.1 1 2908 Breakout preliminary design phase
2910 1.4 1.4.1.1.2.1.1 Breakout preliminary design Started C 7 1 336d 03/25/21 07/07/22 03/25/21 8:00 AM 07/07/22 4:59 PM 2887FF +4w, 2886FF +3w 0.00% 20.0% Green $0.00 $10,017.24 $0.00 $10,017.24 0% $2,003.45 Tyce Deyoung 1.4.1.1.2.1.1 1 2909 Breakout preliminary design
2911 1.4 1.4.1.1.2.1.2 Breakout preliminary design review Not Started C 7 1 22d 07/08/22 08/08/22 07/08/22 8:00 AM 08/08/22 4:59 PM 2909 0.00% 0% Green $0.00 $3,756.46 $0.00 $3,756.46 0% $0.00 Tyce Deyoung 1.4.1.1.2.1.2 1 2910 Breakout preliminary design review
2912 1.4 1.4.1.1.2.1.3 Breakout preliminary design review complete Not Started C 7 1 1 0 08/08/22 08/08/22 08/08/22 4:59 PM 08/08/22 4:59 PM 2910 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.2.1.3 1 2911 Breakout preliminary design review complete
2913 1.4 1.4.1.1.2.2 Breakout final design phase Not Started P 6 1 104d 08/09/22 12/30/22 08/09/22 8:00 AM 12/30/22 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $13,773.70 0% Tyce Deyoung 1.4.1.1.2.2 1 2912 Breakout final design phase
2914 1.4 1.4.1.1.2.2.1 Breakout final design Not Started C 7 1 10w 08/09/22 10/17/22 08/09/22 8:00 AM 10/17/22 4:59 PM 2910 0.00% 0% Green $0.00 $11,269.39 $0.00 $11,269.39 0% $0.00 Tyce Deyoung 1.4.1.1.2.2.1 1 2913 Breakout final design
2915 1.4 1.4.1.1.2.2.2 Breakout prototype production Not Started C 7 1 14w 08/09/22 11/14/22 08/09/22 8:00 AM 11/14/22 4:59 PM 2887, 2913SS 0.00% 0% Green $0.00 $2,504.31 $0.00 $2,504.31 0% $0.00 Tyce Deyoung 1.4.1.1.2.2.2 1 2914 Breakout prototype production
2916 1.4 1.4.1.1.2.2.3 Breakout prototype testing Not Started C 7 1 12d 11/15/22 11/30/22 11/15/22 8:00 AM 11/30/22 4:59 PM 2914 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.2.2.3 1 2915 Breakout prototype testing
2917 1.4 1.4.1.1.2.2.4 Breakout final design review Not Started C 7 1 22d 12/01/22 12/30/22 12/01/22 8:00 AM 12/30/22 4:59 PM 2915 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.2.2.4 1 2916 Breakout final design review
2918 1.4 1.4.1.1.2.2.5 Breakout final design review complete Not Started C 7 1 1 1 0 12/30/22 12/30/22 12/30/22 4:59 PM 12/30/22 4:59 PM 2916 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.2.2.5 1 2917 Breakout final design review complete
2919 1.4 1.4.1.1.3 Main Cable Assembly production Not Started P 5 1 102d 06/22/23 11/10/23 06/22/23 8:00 AM 11/10/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.3 1 2918 Main Cable Assembly production
2920 1.4 1.4.1.1.3.2 MCA production Not Started C 6 1 12w 06/22/23 09/13/23 06/22/23 8:00 AM 09/13/23 4:59 PM 2906, 2917, 2979 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.3.2 1 2919 MCA production
2921 1.4 1.4.1.1.3.3 Pre-ship review Not Started C 6 1 2d 09/14/23 09/15/23 09/14/23 8:00 AM 09/15/23 4:59 PM 2919 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.3.3 1 2920 Pre-ship review
2922 1.4 1.4.1.1.3.4 Main Cable Assembly shipping to PTH (RDD 12/1/23 for FY24 vessel. ROS 12/1/2025) Not Started C 6 1 8w 09/18/23 11/10/23 09/18/23 8:00 AM 11/10/23 4:59 PM 2920 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.3.4 1 2921 Main Cable Assembly shipping to PTH (RDD 12/1/23 for FY24 vessel. ROS 12/1/2025)
2923 1.4 1.4.1.1.3.5 MCAs shipped to PTH Not Started C 6 1 1 1 1 0 09/18/23 09/18/23 09/18/23 8:00 AM 09/18/23 8:00 AM 2921SS 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.3.5 1 2922 MCAs shipped to PTH
2924 1.4 1.4.1.1.4 Main Cable Assembly support Should have Started C 5 1 551d 10/01/21 11/10/23 10/01/21 8:00 AM 11/10/23 4:59 PM 15.95% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.1.4 1 2923 Main Cable Assembly support
2925 1.4 1.4.1.2 Breakout Cable Assemblies Started P 4 1 537d 10/01/21 10/23/23 10/01/21 8:00 AM 10/23/23 4:59 PM 11.94% 2.00% Yellow $0.00 $375.00 $10,017.24 $83,921.96 12% $7.50 Tyce Deyoung 1.4.1.2 1 2924 Breakout Cable Assemblies
2926 1.4 1.4.1.2.1 BCA preliminary design phase Started P 5 1 249d 11/01/21 10/13/22 11/01/21 8:00 AM 10/13/22 4:59 PM 13.40% 10.0% Green $0.00 $0.00 $10,017.24 $74,781.88 13% Tyce Deyoung 1.4.1.2.1 1 2925 BCA preliminary design phase
2927 1.4 1.4.1.2.1.1 BCA preliminary design Started C 6 1 125d 11/01/21 04/22/22 11/01/21 8:00 AM 04/22/22 4:59 PM 44.44% 20% Red $10,017.24 $22,538.78 $10,017.24 $22,538.78 44% $4,507.76 Tyce Deyoung 1.4.1.2.1.1 1 2926 BCA preliminary design
2928 1.4 1.4.1.2.1.2 BCA preliminary design review Not Started C 6 1 2d 04/25/22 04/26/22 04/25/22 8:00 AM 04/26/22 4:59 PM 2926 0.00% 0% Green $0.00 $11,112.93 $0.00 $11,112.93 0% $0.00 Tyce Deyoung 1.4.1.2.1.2 1 2927 BCA preliminary design review
2929 1.4 1.4.1.2.1.3 BCA prototype procurement Not Started C 6 1 6w 04/27/22 06/07/22 04/27/22 8:00 AM 06/07/22 4:59 PM 2927 0.00% 0% Green $0.00 $4,382.54 $0.00 $4,382.54 0% $0.00 Tyce Deyoung 1.4.1.2.1.3 1 2928 BCA prototype procurement
2930 1.4 1.4.1.2.1.4 BCA prototype production Not Started C 6 1 16w 06/08/22 09/27/22 06/08/22 8:00 AM 09/27/22 4:59 PM 2928 0.00% 0% Green $0.00 $25,634.70 $0.00 $25,634.70 0% $0.00 Tyce Deyoung 1.4.1.2.1.4 1 2929 BCA prototype production
2931 1.4 1.4.1.2.1.5 BCA prototype testing Not Started C 6 1 12d 09/28/22 10/13/22 09/28/22 8:00 AM 10/13/22 4:59 PM 2929 0.00% 0% Green $0.00 $11,112.93 $0.00 $11,112.93 0% $0.00 Tyce Deyoung 1.4.1.2.1.5 1 2930 BCA prototype testing
2932 1.4 1.4.1.2.1.6 BCA prototype testing complete Not Started C 6 1 1 0 10/13/22 10/13/22 10/13/22 4:59 PM 10/13/22 4:59 PM 2930 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.1.6 1 2931 BCA prototype testing complete
2933 1.4 1.4.1.2.2 BCA final design phase Not Started P 5 1 82d 10/14/22 02/06/23 10/14/22 8:00 AM 02/06/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $8,765.08 0% Tyce Deyoung 1.4.1.2.2 1 2932 BCA final design phase
2934 1.4 1.4.1.2.2.1 BCA final design Not Started C 6 1 4w 10/14/22 11/10/22 10/14/22 8:00 AM 11/10/22 4:59 PM 2930 0.00% 0% Green $0.00 $6,260.77 $0.00 $6,260.77 0% $0.00 Tyce Deyoung 1.4.1.2.2.1 1 2933 BCA final design
2935 1.4 1.4.1.2.2.2 BCA final design review Not Started C 6 1 22d 11/11/22 12/12/22 11/11/22 8:00 AM 12/12/22 4:59 PM 2933 0.00% 0% Green $0.00 $2,504.31 $0.00 $2,504.31 0% $0.00 Tyce Deyoung 1.4.1.2.2.2 1 2934 BCA final design review
2936 1.4 1.4.1.2.2.3 BCA final design complete Not Started C 6 1 1 0 12/12/22 12/12/22 12/12/22 4:59 PM 12/12/22 4:59 PM 2934 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.2.3 1 2935 BCA final design complete
2937 1.4 1.4.1.2.2.4 BCA procurement Not Started C 6 1 8w 12/13/22 02/06/23 12/13/22 8:00 AM 02/06/23 4:59 PM 2935 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.2.4 1 2936 BCA procurement
2938 1.4 1.4.1.2.3 BCA production for first two strings Not Started P 5 1 116d 02/07/23 07/18/23 02/07/23 8:00 AM 07/18/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.3 1 2937 BCA production for first two strings
2939 1.4 1.4.1.2.3.1 BCA manufacturing Not Started C 6 1 20w 02/07/23 06/26/23 02/07/23 8:00 AM 06/26/23 4:59 PM 2936 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.3.1 1 2938 BCA manufacturing
2940 1.4 1.4.1.2.3.2 BCA pre-ship review Not Started C 6 1 1d 06/27/23 06/27/23 06/27/23 8:00 AM 06/27/23 4:59 PM 2938 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.3.2 1 2939 BCA pre-ship review
2941 1.4 1.4.1.2.3.3 Shipping to PTH (FY24 vessel, RDD 12/1/23 - ROS 2/1/25 to pre-position) Not Started C 6 1 3w 06/28/23 07/18/23 06/28/23 8:00 AM 07/18/23 4:59 PM 2939 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.3.3 1 2940 Shipping to PTH (FY24 vessel, RDD 12/1/23 - ROS 2/1/25 to pre-position)
2942 1.4 1.4.1.2.3.4 BCAs for first two strings shipped Not Started C 6 1 1 0 07/18/23 07/18/23 07/18/23 4:59 PM 07/18/23 4:59 PM 2940 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.3.4 1 2941 BCAs for first two strings shipped
2943 1.4 1.4.1.2.4 BCA production for final five strings Not Started P 5 1 85d 06/27/23 10/23/23 06/27/23 8:00 AM 10/23/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.4 1 2942 BCA production for final five strings
2944 1.4 1.4.1.2.4.1 BCA manufacturing - final five strings Not Started C 6 1 14w 06/27/23 10/02/23 06/27/23 8:00 AM 10/02/23 4:59 PM 2938 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.4.1 1 2943 BCA manufacturing - final five strings
2945 1.4 1.4.1.2.4.2 Shipping to PTH (FY24 vessel, RDD 12/1/23 - ROS 12/1/25) Not Started C 6 1 3w 10/03/23 10/23/23 10/03/23 8:00 AM 10/23/23 4:59 PM 2943 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.4.2 1 2944 Shipping to PTH (FY24 vessel, RDD 12/1/23 - ROS 12/1/25)
2946 1.4 1.4.1.2.4.3 BCA manufacturing complete Not Started C 6 1 1 1 0 10/02/23 10/02/23 10/02/23 4:59 PM 10/02/23 4:59 PM 2943 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.4.3 1 2945 BCA manufacturing complete
2947 1.4 1.4.1.2.5 Breakout Cable Assemblies support Should have Started C 5 1 523d 10/01/21 10/03/23 10/01/21 8:00 AM 10/03/23 4:59 PM 16.77% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.2.5 1 2946 Breakout Cable Assemblies support
2948 1.4 1.4.1.3 Penetrator Cable Assembly Started P 4 1 491d 01/01/21 11/18/22 01/01/21 8:00 AM 11/18/22 4:59 PM 46.36% 38.00% Yellow $125.00 $375.00 $8,929.75 $19,262.95 46% $142.50 Tyce Deyoung 1.4.1.3 1 2947 Penetrator Cable Assembly
2949 1.4 1.4.1.3.1 v1 PCAs (Harwin connectors) Started P 5 1 365d 01/01/21 05/26/22 01/01/21 8:00 AM 05/26/22 4:59 PM 64.71% 40.0% Red $0.00 $0.00 $5,249.15 $8,111.58 65% Tyce Deyoung 1.4.1.3.1 1 2948 v1 PCAs (Harwin connectors)
2950 1.4 1.4.1.3.1.1 v1 PCA fabrication Complete C 6 1 42d 01/01/21 03/01/21 01/01/21 8:00 AM 03/01/21 4:59 PM 99.38% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.3.1.1 1 2949 v1 PCA fabrication
2951 1.4 1.4.1.3.1.2 v1 PCA shipping to MMB device production facilities Started C 6 1 8w 04/01/22 05/26/22 04/01/22 8:00 AM 05/26/22 4:59 PM 2949SS, 2951 28.57% 60% Green $1,001.72 $3,506.03 $1,001.72 $3,506.03 29% $2,103.62 Tyce Deyoung 1.4.1.3.1.2 1 2950 v1 PCA shipping to MMB device production facilities
2952 1.4 1.4.1.3.1.3 v1 PCA restesting Started C 6 1 26w 10/01/21 03/31/22 10/01/21 8:00 AM 03/31/22 4:59 PM 92.22% 15.00% Red $4,247.43 $4,605.54 $4,247.43 $4,605.54 92% $690.83 Tyce Deyoung 1.4.1.3.1.3 1 2951 v1 PCA restesting
2953 1.4 1.4.1.3.1.4 Harwin PCA production complete Not Started C 6 1 1 0 05/26/22 05/26/22 05/26/22 4:59 PM 05/26/22 4:59 PM 2950 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.3.1.4 1 2952 Harwin PCA production complete
2954 1.4 1.4.1.3.3 PCA mating cables for FAT Complete P 5 1 52d 01/01/21 03/15/21 01/01/21 8:00 AM 03/15/21 4:59 PM 98.17% 100% Gray $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.3.3 1 2953 PCA mating cables for FAT
2955 1.4 1.4.1.3.3.1 PCA mating cable design Complete C 6 1 21d 01/01/21 01/29/21 01/01/21 8:00 AM 01/29/21 4:59 PM 98.72% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.3.3.1 1 2954 PCA mating cable design
2956 1.4 1.4.1.3.3.2 PCA mating cable prototyping Complete C 6 1 32d 01/01/21 02/15/21 01/01/21 8:00 AM 02/15/21 4:59 PM 2954SS 99.19% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.3.3.2 1 2955 PCA mating cable prototyping
2957 1.4 1.4.1.3.3.3 PCA mating cable materials procurement Complete C 6 1 10d 02/16/21 03/01/21 02/16/21 8:00 AM 03/01/21 4:59 PM 2955 97.39% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.3.3.3 1 2956 PCA mating cable materials procurement
2958 1.4 1.4.1.3.3.4 PCA mating cable materials shipping Complete C 6 1 10d 03/02/21 03/15/21 03/02/21 8:00 AM 03/15/21 4:59 PM 2956 97.39% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.3.3.4 1 2957 PCA mating cable materials shipping
2959 1.4 1.4.1.3.2 v2 PCAs (Molex connectors) Started P 5 1 321d 01/01/21 03/25/22 01/01/21 8:00 AM 03/25/22 4:59 PM 60.52% 85.00% Green $0.00 $0.00 $2,303.45 $3,806.03 61% Tyce Deyoung 1.4.1.3.2 1 2958 v2 PCAs (Molex connectors)
2960 1.4 1.4.1.3.2.1 v2 PCA design revisions Complete C 6 1 64d 01/01/21 03/31/21 01/01/21 8:00 AM 03/31/21 4:59 PM 99.59% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.3.2.1 1 2959 v2 PCA design revisions
2961 1.4 1.4.1.3.2.2 v2 PCA fabrication Started C 6 1 197d 04/01/21 12/31/21 04/01/21 8:00 AM 12/31/21 4:59 PM 2959 66.67% 95.00% Green $1,001.72 $1,502.59 $1,001.72 $1,502.59 67% $1,427.46 Tyce Deyoung 1.4.1.3.2.2 1 2960 v2 PCA fabrication
2962 1.4 1.4.1.3.2.3 v2 PCA shipping to DOM production facilities Started C 6 1 12w 01/03/22 03/25/22 01/03/22 8:00 AM 03/25/22 4:59 PM 2960 56.51% 35.00% Red holding to ship to Germany in one batch together with MMB PCAs $1,301.72 $2,303.45 $1,301.72 $2,303.45 57% $806.21 Tyce Deyoung 1.4.1.3.2.3 1 2961 v2 PCA shipping to DOM production facilities
2963 1.4 1.4.1.3.2.4 mDOM PCA production complete Not Started C 6 1 1 0 03/25/22 03/25/22 03/25/22 4:59 PM 03/25/22 4:59 PM 2961 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.3.2.4 1 2962 mDOM PCA production complete
2964 1.4 1.4.1.3.4 PCA mating cables for SPAT Started P 5 1 308d 09/15/21 11/18/22 09/15/21 8:00 AM 11/18/22 4:59 PM 17.96% 14.00% Green $0.00 $0.00 $1,252.15 $6,970.34 18% Tyce Deyoung 1.4.1.3.4 1 2963 PCA mating cables for SPAT
2965 1.4 1.4.1.3.4.1 SPAT cable design Started C 6 1 208d 09/15/21 07/01/22 09/15/21 8:00 AM 07/01/22 4:59 PM 40.00% 20.0% Yellow $1,252.15 $3,130.39 $1,252.15 $3,130.39 40% $626.08 Tyce Deyoung 1.4.1.3.4.1 1 2964 SPAT cable design
2966 1.4 1.4.1.3.4.2 SPAT cable materials procurement Not Started C 6 1 14w 07/04/22 10/07/22 07/04/22 8:00 AM 10/07/22 4:59 PM 2964 0.00% 0% Green $0.00 $1,460.86 $0.00 $1,460.86 0% $0.00 Tyce Deyoung 1.4.1.3.4.2 1 2965 SPAT cable materials procurement
2967 1.4 1.4.1.3.4.3 SPAT cable production Not Started C 6 1 3w 10/10/22 10/28/22 10/10/22 8:00 AM 10/28/22 4:59 PM 2965 0.00% 0% Green $0.00 $1,878.23 $0.00 $1,878.23 0% $0.00 Tyce Deyoung 1.4.1.3.4.3 1 2966 SPAT cable production
2968 1.4 1.4.1.3.4.4 SPAT cable shipping to WIPAC Not Started C 6 1 3w 10/31/22 11/18/22 10/31/22 8:00 AM 11/18/22 4:59 PM 2966 0.00% 0% Green $0.00 $500.86 $0.00 $500.86 0% $0.00 Tyce Deyoung 1.4.1.3.4.4 1 2967 SPAT cable shipping to WIPAC
2969 1.4 1.4.1.3.4.5 SPAT cable production complete Not Started C 6 1 1 0 11/18/22 11/18/22 11/18/22 4:59 PM 11/18/22 4:59 PM 2967 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.3.4.5 1 2968 SPAT cable production complete
2970 1.4 1.4.1.3.5 Penetrator Cable Assemblies support Should have Started C 5 1 296d 10/01/21 11/18/22 10/01/21 8:00 AM 11/18/22 4:59 PM 29.68% Red $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.3.5 1 2969 Penetrator Cable Assemblies support
2971 1.4 1.4.1.4 String Hardware and Support Rope Started P 4 1 567d 01/01/21 03/06/23 01/01/21 8:00 AM 03/06/23 4:59 PM 5.71% 48.00% Green $125.00 $500.00 $10,643.10 $186,344.82 6% $240.00 Tyce Deyoung 1.4.1.4 1 2970 String Hardware and Support Rope
2972 1.4 1.4.1.4.1 Main cable connections Started P 5 1 567d 01/01/21 03/06/23 01/01/21 8:00 AM 03/06/23 4:59 PM 5.66% 74.00% Green $0.00 $0.00 $10,518.10 $185,844.82 6% Tyce Deyoung 1.4.1.4.1 1 2971 Main cable connections
2973 1.4 1.4.1.4.1.1 Final design Complete C 6 1 326d 01/01/21 04/01/22 01/01/21 8:00 AM 04/01/22 4:59 PM 100.00% 100% Gray $2,504.31 $2,504.31 $2,504.31 $2,504.31 100% $2,504.31 Tyce Deyoung 1.4.1.4.1.1 1 2972 Final design
2974 1.4 1.4.1.4.1.2 Support rope prototype procurement Complete C 6 1 82d 07/08/21 10/29/21 07/08/21 8:00 AM 10/29/21 4:59 PM 100.00% 100% Gray Completed for JDR spec cable, finalization depends on MCA final spec $500.86 $500.86 $500.86 $500.86 100% $500.86 Tyce Deyoung 1.4.1.4.1.2 1 2973 Support rope prototype procurement
2975 1.4 1.4.1.4.1.3 Support rope prototype testing Started C 6 1 6w 02/18/22 03/31/22 02/18/22 8:00 AM 03/31/22 4:59 PM 2973, 2883FF 50.00% 10.0% Red $2,504.31 $5,008.62 $2,504.31 $5,008.62 50% $500.86 Tyce Deyoung 1.4.1.4.1.3 1 2974 Support rope prototype testing
2976 1.4 1.4.1.4.1.4 YaleGrip tests with prototype cable Started C 6 1 6w 02/18/22 03/31/22 02/18/22 8:00 AM 03/31/22 4:59 PM 2883FF 100.00% 50.0% Red $5,008.62 $5,008.62 $5,008.62 $5,008.62 100% $2,504.31 Tyce Deyoung 1.4.1.4.1.4 1 2975 YaleGrip tests with prototype cable
2977 1.4 1.4.1.4.1.5 String hardware final design review Not Started C 6 1 1 1d 10/17/22 10/17/22 10/17/22 8:00 AM 10/17/22 4:59 PM 2883, 2975, 2886, 1912 0.00% 0% Green $0.00 $6,808.62 $0.00 $6,808.62 0% $0.00 Tyce Deyoung 1.4.1.4.1.5 1 2976 String hardware final design review
2978 1.4 1.4.1.4.1.6 String hardware procurement (shackles, chains etc) Not Started C 6 1 12w 10/18/22 01/09/23 10/18/22 8:00 AM 01/09/23 4:59 PM 2976 0.00% 0% Green $0.00 $163,008.62 $0.00 $163,008.62 0% $0.00 Tyce Deyoung 1.4.1.4.1.6 1 2977 String hardware procurement (shackles, chains etc)
2979 1.4 1.4.1.4.1.7 String hardware production Not Started C 6 1 8w 01/10/23 03/06/23 01/10/23 8:00 AM 03/06/23 4:59 PM 2977 0.00% 0% Green $0.00 $3,005.17 $0.00 $3,005.17 0% $0.00 Tyce Deyoung 1.4.1.4.1.7 1 2978 String hardware production
2980 1.4 1.4.1.4.1.8 Cable grip shipping to MCA production facility Not Started C 6 1 2w 01/10/23 01/23/23 01/10/23 8:00 AM 01/23/23 4:59 PM 2977 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.4.1.8 1 2979 Cable grip shipping to MCA production facility
2981 1.4 1.4.1.4.1.9 String hardware production complete Not Started C 6 1 1 0 01/23/23 01/23/23 01/23/23 4:59 PM 01/23/23 4:59 PM 2979 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.4.1.9 1 2980 String hardware production complete
2982 1.4 1.4.1.4.2 String hardware support Should have Started C 5 1 307d 10/01/21 12/05/22 10/01/21 8:00 AM 12/05/22 4:59 PM 28.51% Red $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.4.2 1 2981 String hardware support
2983 1.4 1.4.1.5 Cable emulators Started P 4 1 393d 01/01/21 07/05/22 01/01/21 8:00 AM 07/05/22 4:59 PM 0.00% 6.00% Green $0.00 $250.00 $0.00 $35,133.82 0% $15.00 Tyce Deyoung 1.4.1.5 1 2982 Cable emulators
2984 1.4 1.4.1.5.1 Determine cable emulator requirements Complete C 5 1 21d 01/01/21 01/29/21 01/01/21 8:00 AM 01/29/21 4:59 PM 98.72% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.5.1 1 2983 Determine cable emulator requirements
2985 1.4 1.4.1.5.2 Cable emulator box design Started C 5 1 64d 12/01/21 02/28/22 12/01/21 8:00 AM 02/28/22 4:59 PM 0.00% 10% Green $0.00 $10,017.24 $0.00 $10,017.24 0% $1,001.72 Tyce Deyoung 1.4.1.5.2 1 2984 Cable emulator box design
2986 1.4 1.4.1.5.3 Cable emulator PCB layout Should have Started C 5 1 44d 12/01/21 01/31/22 12/01/21 8:00 AM 01/31/22 4:59 PM 0.00% 0% Green $0.00 $15,025.86 $0.00 $15,025.86 0% $0.00 Tyce Deyoung 1.4.1.5.3 1 2985 Cable emulator PCB layout
2987 1.4 1.4.1.5.4 Cable emulator PCB procurement Not Started C 5 1 4w 02/01/22 02/28/22 02/01/22 8:00 AM 02/28/22 4:59 PM 2985 0.00% 0% Green $0.00 $6,234.70 $0.00 $6,234.70 0% $0.00 Tyce Deyoung 1.4.1.5.4 1 2986 Cable emulator PCB procurement
2988 1.4 1.4.1.5.5 Cable emulator prototype components procurement Should have Started C 5 1 55d 12/01/21 02/15/22 12/01/21 8:00 AM 02/15/22 4:59 PM 2985SS 0.00% 0% Green $0.00 $3,606.03 $0.00 $3,606.03 0% $0.00 Tyce Deyoung 1.4.1.5.5 1 2987 Cable emulator prototype components procurement
2989 1.4 1.4.1.5.6 Prototype assembly Not Started C 5 1 1w 03/01/22 03/07/22 03/01/22 8:00 AM 03/07/22 4:59 PM 2987, 2986 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.5.6 1 2988 Prototype assembly
2990 1.4 1.4.1.5.7 Cable emulator testing Not Started C 5 1 2w 03/08/22 03/21/22 03/08/22 8:00 AM 03/21/22 4:59 PM 2988 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.5.7 1 2989 Cable emulator testing
2991 1.4 1.4.1.5.8 Cable emulator final design review Not Started C 5 1 1d 03/22/22 03/22/22 03/22/22 8:00 AM 03/22/22 4:59 PM 2989 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.5.8 1 2990 Cable emulator final design review
2992 1.4 1.4.1.5.9 Procurement of materials for cable emulator production Not Started C 5 1 8w 03/23/22 05/17/22 03/23/22 8:00 AM 05/17/22 4:59 PM 2990 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.5.9 1 2991 Procurement of materials for cable emulator production
2993 1.4 1.4.1.5.10 Cable emulator assembly Not Started C 5 1 3w 05/18/22 06/07/22 05/18/22 8:00 AM 06/07/22 4:59 PM 2991 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.5.10 1 2992 Cable emulator assembly
2994 1.4 1.4.1.5.11 Cable emulator shipping Not Started C 5 1 4w 06/08/22 07/05/22 06/08/22 8:00 AM 07/05/22 4:59 PM 2992 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.5.11 1 2993 Cable emulator shipping
2995 1.4 1.4.1.5.12 Cable emulator production complete Not Started C 5 1 1 0 06/07/22 06/07/22 06/07/22 4:59 PM 06/07/22 4:59 PM 2992 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.5.12 1 2994 Cable emulator production complete
2996 1.4 1.4.1.5.13 Cable emulator support Should have Started C 5 1 198d 10/01/21 07/05/22 10/01/21 8:00 AM 07/05/22 4:59 PM 44.19% Red $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.5.13 1 2995 Cable emulator support
2997 1.4 1.4.1.6 On-ice support for string installation Not Started P 4 1 187d 06/01/25 02/19/26 06/01/25 8:00 AM 02/19/26 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.6 1 2996 On-ice support for string installation
2998 1.4 1.4.1.6.1 Off-ice training Cable SMEs (FS3) Not Started C 5 1 3d 08/15/25 08/19/25 08/15/25 8:00 AM 08/19/25 4:59 PM 997FF 0 Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.6.1 1 2997 Off-ice training Cable SMEs (FS3)
2999 1.4 1.4.1.6.2 Cable SME arrives to support FS3 activities Not Started C 5 1 0 11/20/25 11/20/25 11/20/25 8:00 AM 11/20/25 8:00 AM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.6.2 1 2998 Cable SME arrives to support FS3 activities
3000 1.4 1.4.1.6.3 PQ, ECW & Deployment Travel Costs Cable SMEs (FS3) Not Started C 5 1 187d 06/01/25 02/19/26 06/01/25 8:00 AM 02/19/26 4:59 PM 0 Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.6.3 1 2999 PQ, ECW & Deployment Travel Costs Cable SMEs (FS3)
3001 1.4 1.4.1.6.4 Cable SME support for FS3 activities (slot 1) Not Started C 5 1 34d 11/20/25 01/09/26 11/20/25 8:00 AM 01/09/26 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.6.4 1 3000 Cable SME support for FS3 activities (slot 1)
3002 1.4 1.4.1.6.5 Cable SME support for FS3 activities (slot 2) Not Started C 5 11d 01/06/26 01/20/26 01/06/26 8:00 AM 01/20/26 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.1.6.5 1 3001 Cable SME support for FS3 activities (slot 2)
3003 1.4 1.4.2 Surface Cables Started P 3 1 1359d 12/01/20 02/26/26 12/01/20 8:00 AM 02/26/26 4:59 PM 40.92% 10.0% Red Replacement for 1.4.2 IDF via CR2 $0.00 $0.00 $45,316.49 $110,757.46 41% Tyce Deyoung 1.4.2 1 3002 Surface Cables
3004 1.4 1.4.2.1 Surface Cable Assemblies Started P 4 1 434d 12/01/20 07/29/22 12/01/20 8:00 AM 07/29/22 4:59 PM 98.87% 34.00% Red $0.00 $500.00 $43,726.47 $44,226.47 99% $170.00 Tyce Deyoung 1.4.2.1 1 3003 Surface Cable Assemblies
3005 1.4 1.4.2.1.1 Final design Complete C 5 1 44d 12/01/20 01/29/21 12/01/20 8:00 AM 01/29/21 4:59 PM 99.38% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.1.1 1 3004 Final design
3006 1.4 1.4.2.1.2 Final design review Complete C 5 1 2d 02/01/21 02/02/21 02/01/21 8:00 AM 02/02/21 4:59 PM 3004 84.21% 100% Gray is this target based on dates carried over from the IDF plan? $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.1.2 1 3005 Final design review
3007 1.4 1.4.2.1.3 Procurement Complete C 5 40d 02/03/21 03/30/21 02/03/21 8:00 AM 03/30/21 4:59 PM 3005 99.33% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.1.3 1 3006 Procurement
3008 1.4 1.4.2.1.4 Cable production Complete C 5 60d 03/31/21 06/22/21 03/31/21 8:00 AM 06/22/21 4:59 PM 3006 99.56% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.1.4 1 3007 Cable production
3009 1.4 1.4.2.1.5 Shipping to connectorization facility Complete C 5 1 1 50d 06/23/21 08/31/21 06/23/21 8:00 AM 08/31/21 4:59 PM 3007 99.47% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.1.5 1 3008 Shipping to connectorization facility
3010 1.4 1.4.2.1.6 Connectorization and testing Started C 5 1 153d 12/01/21 07/01/22 12/01/21 8:00 AM 07/01/22 4:59 PM 100.00% 12% Red $36,115.73 $36,115.73 $36,115.73 $36,115.73 100% $4,333.89 Tyce Deyoung 1.4.2.1.6 1 3009 Connectorization and testing
3011 1.4 1.4.2.1.7 Pre-ship review Not Started C 5 1 68d 02/10/22 05/16/22 02/10/22 8:00 AM 05/16/22 4:59 PM 100.00% 0% Red is this target based on dates carried over from the IDF plan? $1,984.67 $1,984.67 $1,984.67 $1,984.67 100% $0.00 Tyce Deyoung 1.4.2.1.7 1 3010 Pre-ship review
3012 1.4 1.4.2.1.8 Shipping to PTH (RDD 12/1/22 for FY23 vessel, ROS 12/1/24) Not Started C 5 1 4w 07/04/22 07/29/22 07/04/22 8:00 AM 07/29/22 4:59 PM 3009, 3010 100.00% 0% Red $5,626.08 $5,626.08 $5,626.08 $5,626.08 100% $0.00 Tyce Deyoung 1.4.2.1.8 1 3011 Shipping to PTH (RDD 12/1/22 for FY23 vessel, ROS 12/1/24)
3013 1.4 1.4.2.1.9 SCAs shipped to PTH Not Started C 5 1 1 1 0 07/04/22 07/04/22 07/04/22 8:00 AM 07/04/22 8:00 AM 3011SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.1.9 1 3012 SCAs shipped to PTH
3014 1.4 1.4.2.1.10 Surface Cable Assembly support Should have Started C 5 1 201d 10/01/21 07/08/22 10/01/21 8:00 AM 07/08/22 4:59 PM 43.71% Red $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.1.10 1 3013 Surface Cable Assembly support
3015 1.4 1.4.2.2 Surface Junction Boxes Started P 4 1 296d 10/01/21 11/18/22 10/01/21 8:00 AM 11/18/22 4:59 PM 0.00% 14.00% Green $0.00 $375.00 $0.00 $14,222.58 0% $52.50 Tyce Deyoung 1.4.2.2 1 3014 Surface Junction Boxes
3016 1.4 1.4.2.2.1 Final design Started C 5 1 20w 03/03/22 07/20/22 03/03/22 8:00 AM 07/20/22 4:59 PM 2895FF +2d 0.00% 70.0% Green $0.00 $5,954.00 $0.00 $5,954.00 0% $4,167.80 Tyce Deyoung 1.4.2.2.1 1 3015 Final design
3017 1.4 1.4.2.2.2 Final design review Not Started C 5 1 1d 07/21/22 07/21/22 07/21/22 8:00 AM 07/21/22 4:59 PM 3015 0.00% 0% Green $0.00 $4,763.20 $0.00 $4,763.20 0% $0.00 Tyce Deyoung 1.4.2.2.2 1 3016 Final design review
3018 1.4 1.4.2.2.3 Procurement Not Started C 5 1 6w 07/22/22 09/01/22 07/22/22 8:00 AM 09/01/22 4:59 PM 3016 0.00% 0% Green $0.00 $3,130.39 $0.00 $3,130.39 0% $0.00 Tyce Deyoung 1.4.2.2.3 1 3017 Procurement
3019 1.4 1.4.2.2.4 Fabrication Not Started C 5 1 6w 09/02/22 10/13/22 09/02/22 8:00 AM 10/13/22 4:59 PM 3017 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.2.4 1 3018 Fabrication
3020 1.4 1.4.2.2.5 SJB production complete Not Started C 5 1 1 0 10/13/22 10/13/22 10/13/22 4:59 PM 10/13/22 4:59 PM 3018 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.2.5 1 3019 SJB production complete
3021 1.4 1.4.2.2.6 Pre-ship review Not Started C 5 1 11d 10/14/22 10/28/22 10/14/22 8:00 AM 10/28/22 4:59 PM 3018 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.2.6 1 3020 Pre-ship review
3022 1.4 1.4.2.2.7 Shipping to PTH (RDD 12/1/22 for FY23 vessel - ROS 12/1/24) Not Started C 5 1 3w 10/31/22 11/18/22 10/31/22 8:00 AM 11/18/22 4:59 PM 3020 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.2.7 1 3021 Shipping to PTH (RDD 12/1/22 for FY23 vessel - ROS 12/1/24)
3023 1.4 1.4.2.2.8 Surface Junction Box support Should have Started C 5 1 296d 10/01/21 11/18/22 10/01/21 8:00 AM 11/18/22 4:59 PM 29.68% Red $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.2.8 1 3022 Surface Junction Box support
3024 1.4 1.4.2.3 ICL Upgrade Started P 4 1 1336d 01/01/21 02/26/26 01/01/21 8:00 AM 02/26/26 4:59 PM 3.04% 6.00% Green $125.00 $500.00 $1,590.02 $52,308.40 3% $30.00 Tyce Deyoung 1.4.2.3 1 3023 ICL Upgrade
3025 1.4 1.4.2.3.1 ASC liaison Started C 5 1 1336d 01/01/21 02/26/26 01/01/21 8:00 AM 02/26/26 4:59 PM 16.67% 8.00% Yellow $1,465.02 $8,790.13 $1,465.02 $8,790.13 17% $703.21 Tyce Deyoung 1.4.2.3.1 1 3024 ASC liaison
3026 1.4 1.4.2.3.2 Patch panels Started P 5 1 445d 04/01/22 12/15/23 04/01/22 8:00 AM 12/15/23 4:59 PM 0.00% 21.00% Green $0.00 $0.00 $0.00 $8,618.11 0% Tyce Deyoung 1.4.2.3.2 1 3025 Patch panels
3027 1.4 1.4.2.3.2.1 Final design Started C 6 1 44d 04/01/22 06/01/22 04/01/22 8:00 AM 06/01/22 4:59 PM 0.00% 90.0% Green $0.00 $2,930.04 $0.00 $2,930.04 0% $2,637.04 Tyce Deyoung 1.4.2.3.2.1 1 3026 Final design
3028 1.4 1.4.2.3.2.2 Procurement Not Started C 6 1 16w 06/02/22 09/21/22 06/02/22 8:00 AM 09/21/22 4:59 PM 3026 0.00% 0% Green $0.00 $2,758.03 $0.00 $2,758.03 0% $0.00 Tyce Deyoung 1.4.2.3.2.2 1 3027 Procurement
3029 1.4 1.4.2.3.2.3 Fabrication Not Started C 6 1 6w 09/22/22 11/02/22 09/22/22 8:00 AM 11/02/22 4:59 PM 3027 0.00% 0% Green $0.00 $2,930.04 $0.00 $2,930.04 0% $0.00 Tyce Deyoung 1.4.2.3.2.3 1 3028 Fabrication
3030 1.4 1.4.2.3.2.4 Pre-ship review Not Started C 6 1 2w 11/03/22 11/16/22 11/03/22 8:00 AM 11/16/22 4:59 PM 3028 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.3.2.4 1 3029 Pre-ship review
3031 1.4 1.4.2.3.2.5 Shipping to PTH (NB: small -- RDD 9/15/23 for ComSur FY25, ROS 12/15/23) Not Started C 6 1 4w 11/17/22 12/14/22 11/17/22 8:00 AM 12/14/22 4:59 PM 3029 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.3.2.5 1 3030 Shipping to PTH (NB: small -- RDD 9/15/23 for ComSur FY25, ROS 12/15/23)
3032 1.4 1.4.2.3.2.6 Patch panels shipped to PTH Not Started C 6 1 1 0 11/17/22 11/17/22 11/17/22 8:00 AM 11/17/22 8:00 AM 3030SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.3.2.6 1 3031 Patch panels shipped to PTH
3033 1.4 1.4.2.3.2.7 Patch panels installation in ICL Not Started C 6 1 1d 12/15/23 12/15/23 12/15/23 8:00 AM 12/15/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.3.2.7 1 3032 Patch panels installation in ICL
3034 1.4 1.4.2.3.3 Patch cables Started P 5 1 729d 04/12/22 02/03/25 04/12/22 8:00 AM 02/03/25 4:59 PM 0.00% 4.00% Green $0.00 $0.00 $0.00 $34,400.17 0% Tyce Deyoung 1.4.2.3.3 1 3033 Patch cables
3035 1.4 1.4.2.3.3.1 Final design Started C 6 1 35w 06/30/22 03/01/23 06/30/22 8:00 AM 03/01/23 4:59 PM 3046FF +3w 0.00% 10.0% Green $0.00 $1,465.02 $0.00 $1,465.02 0% $146.50 Tyce Deyoung 1.4.2.3.3.1 1 3034 Final design
3036 1.4 1.4.2.3.3.2 Prototype production and evaluation Not Started C 6 1 29w 04/12/22 10/31/22 04/12/22 8:00 AM 10/31/22 4:59 PM 0.00% 0% Green $0.00 $6,502.06 $0.00 $6,502.06 0% $0.00 Tyce Deyoung 1.4.2.3.3.2 1 3035 Prototype production and evaluation
3037 1.4 1.4.2.3.3.3 Final design review Not Started C 6 1 11d 03/02/23 03/16/23 03/02/23 8:00 AM 03/16/23 4:59 PM 3034, 3035 0.00% 0% Green $0.00 $1,758.03 $0.00 $1,758.03 0% $0.00 Tyce Deyoung 1.4.2.3.3.3 1 3036 Final design review
3038 1.4 1.4.2.3.3.4 Procurement Started C 6 1 16w 03/17/23 07/06/23 03/17/23 8:00 AM 07/06/23 4:59 PM 3036 0.00% 5.00% Green $0.00 $21,745.02 $0.00 $21,745.02 0% $1,087.25 Tyce Deyoung 1.4.2.3.3.4 1 3037 Procurement
3039 1.4 1.4.2.3.3.5 Production Not Started C 6 1 15w 07/07/23 10/19/23 07/07/23 8:00 AM 10/19/23 4:59 PM 3037 0.00% 0% Green $0.00 $2,930.04 $0.00 $2,930.04 0% $0.00 Tyce Deyoung 1.4.2.3.3.5 1 3038 Production
3040 1.4 1.4.2.3.3.6 Pre-ship review Started C 6 1 7d 10/20/23 10/30/23 10/20/23 8:00 AM 10/30/23 4:59 PM 3038 0.00% 5.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.3.3.6 1 3039 Pre-ship review
3041 1.4 1.4.2.3.3.7 Shipping to PTH (RDD 9/15/24 for FY25 ComSur, ROS 12/1/24) Not Started C 6 1 4w 10/31/23 11/28/23 10/31/23 8:00 AM 11/28/23 4:59 PM 3039 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.3.3.7 1 3040 Shipping to PTH (RDD 9/15/24 for FY25 ComSur, ROS 12/1/24)
3042 1.4 1.4.2.3.3.8 Patch cables shipped to PTH Not Started C 6 1 1 0 10/31/23 10/31/23 10/31/23 8:00 AM 10/31/23 8:00 AM 3040SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.3.3.8 1 3041 Patch cables shipped to PTH
3043 1.4 1.4.2.3.3.9 Patch cables installation in ICL Not Started C 6 1 5d 01/28/25 02/03/25 01/28/25 8:00 AM 02/03/25 4:59 PM 3082, 3090, 3115, 3032, 3072, 3119SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.3.3.9 1 3042 Patch cables installation in ICL
3044 1.4 1.4.2.3.3.10 Patch cables and panels installed in ICL Not Started C 6 1 1 0 02/03/25 02/03/25 02/03/25 4:59 PM 02/03/25 4:59 PM 3032, 3042 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.3.3.10 1 3043 Patch cables and panels installed in ICL
3045 1.4 1.4.2.3.4 ICL Upgrade support Should have Started C 5 1 1141d 10/01/21 02/26/26 10/01/21 8:00 AM 02/26/26 4:59 PM 7.64% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.3.4 1 3044 ICL Upgrade support
3046 1.4 1.4.2.4 On-ice support for surface cable installation Not Started P 4 1 564d 12/15/22 02/19/25 12/15/22 8:00 AM 02/19/25 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.4 1 3045 On-ice support for surface cable installation
3047 1.4 1.4.2.4.1 Prepare Upgrade electronics rack (M&O) Not Started C 5 1 40d 12/15/22 02/08/23 12/15/22 8:00 AM 02/08/23 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.4.1 1 3046 Prepare Upgrade electronics rack (M&O)
3048 1.4 1.4.2.4.3 Cable SME arrives to support FS2 activities Not Started C 5 1 0 12/15/24 12/15/24 12/15/24 8:00 AM 12/15/24 8:00 AM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.4.3 1 3047 Cable SME arrives to support FS2 activities
3049 1.4 1.4.2.4.4 PQ, ECW, Deployment Travel Costs Cable SMEs (FS2) Not Started C 5 1 186d 06/01/24 02/19/25 06/01/24 8:00 AM 02/19/25 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.4.4 1 3048 PQ, ECW, Deployment Travel Costs Cable SMEs (FS2)
3050 1.4 1.4.2.4.5 Cable SME support for FS2 activities (slot 1) Not Started C 5 1 18d 12/15/24 01/09/25 12/15/24 8:00 AM 01/09/25 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.4.5 1 3049 Cable SME support for FS2 activities (slot 1)
3051 1.4 1.4.2.4.6 Cable SME support for FS2 activities (slot 2) Not Started C 5 1 24d 12/15/24 01/17/25 12/15/24 8:00 AM 01/17/25 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.2.4.6 1 3050 Cable SME support for FS2 activities (slot 2)
3052 1.4 1.4.3 FieldHub Started P 3 1051d 01/01/21 01/20/25 01/01/21 8:00 AM 01/20/25 4:59 PM 0.00% 26.00% Green $0.00 $0.00 $0.00 $1,334.80 0% Tyce Deyoung 1.4.3 1 3051 FieldHub
3053 1.4 1.4.3.1 FieldHub Electronics Started P 4 1051d 01/01/21 01/20/25 01/01/21 8:00 AM 01/20/25 4:59 PM 0.00% 26.00% Green $0.00 $0.00 $0.00 $1,334.80 0% Tyce Deyoung 1.4.3.1 1 3052 FieldHub Electronics
3054 1.4 1.4.3.1.1 FieldHub Design Started P 5 632d 01/01/21 06/05/23 01/01/21 8:00 AM 06/05/23 4:59 PM 0.00% 44.00% Green $0.00 $0.00 $0.00 $1,334.80 0% Tyce Deyoung 1.4.3.1.1 1 3053 FieldHub Design
3055 1.4 1.4.3.1.1.1 FieldHub rev1 design Started C 6 346d 01/01/21 04/29/22 01/01/21 8:00 AM 04/29/22 4:59 PM 81.75% 80% Green including FDOR firmware adapatation $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.1.1 1 3054 FieldHub rev1 design
3056 1.4 1.4.3.1.1.2 FieldHub rev1 prototype production Not Started C 6 9w 05/02/22 07/01/22 05/02/22 8:00 AM 07/01/22 4:59 PM 3054 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.1.2 1 3055 FieldHub rev1 prototype production
3057 1.4 1.4.3.1.1.3 FieldHub rev1 testing and installation at NTS Not Started C 6 1 9w 07/18/22 09/16/22 07/18/22 8:00 AM 09/16/22 4:59 PM 3055, 3096SS 0.00% 0% Green $0.00 $1,334.80 $0.00 $1,334.80 0% $0.00 Tyce Deyoung 1.4.3.1.1.3 1 3056 FieldHub rev1 testing and installation at NTS
3058 1.4 1.4.3.1.1.4 FieldHub rev2 design Not Started C 6 11w 09/19/22 12/02/22 09/19/22 8:00 AM 12/02/22 4:59 PM 3056 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.1.4 1 3057 FieldHub rev2 design
3059 1.4 1.4.3.1.1.5 FieldHub rev2 prototype production Not Started C 6 13w 12/05/22 03/03/23 12/05/22 8:00 AM 03/03/23 4:59 PM 3057 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.1.5 1 3058 FieldHub rev2 prototype production
3060 1.4 1.4.3.1.1.6 FieldHub rev2 testing and installation at NTS Not Started C 6 1 9w 03/06/23 05/05/23 03/06/23 8:00 AM 05/05/23 4:59 PM 3058, 3110 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.1.6 1 3059 FieldHub rev2 testing and installation at NTS
3061 1.4 1.4.3.1.1.8 FieldHub final design review Not Started C 6 2d 05/04/23 05/05/23 05/04/23 8:00 AM 05/05/23 4:59 PM 3059FF 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.1.8 1 3060 FieldHub final design review
3062 1.4 1.4.3.1.1.9 FieldHub rev3 design (if required) Not Started C 6 4w 05/08/23 06/02/23 05/08/23 8:00 AM 06/02/23 4:59 PM 3060 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.1.9 1 3061 FieldHub rev3 design (if required)
3063 1.4 1.4.3.1.1.10 Production readiness review Not Started C 6 1 1d 06/05/23 06/05/23 06/05/23 8:00 AM 06/05/23 4:59 PM 3061 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.1.10 1 3062 Production readiness review
3064 1.4 1.4.3.1.1.11 FieldHub design complete Not Started C 6 1 1 0 06/05/23 06/05/23 06/05/23 4:59 PM 06/05/23 4:59 PM 3062 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.1.11 1 3063 FieldHub design complete
3065 1.4 1.4.3.1.2 FieldHub Production Not Started P 5 419d 06/06/23 01/20/25 06/06/23 8:00 AM 01/20/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.2 1 3064 FieldHub Production
3066 1.4 1.4.3.1.2.1 Component procurement Not Started C 6 6w 06/06/23 07/17/23 06/06/23 8:00 AM 07/17/23 4:59 PM 3062 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.2.1 1 3065 Component procurement
3067 1.4 1.4.3.1.2.2 PCB fabrication Not Started C 6 6w 06/06/23 07/17/23 06/06/23 8:00 AM 07/17/23 4:59 PM 3065SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.2.2 1 3066 PCB fabrication
3068 1.4 1.4.3.1.2.3 FieldHub assembly Not Started C 6 9w 07/18/23 09/18/23 07/18/23 8:00 AM 09/18/23 4:59 PM 3065, 3066 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.2.3 1 3067 FieldHub assembly
3069 1.4 1.4.3.1.2.4 FieldHub acceptance testing Not Started C 6 4w 09/19/23 10/16/23 09/19/23 8:00 AM 10/16/23 4:59 PM 3067 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.2.4 1 3068 FieldHub acceptance testing
3070 1.4 1.4.3.1.2.5 FieldHub production complete Not Started C 6 1 1 0 10/16/23 10/16/23 10/16/23 4:59 PM 10/16/23 4:59 PM 3068 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.2.5 1 3069 FieldHub production complete
3071 1.4 1.4.3.1.2.6 Pre-ship review Not Started C 6 11d 10/17/23 10/31/23 10/17/23 8:00 AM 10/31/23 4:59 PM 3068 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.2.6 1 3070 Pre-ship review
3072 1.4 1.4.3.1.2.7 Shipping to CHC (Air to Pole, RDD ??, ROS 12/1/24) Not Started C 6 6w 11/01/23 12/13/23 11/01/23 8:00 AM 12/13/23 4:59 PM 3070 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.2.7 1 3071 Shipping to CHC (Air to Pole, RDD ??, ROS 12/1/24)
3073 1.4 1.4.3.1.2.8 FieldHub installation and commissioning in ICL Not Started C 6 1 5d 01/14/25 01/20/25 01/14/25 8:00 AM 01/20/25 4:59 PM 3082, 3115, 3455 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.2.8 1 3072 FieldHub installation and commissioning in ICL
3074 1.4 1.4.3.1.2.9 FieldHubs installed in ICL Not Started C 6 1 1 1 0 01/20/25 01/20/25 01/20/25 4:59 PM 01/20/25 4:59 PM 3072 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.3.1.2.9 1 3073 FieldHubs installed in ICL
3075 1.4 1.4.4 CPT Central Infrastructure Started P 3 1 1310d 02/01/21 02/19/26 02/01/21 8:00 AM 02/19/26 4:59 PM 0.10% 16.00% Green $0.00 $0.00 $125.00 $121,558.50 0% Tyce Deyoung 1.4.4 1 3074 CPT Central Infrastructure
3076 1.4 1.4.4.1 Communications and Timing Systems Started P 4 1 1041d 02/01/21 02/04/25 02/01/21 8:00 AM 02/04/25 4:59 PM 0.33% 27.00% Green $125.00 $500.00 $125.00 $37,558.03 0% $135.00 Tyce Deyoung 1.4.4.1 1 3075 Communications and Timing Systems
3077 1.4 1.4.4.1.1 Timing distribution system Started P 5 1 1025d 02/01/21 01/13/25 02/01/21 8:00 AM 01/13/25 4:59 PM 0.00% 53% Green $0.00 $0.00 $0.00 $37,058.03 0% Tyce Deyoung 1.4.4.1.1 1 3076 Timing distribution system
3078 1.4 1.4.4.1.1.1 Procurement Started C 6 1 533d 02/01/21 02/15/23 02/01/21 8:00 AM 02/15/23 4:59 PM 0.00% 60% Green $0.00 $37,058.03 $0.00 $37,058.03 0% $22,234.82 Tyce Deyoung 1.4.4.1.1.1 1 3077 Procurement
3079 1.4 1.4.4.1.1.2 Testing Started C 6 1 8w 02/16/23 04/12/23 02/16/23 8:00 AM 04/12/23 4:59 PM 3077 0.00% 25.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.1.2 1 3078 Testing
3080 1.4 1.4.4.1.1.3 Pre-ship review Not Started C 6 1 11d 04/13/23 04/27/23 04/13/23 8:00 AM 04/27/23 4:59 PM 3078 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.1.3 1 3079 Pre-ship review
3081 1.4 1.4.4.1.1.4 Timing distribution system complete Not Started C 6 1 1 0 04/27/23 04/27/23 04/27/23 4:59 PM 04/27/23 4:59 PM 3079 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.1.4 1 3080 Timing distribution system complete
3082 1.4 1.4.4.1.1.5 Shipping to PTH (RDD 9/15/24 for FY25 ComSur - ROS 12/1/24) Not Started C 6 1 7w 04/28/23 06/15/23 04/28/23 8:00 AM 06/15/23 4:59 PM 3079 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.1.5 1 3081 Shipping to PTH (RDD 9/15/24 for FY25 ComSur - ROS 12/1/24)
3083 1.4 1.4.4.1.1.7 Timing distribution system installation in ICL Not Started C 6 1 5d 01/07/25 01/13/25 01/07/25 8:00 AM 01/13/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.1.7 1 3082 Timing distribution system installation in ICL
3084 1.4 1.4.4.1.2 Timing monitoring system Started P 5 1 545d 12/19/22 01/27/25 12/19/22 8:00 AM 01/27/25 4:59 PM 0.00% 21.00% Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.2 1 3083 Timing monitoring system
3085 1.4 1.4.4.1.2.1 Final design Started C 6 1 372d 12/19/22 05/24/24 12/19/22 8:00 AM 05/24/24 4:59 PM 3086FF 0.00% 25.00% Green requires pDAQ software support $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.2.1 1 3084 Final design
3086 1.4 1.4.4.1.2.2 Prototype production Started C 6 1 1 4w 04/01/24 04/26/24 04/01/24 8:00 AM 04/26/24 4:59 PM 0.00% 10.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.2.2 1 3085 Prototype production
3087 1.4 1.4.4.1.2.3 Installation and testing at NTS/SPTS Not Started C 6 1 4w 04/29/24 05/24/24 04/29/24 8:00 AM 05/24/24 4:59 PM 3085 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.2.3 1 3086 Installation and testing at NTS/SPTS
3088 1.4 1.4.4.1.2.4 Production of ICL system Not Started C 6 1 6w 05/27/24 07/05/24 05/27/24 8:00 AM 07/05/24 4:59 PM 3084 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.2.4 1 3087 Production of ICL system
3089 1.4 1.4.4.1.2.5 Timing monitoring system complete Not Started C 6 1 1 0 07/05/24 07/05/24 07/05/24 4:59 PM 07/05/24 4:59 PM 3087 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.2.5 1 3088 Timing monitoring system complete
3090 1.4 1.4.4.1.2.6 Shipping to PTH (RDD 9/15/24 for FY25 ComSur, ROS 12/1/24) Not Started C 6 1 3w 07/08/24 07/26/24 07/08/24 8:00 AM 07/26/24 4:59 PM 3087 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.2.6 1 3089 Shipping to PTH (RDD 9/15/24 for FY25 ComSur, ROS 12/1/24)
3091 1.4 1.4.4.1.2.8 Timing monitoring system installation in ICL Not Started C 6 1 5d 01/21/25 01/27/25 01/21/25 8:00 AM 01/27/25 4:59 PM 3073 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.2.8 1 3090 Timing monitoring system installation in ICL
3092 1.4 1.4.4.1.3 Timing systems support Should have Started C 5 1 867d 10/01/21 02/04/25 10/01/21 8:00 AM 02/04/25 4:59 PM 10.05% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.1.3 1 3091 Timing systems support
3093 1.4 1.4.4.2 Power systems Started P 4 1 1287d 03/04/21 02/19/26 03/04/21 8:00 AM 02/19/26 4:59 PM 0.00% 8.00% Green $0.00 $0.00 $0.00 $84,000.48 0% Tyce Deyoung 1.4.4.2 1 3092 Power systems
3094 1.4 1.4.4.2.1 DOM power supply Started P 5 1 572d 03/04/21 05/12/23 03/04/21 8:00 AM 05/12/23 4:59 PM 0.00% 38% Green $0.00 $0.00 $0.00 $15,578.93 0% Tyce Deyoung 1.4.4.2.1 1 3093 DOM power supply
3095 1.4 1.4.4.2.1.1 Final design Started C 6 1 68w 05/07/21 08/25/22 05/07/21 8:00 AM 08/25/22 4:59 PM 3096FF 0.00% 40.0% Green $0.00 $4,395.06 $0.00 $4,395.06 0% $1,758.03 Tyce Deyoung 1.4.4.2.1.1 1 3094 Final design
3096 1.4 1.4.4.2.1.2 Sample procurement and evaluation Started C 6 1 412d 03/04/21 09/30/22 03/04/21 8:00 AM 09/30/22 4:59 PM 0.00% 50.0% Green $0.00 $7,155.06 $0.00 $7,155.06 0% $3,577.53 Tyce Deyoung 1.4.4.2.1.2 1 3095 Sample procurement and evaluation
3097 1.4 1.4.4.2.1.3 Sample installation and testing at NTS Not Started C 6 1 6w 07/16/22 08/25/22 07/16/22 8:00 AM 08/25/22 4:59 PM 0.00% Green $0.00 $2,930.04 $0.00 $2,930.04 0% $0.00 Tyce Deyoung 1.4.4.2.1.3 1 3096 Sample installation and testing at NTS
3098 1.4 1.4.4.2.1.5 Procurement Not Started C 6 1 25w 11/21/22 05/12/23 11/21/22 8:00 AM 05/12/23 4:59 PM 3111 0.00% 0% Green $0.00 $1,098.77 $0.00 $1,098.77 0% $0.00 Tyce Deyoung 1.4.4.2.1.5 1 3097 Procurement
3099 1.4 1.4.4.2.1.6 Power supply system complete Not Started C 6 1 1 0 05/12/23 05/12/23 05/12/23 4:59 PM 05/12/23 4:59 PM 3097 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.2.1.6 1 3098 Power supply system complete
3100 1.4 1.4.4.2.2 DOM power distribution Started P 5 1 416d 09/03/21 04/07/23 09/03/21 8:00 AM 04/07/23 4:59 PM 0.00% 20% Green $0.00 $0.00 $0.00 $44,911.25 0% Tyce Deyoung 1.4.4.2.2 1 3099 DOM power distribution
3101 1.4 1.4.4.2.2.1 Final design Started C 6 1 296d 09/03/21 10/21/22 09/03/21 8:00 AM 10/21/22 4:59 PM 3095FF +3w 0.00% 25.00% Green $0.00 $26,057.34 $0.00 $26,057.34 0% $6,514.33 Tyce Deyoung 1.4.4.2.2.1 1 3100 Final design
3102 1.4 1.4.4.2.2.2 Prototype production and evaluation Started C 6 1 20w 05/16/22 09/30/22 05/16/22 8:00 AM 09/30/22 4:59 PM 3095FF 0.00% 25.00% Green $0.00 $7,735.08 $0.00 $7,735.08 0% $1,933.77 Tyce Deyoung 1.4.4.2.2.2 1 3101 Prototype production and evaluation
3103 1.4 1.4.4.2.2.4 Production Not Started C 6 1 20w 11/21/22 04/07/23 11/21/22 8:00 AM 04/07/23 4:59 PM 3111 0.00% 0% Green $0.00 $10,020.06 $0.00 $10,020.06 0% $0.00 Tyce Deyoung 1.4.4.2.2.4 1 3102 Production
3104 1.4 1.4.4.2.2.5 Power distribution system complete Not Started C 6 1 1 0 04/07/23 04/07/23 04/07/23 4:59 PM 04/07/23 4:59 PM 3102 0.00% 0% Green $0.00 $1,098.77 $0.00 $1,098.77 0% $0.00 Tyce Deyoung 1.4.4.2.2.5 1 3103 Power distribution system complete
3105 1.4 1.4.4.2.3 DOM power control Should have Started P 5 1 496d 05/15/21 04/07/23 05/15/21 8:00 AM 04/07/23 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $23,510.29 0% Tyce Deyoung 1.4.4.2.3 1 3104 DOM power control
3106 1.4 1.4.4.2.3.1 Final design Should have Started C 6 1 286d 05/15/21 06/17/22 05/15/21 8:00 AM 06/17/22 4:59 PM 0.00% 0% Green $0.00 $8,790.13 $0.00 $8,790.13 0% $0.00 Tyce Deyoung 1.4.4.2.3.1 1 3105 Final design
3107 1.4 1.4.4.2.3.2 Prototype production and evaluation Not Started C 6 1 20w 05/16/22 09/30/22 05/16/22 8:00 AM 09/30/22 4:59 PM 3101FF 0.00% 0% Green $0.00 $2,947.53 $0.00 $2,947.53 0% $0.00 Tyce Deyoung 1.4.4.2.3.2 1 3106 Prototype production and evaluation
3108 1.4 1.4.4.2.3.4 Production Not Started C 6 1 20w 11/21/22 04/07/23 11/21/22 8:00 AM 04/07/23 4:59 PM 3111 0.00% 0% Green $0.00 $11,040.13 $0.00 $11,040.13 0% $0.00 Tyce Deyoung 1.4.4.2.3.4 1 3107 Production
3109 1.4 1.4.4.2.3.5 Power control system complete Not Started C 6 1 1 0 04/07/23 04/07/23 04/07/23 4:59 PM 04/07/23 4:59 PM 3107 0.00% 0% Green $0.00 $732.51 $0.00 $732.51 0% $0.00 Tyce Deyoung 1.4.4.2.3.5 1 3108 Power control system complete
3110 1.4 1.4.4.2.4 Power system shipping and installation Not Started P 5 1 590d 10/03/22 01/13/25 10/03/22 8:00 AM 01/13/25 4:59 PM 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.2.4 1 3109 Power system shipping and installation
3111 1.4 1.4.4.2.4.1 Power system installation and testing at NTS Not Started C 6 1 1 4w 10/03/22 10/28/22 10/03/22 8:00 AM 10/28/22 4:59 PM 3095, 3101, 3106 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.2.4.1 1 3110 Power system installation and testing at NTS
3112 1.4 1.4.4.2.4.2 Power system final design review Not Started C 6 1 3w 10/31/22 11/18/22 10/31/22 8:00 AM 11/18/22 4:59 PM 3110 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.2.4.2 1 3111 Power system final design review
3113 1.4 1.4.4.2.4.3 Pre-ship review Not Started C 6 1 1d 05/15/23 05/15/23 05/15/23 8:00 AM 05/15/23 4:59 PM 3098, 3103, 3108 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.2.4.3 1 3112 Pre-ship review
3114 1.4 1.4.4.2.4.4 Shipping to PTH (ComSur RDD 9/15/24, ROS 12/1/24) Not Started C 6 1 4w 05/16/23 06/12/23 05/16/23 8:00 AM 06/12/23 4:59 PM 3112 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.2.4.4 1 3113 Shipping to PTH (ComSur RDD 9/15/24, ROS 12/1/24)
3115 1.4 1.4.4.2.4.5 Power system shipped Not Started C 6 1 1 1 0 05/16/23 05/16/23 05/16/23 8:00 AM 05/16/23 8:00 AM 3113SS 0.00% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.2.4.5 1 3114 Power system shipped
3116 1.4 1.4.4.2.4.6 Power system installation in ICL Not Started C 6 1 5d 01/07/25 01/13/25 01/07/25 8:00 AM 01/13/25 4:59 PM 0.00% 0% Green – requires ICL electrical upgrade by ASC $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.2.4.6 1 3115 Power system installation in ICL
3117 1.4 1.4.4.2.5 Power systems support Should have Started C 5 1 1121d 10/01/21 01/29/26 10/01/21 8:00 AM 01/29/26 4:59 PM 7.77% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.2.5 1 3116 Power systems support
3118 1.4 1.4.4.3 On-ice support for CPT electronics Not Started P 5 1 549d 01/07/24 02/19/26 01/07/24 8:00 AM 02/19/26 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.3 1 3117 On-ice support for CPT electronics
3119 1.4 1.4.4.3.1 Electronics SME arrives to support FS2 activities Not Started C 6 1 0 01/07/24 01/07/24 01/07/24 8:00 AM 01/07/24 8:00 AM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.4.4.3.1 1 3118 Electronics SME arrives to support FS2 activities
3120 1.4 1.4.4.3.2 PQ, ECW, Deployment Travel Costs FS2 Electronics SMEs (Headcount 2) Not Started C 6 1 186d 06/01/24 02/19/25 06/01/24 8:00 AM 02/19/25 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.3.2 1 3119 PQ, ECW, Deployment Travel Costs FS2 Electronics SMEs (Headcount 2)
3121 1.4 1.4.4.3.3 Electronics SME support for FS2 activities (slot 1) Not Started C 6 1 19d 01/07/25 01/31/25 01/07/25 8:00 AM 01/31/25 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.3.3 1 3120 Electronics SME support for FS2 activities (slot 1)
3122 1.4 1.4.4.3.4 Electronics SME support for FS2 activities (slot 2) Not Started C 6 1 14d 01/15/25 02/03/25 01/15/25 8:00 AM 02/03/25 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.3.4 1 3121 Electronics SME support for FS2 activities (slot 2)
3123 1.4 1.4.4.3.5 Off-ice training Electronics SMEs (FS3) Not Started C 6 1 21d 08/01/25 08/29/25 08/01/25 8:00 AM 08/29/25 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.4.4.3.5 1 3122 Off-ice training Electronics SMEs (FS3)
3124 1.4 1.4.4.3.6 Electronics SME arrives to support FS3 activities Not Started C 6 1 0 11/15/25 11/15/25 11/15/25 8:00 AM 11/15/25 8:00 AM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.3.6 1 3123 Electronics SME arrives to support FS3 activities
3125 1.4 1.4.4.3.7 PQ, ECW, Deployment Travel Costs FS3 Electronics SMEs (Headcount 2) Not Started C 6 1 187d 06/01/25 02/19/26 06/01/25 8:00 AM 02/19/26 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.4.4.3.7 1 3124 PQ, ECW, Deployment Travel Costs FS3 Electronics SMEs (Headcount 2)
3126 1.4 1.4.4.3.8 Electronics SME support for FS3 activities (slot 1) Not Started C 6 1 21d 11/15/25 12/15/25 11/15/25 8:00 AM 12/15/25 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.4.3.8 1 3125 Electronics SME support for FS3 activities (slot 1)
3127 1.4 1.4.4.3.9 Electronics SME support for FS3 activities (slot 2) Not Started C 6 1 20d 12/18/25 01/16/26 12/18/25 8:00 AM 01/16/26 4:59 PM 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.4.4.3.9 1 3126 Electronics SME support for FS3 activities (slot 2)
3128 1.4 1.4.5 Northern Test System Started P 3 1 1363d 01/01/21 04/06/26 01/01/21 8:00 AM 04/06/26 4:59 PM 16.35% 25.00% Green $0.00 $0.00 $7,184.65 $43,952.70 16% Tyce Deyoung 1.4.5 1 3127 Northern Test System
3129 1.4 1.4.5.2 NTS Cables Should have Started P 4 1 257d 10/01/21 09/26/22 10/01/21 8:00 AM 09/26/22 4:59 PM 0.00% 0% Green $0.00 $125.00 $0.00 $11,724.96 0% $0.00 Tyce Deyoung 1.4.5.2 1 3128 NTS Cables
3130 1.4 1.4.5.2.1 Design of permanent installation scheme Not Started C 5 1 4w 07/19/22 08/15/22 07/19/22 8:00 AM 08/15/22 4:59 PM 2894 0.00% 0% Green $0.00 $10,265.16 $0.00 $10,265.16 0% $0.00 Tyce Deyoung 1.4.5.2.1 1 3129 Design of permanent installation scheme
3131 1.4 1.4.5.2.2 Facility construction Not Started C 5 1 5w 08/16/22 09/19/22 08/16/22 8:00 AM 09/19/22 4:59 PM 3129 0.00% 0% Green $0.00 $1,334.80 $0.00 $1,334.80 0% $0.00 Tyce Deyoung 1.4.5.2.2 1 3130 Facility construction
3132 1.4 1.4.5.2.3 Permanent mounting of NTS quads Not Started C 5 1 1w 09/20/22 09/26/22 09/20/22 8:00 AM 09/26/22 4:59 PM 3130 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.5.2.3 1 3131 Permanent mounting of NTS quads
3133 1.4 1.4.5.2.4 NTS cable permanent installation finished Not Started C 5 1 1 0 09/26/22 09/26/22 09/26/22 4:59 PM 09/26/22 4:59 PM 3131 0.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.5.2.4 1 3132 NTS cable permanent installation finished
3134 1.4 1.4.5.2.5 NTS cables support Should have Started C 5 1 257d 10/01/21 09/26/22 10/01/21 8:00 AM 09/26/22 4:59 PM 34.04% Red $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.5.2.5 1 3133 NTS cables support
3135 1.4 1.4.5.3 NTS dark boxes Started P 4 1 326d 01/01/21 04/01/22 01/01/21 8:00 AM 04/01/22 4:59 PM 100.00% 48.00% Red $125.00 $125.00 $2,176.03 $2,176.03 100% $60.00 Tyce Deyoung 1.4.5.3 1 3134 NTS dark boxes
3136 1.4 1.4.5.3.1 Order materials Complete C 5 1 21d 01/01/21 01/29/21 01/01/21 8:00 AM 01/29/21 4:59 PM 98.72% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.5.3.1 1 3135 Order materials
3137 1.4 1.4.5.3.2 Construction Started C 5 1 61w 02/01/21 04/01/22 02/01/21 8:00 AM 04/01/22 4:59 PM 3135 100.00% 65.00% Red $2,051.03 $2,051.03 $2,051.03 $2,051.03 100% $1,333.17 Tyce Deyoung 1.4.5.3.2 1 3136 Construction
3138 1.4 1.4.5.3.3 NTS dark boxes ready Complete C 5 1 1 1d 04/15/21 04/15/21 04/15/21 8:00 AM 04/15/21 4:59 PM 100.00% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.5.3.3 1 3137 NTS dark boxes ready
3139 1.4 1.4.5.3.4 NTS dark boxes support Should have Started C 5 1 131d 10/01/21 04/01/22 10/01/21 8:00 AM 04/01/22 4:59 PM 67.08% Red $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.5.3.4 1 3138 NTS dark boxes support
3140 1.4 1.4.5.4 NTS Operations Started P 4 1 1363d 01/01/21 04/06/26 01/01/21 8:00 AM 04/06/26 4:59 PM 16.67% 24.00% Green $0.00 $0.00 $5,008.62 $30,051.71 17% Tyce Deyoung 1.4.5.4 1 3139 NTS Operations
3141 1.4 1.4.5.4.1 Commissioning Complete C 5 1 107d 01/01/21 05/31/21 01/01/21 8:00 AM 05/31/21 4:59 PM 99.75% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.5.4.1 1 3140 Commissioning
3142 1.4 1.4.5.4.2 NTS Fully Operational Complete C 5 1 1 1d 06/01/21 06/01/21 06/01/21 8:00 AM 06/01/21 4:59 PM 3140 100.00% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.5.4.2 1 3141 NTS Fully Operational
3143 1.4 1.4.5.4.3 NTS Operations Started C 5 1 1255d 06/02/21 04/06/26 06/02/21 8:00 AM 04/06/26 4:59 PM 3141 16.67% 17.00% Green $5,008.62 $30,051.71 $5,008.62 $30,051.71 17% $5,108.79 Tyce Deyoung 1.4.5.4.3 1 3142 NTS Operations
3144 1.4 1.4.6 CPT Management (PY4 onward) Should have Started C 3 1 1168d 10/01/21 04/06/26 10/01/21 8:00 AM 04/06/26 4:59 PM 7.46% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Tyce Deyoung 1.4.6 1 3143 CPT Management (PY4 onward)
3145 1.5 1.5 Characterization and Calibration System Started P 2 1 1957d 10/01/18 04/13/26 10/01/18 8:00 AM 04/13/26 4:59 PM 1.28% 29.00% Green $0.00 $0.00 $500.00 $38,944.83 1% Dawn Williams 1.5 1 3144 Characterization and Calibration System
3146 1.5 1.5.1 Module Calibration Started P 3 1350d 12/19/18 02/23/24 12/19/18 8:00 AM 02/23/24 4:59 PM 16% 57.00% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.1 1 3145 Module Calibration
3147 1.5 1.5.1.1 Production Calibration Started P 4 1 1248d 12/19/18 09/29/23 12/19/18 8:00 AM 09/29/23 4:59 PM 33% 58.00% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.1.1 1 3146 Production Calibration
3148 1.5 1.5.1.1.1 Entry of Production Calibration Data into Database Started C 5 1 1248d 12/19/18 09/29/23 12/19/18 8:00 AM 09/29/23 4:59 PM 65% 58.00% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.1.1.1 1 3147 Entry of Production Calibration Data into Database
3149 1.5 1.5.1.1.2 PSL Water Tank for Calibration Complete Not Started C 5 1 1 0 12/31/22 12/31/22 12/31/22 8:00 AM 12/31/22 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.1.1.2 1 3148 PSL Water Tank for Calibration Complete
3150 1.5 1.5.1.2 In-situ Sensor Response Calibration Not Started C 4 29d 01/16/24 02/23/24 01/16/24 8:00 AM 02/23/24 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.1.2 1 3149 In-situ Sensor Response Calibration
3151 1.5 1.5.2 Calibration Assemblies Started P 3 1778d 10/01/18 08/01/25 10/01/18 8:00 AM 08/01/25 8:00 AM 42% 41.00% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2 1 3150 Calibration Assemblies
3152 1.5 1.5.2.1 On-board LED Flashers Started P 4 1155d 10/01/18 03/03/23 10/01/18 8:00 AM 03/03/23 4:59 PM 67% 68.00% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1 1 3151 On-board LED Flashers
3153 1.5 1.5.2.1.1 D-egg Flashers Complete P 5 610d 10/01/18 01/29/21 10/01/18 8:00 AM 01/29/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.1 1 3152 D-egg Flashers
3154 1.5 1.5.2.1.1.1 LED selection Complete C 6 229d 10/01/18 08/15/19 10/01/18 8:00 AM 08/15/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.1.1 1 3153 LED selection
3155 1.5 1.5.2.1.1.2 Common Electrical interface to MB and Driver Circuit Complete C 6 36d 12/13/18 01/31/19 12/13/18 8:00 AM 01/31/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.1.2 1 3154 Common Electrical interface to MB and Driver Circuit
3156 1.5 1.5.2.1.1.3 Design of Opto-mechanical interface for D-egg Complete C 6 176d 12/13/18 08/15/19 12/13/18 8:00 AM 08/15/19 4:59 PM 3154SS, 3153FF 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.1.3 1 3155 Design of Opto-mechanical interface for D-egg
3157 1.5 1.5.2.1.1.4 Design of Opto-mechanical interface for mDOM Complete C 6 197d 12/13/18 09/13/19 12/13/18 8:00 AM 09/13/19 4:59 PM 3155SS 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.1.4 1 3156 Design of Opto-mechanical interface for mDOM
3158 1.5 1.5.2.1.1.5 D-egg Flasher Production and Testing Complete C 6 610d 10/01/18 01/29/21 10/01/18 8:00 AM 01/29/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.1.5 1 3157 D-egg Flasher Production and Testing
3159 1.5 1.5.2.1.2 mDOM Flashers Not Started P 5 284d 02/01/22 03/03/23 02/01/22 8:00 AM 03/03/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2 1 3158 mDOM Flashers
3160 1.5 1.5.2.1.2.0 mDOM Flasher DESY Batch 0 Production Not Started C 6 11d 02/01/22 02/15/22 02/01/22 8:00 AM 02/15/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.0 1 3159 mDOM Flasher DESY Batch 0 Production
3161 1.5 1.5.2.1.2.1 mDOM Flasher DESY Batch 1 Production Not Started C 6 15d 04/25/22 05/13/22 04/25/22 8:00 AM 05/13/22 4:59 PM 2535FS +20d 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.1 1 3160 mDOM Flasher DESY Batch 1 Production
3162 1.5 1.5.2.1.2.2 mDOM Flasher DESY Batch 2 Production Not Started C 6 15d 05/16/22 06/03/22 05/16/22 8:00 AM 06/03/22 4:59 PM 3160 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.2 1 3161 mDOM Flasher DESY Batch 2 Production
3163 1.5 1.5.2.1.2.3 mDOM Flasher DESY Batch 3 Production Not Started C 6 15d 06/06/22 06/24/22 06/06/22 8:00 AM 06/24/22 4:59 PM 3161 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.3 1 3162 mDOM Flasher DESY Batch 3 Production
3164 1.5 1.5.2.1.2.4 mDOM Flasher DESY Batch 4 Production Not Started C 6 15d 06/27/22 07/15/22 06/27/22 8:00 AM 07/15/22 4:59 PM 3162 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.4 1 3163 mDOM Flasher DESY Batch 4 Production
3165 1.5 1.5.2.1.2.5 mDOM Flasher DESY Batch 5 Production Not Started C 6 15d 07/18/22 08/05/22 07/18/22 8:00 AM 08/05/22 4:59 PM 3163 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.5 1 3164 mDOM Flasher DESY Batch 5 Production
3166 1.5 1.5.2.1.2.6 mDOM Flasher DESY Batch 6 Production Not Started C 6 15d 08/08/22 08/26/22 08/08/22 8:00 AM 08/26/22 4:59 PM 3164 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.6 1 3165 mDOM Flasher DESY Batch 6 Production
3167 1.5 1.5.2.1.2.7 mDOM Flasher DESY Batch 7 Production Not Started C 6 15d 08/29/22 09/16/22 08/29/22 8:00 AM 09/16/22 4:59 PM 3165 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.7 1 3166 mDOM Flasher DESY Batch 7 Production
3168 1.5 1.5.2.1.2.8 mDOM Flasher DESY Batch 8 Production Not Started C 6 15d 09/19/22 10/07/22 09/19/22 8:00 AM 10/07/22 4:59 PM 3166 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.8 1 3167 mDOM Flasher DESY Batch 8 Production
3169 1.5 1.5.2.1.2.9 mDOM Flasher MSU Batch 1 Production Not Started C 6 15d 10/10/22 10/28/22 10/10/22 8:00 AM 10/28/22 4:59 PM 3167 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.9 1 3168 mDOM Flasher MSU Batch 1 Production
3170 1.5 1.5.2.1.2.10 mDOM Flasher MSU Batch 2 Production Not Started C 6 15d 10/31/22 11/18/22 10/31/22 8:00 AM 11/18/22 4:59 PM 3168 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.10 1 3169 mDOM Flasher MSU Batch 2 Production
3171 1.5 1.5.2.1.2.11 mDOM Flasher MSU Batch 3 Production Not Started C 6 15d 11/21/22 12/09/22 11/21/22 8:00 AM 12/09/22 4:59 PM 3169 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.11 1 3170 mDOM Flasher MSU Batch 3 Production
3172 1.5 1.5.2.1.2.12 mDOM Flasher MSU Batch 4 Production Not Started C 6 15d 12/12/22 12/30/22 12/12/22 8:00 AM 12/30/22 4:59 PM 3170 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.12 1 3171 mDOM Flasher MSU Batch 4 Production
3173 1.5 1.5.2.1.2.13 mDOM Flasher MSU Batch 5 Production Not Started C 6 15d 01/02/23 01/20/23 01/02/23 8:00 AM 01/20/23 4:59 PM 3171 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.13 1 3172 mDOM Flasher MSU Batch 5 Production
3174 1.5 1.5.2.1.2.14 mDOM Flasher MSU Batch 6 Production Not Started C 6 15d 01/23/23 02/10/23 01/23/23 8:00 AM 02/10/23 4:59 PM 3172 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.14 1 3173 mDOM Flasher MSU Batch 6 Production
3175 1.5 1.5.2.1.2.15 mDOM Flasher MSU Batch 7 Production Not Started C 6 15d 02/13/23 03/03/23 02/13/23 8:00 AM 03/03/23 4:59 PM 3173 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.2.15 1 3174 mDOM Flasher MSU Batch 7 Production
3176 1.5 1.5.2.1.4 Final Onboard Design Review (FDR) Complete C 5 1 0 09/14/19 09/14/19 09/14/19 8:00 AM 09/14/19 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.1.4 1 3175 Final Onboard Design Review (FDR)
3177 1.5 1.5.2.2 Standalone Light Sources Should have Started P 4 923d 01/10/22 08/01/25 01/10/22 8:00 AM 08/01/25 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2 1 3176 Standalone Light Sources
3178 1.5 1.5.2.2.1 POCAM Not Started P 5 844d 05/01/22 08/01/25 05/01/22 8:00 AM 08/01/25 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.1 1 3177 POCAM
3179 1.5 1.5.2.2.1.1 POCAM DVT Modules Built Not Started C 6 24d 05/01/22 06/01/22 05/01/22 8:00 AM 06/01/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.1.1 1 3178 POCAM DVT Modules Built
3180 1.5 1.5.2.2.1.2 POCAM Design verification testing Not Started C 6 44d 06/01/22 08/01/22 06/01/22 8:00 AM 08/01/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.1.2 1 3179 POCAM Design verification testing
3181 1.5 1.5.2.2.1.3 Update POCAM design Not Started C 6 24d 08/01/22 09/01/22 08/01/22 8:00 AM 09/01/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.1.3 1 3180 Update POCAM design
3182 1.5 1.5.2.2.1.4 POCAM Design complete, Final Design Review Not Started C 6 1 1 0 09/15/22 09/15/22 09/15/22 8:00 AM 09/15/22 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.1.4 1 3181 POCAM Design complete, Final Design Review
3183 1.5 1.5.2.2.1.5 POCAM Batch 1 production (30) Not Started C 6 67d 03/01/23 06/01/23 03/01/23 8:00 AM 06/01/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.1.5 1 3182 POCAM Batch 1 production (30)
3184 1.5 1.5.2.2.1.6 POCAM Batch 1 calibration Not Started C 6 66d 04/01/23 06/30/23 04/01/23 8:00 AM 06/30/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.1.6 1 3183 POCAM Batch 1 calibration
3185 1.5 1.5.2.2.1.7 POCAM Batch 1 FAT testing Not Started C 6 23d 07/01/23 08/01/23 07/01/23 8:00 AM 08/01/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.1.7 1 3184 POCAM Batch 1 FAT testing
3186 1.5 1.5.2.2.1.8 POCAM ready to ship Not Started C 6 1 1 0 08/01/23 08/01/23 08/01/23 4:59 PM 08/01/23 4:59 PM 3184 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.2.1.8 1 3185 POCAM ready to ship
3187 1.5 1.5.2.2.1.9 Deliver 1 POCAM module to NTS Not Started C 6 1 0 12/15/23 12/15/23 12/15/23 8:00 AM 12/15/23 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.1.9 1 3186 Deliver 1 POCAM module to NTS
3188 1.5 1.5.2.2.1.10 Deliver Str. 87-88 POCAM Modules to CHC (4) Not Started C 6 1 0 08/01/24 08/01/24 08/01/24 8:00 AM 08/01/24 8:00 AM 0% Green Assume shipping by air from Europe, shipping should occur a few weeks before to make delivery date $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.1.10 1 3187 Deliver Str. 87-88 POCAM Modules to CHC (4)
3189 1.5 1.5.2.2.1.11 Deliver Str. 89-93 POCAM Modules to CHC (17) Not Started C 6 1 0 08/01/25 08/01/25 08/01/25 8:00 AM 08/01/25 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.1.11 1 3188 Deliver Str. 89-93 POCAM Modules to CHC (17)
3190 1.5 1.5.2.2.2 Pencil Beam ( at UW, Chris Wendt ) Should have Started P 5 923d 01/10/22 08/01/25 01/10/22 8:00 AM 08/01/25 8:00 AM 1% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2 1 3189 Pencil Beam ( at UW, Chris Wendt )
3191 1.5 1.5.2.2.2.0 Pencil Beam Engineering Should have Started C 6 666d 01/10/22 08/01/24 01/10/22 8:00 AM 08/01/24 4:59 PM 2% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.2.2.0 1 3190 Pencil Beam Engineering
3192 1.5 1.5.2.2.2.1 Pencil Beam DVT Module(s) built Should have Started C 6 255d 01/10/22 12/30/22 01/10/22 8:00 AM 12/30/22 4:59 PM 6% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.1 1 3191 Pencil Beam DVT Module(s) built
3193 1.5 1.5.2.2.2.2 Pencil Beam Design verification testing Not Started C 6 252d 03/15/22 03/01/23 03/15/22 8:00 AM 03/01/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.2 1 3192 Pencil Beam Design verification testing
3194 1.5 1.5.2.2.2.3 Update Pencil Beam design Not Started C 6 209d 03/15/22 12/30/22 03/15/22 8:00 AM 12/30/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.3 1 3193 Update Pencil Beam design
3195 1.5 1.5.2.2.2.4 Pencil Beam Final Design Review Not Started C 6 1 1 0 03/01/23 03/01/23 03/01/23 8:00 AM 03/01/23 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.4 1 3194 Pencil Beam Final Design Review
3196 1.5 1.5.2.2.2.5 Pencil Beam Batch 1 production Not Started C 6 43d 03/02/23 05/01/23 03/02/23 8:00 AM 05/01/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.5 1 3195 Pencil Beam Batch 1 production
3197 1.5 1.5.2.2.2.6 Pencil Beam Batch 1 calibration Not Started C 6 67d 05/01/23 08/01/23 05/01/23 8:00 AM 08/01/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.6 1 3196 Pencil Beam Batch 1 calibration
3198 1.5 1.5.2.2.2.7 Pencil Beam Batch 1 FAT testing Not Started C 6 67d 05/01/23 08/01/23 05/01/23 8:00 AM 08/01/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.7 1 3197 Pencil Beam Batch 1 FAT testing
3199 1.5 1.5.2.2.2.8 Pencil Beam Batch 2 production Not Started C 6 108d 08/02/23 01/03/24 08/02/23 8:00 AM 01/03/24 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.8 1 3198 Pencil Beam Batch 2 production
3200 1.5 1.5.2.2.2.9 Pencil Beam Batch 2 calibration Not Started C 6 154d 01/01/24 08/01/24 01/01/24 8:00 AM 08/01/24 4:59 PM 0% Green PDR delayed due to lockdowns delaying prototype development $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.9 1 3199 Pencil Beam Batch 2 calibration
3201 1.5 1.5.2.2.2.10 Pencil Beam Batch 2 FAT testing Not Started C 6 154d 01/01/24 08/01/24 01/01/24 8:00 AM 08/01/24 4:59 PM 0% Green Prototypes delayed due to COVID 19 lockdowns $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.10 1 3200 Pencil Beam Batch 2 FAT testing
3202 1.5 1.5.2.2.2.11 PencilBeam Batch 1 Ready to Ship Not Started C 6 1 1 0 08/01/23 08/01/23 08/01/23 4:59 PM 08/01/23 4:59 PM 3197 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.2.2.11 1 3201 PencilBeam Batch 1 Ready to Ship
3203 1.5 1.5.2.2.2.12 PencilBeam Batch 2 Ready to Ship Not Started C 6 1 1 0 08/01/24 08/01/24 08/01/24 4:59 PM 08/01/24 4:59 PM 3200 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.2.2.12 1 3202 PencilBeam Batch 2 Ready to Ship
3204 1.5 1.5.2.2.2.13 Deliver 1 Pencil Beam module to NTS Not Started C 6 1 0 12/15/23 12/15/23 12/15/23 8:00 AM 12/15/23 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.13 1 3203 Deliver 1 Pencil Beam module to NTS
3205 1.5 1.5.2.2.2.14 Deliver Str. 87-88 Pencil Beam Modules to PTH (4) Not Started C 6 1 0 08/01/24 08/01/24 08/01/24 8:00 AM 08/01/24 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.14 1 3204 Deliver Str. 87-88 Pencil Beam Modules to PTH (4)
3206 1.5 1.5.2.2.2.15 Deliver Str. 89-93 Pencil Beam Modules to PTH (8) Not Started C 6 1 0 08/01/25 08/01/25 08/01/25 8:00 AM 08/01/25 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.2.2.15 1 3205 Deliver Str. 89-93 Pencil Beam Modules to PTH (8)
3207 1.5 1.5.2.3 Camera and Light Detection Started P 4 1386d 04/01/20 08/01/25 04/01/20 8:00 AM 08/01/25 8:00 AM 43% 42.00% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3 1 3206 Camera and Light Detection
3208 1.5 1.5.2.3.1 Cameras in Photosensors Started P 5 696d 04/01/20 11/30/22 04/01/20 8:00 AM 11/30/22 4:59 PM 67% 59.00% Yellow $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1 1 3207 Cameras in Photosensors
3209 1.5 1.5.2.3.1.1 D-egg cameras Complete P 6 328d 04/01/20 07/02/21 04/01/20 8:00 AM 07/02/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.1 1 3208 D-egg cameras
3210 1.5 1.5.2.3.1.1.1 Camera D-egg batch 3.1 production Complete C 7 69d 04/01/20 07/06/20 04/01/20 8:00 AM 07/06/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.1.1 1 3209 Camera D-egg batch 3.1 production
3211 1.5 1.5.2.3.1.1.2 Camera D-egg batch 3.1 Calibration (CAT) Complete C 7 35d 02/01/21 03/19/21 02/01/21 8:00 AM 03/19/21 4:59 PM 3209FS +149d 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.1.2 1 3210 Camera D-egg batch 3.1 Calibration (CAT)
3212 1.5 1.5.2.3.1.1.3 Delivery of Camera D-egg batch 3.1 to Chiba Complete C 7 15d 03/22/21 04/09/21 03/22/21 8:00 AM 04/09/21 4:59 PM 3210 98% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.1.3 1 3211 Delivery of Camera D-egg batch 3.1 to Chiba
3213 1.5 1.5.2.3.1.1.4 Camera D-egg batch 3.2 production Complete C 7 63d 12/23/20 03/19/21 12/23/20 8:00 AM 03/19/21 4:59 PM 3210FF 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.1.4 1 3212 Camera D-egg batch 3.2 production
3214 1.5 1.5.2.3.1.1.5 Camera D-egg batch 3.2 Calibration (CAT) Complete C 7 1 45d 04/12/21 06/11/21 04/12/21 8:00 AM 06/11/21 4:59 PM 3211, 3212 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.1.5 1 3213 Camera D-egg batch 3.2 Calibration (CAT)
3215 1.5 1.5.2.3.1.1.6 Delivery of Camera D-egg batch 3.2 to Chiba Complete C 7 15d 06/14/21 07/02/21 06/14/21 8:00 AM 07/02/21 4:59 PM 3213 98% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.1.6 1 3214 Delivery of Camera D-egg batch 3.2 to Chiba
3216 1.5 1.5.2.3.1.1.7 Delivery of Camera D-egg to Chiba Finalized Complete C 7 1 0 07/02/21 07/02/21 07/02/21 4:59 PM 07/02/21 4:59 PM 3214 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.1.7 1 3215 Delivery of Camera D-egg to Chiba Finalized
3217 1.5 1.5.2.3.1.2 mDOM Cameras Started P 6 696d 04/01/20 11/30/22 04/01/20 8:00 AM 11/30/22 4:59 PM 35% 39.00% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2 1 3216 mDOM Cameras
3218 1.5 1.5.2.3.1.2.1 Camera mDOM batch 1-3 production Complete C 7 69d 04/01/20 07/06/20 04/01/20 8:00 AM 07/06/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.1 1 3217 Camera mDOM batch 1-3 production
3219 1.5 1.5.2.3.1.2.2 Camera mDOM batch 4-8 DESY / 1-7 MSU production Complete C 7 65d 04/01/21 06/30/21 04/01/21 8:00 AM 06/30/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.2 1 3218 Camera mDOM batch 4-8 DESY / 1-7 MSU production
3220 1.5 1.5.2.3.1.2.3 Camera mDOM DESY batch 1 Calibration (CAT) Complete C 7 15d 11/30/20 12/18/20 11/30/20 8:00 AM 12/18/20 4:59 PM 3217FS +104d 98% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.3 1 3219 Camera mDOM DESY batch 1 Calibration (CAT)
3221 1.5 1.5.2.3.1.2.4 Delivery of Camera mDOM batch 1 to DESY Complete C 7 1 23d 12/21/20 01/20/21 12/21/20 8:00 AM 01/20/21 4:59 PM 3219 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.4 1 3220 Delivery of Camera mDOM batch 1 to DESY
3222 1.5 1.5.2.3.1.2.5 Camera mDOM DESY batch 2 Calibration (CAT) Complete C 7 10d 01/04/21 01/15/21 01/04/21 8:00 AM 01/15/21 4:59 PM 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.5 1 3221 Camera mDOM DESY batch 2 Calibration (CAT)
3223 1.5 1.5.2.3.1.2.6 Delivery of Camera mDOM batch 2 to DESY Complete C 7 23d 01/18/21 02/17/21 01/18/21 8:00 AM 02/17/21 4:59 PM 3221, 3220SS 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.6 1 3222 Delivery of Camera mDOM batch 2 to DESY
3224 1.5 1.5.2.3.1.2.7 Camera mDOM DESY batch 3 Calibration (CAT) Complete C 7 10d 01/18/21 01/29/21 01/18/21 8:00 AM 01/29/21 4:59 PM 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.7 1 3223 Camera mDOM DESY batch 3 Calibration (CAT)
3225 1.5 1.5.2.3.1.2.8 Delivery of Camera mDOM batch 3 to DESY Complete C 7 21d 02/01/21 03/01/21 02/01/21 8:00 AM 03/01/21 4:59 PM 3223 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.8 1 3224 Delivery of Camera mDOM batch 3 to DESY
3226 1.5 1.5.2.3.1.2.9 Camera mDOM DESY batch 4 Calibration (CAT) Complete C 7 10d 06/10/21 06/23/21 06/10/21 8:00 AM 06/23/21 4:59 PM 3218FS -15d 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.9 1 3225 Camera mDOM DESY batch 4 Calibration (CAT)
3227 1.5 1.5.2.3.1.2.10 Delivery of Camera mDOM batch 4 to DESY Complete C 7 15d 06/24/21 07/14/21 06/24/21 8:00 AM 07/14/21 4:59 PM 3225 98% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.10 1 3226 Delivery of Camera mDOM batch 4 to DESY
3228 1.5 1.5.2.3.1.2.11 Camera mDOM DESY batch 5 Calibration (CAT) Complete C 7 10d 07/15/21 07/28/21 07/15/21 8:00 AM 07/28/21 4:59 PM 3226 97% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.11 1 3227 Camera mDOM DESY batch 5 Calibration (CAT)
3229 1.5 1.5.2.3.1.2.12 Delivery of Camera mDOM batch 5 to DESY Complete C 7 15d 07/15/21 08/04/21 07/15/21 8:00 AM 08/04/21 4:59 PM 3227SS 98% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.12 1 3228 Delivery of Camera mDOM batch 5 to DESY
3230 1.5 1.5.2.3.1.2.13 Camera mDOM DESY batch 6 Calibration (CAT) Not Started C 7 20d 02/01/22 02/28/22 02/01/22 8:00 AM 02/28/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.13 1 3229 Camera mDOM DESY batch 6 Calibration (CAT)
3231 1.5 1.5.2.3.1.2.14 Delivery of Camera mDOM batch 6 to DESY Not Started C 7 24d 02/28/22 03/31/22 02/28/22 8:00 AM 03/31/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.14 1 3230 Delivery of Camera mDOM batch 6 to DESY
3232 1.5 1.5.2.3.1.2.15 Camera mDOM DESY batch 7 Calibration (CAT) Not Started C 7 24d 02/28/22 03/31/22 02/28/22 8:00 AM 03/31/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.15 1 3231 Camera mDOM DESY batch 7 Calibration (CAT)
3233 1.5 1.5.2.3.1.2.16 Delivery of Camera mDOM batch 7 to DESY Not Started C 7 22d 03/31/22 04/29/22 03/31/22 8:00 AM 04/29/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.16 1 3232 Delivery of Camera mDOM batch 7 to DESY
3234 1.5 1.5.2.3.1.2.17 Camera mDOM DESY batch 8 Calibration (CAT) Not Started C 7 10d 03/31/22 04/13/22 03/31/22 8:00 AM 04/13/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.17 1 3233 Camera mDOM DESY batch 8 Calibration (CAT)
3235 1.5 1.5.2.3.1.2.18 Delivery of Camera mDOM batch 8 to DESY Not Started C 7 25d 04/14/22 05/18/22 04/14/22 8:00 AM 05/18/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.18 1 3234 Delivery of Camera mDOM batch 8 to DESY
3236 1.5 1.5.2.3.1.2.19 Delivery of Camera mDOM to DESY Completed Not Started C 7 1 1 0 05/18/22 05/18/22 05/18/22 8:00 AM 05/18/22 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.19 1 3235 Delivery of Camera mDOM to DESY Completed
3237 1.5 1.5.2.3.1.2.20 Camera mDOM MSU batch 1 Calibration (CAT) Not Started C 7 22d 03/31/22 04/29/22 03/31/22 8:00 AM 04/29/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.20 1 3236 Camera mDOM MSU batch 1 Calibration (CAT)
3238 1.5 1.5.2.3.1.2.21 Delivery of Camera mDOM batch 1 to MSU Not Started C 7 23d 04/30/22 05/31/22 04/30/22 8:00 AM 05/31/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.21 1 3237 Delivery of Camera mDOM batch 1 to MSU
3239 1.5 1.5.2.3.1.2.22 Camera mDOM MSU batch 2 Calibration (CAT) Not Started C 7 23d 05/01/22 05/31/22 05/01/22 8:00 AM 05/31/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.22 1 3238 Camera mDOM MSU batch 2 Calibration (CAT)
3240 1.5 1.5.2.3.1.2.23 Delivery of Camera mDOM batch 2 to MSU Not Started C 7 23d 05/31/22 06/30/22 05/31/22 8:00 AM 06/30/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.23 1 3239 Delivery of Camera mDOM batch 2 to MSU
3241 1.5 1.5.2.3.1.2.24 Camera mDOM MSU batch 3 Calibration (CAT) Not Started C 7 22d 06/01/22 06/30/22 06/01/22 8:00 AM 06/30/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.24 1 3240 Camera mDOM MSU batch 3 Calibration (CAT)
3242 1.5 1.5.2.3.1.2.25 Delivery of Camera mDOM batch 3 to MSU Not Started C 7 22d 06/30/22 07/29/22 06/30/22 8:00 AM 07/29/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.25 1 3241 Delivery of Camera mDOM batch 3 to MSU
3243 1.5 1.5.2.3.1.2.26 Camera mDOM MSU batch 4 Calibration (CAT) Not Started C 7 21d 07/01/22 07/29/22 07/01/22 8:00 AM 07/29/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.26 1 3242 Camera mDOM MSU batch 4 Calibration (CAT)
3244 1.5 1.5.2.3.1.2.27 Delivery of Camera mDOM batch 4 to MSU Not Started C 7 24d 07/31/22 08/31/22 07/31/22 8:00 AM 08/31/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.27 1 3243 Delivery of Camera mDOM batch 4 to MSU
3245 1.5 1.5.2.3.1.2.28 Camera mDOM MSU batch 5 Calibration (CAT) Not Started C 7 23d 08/01/22 08/31/22 08/01/22 8:00 AM 08/31/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.28 1 3244 Camera mDOM MSU batch 5 Calibration (CAT)
3246 1.5 1.5.2.3.1.2.29 Delivery of Camera mDOM batch 5 to MSU Not Started C 7 23d 08/31/22 09/30/22 08/31/22 8:00 AM 09/30/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.29 1 3245 Delivery of Camera mDOM batch 5 to MSU
3247 1.5 1.5.2.3.1.2.30 Camera mDOM MSU batch 6 Calibration (CAT) Not Started C 7 22d 09/01/22 09/30/22 09/01/22 8:00 AM 09/30/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.30 1 3246 Camera mDOM MSU batch 6 Calibration (CAT)
3248 1.5 1.5.2.3.1.2.31 Delivery of Camera mDOM batch 6 to MSU Not Started C 7 22d 09/30/22 10/31/22 09/30/22 8:00 AM 10/31/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.31 1 3247 Delivery of Camera mDOM batch 6 to MSU
3249 1.5 1.5.2.3.1.2.32 Camera mDOM MSU batch 7 Calibration (CAT) Not Started C 7 22d 10/01/22 10/31/22 10/01/22 8:00 AM 10/31/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.32 1 3248 Camera mDOM MSU batch 7 Calibration (CAT)
3250 1.5 1.5.2.3.1.2.33 Delivery of Camera mDOM batch 7 to MSU Not Started C 7 23d 10/31/22 11/30/22 10/31/22 8:00 AM 11/30/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.33 1 3249 Delivery of Camera mDOM batch 7 to MSU
3251 1.5 1.5.2.3.1.2.34 Delivery of Camera mDOM to MSU Completed Not Started C 7 1 1 0 11/30/22 11/30/22 11/30/22 8:00 AM 11/30/22 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.1.2.34 1 3250 Delivery of Camera mDOM to MSU Completed
3252 1.5 1.5.2.3.2 Sweden Camera 2.0 Started P 5 1100d 05/06/21 08/01/25 05/06/21 8:00 AM 08/01/25 8:00 AM 20% 31.00% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.2 1 3251 Sweden Camera 2.0
3253 1.5 1.5.2.3.2.1 Preliminary Design Review Complete C 6 1 0 05/06/21 05/06/21 05/06/21 8:00 AM 05/06/21 8:00 AM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.2.1 1 3252 Preliminary Design Review
3254 1.5 1.5.2.3.2.2 Build Sweden Camera DVT Module Started C 6 254d 07/01/21 06/21/22 07/01/21 8:00 AM 06/21/22 4:59 PM 60% 60.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.2.2 1 3253 Build Sweden Camera DVT Module
3255 1.5 1.5.2.3.2.3 Sweden Camera Final Design Review Not Started C 6 1 1 0 10/03/22 10/03/22 10/03/22 8:00 AM 10/03/22 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.2.3 1 3254 Sweden Camera Final Design Review
3256 1.5 1.5.2.3.2.4 Sweden Camera Production Not Started C 6 240d 10/03/22 09/01/23 10/03/22 8:00 AM 09/01/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.2.4 1 3255 Sweden Camera Production
3257 1.5 1.5.2.3.2.5 Sweden Camera Ready to Ship Not Started C 6 1 1 0 09/01/23 09/01/23 09/01/23 4:59 PM 09/01/23 4:59 PM 3255 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.3.2.5 1 3256 Sweden Camera Ready to Ship
3258 1.5 1.5.2.3.2.6 Delivery of 1 Sweden Camera Module to NTS Not Started C 6 1 0 10/02/23 10/02/23 10/02/23 8:00 AM 10/02/23 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.2.6 1 3257 Delivery of 1 Sweden Camera Module to NTS
3259 1.5 1.5.2.3.2.7 Delivery of Str. 87-88 Sweden Camera Modules to CHC (2) Not Started C 6 1 0 08/01/24 08/01/24 08/01/24 8:00 AM 08/01/24 8:00 AM 0% Green Assume shipping by air from Europe, shipping should occur a few weeks before to make delivery date $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.2.7 1 3258 Delivery of Str. 87-88 Sweden Camera Modules to CHC (2)
3260 1.5 1.5.2.3.2.8 Delivery of Str. 89-93 Sweden Camera Modules to CHC (3) Not Started C 6 1 0 08/01/25 08/01/25 08/01/25 8:00 AM 08/01/25 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.3.2.8 1 3259 Delivery of Str. 89-93 Sweden Camera Modules to CHC (3)
3261 1.5 1.5.2.4 Acoustic Sensors Started P 4 1039d 08/01/21 08/01/25 08/01/21 8:00 AM 08/01/25 8:00 AM 12% 19.00% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4 1 3260 Acoustic Sensors
3262 1.5 1.5.2.4.1 Acoustic DVT Module(s) built Started C 5 218d 08/01/21 05/31/22 08/01/21 8:00 AM 05/31/22 4:59 PM 60% 60.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.1 1 3261 Acoustic DVT Module(s) built
3263 1.5 1.5.2.4.2 Pressure Testing Complete C 5 2d 12/02/21 12/03/21 12/02/21 8:00 AM 12/03/21 4:59 PM 84% 100% Gray Acoustic system under review. $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.2 1 3262 Pressure Testing
3264 1.5 1.5.2.4.3 Acoustic Design verification Testing Started C 5 152d 01/01/22 08/01/22 01/01/22 8:00 AM 08/01/22 4:59 PM 15% 15.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.3 1 3263 Acoustic Design verification Testing
3265 1.5 1.5.2.4.4 Acoustic Update design Not Started C 5 174d 02/01/22 09/30/22 02/01/22 8:00 AM 09/30/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.4 1 3264 Acoustic Update design
3266 1.5 1.5.2.4.5 Acoustic Electronic Update and test Not Started C 5 45d 10/01/22 12/01/22 10/01/22 8:00 AM 12/01/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.5 1 3265 Acoustic Electronic Update and test
3267 1.5 1.5.2.4.6 Acoustic Design complete, Final Design Review Not Started C 5 1 1 0 11/01/22 11/01/22 11/01/22 8:00 AM 11/01/22 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.6 1 3266 Acoustic Design complete, Final Design Review
3268 1.5 1.5.2.4.7 Acoustic Batch 1 production Not Started C 5 66d 01/01/23 03/31/23 01/01/23 8:00 AM 03/31/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.7 1 3267 Acoustic Batch 1 production
3269 1.5 1.5.2.4.8 Acoustic Batch 1 calibration Not Started C 5 88d 03/01/23 06/30/23 03/01/23 8:00 AM 06/30/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.8 1 3268 Acoustic Batch 1 calibration
3270 1.5 1.5.2.4.9 Acoustic Batch 1 FAT testing Not Started C 5 67d 06/01/23 09/01/23 06/01/23 8:00 AM 09/01/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.9 1 3269 Acoustic Batch 1 FAT testing
3271 1.5 1.5.2.4.10 Acoustic Modules Ready to Ship Not Started C 5 1 1 0 09/01/23 09/01/23 09/01/23 4:59 PM 09/01/23 4:59 PM 3269 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.4.10 1 3270 Acoustic Modules Ready to Ship
3272 1.5 1.5.2.4.11 Acoustic deliver one module to Northern Test System Not Started C 5 1 0 10/02/23 10/02/23 10/02/23 4:59 PM 10/02/23 4:59 PM 3270FS +21d 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.11 1 3271 Acoustic deliver one module to Northern Test System
3273 1.5 1.5.2.4.12 Delivery of Str. 87-88 Acoustic modules to CHC (4) Not Started C 5 1 0 08/01/24 08/01/24 08/01/24 8:00 AM 08/01/24 8:00 AM 0% Green Assume shipping by air from Europe, shipping should occur a few weeks before to make delivery date $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.12 1 3272 Delivery of Str. 87-88 Acoustic modules to CHC (4)
3274 1.5 1.5.2.4.13 Delivery of Str. 89-93 Acoustic modules to CHC (8) Not Started C 5 1 0 08/01/25 08/01/25 08/01/25 8:00 AM 08/01/25 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.4.13 1 3273 Delivery of Str. 89-93 Acoustic modules to CHC (8)
3275 1.5 1.5.2.5 Inclinometers and Compasses (UW, Mike ) Complete P 4 250d 10/01/18 09/13/19 10/01/18 8:00 AM 09/13/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.5 1 3274 Inclinometers and Compasses (UW, Mike )
3276 1.5 1.5.2.5.1 Design Complete C 5 154d 10/01/18 05/02/19 10/01/18 8:00 AM 05/02/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.5.1 1 3275 Design
3277 1.5 1.5.2.5.2 Selection and testing of devices Complete C 5 96d 05/03/19 09/13/19 05/03/19 8:00 AM 09/13/19 4:59 PM 3275 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.5.2 1 3276 Selection and testing of devices
3278 1.5 1.5.2.6 Mini-Mainboard Started P 4 739d 10/01/19 07/31/22 10/01/19 8:00 AM 07/31/22 8:00 AM 29% 56.00% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.6 1 3277 Mini-Mainboard
3279 1.5 1.5.2.6.1 Mini-Mainboard Design Complete Complete C 5 349d 10/01/19 01/29/21 10/01/19 8:00 AM 01/29/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.6.1 1 3278 Mini-Mainboard Design Complete
3280 1.5 1.5.2.6.2 Mini-Mainboard V2 First Articles Delivered Complete C 5 1 0 05/28/21 05/28/21 05/28/21 4:59 PM 05/28/21 4:59 PM 3278FS +85d 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.2.6.2 1 3279 Mini-Mainboard V2 First Articles Delivered
3281 1.5 1.5.2.6.3 Testing of Rev2 mainboard Should have Started C 5 76d 01/01/22 04/15/22 01/01/22 8:00 AM 04/15/22 4:59 PM 29% Red $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.6.3 1 3280 Testing of Rev2 mainboard
3282 1.5 1.5.2.6.4 Design layout of MMB Rev3 Should have Started C 5 130d 11/01/21 04/29/22 11/01/21 8:00 AM 04/29/22 4:59 PM 51% Red $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.6.4 1 3281 Design layout of MMB Rev3
3283 1.5 1.5.2.6.5 Procurement of components of MMB Rev3 Should have Started C 5 62d 01/20/22 04/15/22 01/20/22 8:00 AM 04/15/22 4:59 PM 14% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.6.5 1 3282 Procurement of components of MMB Rev3
3284 1.5 1.5.2.6.6 Place order for MMB Rev3 First articles Not Started C 5 1 0 05/10/22 05/10/22 05/10/22 8:00 AM 05/10/22 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.6.6 1 3283 Place order for MMB Rev3 First articles
3285 1.5 1.5.2.6.7 MMB Rev3 First articles delivered Not Started C 5 1 0 06/01/22 06/01/22 06/01/22 8:00 AM 06/01/22 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.6.7 1 3284 MMB Rev3 First articles delivered
3286 1.5 1.5.2.6.8 Testing of MMB Rev3 Not Started C 5 10d 06/02/22 06/15/22 06/02/22 8:00 AM 06/15/22 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.6.8 1 3285 Testing of MMB Rev3
3287 1.5 1.5.2.6.9 Place order for MMB rev3 full production Not Started C 5 1 0 07/01/22 07/01/22 07/01/22 8:00 AM 07/01/22 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.6.9 1 3286 Place order for MMB rev3 full production
3288 1.5 1.5.2.6.10 MMB Rev3 delivered Not Started C 5 1 1 0 07/31/22 07/31/22 07/31/22 8:00 AM 07/31/22 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.2.6.10 1 3287 MMB Rev3 delivered
3289 1.5 1.5.3 Array Calibration Started P 3 1 1948d 10/01/18 03/31/26 10/01/18 8:00 AM 03/31/26 4:59 PM 0% 28.00% Green $0.00 $0.00 $0.00 $17,900.99 0% Dawn Williams 1.5.3 1 3288 Array Calibration
3290 1.5 1.5.3.1 Calibration Benchmarks Started P 4 1 1901d 10/01/18 01/23/26 10/01/18 8:00 AM 01/23/26 4:59 PM 21% 30.0% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.1 1 3289 Calibration Benchmarks
3291 1.5 1.5.3.1.1 Simulation Studies Started C 5 1 1819d 10/01/18 09/26/25 10/01/18 8:00 AM 09/26/25 4:59 PM 48% 48.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.1.1 1 3290 Simulation Studies
3292 1.5 1.5.3.1.2 Plan Started C 5 1 1564d 01/01/20 01/09/26 01/01/20 8:00 AM 01/09/26 4:59 PM 35% 35.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.1.2 1 3291 Plan
3293 1.5 1.5.3.1.3 Software Development Not Started C 5 1 782d 12/30/22 01/09/26 12/30/22 8:00 AM 01/09/26 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.1.3 1 3292 Software Development
3294 1.5 1.5.3.1.4 Execution Not Started C 5 1 524d 01/15/24 01/23/26 01/15/24 8:00 AM 01/23/26 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.1.4 1 3293 Execution
3295 1.5 1.5.3.2 Timing Calibration Started P 4 1 1901d 12/05/18 03/31/26 12/05/18 8:00 AM 03/31/26 4:59 PM 24% 45.00% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.2 1 3294 Timing Calibration
3296 1.5 1.5.3.2.1 Develop Flasher Plan w New Timing System Started C 5 1 1050d 12/05/18 12/13/22 12/05/18 8:00 AM 12/13/22 4:59 PM 78% 78.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.2.1 1 3295 Develop Flasher Plan w New Timing System
3297 1.5 1.5.3.2.2 TEST Flasher in IceCube w New Timing System Not Started C 5 1 263d 12/14/22 12/18/23 12/14/22 8:00 AM 12/18/23 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.2.2 1 3296 TEST Flasher in IceCube w New Timing System
3298 1.5 1.5.3.2.3 Development of Timing Calibration Plan Started C 5 1 1346d 11/01/19 01/06/25 11/01/19 8:00 AM 01/06/25 4:59 PM 43% 46.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.2.3 1 3297 Development of Timing Calibration Plan
3299 1.5 1.5.3.2.4 Create Database Structure for Timing Calibration Data Not Started C 5 1 458d 04/01/24 01/08/26 04/01/24 8:00 AM 01/08/26 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.2.4 1 3298 Create Database Structure for Timing Calibration Data
3300 1.5 1.5.3.2.5 Analyze Timing Calibration Data from Deployed Modules Not Started C 5 1 64d 01/01/26 03/31/26 01/01/26 8:00 AM 03/31/26 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.2.5 1 3299 Analyze Timing Calibration Data from Deployed Modules
3301 1.5 1.5.3.3 Geometry Calibration Started P 4 1 1664d 11/01/19 03/31/26 11/01/19 8:00 AM 03/31/26 4:59 PM 11% 33.00% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.3 1 3300 Geometry Calibration
3302 1.5 1.5.3.3.1 Develop Geometry Plan Started C 5 1 1282d 11/01/19 10/03/24 11/01/19 8:00 AM 10/03/24 4:59 PM 46% 46.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.3.1 1 3301 Develop Geometry Plan
3303 1.5 1.5.3.3.2 Create Database Structure for Geometry Calibration Data Not Started C 5 1 458d 04/01/24 01/08/26 04/01/24 8:00 AM 01/08/26 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.3.2 1 3302 Create Database Structure for Geometry Calibration Data
3304 1.5 1.5.3.3.3 Analyze Geometry Calibration Data from Deployed Modules Not Started C 5 1 64d 01/01/26 03/31/26 01/01/26 8:00 AM 03/31/26 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.3.3 1 3303 Analyze Geometry Calibration Data from Deployed Modules
3305 1.5 1.5.3.3.4 Delivery of Preliminary Timimg and Geometry Calibration Not Started C 5 1 1 1 0 03/31/26 03/31/26 03/31/26 4:59 PM 03/31/26 4:59 PM 3303 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.3.4 1 3304 Delivery of Preliminary Timimg and Geometry Calibration
3306 1.5 1.5.3.4 Ice Properties Calibration Not Started P 4 1 1054d 03/04/22 03/31/26 03/04/22 8:00 AM 03/31/26 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.4 1 3305 Ice Properties Calibration
3307 1.5 1.5.3.4.1 Plan Not Started C 5 1 667d 03/04/22 09/26/24 03/04/22 8:00 AM 09/26/24 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.4.1 1 3306 Plan
3308 1.5 1.5.3.4.2 Software Development Not Started C 5 1 458d 04/01/24 01/08/26 04/01/24 8:00 AM 01/08/26 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.4.2 1 3307 Software Development
3309 1.5 1.5.3.4.3 Execution of Array Calibration Not Started C 5 1 1 64d 01/01/26 03/31/26 01/01/26 8:00 AM 03/31/26 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.4.3 1 3308 Execution of Array Calibration
3310 1.5 1.5.3.4.4 Preliminary Array Calibration Complete Not Started C 5 1 1 0 03/31/26 03/31/26 03/31/26 4:59 PM 03/31/26 4:59 PM 3308 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.4.4 1 3309 Preliminary Array Calibration Complete
3311 1.5 1.5.3.5 Pre-deployment Hole Measurement Not Started P 4 1 428d 08/01/24 03/31/26 08/01/24 8:00 AM 03/31/26 4:59 PM 0% Green $0.00 $0.00 $0.00 $17,900.99 0% Dawn Williams 1.5.3.5 1 3310 Pre-deployment Hole Measurement
3312 1.5 1.5.3.5.1 Testing of dust logger and IDP winch Not Started C 5 1 22d 08/01/24 08/30/24 08/01/24 8:00 AM 08/30/24 4:59 PM 0% Green $0.00 $17,900.99 $0.00 $17,900.99 0% $0.00 Dawn Williams 1.5.3.5.1 1 3311 Testing of dust logger and IDP winch
3313 1.5 1.5.3.5.2 Dust Logger and IDP Winch - Ready to Ship Not Started C 5 1 1 1 0 08/30/24 08/30/24 08/30/24 4:59 PM 08/30/24 4:59 PM 3311 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.3.5.2 1 3312 Dust Logger and IDP Winch - Ready to Ship
3314 1.5 1.5.3.5.3 Delivery of logger and winch to PTH Not Started C 5 1 1 0 09/01/25 09/01/25 09/01/25 8:00 AM 09/01/25 8:00 AM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.5.3 1 3313 Delivery of logger and winch to PTH
3315 1.5 1.5.3.5.4 Analyze Hole Log Data Not Started C 5 1 54d 01/15/26 03/31/26 01/15/26 8:00 AM 03/31/26 4:59 PM 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Dawn Williams 1.5.3.5.4 1 3314 Analyze Hole Log Data
3316 1.5 1.5.3.5.5 Preliminary Delivery of Dust Logger Data Not Started C 5 1 1 1 0 03/31/26 03/31/26 03/31/26 4:59 PM 03/31/26 4:59 PM 3314 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 1.5.3.5.5 1 3315 Preliminary Delivery of Dust Logger Data
3317 1.5 1.5.4 Calibration Management and Organization Should have Started P 3 1 1883d 01/11/19 04/13/26 01/11/19 8:00 AM 04/13/26 4:59 PM 2% Green $0.00 $0.00 $500.00 $21,043.84 2% Dawn Williams 1.5.4 1 3316 Calibration Management and Organization
3318 1.5 1.5.4.1 Calibration management Should have Started C 4 1 1883d 01/11/19 04/13/26 01/11/19 8:00 AM 04/13/26 4:59 PM 5% Green $500.00 $11,043.84 $500.00 $11,043.84 5% $0.00 Dawn Williams 1.5.4.1 1 3317 Calibration management
3319 1.5 1.5.4.2 Travel Should have Started C 4 1 1883d 01/11/19 04/13/26 01/11/19 8:00 AM 04/13/26 4:59 PM 0% Green $0.00 $10,000.00 $0.00 $10,000.00 0% $0.00 Dawn Williams 1.5.4.2 1 3318 Travel
3320 1.6 1.6 IceCube Data Systems Integration Started P 2 1 2043d 06/01/18 04/13/26 06/01/18 8:00 AM 04/13/26 4:59 PM 14.03% 34.00% Green $0.00 $0.00 $44,222.89 $315,144.86 14% Erik Blaufuss 1.6 1 3319 IceCube Data Systems Integration
3321 1.6 1.6.0 L2 Task Management Started C 3 1 1434d 10/01/20 04/13/26 10/01/20 8:00 AM 04/13/26 4:59 PM 14% 14.00% Green $7,871.80 $54,430.77 $7,871.80 $54,430.77 14% $7,620.31 Erik Blaufuss 1.6.0 1 3320 L2 Task Management
3322 1.6 1.6.1 Online Systems Software Started P 3 1 2043d 06/01/18 04/13/26 06/01/18 8:00 AM 04/13/26 4:59 PM 14% 31.00% Green $0.00 $0.00 $31,279.87 $223,886.73 14% Erik Blaufuss 1.6.1 1 3321 Online Systems Software
3323 1.6 1.6.1.0 L3 Task Management Started C 4 1 1434d 10/01/20 04/13/26 10/01/20 8:00 AM 04/13/26 4:59 PM 17% 17.00% Green $1,155.11 $6,930.68 $1,155.11 $6,930.68 17% $1,178.21 Erik Blaufuss 1.6.1.0 1 3322 L3 Task Management
3324 1.6 1.6.1.1 DAQ Software Started P 4 1 1920d 11/01/18 03/24/26 11/01/18 8:00 AM 03/24/26 4:59 PM 6% 31.00% Green $0.00 $4,450.00 $1,126.94 $17,973.27 6% $1,379.50 Erik Blaufuss 1.6.1.1 1 3323 DAQ Software
3325 1.6 1.6.1.1.1 Interface to OM Sensors Started P 5 1 1872d 11/01/18 01/15/26 11/01/18 8:00 AM 01/15/26 4:59 PM 0% 47.00% Green $0.00 $0.00 $0.00 $6,761.64 0% Erik Blaufuss 1.6.1.1.1 1 3324 Interface to OM Sensors
3326 1.6 1.6.1.1.1.1 DAQ-OM Interface Design Complete C 6 1 146d 11/01/18 05/23/19 11/01/18 8:00 AM 05/23/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.1 1 3325 DAQ-OM Interface Design
3327 1.6 1.6.1.1.1.2 DAQ-OM Interface Documented Complete C 6 1 1 0 05/23/19 05/23/19 05/23/19 4:59 PM 05/23/19 4:59 PM 3325 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.2 1 3326 DAQ-OM Interface Documented
3328 1.6 1.6.1.1.1.3 Testing minimal DAQ software tools developed for DVT testing Complete C 6 1 89d 05/24/19 09/25/19 05/24/19 8:00 AM 09/25/19 4:59 PM 3326 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.3 1 3327 Testing minimal DAQ software tools developed for DVT testing
3329 1.6 1.6.1.1.1.4 Testing minimal DAQ ready for sensor DVT testing Complete P 6 1 57d 08/15/19 11/01/19 08/15/19 8:00 AM 11/01/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.4 1 3328 Testing minimal DAQ ready for sensor DVT testing
3330 1.6 1.6.1.1.1.4.1 Define DAQ interface to FieldHub Complete C 7 1 57d 08/15/19 11/01/19 08/15/19 8:00 AM 11/01/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.4.1 1 3329 Define DAQ interface to FieldHub
3331 1.6 1.6.1.1.1.5 Testing DAQ software implementation and testing for FATs Complete C 6 1 131d 11/04/19 05/04/20 11/04/19 8:00 AM 05/04/20 4:59 PM 3329, 3327 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.5 1 3330 Testing DAQ software implementation and testing for FATs
3332 1.6 1.6.1.1.1.6 Testing DAQ software ready for FAT testing on DEgg Complete C 6 1 1 0 05/04/20 05/04/20 05/04/20 4:59 PM 05/04/20 4:59 PM 3330 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.6 1 3331 Testing DAQ software ready for FAT testing on DEgg
3333 1.6 1.6.1.1.1.7 Extend DAQ testing software for all OM types (mDOM, pDOM) Complete C 6 1 229d 05/05/20 03/19/21 05/05/20 8:00 AM 03/19/21 4:59 PM 3331 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.7 1 3332 Extend DAQ testing software for all OM types (mDOM, pDOM)
3334 1.6 1.6.1.1.1.8 Support DAQ installation for all sensor testing Started C 6 1 783d 09/30/20 09/29/23 09/30/20 8:00 AM 09/29/23 4:59 PM 3332SS +106d 45% 62.00% Green new end date for mDOM FAT $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.8 1 3333 Support DAQ installation for all sensor testing
3335 1.6 1.6.1.1.1.9 Not Started C 6 1 66d 04/01/22 07/01/22 04/01/22 8:00 AM 07/01/22 4:59 PM 0% 0% Green $0.00 $5,634.70 $0.00 $5,634.70 0% $0.00 Erik Blaufuss 1.6.1.1.1.9 1 3334
3336 1.6 1.6.1.1.1.9.1 Prototype and evalulate Upgrade DAQ components within existing IceCube DAQ architecture Not Started C 6 1 227d 07/04/22 05/16/23 07/04/22 8:00 AM 05/16/23 4:59 PM 09/30/22 3334 0% 0% Green EG. Trigger system rate issues ID'd early - $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.9.1 1 3335 Prototype and evalulate Upgrade DAQ components within existing IceCube DAQ architecture
3337 1.6 1.6.1.1.1.10 Review DAQ Operation plans for new modules Not Started C 6 1 1 0 05/16/23 05/16/23 05/16/23 4:59 PM 05/16/23 4:59 PM 3335 0% 0% Green review - major milestone - moved to May 2023 to better fit M&O yearly pole plan $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.10 1 3336 Review DAQ Operation plans for new modules
3338 1.6 1.6.1.1.1.11 DAQ DataCollector component interface development for Upgrade OM sensors Not Started C 6 1 160d 05/17/23 12/28/23 05/17/23 8:00 AM 12/28/23 4:59 PM 3336 0% 0% Green $0.00 $1,126.94 $0.00 $1,126.94 0% $0.00 Erik Blaufuss 1.6.1.1.1.11 1 3337 DAQ DataCollector component interface development for Upgrade OM sensors
3339 1.6 1.6.1.1.1.11.1 DAQ DataCollector component coding and testing for Upgrade OM sensors Not Started C 6 1 160d 12/29/23 08/09/24 12/29/23 8:00 AM 08/09/24 4:59 PM 3337 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.11.1 1 3338 DAQ DataCollector component coding and testing for Upgrade OM sensors
3340 1.6 1.6.1.1.1.11.2 IceCube DAQ systems adapted for Upgrade DataCollector intergration Not Started C 6 1 160d 08/12/24 03/26/25 08/12/24 8:00 AM 03/26/25 4:59 PM 3338 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.11.2 1 3339 IceCube DAQ systems adapted for Upgrade DataCollector intergration
3341 1.6 1.6.1.1.1.11.3 IceCube DAQ system level testing at SPTS and NTS Not Started C 6 1 188d 03/27/25 12/16/25 03/27/25 8:00 AM 12/16/25 4:59 PM 10/01/25 3339 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.11.3 1 3340 IceCube DAQ system level testing at SPTS and NTS
3342 1.6 1.6.1.1.1.12 DAQ software ready for deployment including support for all new OMs Not Started C 6 1 1 1 0 12/16/25 12/16/25 12/16/25 4:59 PM 12/16/25 4:59 PM 3340 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.12 1 3341 DAQ software ready for deployment including support for all new OMs
3343 1.6 1.6.1.1.1.13 DAQ software deployment at SPS Not Started C 6 1 20d 12/17/25 01/15/26 12/17/25 8:00 AM 01/15/26 4:59 PM 3341 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.1.13 1 3342 DAQ software deployment at SPS
3344 1.6 1.6.1.1.2 Interface to Stand Alone calibration devices Started P 5 1 1399d 11/01/20 03/24/26 11/01/20 8:00 AM 03/24/26 4:59 PM 17% 9.00% Yellow $0.00 $0.00 $1,126.94 $6,761.64 17% Erik Blaufuss 1.6.1.1.2 1 3343 Interface to Stand Alone calibration devices
3345 1.6 1.6.1.1.2.1 DAQ-Calibraton device MMB Interface Design Complete C 6 1 120d 11/01/20 04/15/21 11/01/20 8:00 AM 04/15/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.1 1 3344 DAQ-Calibraton device MMB Interface Design
3346 1.6 1.6.1.1.2.2 DAQ-Calibration device MMB Interface Documented Complete C 6 1 1 1d 04/16/21 04/16/21 04/16/21 8:00 AM 04/16/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.2 1 3345 DAQ-Calibration device MMB Interface Documented
3347 1.6 1.6.1.1.2.3 DAQ-Calibration MMB software implementation and testing for NTS Started C 6 1 207d 11/30/21 09/14/22 11/30/21 8:00 AM 09/14/22 4:59 PM 22% 20.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.3 1 3346 DAQ-Calibration MMB software implementation and testing for NTS
3348 1.6 1.6.1.1.2.4 NTS minimal DAQ ready for calibration device testing at NTS Not Started C 6 1 1 0 09/14/22 09/14/22 09/14/22 4:59 PM 09/14/22 4:59 PM 3346 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.4 1 3347 NTS minimal DAQ ready for calibration device testing at NTS
3349 1.6 1.6.1.1.2.5 Support DAQ installation for NTS calibration device testing Not Started C 6 1 643d 09/15/22 03/11/25 09/15/22 8:00 AM 03/11/25 4:59 PM 3347 17% 0% Yellow $1,126.94 $6,761.64 $1,126.94 $6,761.64 17% $0.00 Erik Blaufuss 1.6.1.1.2.5 1 3348 Support DAQ installation for NTS calibration device testing
3350 1.6 1.6.1.1.2.5.0 Capture higher level DAQ requirements for Calibration devices Not Started C 6 1 97d 04/12/23 08/24/23 04/12/23 8:00 AM 08/24/23 4:59 PM 3254, 3194FS +30d, 3181 0% 0% Green moved to match delayed special device schedule $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.5.0 1 3349 Capture higher level DAQ requirements for Calibration devices
3351 1.6 1.6.1.1.2.5.1 Prototype and evaluate DAQ components for Calibration devices Not Started C 6 1 190d 08/25/23 05/21/24 08/25/23 8:00 AM 05/21/24 4:59 PM 3349 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.5.1 1 3350 Prototype and evaluate DAQ components for Calibration devices
3352 1.6 1.6.1.1.2.5.2 Review DAQ/Special devices operations plan for new calibration devices Not Started C 6 1 1 0 05/21/24 05/21/24 05/21/24 4:59 PM 05/21/24 4:59 PM 3350 0% 0% Green review - major milestone $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.5.2 1 3351 Review DAQ/Special devices operations plan for new calibration devices
3353 1.6 1.6.1.1.2.6 Integrate support for calibration devices into DataCollector component Not Started C 6 1 150d 05/22/24 12/18/24 05/22/24 8:00 AM 12/18/24 4:59 PM 3351 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.6 1 3352 Integrate support for calibration devices into DataCollector component
3354 1.6 1.6.1.1.2.6.1 Integrate support for calibration devices into overall DAQ system Not Started C 6 1 150d 12/19/24 07/18/25 12/19/24 8:00 AM 07/18/25 4:59 PM 3352 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.6.1 1 3353 Integrate support for calibration devices into overall DAQ system
3355 1.6 1.6.1.1.2.6.2 IceCube DAQ system level testing of calibration devices at SPTS and NTS Not Started C 6 1 154d 07/21/25 02/24/26 07/21/25 8:00 AM 02/24/26 4:59 PM 09/30/25 3353 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.6.2 1 3354 IceCube DAQ system level testing of calibration devices at SPTS and NTS
3356 1.6 1.6.1.1.2.7 DAQ software ready for deployment including support for all new Calibration devices Not Started C 6 1 1 1 0 02/24/26 02/24/26 02/24/26 4:59 PM 02/24/26 4:59 PM 3354 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.7 1 3355 DAQ software ready for deployment including support for all new Calibration devices
3357 1.6 1.6.1.1.2.8 DAQ for calibration devices software deployment at SPS Not Started C 6 1 20d 02/25/26 03/24/26 02/25/26 8:00 AM 03/24/26 4:59 PM 3355 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.1.2.8 1 3356 DAQ for calibration devices software deployment at SPS
3358 1.6 1.6.1.2 Experiment Control Started P 4 1 2041d 06/01/18 04/09/26 06/01/18 8:00 AM 04/09/26 4:59 PM 11% 24.00% Green $0.00 $0.00 $2,253.88 $20,284.91 11% Erik Blaufuss 1.6.1.2 1 3357 Experiment Control
3359 1.6 1.6.1.2.1 Interface to OM sensors Started P 5 1 1981d 06/01/18 01/15/26 06/01/18 8:00 AM 01/15/26 4:59 PM 8% 37.00% Green $0.00 $0.00 $1,126.94 $13,523.27 8% Erik Blaufuss 1.6.1.2.1 1 3358 Interface to OM sensors
3360 1.6 1.6.1.2.1.1 Experiment control design for FAT testing Complete C 6 1 371d 06/01/18 11/01/19 06/01/18 8:00 AM 11/01/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.1 1 3359 Experiment control design for FAT testing
3361 1.6 1.6.1.2.1.2 ExpControl- OM Sensor software Interface Documented Complete C 6 1 1 1d 11/04/19 11/04/19 11/04/19 8:00 AM 11/04/19 4:59 PM 3359 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.2 1 3360 ExpControl- OM Sensor software Interface Documented
3362 1.6 1.6.1.2.1.3 Minimal ExpControl for sensor testing development Complete C 6 1 89d 06/19/19 10/21/19 06/19/19 8:00 AM 10/21/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.3 1 3361 Minimal ExpControl for sensor testing development
3363 1.6 1.6.1.2.1.4 Minimal ExpControl ready for sensor testing ready Complete C 6 1 1 1d 10/22/19 10/22/19 10/22/19 8:00 AM 10/22/19 4:59 PM 3361 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.4 1 3362 Minimal ExpControl ready for sensor testing ready
3364 1.6 1.6.1.2.1.5 Testing ExpControl software implementation and testing for FATs Complete C 6 1 131d 10/23/19 04/22/20 10/23/19 8:00 AM 04/22/20 4:59 PM 3362 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.5 1 3363 Testing ExpControl software implementation and testing for FATs
3365 1.6 1.6.1.2.1.6 Testing ExpControl software ready for FAT testing for DEgg Complete C 6 1 1 1d 04/23/20 04/23/20 04/23/20 8:00 AM 04/23/20 4:59 PM 3363 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.6 1 3364 Testing ExpControl software ready for FAT testing for DEgg
3366 1.6 1.6.1.2.1.7 Extend testing ExpControl software to all OM types (mDOM, pDOM) Complete C 6 1 229d 04/24/20 03/10/21 04/24/20 8:00 AM 03/10/21 4:59 PM 3364 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.7 1 3365 Extend testing ExpControl software to all OM types (mDOM, pDOM)
3367 1.6 1.6.1.2.1.8 Support ExpControl installation for sensor testing Started C 6 1 782d 10/01/20 09/29/23 10/01/20 8:00 AM 09/29/23 4:59 PM 17% 17.00% Green new end date for mDOM FAT $1,126.94 $6,761.64 $1,126.94 $6,761.64 17% $1,149.48 Erik Blaufuss 1.6.1.2.1.8 1 3366 Support ExpControl installation for sensor testing
3368 1.6 1.6.1.2.1.9 Capture requirements for ExpControl - Upgrade OM Not Started C 6 1 66d 04/01/22 07/01/22 04/01/22 8:00 AM 07/01/22 4:59 PM 0% 0% Green $0.00 $5,634.70 $0.00 $5,634.70 0% $0.00 Erik Blaufuss 1.6.1.2.1.9 1 3367 Capture requirements for ExpControl - Upgrade OM
3369 1.6 1.6.1.2.1.9.1 Prototype and evalulate I3Live extensitons Not Started C 6 1 227d 07/04/22 05/16/23 07/04/22 8:00 AM 05/16/23 4:59 PM 02/28/23 3367 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.9.1 1 3368 Prototype and evalulate I3Live extensitons
3370 1.6 1.6.1.2.1.10 Review Experiment Control - Upgrade plans for new modules Not Started C 6 1 1 0 05/16/23 05/16/23 05/16/23 4:59 PM 05/16/23 4:59 PM 3368 0% 0% Green review - major milestone $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.10 1 3369 Review Experiment Control - Upgrade plans for new modules
3371 1.6 1.6.1.2.1.11 Define ExpControl-Data Collector component interface Not Started C 6 1 160d 05/17/23 12/28/23 05/17/23 8:00 AM 12/28/23 4:59 PM 3369 0% 0% Green $0.00 $1,126.94 $0.00 $1,126.94 0% $0.00 Erik Blaufuss 1.6.1.2.1.11 1 3370 Define ExpControl-Data Collector component interface
3372 1.6 1.6.1.2.1.11.1 Implement ExpControl-DataCollector component interfaces Not Started C 6 1 160d 12/29/23 08/09/24 12/29/23 8:00 AM 08/09/24 4:59 PM 3370 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.11.1 1 3371 Implement ExpControl-DataCollector component interfaces
3373 1.6 1.6.1.2.1.11.2 Implement ExpControl DB interfaces to support DataCollector component Not Started C 6 1 160d 08/12/24 03/26/25 08/12/24 8:00 AM 03/26/25 4:59 PM 3371 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.11.2 1 3372 Implement ExpControl DB interfaces to support DataCollector component
3374 1.6 1.6.1.2.1.11.3 Testing of ExpControl and DAQ operations at SPTS and NTS Not Started C 6 1 188d 03/27/25 12/16/25 03/27/25 8:00 AM 12/16/25 4:59 PM 05/01/25 3372 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.11.3 1 3373 Testing of ExpControl and DAQ operations at SPTS and NTS
3375 1.6 1.6.1.2.1.12 ExpCont system for deployment - OM sensors support ready Not Started C 6 1 1 0 12/16/25 12/16/25 12/16/25 4:59 PM 12/16/25 4:59 PM 3373 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.12 1 3374 ExpCont system for deployment - OM sensors support ready
3376 1.6 1.6.1.2.1.13 ExpControl deployment at SPS Not Started C 6 1 20d 12/17/25 01/15/26 12/17/25 8:00 AM 01/15/26 4:59 PM 3374 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.1.13 1 3375 ExpControl deployment at SPS
3377 1.6 1.6.1.2.2 Interface to Stand Alone Calibration Devices Started P 5 1 1046d 03/27/22 04/09/26 03/27/22 8:00 AM 04/09/26 4:59 PM 17% 7.00% Yellow $0.00 $0.00 $1,126.94 $6,761.64 17% Erik Blaufuss 1.6.1.2.2 1 3376 Interface to Stand Alone Calibration Devices
3378 1.6 1.6.1.2.2.1 Interface Design to Calibration Devices (ExpControl, Config, Calib) Started C 6 1 120d 03/27/22 09/08/22 03/27/22 8:00 AM 09/08/22 4:59 PM 0% 50.0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.2.1 1 3377 Interface Design to Calibration Devices (ExpControl, Config, Calib)
3379 1.6 1.6.1.2.2.2 Capture higher level Exp Control requirements for Calibration devices Not Started C 6 1 97d 04/12/23 08/24/23 04/12/23 8:00 AM 08/24/23 4:59 PM 3254, 3194FS +30d, 3181 0% 0% Green moved to match delayed special device schedule $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.2.2 1 3378 Capture higher level Exp Control requirements for Calibration devices
3380 1.6 1.6.1.2.2.3 Prototype and evaluate Exp Control components for Calibration devices Not Started C 6 1 190d 08/25/23 05/21/24 08/25/23 8:00 AM 05/21/24 4:59 PM 3378 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.2.3 1 3379 Prototype and evaluate Exp Control components for Calibration devices
3381 1.6 1.6.1.2.2.4 Review ExpControl/Special devices operations plan for new calibration devices Not Started C 6 1 1 1 0 05/21/24 05/21/24 05/21/24 4:59 PM 05/21/24 4:59 PM 3379 0% 0% Green review - major milestone $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.2.4 1 3380 Review ExpControl/Special devices operations plan for new calibration devices
3382 1.6 1.6.1.2.2.5 Define and prototype ExpControl - Calibration device special run configuration interface Not Started C 6 1 140d 05/22/24 12/04/24 05/22/24 8:00 AM 12/04/24 4:59 PM 3380 17% 0% Yellow $1,126.94 $6,761.64 $1,126.94 $6,761.64 17% $0.00 Erik Blaufuss 1.6.1.2.2.5 1 3381 Define and prototype ExpControl - Calibration device special run configuration interface
3383 1.6 1.6.1.2.2.5.1 Implement ExpControl - Calibration device special run configuration interface Not Started C 6 1 140d 12/05/24 06/20/25 12/05/24 8:00 AM 06/20/25 4:59 PM 3381 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.2.5.1 1 3382 Implement ExpControl - Calibration device special run configuration interface
3384 1.6 1.6.1.2.2.5.2 Testing of ExpControl - Calibration device control at SPTS and NTS Not Started C 6 1 175d 06/23/25 02/25/26 06/23/25 8:00 AM 02/25/26 4:59 PM 10/30/25 3382 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.2.5.2 1 3383 Testing of ExpControl - Calibration device control at SPTS and NTS
3385 1.6 1.6.1.2.2.6 ExpControl ready for deployment including support for all new Calibration devices Not Started C 6 1 1 1 0 02/25/26 02/25/26 02/25/26 4:59 PM 02/25/26 4:59 PM 3383, 3355 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.2.6 1 3384 ExpControl ready for deployment including support for all new Calibration devices
3386 1.6 1.6.1.2.2.7 ExpControl deployment at SPS Not Started C 6 1 20d 02/26/26 03/25/26 02/26/26 8:00 AM 03/25/26 4:59 PM 3384 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.2.7 1 3385 ExpControl deployment at SPS
3387 1.6 1.6.1.2.2.8 Support ExpControl operations during initial special devices operations Not Started C 6 1 11d 03/26/26 04/09/26 03/26/26 8:00 AM 04/09/26 4:59 PM 3385 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.2.8 1 3386 Support ExpControl operations during initial special devices operations
3388 1.6 1.6.1.2.3 Extend I3Live and I3Moni system to support run monitoring data from new devices. Not Started C 5 391d 10/01/24 04/08/26 10/01/24 8:00 AM 04/08/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.2.3 1 3387 Extend I3Live and I3Moni system to support run monitoring data from new devices.
3389 1.6 1.6.1.3 Online Filtering Started P 4 1 764d 01/01/23 12/12/25 01/01/23 8:00 AM 12/12/25 4:59 PM 0% 2.00% Green $0.00 $10,000.00 $0.00 $23,382.40 0% $200.00 Erik Blaufuss 1.6.1.3 1 3388 Online Filtering
3390 1.6 1.6.1.3.1 Specify Online Filter Req'mts (New sensors / Calib Devices) Started C 5 1 34d 01/01/23 02/15/23 01/01/23 8:00 AM 02/15/23 4:59 PM 0% 15.00% Green $0.00 $8,452.04 $0.00 $8,452.04 0% $1,267.81 Erik Blaufuss 1.6.1.3.1 1 3389 Specify Online Filter Req'mts (New sensors / Calib Devices)
3391 1.6 1.6.1.3.2 Design Filter Sys for unified DAQ readout of ALL sensors& Calib Devices Not Started C 5 1 65d 02/16/23 05/17/23 02/16/23 8:00 AM 05/17/23 4:59 PM 04/28/23 3389 0% 0% Green $0.00 $4,226.02 $0.00 $4,226.02 0% $0.00 Erik Blaufuss 1.6.1.3.2 1 3390 Design Filter Sys for unified DAQ readout of ALL sensors& Calib Devices
3392 1.6 1.6.1.3.3 Review Online Filtering - Upgrade plans for new modules Not Started C 5 1 1d 05/18/23 05/18/23 05/18/23 8:00 AM 05/18/23 4:59 PM 3390 0% 0% Green delayed M&O review of Upgrade plans to avoid pole season $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.3.3 1 3391 Review Online Filtering - Upgrade plans for new modules
3393 1.6 1.6.1.3.4 Implement and testing of filtering SW for prod. systems Not Started C 5 1 196d 02/13/25 11/13/25 02/13/25 8:00 AM 11/13/25 4:59 PM 08/15/25 0% 0% Green delayed start -> M&O prioritization of PnFNext developement and testing $0.00 $704.34 $0.00 $704.34 0% $0.00 Erik Blaufuss 1.6.1.3.4 1 3392 Implement and testing of filtering SW for prod. systems
3394 1.6 1.6.1.3.5 New Online Filter Sys for SPS (readout New Sensors& Calib Devices Not Started C 5 1 1 0 11/13/25 11/13/25 11/13/25 4:59 PM 11/13/25 4:59 PM 3392 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.3.5 1 3393 New Online Filter Sys for SPS (readout New Sensors& Calib Devices
3395 1.6 1.6.1.3.6 New Online Filter Sys Deployment at SPS Not Started C 5 1 20d 11/14/25 12/12/25 11/14/25 8:00 AM 12/12/25 4:59 PM 3393 0% 0% Green delayed to match 25/26 deployment season $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.3.6 1 3394 New Online Filter Sys Deployment at SPS
3396 1.6 1.6.1.4 OM Software Started P 4 1 1880d 12/06/18 03/03/26 12/06/18 8:00 AM 03/03/26 4:59 PM 16% 31.00% Green $0.00 $1,800.00 $16,270.19 $102,520.19 16% $558.00 Erik Blaufuss 1.6.1.4 1 3395 OM Software
3397 1.6 1.6.1.4.1 Develop OM hardware-software high-level design Complete C 5 1 29d 12/06/18 01/15/19 12/06/18 8:00 AM 01/15/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.1 1 3396 Develop OM hardware-software high-level design
3398 1.6 1.6.1.4.2 Develop OM software development environment allowing cross-compilation on all OM types Complete C 5 1 63d 01/16/19 04/12/19 01/16/19 8:00 AM 04/12/19 4:59 PM 3396 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.2 1 3397 Develop OM software development environment allowing cross-compilation on all OM types
3399 1.6 1.6.1.4.3 OM testing software app Started P 5 1 1821d 01/16/19 01/20/26 01/16/19 8:00 AM 01/20/26 4:59 PM 22% 36.00% Green $0.00 $0.00 $13,171.10 $59,269.96 22% Erik Blaufuss 1.6.1.4.3 1 3398 OM testing software app
3400 1.6 1.6.1.4.3.1 Capture design requirements for OM testing app for DVT testing Complete C 6 1 34d 01/16/19 03/04/19 01/16/19 8:00 AM 03/04/19 4:59 PM 3396 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.1 1 3399 Capture design requirements for OM testing app for DVT testing
3401 1.6 1.6.1.4.3.2 Software design and prototyping of OM testing app Complete P 6 1 92d 03/04/19 07/09/19 03/04/19 8:00 AM 07/09/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.2 1 3400 Software design and prototyping of OM testing app
3402 1.6 1.6.1.4.3.2.1 Specify and implement interfaces from MCU to In-OM devices Complete C 7 1 92d 03/04/19 07/09/19 03/04/19 8:00 AM 07/09/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.2.1 1 3401 Specify and implement interfaces from MCU to In-OM devices
3403 1.6 1.6.1.4.3.2.2 Specify and implanent interface to from MCU to ICM Complete C 7 1 58d 03/04/19 05/22/19 03/04/19 8:00 AM 05/22/19 4:59 PM 3401SS 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.2.2 1 3402 Specify and implanent interface to from MCU to ICM
3404 1.6 1.6.1.4.3.3 Develop and test OM testing app for DV testing Complete C 6 1 124d 05/01/19 10/21/19 05/01/19 8:00 AM 10/21/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.3 1 3403 Develop and test OM testing app for DV testing
3405 1.6 1.6.1.4.3.4 OM testing app for DV testing ready Complete C 6 1 1 1d 10/22/19 10/22/19 10/22/19 8:00 AM 10/22/19 4:59 PM 3403 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.4 1 3404 OM testing app for DV testing ready
3406 1.6 1.6.1.4.3.4.1 Capture design requirements for FAT testing OM software Complete C 6 1 66d 10/23/19 01/22/20 10/23/19 8:00 AM 01/22/20 4:59 PM 3404 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.4.1 1 3405 Capture design requirements for FAT testing OM software
3407 1.6 1.6.1.4.3.5 Develop and test OM testing app for FAT testing Complete C 6 1 111d 01/23/20 06/25/20 01/23/20 8:00 AM 06/25/20 4:59 PM 3405 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.5 1 3406 Develop and test OM testing app for FAT testing
3408 1.6 1.6.1.4.3.6 OM testing app for FAT testing ready Complete C 6 1 1 1d 06/26/20 06/26/20 06/26/20 8:00 AM 06/26/20 4:59 PM 3406 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.6 1 3407 OM testing app for FAT testing ready
3409 1.6 1.6.1.4.3.7 Extend OM testing app for mDOM, pDOM devices Complete C 6 1 110d 06/29/20 11/27/20 06/29/20 8:00 AM 11/27/20 4:59 PM 3407 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.7 1 3408 Extend OM testing app for mDOM, pDOM devices
3410 1.6 1.6.1.4.3.8 Support OM testing app thru FAT testing cycles Started C 6 1 740d 11/30/20 09/29/23 11/30/20 8:00 AM 09/29/23 4:59 PM 3408 25% 25.00% Green new end date for mDOM FAT $13,171.10 $52,684.41 $13,171.10 $52,684.41 25% $13,171.10 Erik Blaufuss 1.6.1.4.3.8 1 3409 Support OM testing app thru FAT testing cycles
3411 1.6 1.6.1.4.3.9 Develop SPAT testing software design and plan Not Started C 6 1 87d 01/31/22 05/31/22 01/31/22 8:00 AM 05/31/22 4:59 PM 0% 0% Green $0.00 $6,585.55 $0.00 $6,585.55 0% $0.00 Erik Blaufuss 1.6.1.4.3.9 1 3410 Develop SPAT testing software design and plan
3412 1.6 1.6.1.4.3.9.1 Extend OM testing app to include support for MMB based special devices Not Started C 6 1 160d 10/01/22 05/11/23 10/01/22 8:00 AM 05/11/23 4:59 PM 0% 0% Green tie to MMB delivery...DW will provide $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.9.1 1 3411 Extend OM testing app to include support for MMB based special devices
3413 1.6 1.6.1.4.3.9.2 Support OM testing app thru calibration device DVT and FAT testing Not Started C 6 1 267d 05/12/23 05/23/24 05/12/23 8:00 AM 05/23/24 4:59 PM 3411 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.9.2 1 3412 Support OM testing app thru calibration device DVT and FAT testing
3414 1.6 1.6.1.4.3.10 Prototype and test SPAT testing software at NTS Not Started C 6 1 77d 01/15/24 04/30/24 01/15/24 8:00 AM 04/30/24 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.10 1 3413 Prototype and test SPAT testing software at NTS
3415 1.6 1.6.1.4.3.10.1 Review SPAT testing plans for Pole Not Started C 6 1 1 1 1d 06/12/24 06/12/24 06/12/24 8:00 AM 06/12/24 4:59 PM 3413FS +30d 0% 0% Green Let's review SPAT plan before we start. $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.10.1 1 3414 Review SPAT testing plans for Pole
3416 1.6 1.6.1.4.3.11 Prepare and ship SPAT toolset to Pole Not Started C 6 1 44d 05/01/24 07/01/24 05/01/24 8:00 AM 07/01/24 4:59 PM 0% 0% Green basic test equipment/computers, special cable and FH are elsewhere $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.11 1 3415 Prepare and ship SPAT toolset to Pole
3417 1.6 1.6.1.4.3.12 SPAT personnel arrives at NPX FS2 Not Started C 6 1 1 0 12/15/24 12/15/24 12/15/24 8:00 AM 12/15/24 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.12 1 3416 SPAT personnel arrives at NPX FS2
3418 1.6 1.6.1.4.3.13 SPAT testing preparation and execution at Pole FS2 Not Started C 6 1 46d 12/24/24 02/27/25 12/24/24 8:00 AM 02/27/25 4:59 PM 2035 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.13 1 3417 SPAT testing preparation and execution at Pole FS2
3419 1.6 1.6.1.4.3.14 SPAT personnel arrives at NPX FS3 Not Started C 6 1 1 0 11/20/25 11/20/25 11/20/25 8:00 AM 11/20/25 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.14 1 3418 SPAT personnel arrives at NPX FS3
3420 1.6 1.6.1.4.3.15 SPAT testing preparation and execution at Pole FS3 Not Started C 6 1 41d 11/20/25 01/20/26 11/20/25 8:00 AM 01/20/26 4:59 PM 3418 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.3.15 1 3419 SPAT testing preparation and execution at Pole FS3
3421 1.6 1.6.1.4.4 OM calibration software app Complete P 5 1 241d 02/03/20 01/04/21 02/03/20 8:00 AM 01/04/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.4 1 3420 OM calibration software app
3422 1.6 1.6.1.4.4.1 Capture design requirements for OM calibration collection app Complete C 6 1 30d 02/03/20 03/13/20 02/03/20 8:00 AM 03/13/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.4.1 1 3421 Capture design requirements for OM calibration collection app
3423 1.6 1.6.1.4.4.2 Software design and prototyping of OM data calibration app Complete C 6 1 35d 03/16/20 05/01/20 03/16/20 8:00 AM 05/01/20 4:59 PM 3421 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.4.2 1 3422 Software design and prototyping of OM data calibration app
3424 1.6 1.6.1.4.4.3 Develop and test OM data calibration app Complete C 6 1 175d 05/04/20 01/01/21 05/04/20 8:00 AM 01/01/21 4:59 PM 3422 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.4.3 1 3423 Develop and test OM data calibration app
3425 1.6 1.6.1.4.4.4 OM data calibration app ready for use Complete C 6 1 1 1d 01/04/21 01/04/21 01/04/21 8:00 AM 01/04/21 4:59 PM 3423 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.4.4 1 3424 OM data calibration app ready for use
3426 1.6 1.6.1.4.5 OM data collection app Started P 5 1 1362d 12/01/20 03/03/26 12/01/20 8:00 AM 03/03/26 4:59 PM 0% 16.00% Green $0.00 $0.00 $0.00 $22,855.74 0% Erik Blaufuss 1.6.1.4.5 1 3425 OM data collection app
3427 1.6 1.6.1.4.5.1 xDOMapp design development Complete C 6 1 229d 12/01/20 10/15/21 12/01/20 8:00 AM 10/15/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.1 1 3426 xDOMapp design development
3428 1.6 1.6.1.4.5.2 xDOMapp software and firmware design review Complete C 6 1 1 0 10/28/21 10/28/21 10/28/21 4:59 PM 10/28/21 4:59 PM 3426FS +9d 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.2 1 3427 xDOMapp software and firmware design review
3429 1.6 1.6.1.4.5.3 Prototype xDOMapp development and testing at NTS Complete C 6 1 55d 10/29/21 01/13/22 10/29/21 8:00 AM 01/13/22 4:59 PM 3426FS +9d, 3427 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.3 1 3428 Prototype xDOMapp development and testing at NTS
3430 1.6 1.6.1.4.5.4 Verification of OM waveform processing with mDOM and DEgg” Not Started C 6 1 78d 06/15/22 09/30/22 06/15/22 8:00 AM 09/30/22 4:59 PM 08/30/22 0% 0% Green includes testing of in OM feature extraction and noise rate mitigations $0.00 $19,756.65 $0.00 $19,756.65 0% $0.00 Erik Blaufuss 1.6.1.4.5.4 1 3429 Verification of OM waveform processing with mDOM and DEgg”
3431 1.6 1.6.1.4.5.4.1 Develop and test xDOMapp data collection app Not Started C 6 1 150d 10/03/22 04/28/23 10/03/22 8:00 AM 04/28/23 4:59 PM 3429 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.4.1 1 3430 Develop and test xDOMapp data collection app
3432 1.6 1.6.1.4.5.4.2 Support integration work and testing with DAQ Data Collector component’ Not Started C 6 1 332d 05/01/23 08/09/24 05/01/23 8:00 AM 08/09/24 4:59 PM 3430 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.4.2 1 3431 Support integration work and testing with DAQ Data Collector component’
3433 1.6 1.6.1.4.5.4.3 Extend xDOMapp to include support for calibration devices in operations Not Started C 6 1 190d 08/25/23 05/21/24 08/25/23 8:00 AM 05/21/24 4:59 PM 3350SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.4.3 1 3432 Extend xDOMapp to include support for calibration devices in operations
3434 1.6 1.6.1.4.5.4.4 Develop and test xDOMapp support for SPAT testing at NTS Not Started C 6 1 77d 01/15/24 04/30/24 01/15/24 8:00 AM 04/30/24 4:59 PM 3413SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.4.4 1 3433 Develop and test xDOMapp support for SPAT testing at NTS
3435 1.6 1.6.1.4.5.4.5 OM data collection app ready for use in SPAT/NTS Not Started C 6 1 1d 06/12/24 06/12/24 06/12/24 8:00 AM 06/12/24 4:59 PM 3433FS +30d 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.4.5 1 3434 OM data collection app ready for use in SPAT/NTS
3436 1.6 1.6.1.4.5.4.6 Support full DAQ testing with xDOMapp at NTS/SPTS with OM devices Not Started C 6 1 188d 03/27/25 12/16/25 03/27/25 8:00 AM 12/16/25 4:59 PM 3373SS 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.4.6 1 3435 Support full DAQ testing with xDOMapp at NTS/SPTS with OM devices
3437 1.6 1.6.1.4.5.5 Review OM data collection app in detector operations Not Started C 6 1 1 0 04/28/23 04/28/23 04/28/23 4:59 PM 04/28/23 4:59 PM 3430 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.5 1 3436 Review OM data collection app in detector operations
3438 1.6 1.6.1.4.5.6 Support full DAQ testing with xDOMapp at NTS/SPTS with Calibration devices Not Started C 6 1 154d 07/21/25 02/24/26 07/21/25 8:00 AM 02/24/26 4:59 PM 3354SS 0% 0% Green $0.00 $3,099.08 $0.00 $3,099.08 0% $0.00 Erik Blaufuss 1.6.1.4.5.6 1 3437 Support full DAQ testing with xDOMapp at NTS/SPTS with Calibration devices
3439 1.6 1.6.1.4.5.7 OM data collection app ready for use at SPS with full DAQ Not Started C 6 1 1 0 12/16/25 12/16/25 12/16/25 4:59 PM 12/16/25 4:59 PM 3435 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.7 1 3438 OM data collection app ready for use at SPS with full DAQ
3440 1.6 1.6.1.4.5.8 Support xDOMapp through SPAT testing and deployment Not Started C 6 1 316d 12/10/24 03/03/26 12/10/24 8:00 AM 03/03/26 4:59 PM 3417SS -10d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.5.8 1 3439 Support xDOMapp through SPAT testing and deployment
3441 1.6 1.6.1.4.6 MMB support software Started P 5 1 1157d 06/01/21 11/13/25 06/01/21 8:00 AM 11/13/25 4:59 PM 17% 20.0% Green $0.00 $0.00 $3,099.08 $18,594.50 17% Erik Blaufuss 1.6.1.4.6 1 3440 MMB support software
3442 1.6 1.6.1.4.6.1 Develop and test MMB software package on prototype MMB Complete C 6 1 109d 06/01/21 10/29/21 06/01/21 8:00 AM 10/29/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.6.1 1 3441 Develop and test MMB software package on prototype MMB
3443 1.6 1.6.1.4.6.2 Review MMB xDOMapp design Complete C 6 1 1 1d 11/01/21 11/01/21 11/01/21 8:00 AM 11/01/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.6.2 1 3442 Review MMB xDOMapp design
3444 1.6 1.6.1.4.6.3 Complete MMB software support package for calibration devices Not Started C 6 1 88d 05/13/22 09/13/22 05/13/22 8:00 AM 09/13/22 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.6.3 1 3443 Complete MMB software support package for calibration devices
3445 1.6 1.6.1.4.6.4 MMB support software ready for calibration device testing at NTS Not Started C 6 1 1 0 09/13/22 09/13/22 09/13/22 8:00 AM 09/13/22 8:00 AM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.4.6.4 1 3444 MMB support software ready for calibration device testing at NTS
3446 1.6 1.6.1.4.6.5 Support MMB software for calibration device interface development Not Started C 6 1 360d 06/25/24 11/13/25 06/25/24 8:00 AM 11/13/25 4:59 PM 3350FS +24d 17% 0% Yellow $3,099.08 $18,594.50 $3,099.08 $18,594.50 17% $0.00 Erik Blaufuss 1.6.1.4.6.5 1 3445 Support MMB software for calibration device interface development
3447 1.6 1.6.1.5 FieldHub Software Started P 4 1 1362d 01/01/21 04/03/26 01/01/21 8:00 AM 04/03/26 4:59 PM 13% 26.00% Green $0.00 $0.00 $3,169.52 $25,039.18 13% Erik Blaufuss 1.6.1.5 1 3446 FieldHub Software
3448 1.6 1.6.1.5.1 maintenance of mini-FieldHub server software for FAT Started C 5 1 716d 01/01/21 09/29/23 01/01/21 8:00 AM 09/29/23 4:59 PM 67% 60.0% Yellow new end of FAT testing $3,169.52 $4,754.27 $3,169.52 $4,754.27 67% $2,852.56 Erik Blaufuss 1.6.1.5.1 1 3447 maintenance of mini-FieldHub server software for FAT
3449 1.6 1.6.1.5.2 development and testing of FieldHub SBC OS and toolchain Complete C 5 1 44d 06/01/21 07/30/21 06/01/21 8:00 AM 07/30/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.5.2 1 3448 development and testing of FieldHub SBC OS and toolchain
3450 1.6 1.6.1.5.2.1 Verification of Field Hub throughput on fully populated strings Not Started C 5 1 144d 03/01/22 09/16/22 03/01/22 8:00 AM 09/16/22 4:59 PM 0% 0% Green retire FH throughput risks in FH design $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.5.2.1 1 3449 Verification of Field Hub throughput on fully populated strings
3451 1.6 1.6.1.5.2.2 FieldHub SBC OS preparation and testing Not Started C 5 1 70d 11/01/22 02/06/23 11/01/22 8:00 AM 02/06/23 4:59 PM 3057FS -24d 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.5.2.2 1 3450 FieldHub SBC OS preparation and testing
3452 1.6 1.6.1.5.3 Modification of FieldHub server software to support full FieldHub functionality Not Started C 5 1 164d 09/19/22 05/04/23 09/19/22 8:00 AM 05/04/23 4:59 PM 3449 0% 0% Green $0.00 $20,284.91 $0.00 $20,284.91 0% $0.00 Erik Blaufuss 1.6.1.5.3 1 3451 Modification of FieldHub server software to support full FieldHub functionality
3453 1.6 1.6.1.5.3.1 Field Hub Software ready for use on FH hardware at NTS Not Started C 5 1 1 0 05/05/23 05/05/23 05/05/23 4:59 PM 05/05/23 4:59 PM 3451, 3059 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.5.3.1 1 3452 Field Hub Software ready for use on FH hardware at NTS
3454 1.6 1.6.1.5.4 Review Field Hub software in Upgrade detector operations Not Started C 5 1 1 0 05/18/23 05/18/23 05/18/23 8:00 AM 05/18/23 8:00 AM 0% 0% Green review - major milestone $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.5.4 1 3453 Review Field Hub software in Upgrade detector operations
3455 1.6 1.6.1.5.5 Development of FieldHub monitoring software (IceCube Live interface) Not Started C 5 1 211d 01/28/24 11/15/24 01/28/24 8:00 AM 11/15/24 4:59 PM 03/26/24 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.5.5 1 3454 Development of FieldHub monitoring software (IceCube Live interface)
3456 1.6 1.6.1.5.5.1 Software available to support FieldHub installation and testing at Pole Not Started C 5 1 1 0 11/15/24 11/15/24 11/15/24 4:59 PM 11/15/24 4:59 PM 3454 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.5.5.1 1 3455 Software available to support FieldHub installation and testing at Pole
3457 1.6 1.6.1.5.6 support of FieldHub / pDAQ Data Collector interface layer with pDAQ development Not Started C 5 1 290d 03/26/24 05/08/25 03/26/24 8:00 AM 05/08/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.5.6 1 3456 support of FieldHub / pDAQ Data Collector interface layer with pDAQ development
3458 1.6 1.6.1.5.7 suopport FieldHub and SBC software system thru DAQ deployment and String commissioning Not Started C 5 1 152d 09/01/25 04/03/26 09/01/25 8:00 AM 04/03/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.5.7 1 3457 suopport FieldHub and SBC software system thru DAQ deployment and String commissioning
3459 1.6 1.6.1.6 OM Firmware support (PSU) Started P 4 1 1902d 12/17/18 04/13/26 12/17/18 8:00 AM 04/13/26 4:59 PM 26% 63.00% Green $3,213.86 $3,213.86 $7,304.24 $27,756.10 26% $2,024.73 Erik Blaufuss 1.6.1.6 1 3458 OM Firmware support (PSU)
3460 1.6 1.6.1.6.1 mDOM DAQ Electronics Complete P 5 1 729d 12/17/18 09/30/21 12/17/18 8:00 AM 09/30/21 4:59 PM 0% 100% Gray $0.00 $0.00 $0.00 $4,090.37 0% Erik Blaufuss 1.6.1.6.1 1 3459 mDOM DAQ Electronics
3461 1.6 1.6.1.6.1.1 Preliminary design phase Complete P 6 1 70d 12/17/18 03/22/19 12/17/18 8:00 AM 03/22/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.1.1 1 3460 Preliminary design phase
3462 1.6 1.6.1.6.1.1.1 Build 4 ch. analog-front end (AFE) demonstrator board Complete C 7 1 50d 12/17/18 02/22/19 12/17/18 8:00 AM 02/22/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.1.1.1 1 3461 Build 4 ch. analog-front end (AFE) demonstrator board
3463 1.6 1.6.1.6.1.1.2 Characterization of AFE performance Complete C 7 1 20d 02/25/19 03/22/19 02/25/19 8:00 AM 03/22/19 4:59 PM 3461 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.1.1.2 1 3462 Characterization of AFE performance
3464 1.6 1.6.1.6.1.2 mDOM Mainboard firmware development Complete C 6 1 1 456d 01/02/20 09/30/21 01/02/20 8:00 AM 09/30/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.1.2 1 3463 mDOM Mainboard firmware development
3465 1.6 1.6.1.6.1.3 Pulsed Laser Test Stand for Design verification Complete C 6 1 20d 06/07/21 07/02/21 06/07/21 8:00 AM 07/02/21 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.1.3 1 3464 Pulsed Laser Test Stand for Design verification
3466 1.6 1.6.1.6.1.4 Tender and procurement (series production) Complete C 6 1 200d 04/22/20 01/26/21 04/22/20 8:00 AM 01/26/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.1.4 1 3465 Tender and procurement (series production)
3467 1.6 1.6.1.6.1.5 mDOM mainboard firmware support for FAT testing Complete C 6 30d 07/26/21 09/03/21 07/26/21 8:00 AM 09/03/21 4:59 PM 0% 100% Gray $0.00 $4,090.37 $0.00 $4,090.37 0% $4,090.37 Erik Blaufuss 1.6.1.6.1.5 1 3466 mDOM mainboard firmware support for FAT testing
3468 1.6 1.6.1.6.2 D-Egg - PSU Complete P 5 501d 05/01/19 03/31/21 05/01/19 8:00 AM 03/31/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.2 1 3467 D-Egg - PSU
3469 1.6 1.6.1.6.2.1 Firmware development Complete C 6 501d 05/01/19 03/31/21 05/01/19 8:00 AM 03/31/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.2.1 1 3468 Firmware development
3470 1.6 1.6.1.6.2.2 Testing Complete C 6 50d 12/19/19 02/26/20 12/19/19 8:00 AM 02/26/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.2.2 1 3469 Testing
3471 1.6 1.6.1.6.3 Integrated D-Egg - PSU Complete P 5 40d 11/11/19 01/03/20 11/11/19 8:00 AM 01/03/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.3 1 3470 Integrated D-Egg - PSU
3472 1.6 1.6.1.6.3.1 Design Verification Test Complete C 6 40d 11/11/19 01/03/20 11/11/19 8:00 AM 01/03/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.3.1 1 3471 Design Verification Test
3473 1.6 1.6.1.6.3.2 Integrated D-Egg Final Design Review Complete C 6 1 1d 11/25/19 11/25/19 11/25/19 8:00 AM 11/25/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.3.2 1 3472 Integrated D-Egg Final Design Review
3474 1.6 1.6.1.6.4 PDOM DAQ Electronics - PSU Started P 5 1 916d 03/01/19 09/02/22 03/01/19 8:00 AM 09/02/22 4:59 PM 20% 55.00% Green $0.00 $0.00 $4,090.37 $20,451.86 20% Erik Blaufuss 1.6.1.6.4 1 3473 PDOM DAQ Electronics - PSU
3475 1.6 1.6.1.6.4.1 Firmware Complete C 6 1 100d 03/01/19 07/18/19 03/01/19 8:00 AM 07/18/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.4.1 1 3474 Firmware
3476 1.6 1.6.1.6.4.2 Testing - Rev2 Complete C 6 1 75d 07/19/19 10/31/19 07/19/19 8:00 AM 10/31/19 4:59 PM 3474 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.4.2 1 3475 Testing - Rev2
3477 1.6 1.6.1.6.4.3 Testing - Rev3 Complete C 6 1 30d 11/12/21 12/23/21 11/12/21 8:00 AM 12/23/21 4:59 PM 20% 100% Gray $4,090.37 $20,451.86 $4,090.37 $20,451.86 20% $20,451.86 Erik Blaufuss 1.6.1.6.4.3 1 3476 Testing - Rev3
3478 1.6 1.6.1.6.4.4 Adapt D-Egg Firmware to PDOM Mainboard and verify design Started C 6 1 207d 11/18/21 09/02/22 11/18/21 8:00 AM 09/02/22 4:59 PM 26% 11.00% Yellow $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.4.4 1 3477 Adapt D-Egg Firmware to PDOM Mainboard and verify design
3479 1.6 1.6.1.6.4.5 PDOM Final Design Review - FW Not Started C 6 1 1 0 09/02/22 09/02/22 09/02/22 4:59 PM 09/02/22 4:59 PM 3477 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.4.5 1 3478 PDOM Final Design Review - FW
3480 1.6 1.6.1.6.5 Special Devices - PSU Complete P 5 437d 05/01/20 01/03/22 05/01/20 8:00 AM 01/03/22 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.5 1 3479 Special Devices - PSU
3481 1.6 1.6.1.6.5.1 R&D module mission review Complete C 6 1d 05/01/20 05/01/20 05/01/20 8:00 AM 05/01/20 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.5.1 1 3480 R&D module mission review
3482 1.6 1.6.1.6.5.2 R&D modules deployment readiness review Complete C 6 1 1d 01/03/22 01/03/22 01/03/22 8:00 AM 01/03/22 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.5.2 1 3481 R&D modules deployment readiness review
3483 1.6 1.6.1.6.6 Firmware device maintenance and support for all OM devices during DAQ Development Not Started C 5 1 913d 10/01/22 04/13/26 10/01/22 8:00 AM 04/13/26 4:59 PM 0% Green Bugfix and feature requests for all device FPGA FW from Tyler (10% FTE 22/3 then 5% ) $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.1.6.6 1 3482 Firmware device maintenance and support for all OM devices during DAQ Development
3484 1.6 1.6.2 Offline Systems Started P 3 1 1891d 01/01/19 04/13/26 01/01/19 8:00 AM 04/13/26 4:59 PM 13% 42.00% Green $0.00 $0.00 $2,620.13 $19,920.80 13% Erik Blaufuss 1.6.2 1 3483 Offline Systems
3485 1.6 1.6.2.0 L3 Task Management Started C 4 1 1434d 10/01/20 04/13/26 10/01/20 8:00 AM 04/13/26 4:59 PM 06/28/24 17% 17.00% Green ramp down management effort early... $1,211.46 $7,268.76 $1,211.46 $7,268.76 17% $1,235.69 Erik Blaufuss 1.6.2.0 1 3484 L3 Task Management
3486 1.6 1.6.2.1 Core Software Started P 4 1 1271d 12/24/19 11/08/24 12/24/19 8:00 AM 11/08/24 4:59 PM 0% 82.00% Green $0.00 $1,800.00 $0.00 $1,800.00 0% $1,476.00 Erik Blaufuss 1.6.2.1 1 3485 Core Software
3487 1.6 1.6.2.1.1 Capture Required changes to IceTray software packages Complete C 5 1 25d 12/24/19 01/27/20 12/24/19 8:00 AM 01/27/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.1.1 1 3486 Capture Required changes to IceTray software packages
3488 1.6 1.6.2.1.2 Design updates to IceTray (support new optical sensor Data/Config/Calib Info) Complete C 5 1 25d 01/28/20 03/02/20 01/28/20 8:00 AM 03/02/20 4:59 PM 3486 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.1.2 1 3487 Design updates to IceTray (support new optical sensor Data/Config/Calib Info)
3489 1.6 1.6.2.1.3 Develop and test Updates to IceTray (support new optical sensor Data/Config/Calib Info) Complete C 5 1 434d 03/03/20 10/29/21 03/03/20 8:00 AM 10/29/21 4:59 PM 3487 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.1.3 1 3488 Develop and test Updates to IceTray (support new optical sensor Data/Config/Calib Info)
3490 1.6 1.6.2.1.4 Core Software Release Supporting Upgrade Complete C 5 1 1 0 10/29/21 10/29/21 10/29/21 4:59 PM 10/29/21 4:59 PM 3488 100% 100% Gray expected Dec 2021 $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.1.4 1 3489 Core Software Release Supporting Upgrade
3491 1.6 1.6.2.1.5 Extend Core Software to include support for new hardware readouts Not Started C 5 1 107d 06/13/24 11/08/24 06/13/24 8:00 AM 11/08/24 4:59 PM 10/15/24 3434 0% 0% Green 1650 $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.1.5 1 3490 Extend Core Software to include support for new hardware readouts
3492 1.6 1.6.2.1.6 Core Software Release for hardware readout support ready Not Started C 5 1 1 0 11/08/24 11/08/24 11/08/24 4:59 PM 11/08/24 4:59 PM 3490 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.1.6 1 3491 Core Software Release for hardware readout support ready
3493 1.6 1.6.2.2 Reconstruction Started P 4 1 1530d 05/12/20 04/03/26 05/12/20 8:00 AM 04/03/26 4:59 PM 80% 54.00% Red $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.2 1 3492 Reconstruction
3494 1.6 1.6.2.2.1 Capture Requirements for reconstruction software updates Complete C 5 1 25d 05/12/20 06/15/20 05/12/20 8:00 AM 06/15/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.2.1 1 3493 Capture Requirements for reconstruction software updates
3495 1.6 1.6.2.2.2 Design changes to IceCube Event Reconstruction Algorithms (use data from New Sensors&Calibr Info) Complete C 5 1 25d 06/16/20 07/20/20 06/16/20 8:00 AM 07/20/20 4:59 PM 3493 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.2.2 1 3494 Design changes to IceCube Event Reconstruction Algorithms (use data from New Sensors&Calibr Info)
3496 1.6 1.6.2.2.3 Develop and test Updates to IceCube Event Reconstruction Algorithms (use data from New Sensors&Calibr Info) Complete C 5 334d 07/21/20 10/29/21 07/21/20 8:00 AM 10/29/21 4:59 PM 3494 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.2.3 1 3495 Develop and test Updates to IceCube Event Reconstruction Algorithms (use data from New Sensors&Calibr Info)
3497 1.6 1.6.2.2.4 Reconstruction tools Release Supporting Upgrade Complete C 5 1 0 10/29/21 10/29/21 10/29/21 4:59 PM 10/29/21 4:59 PM 3495 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.2.4 1 3496 Reconstruction tools Release Supporting Upgrade
3498 1.6 1.6.2.2.5 Offline software support and testing for Upgrade low energy event reconstruction tools Not Started C 5 1 323d 01/05/25 04/03/26 01/05/25 8:00 AM 04/03/26 4:59 PM 0% Green New item to support LE reco tools needed ahead of Upgrade data analyses $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.2.5 1 3497 Offline software support and testing for Upgrade low energy event reconstruction tools
3499 1.6 1.6.2.3 Tools and Infrastructure Started P 4 1 1891d 01/01/19 04/13/26 01/01/19 8:00 AM 04/13/26 4:59 PM 13% 24.00% Green $0.00 $2,400.00 $1,408.67 $10,852.04 13% $576.00 Erik Blaufuss 1.6.2.3 1 3498 Tools and Infrastructure
3500 1.6 1.6.2.3.1 Evaluate readiness of Current IceCube SW Development Infrastructure to Support IceCube Upgrade SW Activities&TimeScales Complete C 5 1 64d 01/01/19 03/29/19 01/01/19 8:00 AM 03/29/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.3.1 1 3499 Evaluate readiness of Current IceCube SW Development Infrastructure to Support IceCube Upgrade SW Activities&TimeScales
3501 1.6 1.6.2.3.2 Upgrade IceCube SW Development Infrastructure to support Upgrade activities Complete C 5 1 87d 04/01/19 07/30/19 04/01/19 8:00 AM 07/30/19 4:59 PM 3499 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.2.3.2 1 3500 Upgrade IceCube SW Development Infrastructure to support Upgrade activities
3502 1.6 1.6.2.3.3 Support Upgrade SW Development environment and infrastructure Started C 5 1 1740d 07/31/19 04/13/26 07/31/19 8:00 AM 04/13/26 4:59 PM 3500 17% 17.00% Green new end: support through end of project. $1,408.67 $8,452.04 $1,408.67 $8,452.04 17% $1,436.85 Erik Blaufuss 1.6.2.3.3 1 3501 Support Upgrade SW Development environment and infrastructure
3503 1.6 1.6.3 Simulation Software Started P 3 1 1934d 11/01/18 04/13/26 11/01/18 8:00 AM 04/13/26 4:59 PM 41% 55.00% Green $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3 1 3502 Simulation Software
3504 1.6 1.6.3.0 L3 Task Management Started C 4 1434d 10/01/20 04/13/26 10/01/20 8:00 AM 04/13/26 4:59 PM 24% 29.00% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.0 1 3503 L3 Task Management
3505 1.6 1.6.3.1 Electronic readout and optical module simulation Started P 4 1514d 05/28/20 03/30/26 05/28/20 8:00 AM 03/30/26 4:59 PM 74% 85.00% Green $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.1 1 3504 Electronic readout and optical module simulation
3506 1.6 1.6.3.1.1 Capture requirements for Optical Sensor Simulation Tools based on Final Designs Complete C 5 25d 05/28/20 07/01/20 05/28/20 8:00 AM 07/01/20 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.1.1 1 3505 Capture requirements for Optical Sensor Simulation Tools based on Final Designs
3507 1.6 1.6.3.1.2 Design Optical Sensor Simulation Tools based on Final Designs Complete C 5 26d 07/02/20 08/06/20 07/02/20 8:00 AM 08/06/20 4:59 PM 3505 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.1.2 1 3506 Design Optical Sensor Simulation Tools based on Final Designs
3508 1.6 1.6.3.1.3 Version 1 - as designed Complete P 5 321d 08/07/20 10/29/21 08/07/20 8:00 AM 10/29/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.1.3 1 3507 Version 1 - as designed
3509 1.6 1.6.3.1.3.1 Implementation and testing Complete C 6 321d 08/07/20 10/29/21 08/07/20 8:00 AM 10/29/21 4:59 PM 3506 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.1.3.1 1 3508 Implementation and testing
3510 1.6 1.6.3.1.3.2 Release v1 simulation tools Complete C 6 1 0 10/29/21 10/29/21 10/29/21 4:59 PM 10/29/21 4:59 PM 3508 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.1.3.2 1 3509 Release v1 simulation tools
3511 1.6 1.6.3.1.4 Version 2 - as built Not Started P 5 65d 12/29/25 03/30/26 12/29/25 8:00 AM 03/30/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.1.4 1 3510 Version 2 - as built
3512 1.6 1.6.3.1.4.1 Capture Improvements of OM device Simulation Tools (w/testing, deployment&initial data collection) Not Started C 6 30d 12/29/25 02/09/26 12/29/25 8:00 AM 02/09/26 4:59 PM 3565FS -65d 0% 0% Green delayed as happens "as built"; depends on early input from string comm. $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.1.4.1 1 3511 Capture Improvements of OM device Simulation Tools (w/testing, deployment&initial data collection)
3513 1.6 1.6.3.1.4.2 Prepare and handoff needed details for as-built simulation final Implementation and testing Not Started C 6 53d 01/15/26 03/30/26 01/15/26 8:00 AM 03/30/26 4:59 PM 0% 0% Green delayed as happens "as built" $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.1.4.2 1 3512 Prepare and handoff needed details for as-built simulation final Implementation and testing
3514 1.6 1.6.3.1.4.3 As built device details delivered to IceCube simulation team for simulation implementation and testing Not Started C 6 1 0 03/30/26 03/30/26 03/30/26 4:59 PM 03/30/26 4:59 PM 3512 0% 0% Green delayed as happens "as built" $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.1.4.3 1 3513 As built device details delivered to IceCube simulation team for simulation implementation and testing
3515 1.6 1.6.3.2 Calibration Device simulation Not Started P 4 800d 03/01/23 04/06/26 03/01/23 8:00 AM 04/06/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.2 1 3514 Calibration Device simulation
3516 1.6 1.6.3.2.1 Capture requirements for Calibration device Simulation Tools based on Final Designs Not Started C 5 25d 03/01/23 04/04/23 03/01/23 8:00 AM 04/04/23 4:59 PM 0% 0% Green pred - special devices FDR $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.2.1 1 3515 Capture requirements for Calibration device Simulation Tools based on Final Designs
3517 1.6 1.6.3.2.2 Design Calibration Device Simulation Tools based on Final Designs Not Started C 5 80d 04/05/23 07/25/23 04/05/23 8:00 AM 07/25/23 4:59 PM 3515 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.2.2 1 3516 Design Calibration Device Simulation Tools based on Final Designs
3518 1.6 1.6.3.2.3 Version 1 - as designed Not Started P 5 74d 07/26/23 11/06/23 07/26/23 8:00 AM 11/06/23 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.2.3 1 3517 Version 1 - as designed
3519 1.6 1.6.3.2.3.1 Implementation and testing Not Started C 6 74d 07/26/23 11/06/23 07/26/23 8:00 AM 11/06/23 4:59 PM 3516 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.2.3.1 1 3518 Implementation and testing
3520 1.6 1.6.3.2.3.2 Release v1 calibration devicesimulation tools Not Started C 6 1 0 11/06/23 11/06/23 11/06/23 4:59 PM 11/06/23 4:59 PM 3518 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.2.3.2 1 3519 Release v1 calibration devicesimulation tools
3521 1.6 1.6.3.2.4 Version 2 - as built Not Started P 5 45d 02/03/26 04/06/26 02/03/26 8:00 AM 04/06/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.2.4 1 3520 Version 2 - as built
3522 1.6 1.6.3.2.4.1 Capture Improvements of Calibration device Simulation Tools (w/testing, deployment&initial data collection) Not Started C 6 23d 02/03/26 03/05/26 02/03/26 8:00 AM 03/05/26 4:59 PM 3571FS -45d 0% 0% Green delayed as happens "as built"; depends on early input from device comm. $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.2.4.1 1 3521 Capture Improvements of Calibration device Simulation Tools (w/testing, deployment&initial data collection)
3523 1.6 1.6.3.2.4.2 Prepare and handoff needed details for as-built simulation final Implementation and testing Not Started C 6 22d 03/06/26 04/06/26 03/06/26 8:00 AM 04/06/26 4:59 PM 3521 0% 0% Green delayed as happens "as built" $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.2.4.2 1 3522 Prepare and handoff needed details for as-built simulation final Implementation and testing
3524 1.6 1.6.3.2.4.3 As built device details delivered to IceCube simulation team for simulation implementation and testing Not Started C 6 1 0 04/06/26 04/06/26 04/06/26 4:59 PM 04/06/26 4:59 PM 3522 0% 0% Green delayed as happens "as built" $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.2.4.3 1 3523 As built device details delivered to IceCube simulation team for simulation implementation and testing
3525 1.6 1.6.3.3 Simulation production Started P 4 1 1925d 11/01/18 03/31/26 11/01/18 8:00 AM 03/31/26 4:59 PM 67% 75.00% Green $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.3 1 3524 Simulation production
3526 1.6 1.6.3.3.1 Initial Production of simulation samples for Design Studies Complete C 5 1 66d 11/01/18 01/31/19 11/01/18 8:00 AM 01/31/19 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.3.1 1 3525 Initial Production of simulation samples for Design Studies
3527 1.6 1.6.3.3.2 Design study simulation sample ready Complete C 5 1 1 0 01/31/19 01/31/19 01/31/19 4:59 PM 01/31/19 4:59 PM 3525 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.3.2 1 3526 Design study simulation sample ready
3528 1.6 1.6.3.3.3 Produce"as designed" Simulation Samples (for analysis tool development) Complete C 5 1 60d 11/01/21 01/21/22 11/01/21 8:00 AM 01/21/22 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.3.3 1 3527 Produce"as designed" Simulation Samples (for analysis tool development)
3529 1.6 1.6.3.3.4 “As designed” simulation sample ready Complete C 5 1 1 0 01/21/22 01/21/22 01/21/22 4:59 PM 01/21/22 4:59 PM 3527 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.3.4 1 3528 “As designed” simulation sample ready
3530 1.6 1.6.3.3.5 Develop tools for "As -Built"Simulation Samples for Data Quality Verification Studies Not Started C 5 1 43d 01/31/26 03/31/26 01/31/26 8:00 AM 03/31/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.3.5 1 3529 Develop tools for "As -Built"Simulation Samples for Data Quality Verification Studies
3531 1.6 1.6.3.3.6 Tools to provide “As Built” simulation sample ready Not Started C 5 1 1 0 03/31/26 03/31/26 03/31/26 4:59 PM 03/31/26 4:59 PM 3529 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.3.3.6 1 3530 Tools to provide “As Built” simulation sample ready
3532 1.6 1.6.4 Computing Infrastructure Started P 3 1 1868d 02/01/19 04/13/26 02/01/19 8:00 AM 04/13/26 4:59 PM 14% 29.00% Green $0.00 $0.00 $2,451.09 $16,906.56 14% Erik Blaufuss 1.6.4 1 3531 Computing Infrastructure
3533 1.6 1.6.4.0 L3 Task Management Started C 4 1 1434d 10/01/20 04/13/26 10/01/20 8:00 AM 04/13/26 4:59 PM 17% 7.00% Yellow $1,324.15 $7,944.92 $1,324.15 $7,944.92 17% $556.14 Erik Blaufuss 1.6.4.0 1 3532 L3 Task Management
3534 1.6 1.6.4.1 SPTS/NTS computing needs Started P 4 1 1868d 02/01/19 04/13/26 02/01/19 8:00 AM 04/13/26 4:59 PM 16% 36.00% Green $0.00 $500.00 $1,126.94 $7,261.64 16% $180.00 Erik Blaufuss 1.6.4.1 1 3533 SPTS/NTS computing needs
3535 1.6 1.6.4.1.1 NTS Started P 5 1 1868d 02/01/19 04/13/26 02/01/19 8:00 AM 04/13/26 4:59 PM 17% 21.00% Green $0.00 $0.00 $1,126.94 $6,761.64 17% Erik Blaufuss 1.6.4.1.1 1 3534 NTS
3536 1.6 1.6.4.1.1.1 Specify Requirements/Design NTS Computing Sys Complete C 6 1 20d 02/01/19 02/28/19 02/01/19 8:00 AM 02/28/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.1.1.1 1 3535 Specify Requirements/Design NTS Computing Sys
3537 1.6 1.6.4.1.1.2 Procure NTS Computing Hardware Complete C 6 1 21d 03/01/19 03/29/19 03/01/19 8:00 AM 03/29/19 4:59 PM 3535 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.1.1.2 1 3536 Procure NTS Computing Hardware
3538 1.6 1.6.4.1.1.3 Buildout NTS Computing System Complete C 6 1 45d 04/01/19 05/31/19 04/01/19 8:00 AM 05/31/19 4:59 PM 3536 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.1.1.3 1 3537 Buildout NTS Computing System
3539 1.6 1.6.4.1.1.4 NTS computing system complete Complete C 6 1 1 0 05/31/19 05/31/19 05/31/19 4:59 PM 05/31/19 4:59 PM 3537 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.1.1.4 1 3538 NTS computing system complete
3540 1.6 1.6.4.1.1.5 Refresh NTS HW to match SPS Not Started C 6 1 21d 04/01/25 04/29/25 04/01/25 8:00 AM 04/29/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.1.1.5 1 3539 Refresh NTS HW to match SPS
3541 1.6 1.6.4.1.1.6 Support NTS System Started C 6 1 1708d 09/15/19 04/13/26 09/15/19 8:00 AM 04/13/26 4:59 PM 17% 17.00% Green NTS support thru project $1,126.94 $6,761.64 $1,126.94 $6,761.64 17% $1,149.48 Erik Blaufuss 1.6.4.1.1.6 1 3540 Support NTS System
3542 1.6 1.6.4.1.2 SPTS Complete P 5 1 455d 01/06/20 10/01/21 01/06/20 8:00 AM 10/01/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.1.2 1 3541 SPTS
3543 1.6 1.6.4.1.2.1 Design/Specify SPTS Ext req'd to support Upgrade Activities Complete C 6 1 347d 01/06/20 05/04/21 01/06/20 8:00 AM 05/04/21 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.1.2.1 1 3542 Design/Specify SPTS Ext req'd to support Upgrade Activities
3544 1.6 1.6.4.1.2.2 Procure Computing Hardware for SPTS Ext Complete C 6 1 66d 05/05/21 08/04/21 05/05/21 8:00 AM 08/04/21 4:59 PM 3542 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.1.2.2 1 3543 Procure Computing Hardware for SPTS Ext
3545 1.6 1.6.4.1.2.3 Buildout SPTS Computing System for Ext(s) Complete C 6 1 42d 08/05/21 10/01/21 08/05/21 8:00 AM 10/01/21 4:59 PM 3543 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.1.2.3 1 3544 Buildout SPTS Computing System for Ext(s)
3546 1.6 1.6.4.1.2.4 SPTS computing system complete Complete C 6 1 1 0 10/01/21 10/01/21 10/01/21 4:59 PM 10/01/21 4:59 PM 3544 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.1.2.4 1 3545 SPTS computing system complete
3547 1.6 1.6.4.2 SPS computing needs Started P 4 1 1745d 05/01/19 01/19/26 05/01/19 8:00 AM 01/19/26 4:59 PM 0% 22.00% Green $0.00 $1,700.00 $0.00 $1,700.00 0% $374.00 Erik Blaufuss 1.6.4.2 1 3546 SPS computing needs
3548 1.6 1.6.4.2.1 Specify space and power needs for IDF design process Complete C 5 1 43d 05/01/19 06/28/19 05/01/19 8:00 AM 06/28/19 4:59 PM 99% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.2.1 1 3547 Specify space and power needs for IDF design process
3549 1.6 1.6.4.2.9 Design/Specify SPS Computing Sys Extensions for Upgrade Not Started C 5 1 44d 02/01/25 04/02/25 02/01/25 8:00 AM 04/02/25 4:59 PM 0% 0% Green deployment delayed $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.2.9 1 3548 Design/Specify SPS Computing Sys Extensions for Upgrade
3550 1.6 1.6.4.2.10 Procure Computing Sys for SPSExt Not Started C 5 1 21d 04/03/25 05/01/25 04/03/25 8:00 AM 05/01/25 4:59 PM 3548 0% 0% Green deployment delayed $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.2.10 1 3549 Procure Computing Sys for SPSExt
3551 1.6 1.6.4.2.11 Buildout and test SPS systems in North Not Started C 5 1 45d 05/02/25 07/03/25 05/02/25 8:00 AM 07/03/25 4:59 PM 3549 0% 0% Green deployment delayed $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.2.11 1 3550 Buildout and test SPS systems in North
3552 1.6 1.6.4.2.12 Ship Computing Sys for SPS Ext to Pole Not Started C 5 1 22d 07/04/25 08/04/25 07/04/25 8:00 AM 08/04/25 4:59 PM 3550 0% 0% Green deployment delayed $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.2.12 1 3551 Ship Computing Sys for SPS Ext to Pole
3553 1.6 1.6.4.2.13 Computing HW for SPS Ext Arrival at NPX Not Started C 5 1 1 0 12/13/25 12/13/25 12/13/25 8:00 AM 12/13/25 8:00 AM 0% 0% Green deployment delayed $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.2.13 1 3552 Computing HW for SPS Ext Arrival at NPX
3554 1.6 1.6.4.2.14 Installation at Pole Not Started C 5 1 24d 12/15/25 01/19/26 12/15/25 8:00 AM 01/19/26 4:59 PM 3552 0% 0% Green deployment delayed $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.2.14 1 3553 Installation at Pole
3555 1.6 1.6.4.2.15 SPS computing system for Upgrade complete at pole Not Started C 5 1 1 1 0 01/19/26 01/19/26 01/19/26 4:59 PM 01/19/26 4:59 PM 3553 0% 0% Green deployment delayed $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.2.15 1 3554 SPS computing system for Upgrade complete at pole
3556 1.6 1.6.4.3 Distributed computing needs Started P 4 1 1141d 11/03/21 03/31/26 11/03/21 8:00 AM 03/31/26 4:59 PM 50% 58.00% Green $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.3 1 3555 Distributed computing needs
3557 1.6 1.6.4.3.1 Support Upgrade Distributed Mass Production - as designed Complete C 5 1 60d 11/03/21 01/25/22 11/03/21 8:00 AM 01/25/22 4:59 PM 100% 100% Gray $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.3.1 1 3556 Support Upgrade Distributed Mass Production - as designed
3558 1.6 1.6.4.3.2 Prepare Distributed Mass Production for"As Built" Detector Verification Not Started C 5 1 43d 02/01/26 03/31/26 02/01/26 8:00 AM 03/31/26 4:59 PM 0% 0% Green deployment delayed $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.4.3.2 1 3557 Prepare Distributed Mass Production for"As Built" Detector Verification
3559 1.6 1.6.5 Upgrade String Commissioning Not Started P 3 1 326d 01/01/25 04/06/26 01/01/25 8:00 AM 04/06/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5 1 3558 Upgrade String Commissioning
3560 1.6 1.6.5.0 L3 Task Management Not Started C 4 1 325d 01/01/25 04/03/26 01/01/25 8:00 AM 04/03/26 4:59 PM 0% 0% Green dedicated L3 effort not needed until 2025 activities $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.0 1 3559 L3 Task Management
3561 1.6 1.6.5.1 Upgrade OM module commissioning Not Started P 4 1 257d 04/01/25 03/30/26 04/01/25 8:00 AM 03/30/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.1 1 3560 Upgrade OM module commissioning
3562 1.6 1.6.5.1.1 Develop and review OM module commissioning plan Not Started C 5 1 87d 04/01/25 07/30/25 04/01/25 8:00 AM 07/30/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.1.1 1 3561 Develop and review OM module commissioning plan
3563 1.6 1.6.5.1.2 Review OM module commissioning plan Not Started C 5 1 1 0 07/30/25 07/30/25 07/30/25 4:59 PM 07/30/25 4:59 PM 3561 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.1.2 1 3562 Review OM module commissioning plan
3564 1.6 1.6.5.1.3 Develop software needed for OM commissioning Not Started C 5 1 108d 07/31/25 12/31/25 07/31/25 8:00 AM 12/31/25 4:59 PM 09/30/25 3562 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.1.3 1 3563 Develop software needed for OM commissioning
3565 1.6 1.6.5.1.4 Commission newly deployed OMs following deployment Not Started C 5 1 1 83d 12/02/25 03/30/26 12/02/25 8:00 AM 03/30/26 4:59 PM 2148SS -14d 0% 0% Green need pred: + string deployment $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.1.4 1 3564 Commission newly deployed OMs following deployment
3566 1.6 1.6.5.1.5 Deliver commissioned OMs to detector operations team for integration Not Started C 5 1 1 1 0 03/30/26 03/30/26 03/30/26 4:59 PM 03/30/26 4:59 PM 3564 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.1.5 1 3565 Deliver commissioned OMs to detector operations team for integration
3567 1.6 1.5.5.2 Upgrade calibration device commissioning Not Started P 4 1 197d 07/01/25 04/06/26 07/01/25 8:00 AM 04/06/26 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.5.5.2 1 3566 Upgrade calibration device commissioning
3568 1.6 1.6.5.2.1 Develop and review calibration device commissioning plan Not Started C 5 1 46d 07/01/25 09/02/25 07/01/25 8:00 AM 09/02/25 4:59 PM 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.2.1 1 3567 Develop and review calibration device commissioning plan
3569 1.6 1.6.5.2.2 Review calibration device commissioing plan Not Started C 5 1 1 0 09/02/25 09/02/25 09/02/25 4:59 PM 09/02/25 4:59 PM 3567 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.2.2 1 3568 Review calibration device commissioing plan
3570 1.6 1.6.5.2.3 Develop software needed for calibration device commissioning Not Started C 5 1 85d 09/03/25 01/02/26 09/03/25 8:00 AM 01/02/26 4:59 PM 11/02/23 3568 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.2.3 1 3569 Develop software needed for calibration device commissioning
3571 1.6 1.6.5.2.4 Commission newly deployed calibration devices following deployment Not Started C 5 1 1 77d 12/17/25 04/06/26 12/17/25 8:00 AM 04/06/26 4:59 PM 2148SS -3d 0% 0% Green need pred: + string deployment $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.2.4 1 3570 Commission newly deployed calibration devices following deployment
3572 1.6 1.6.5.2.5 Deliver commissioned calibration devices to detector operations team for integration Not Started C 5 1 1 1 0 04/06/26 04/06/26 04/06/26 4:59 PM 04/06/26 4:59 PM 3570 0% 0% Green $0.00 $0.00 $0.00 $0.00 $0.00 Erik Blaufuss 1.6.5.2.5 1 3571 Deliver commissioned calibration devices to detector operations team for integration
3573

Back to top


  A B C D
1 Row 3319 *OCT 2021 update*
ON PROJECT
- Continued device software support for FAT and DVT testing of DEgg, mDOM and pDOM hardware, including:
- initial support for pDOM devices
- on-board camera interface debugging and improvements

OFF PROJECT
- Continued testing infrastructure support for FAT and DVT testing of DEgg, mDOM and pDOM hardware.
- FieldHub software developement with SBC prototypes
- continued development and testing for "As-designed" simulation data samples
Erik Blaufuss 11/05/21 8:26 AM
2        
3        
4 Row 3319 April 2020 Status update:
- Continued progress on DEgg mainboard software for FAT testing
- Refinement of FAT and DVT test database and display tools
Erik Blaufuss 05/04/20 2:10 PM
5        
6        
7 Row 3319 Mar 2020 Status Update
- Continued DVT testing support for Rev4 DEgg mainboard at Chiba
- DVT/FAT testing results DB and visualization tools prototype now in use
- Continued development of software tools for FAT testing of DEggs
Erik Blaufuss 04/03/20 12:44 PM
8        
9        
10 Row 3319 Feb 2020 status update:
- Supported DVT testing software for DEgg test modules through final design review
-- Held DEgg FAT workshop - pushed FAT plan toward maturity.
- Developing IceTray software framework extensions for IceCube Upgrade support.
Erik Blaufuss 03/03/20 1:44 PM
11        
12        
13 Row 3319 Jan 2019 status updates:
- STF testing framework complete and in use for ongoing DVT D-Egg testing
- Providing software support for DVT acitivities fpr D-Egg sensors.
- Ongoing planning for D-Egg FAT activities and needed software
Erik Blaufuss 02/04/20 11:28 AM
14        
15        
16 Row 3319 Dec 2019 Status updates:
- STF testing framework for DVT testing nearing completion for use in testing programs
- Integration of Rev3 DEgg main boards into testing systems.
- Support for all DEgg Mainboard components within MB software package.
Erik Blaufuss 01/05/20 6:09 PM
17        
18        
19 Row 3319 Nov 2019 Status updates:
- Integration work of D-Egg Component devices with Mainboard control and readout software progressing well. Expect to have support for all on-board devices ready for testing suites by end of year
- Preparations continue on DVT D-Egg software testing suite for Rev3 D-Egg mainboard and full device testing.
Erik Blaufuss 12/03/19 11:37 AM
20        
21        
22 Row 3319 Oct 2019 Status updates:
- NTS computing environment setup and integration with the SPTS system at U-Wisconsin complete
- D-Egg mainboard software development progressing with focus on integrating all D-Egg system components
- Preparing integrated software testing suite for rev3 and production D-Egg mainboard design verification and testing
Erik Blaufuss 11/04/19 10:43 AM
23        
24        
25 Row 3319 • Developing software testing environment for first item DEgg mainboards
• Developing optical module testing and verification plans for design verification and final acceptance testing phases
• Evaluating IceCube analysis and simulation software for readiness to handle Upgrade sensors and calibration devices
• We have first versions of the OM-DAQ interfaces that will reside within the OM on-board software and more advanced design work is underway to implement and test these with the first article DEgg electronic mainboards.
Catherine Vakhnina 07/16/19 2:19 PM
26        
27        
28 Sheet WBS 1.5 Update for October 2021

On project: WBS 1.5 L2 manager Dawn Williams began discussions on gathering calibration constants from mDOM and D-egg PMTs

Off project: Cameras on mDOMs had a readout issue due to slow ramp-up of a voltage regulator. A software fix has been identified for this so that the camera firmware will not need to be reprogrammed.

Mini-mainboard requirements discussions continue.
Dawn Williams 11/05/21 4:40 PM
29        
30        
31 Sheet May 2020 Updated 1.6:
- Development of DEgg FAT testing software progressing, including: data collection software, database storage of results, and visualization tools in preparation for start of DEgg FAT testing this summer.
- First version of interface definition between MCU and ICM software available.
Erik Blaufuss 06/03/20 8:02 AM
32        
33        
34 Sheet May 2020 report for 1.5

There is an issue with one of the flasher parts for the mDOM: the NTE2403 5 GHz wideband PNP transistor is a Critical component for flasher performance. The part is not currently available in Europe, cost is 3.10 USD / pc. in the US. Possible drop-in replacement is BFT92,215. This is a discontinued part, but 186,000 pcs. in stock at AVNET Europe at a cost of 0.158 EUR / pc. Would save 15 kEUR to the project but rely on a discontinued part and mean the electronics are not identical for D-egg and mDOM flashers since the NTE2403 is already procured for the D-egg. To evaluate the new part, the mDOM DVT PCB panel features 220 flashers but only 120 are needed for DVT mDOMs (incl. spares). We will populate the other 100 flashers on the panel assuming the BFT92 can be used as a direct drop-in-replacement for the NTE2403. These will then be tested in comparison to the default boards.

Flasherboard testing (FLAT) electronics are assembled in a custom / easily accessible dark box.
Cabling, software still being prepared. Electronics are being adapted for D-egg flasher testing.

Integrating cameras into the batch 1 D-eggs before sealing is a potential issue since this was going to rely on people traveling from SKKU to Chiba, but there are still travel restrictions due to COVID 19 for the foreseeable future.

We expect to have prototype of the mini-mainboard out in a couple of weeks for the POCAM, PencilBeam and Acoustic teams to evaluate. After that we will begin planning the Acoustic module review.

The acoustic combined receiver/pinger module is being developed: acoustic sensors with variable gain between 50 dB and 70 dB at bandwidths up to 38 kHz. The positioning of the acoustic sensors was validated with a trilateration measurement in a swimming pool with an average deviation of 5 cm from the expected positions; acoustic positioning improves with chirp signal.

For the POCAM, testing of all 8 Housings and ordering the remaining 22 housings is expected in June. By the end of the year, all boards should be ready, the first complete module should be ready, and the calibration setup will be ready for underwater
isotropy measurement. A POCAM paper has been submitted to JINST.


The Swedish camera was added to project geometry as part of updating the upgrade string design. Scope is currently at 5 cameras in the physics region of the detector.
Dawn Williams 06/02/20 5:07 PM
35        
36        
37 Sheet May 2020 status update for 1.4:
* first iteration of ICM / MCU / SoC software/firmware interface defined with preliminary documentation available
* initial version of power control interface software complete, can query and report status on power supply modules
* schematic entry for the power control board, implemented as a BeagleBone Black single-board computer, underway
Tyce DeYoung 06/01/20 1:09 PM
38        
39        
40 Sheet February 2020 report for 1.5

FAT planning workshop : result of calibration discussion was that only basic functionality (on/off) can be tested in FAT, we need to do more detailed characterization on individual boards and a subset of fully characterized "golden" DOMs.

Flashers: after further checks, the flashers appear to have the same intensity vs. DAC setting behavior when threshold corrected. A meeting is planned for the week of March 9 to discuss mDOM production plans for flashers and testing and charcaterization.

Cameras: D-egg camera mount fixed and tested in Madison. Due to delay in camera mount testing and shipping of materials between US, South Korea and Japan, 30 D-eggs in production batch 1 will have cameras, 20 will not. Cameras may be backfilled when D-eggs are sealed in April or May.
Dawn Williams 03/03/20 8:40 PM
41        
42        
43 Sheet Oct. 2019 report for 1.5
-- Camera mounting solution was finalized for the D-egg. The camera will be mounted below the mainboard.
-- Adhesive for D-egg LEDs has been tested at room temperature and -40 C.
-- POCAM was successfully reviewed. Procurement of pressure vessels has begun.
-- Work continues on mini-mainboard which will be used by standalone calibration devices.
Dawn Williams 11/04/19 6:06 PM