| 2 | Row Labels | FS1 - November | FS1 - December | FS1 - January | FS1 - February |
| 3 | 1.2.8.5.10 END NPX FS1 | ||||
| 4 | EN | ||||
| 5 | 1.2.8.5.5.1 SES: Drillers Support for SES Layout | 18 | 18 | 4 | |
| 6 | EN | 18 | 18 | 4 | |
| 7 | 1.2.8.5.5.2 SES: Layout - Hoses, Cables, Interconnects and Cable trays | 288 | |||
| 8 | TE | 288 | |||
| 9 | 1.2.8.5.5.3.1 SES: Deliver, Upgrade,/Repair, Connect, Test Fuel Tower | 16 | 4 | ||
| 10 | EN | 16 | 4 | ||
| 11 | 1.2.8.5.5.4 SES: Temp power from backup generator (CRELL, ONAN) | 1 | 2 | 1 | |
| 12 | EN | 1 | 2 | 1 | |
| 13 | 1.2.8.5.6.1 Gens/PDM: Lift generators onto Skis with Crane | 8 | |||
| 14 | TE | 8 | |||
| 15 | 1.2.8.5.6.3 Gens/PDM: Generators - Misc Repairs | 40 | 40 | ||
| 16 | EN | 40 | 40 | ||
| 17 | 1.2.8.5.6.5 Gens/PDM: Preliminary GEN Testing | 16 | |||
| 18 | EN | 16 | |||
| 19 | 1.2.8.5.7.1.1 Computing/Controls: Install Retrofit Kits | 48 | 60 | 36 | |
| 20 | EN | 48 | 60 | 36 | |
| 21 | 1.2.8.5.7.1.2 Computing/Controls: Install Modbus & DGH Modules (EE) | 8 | 8 | ||
| 22 | EN | 8 | 8 | ||
| 23 | 1.2.8.5.7.1.2 Computing/Controls: Misc. Controls Tasking (EE) | 8 | 8 | ||
| 24 | EN | 8 | 8 | ||
| 25 | 1.2.8.5.7.1.3 Computing/Controls: Conduit wiring | ||||
| 26 | TE | ||||
| 27 | 1.2.8.5.7.10.1 RWCR: Integrate & Test (EE) | 8 | |||
| 28 | EN | 8 | |||
| 29 | 1.2.8.5.7.10.1 RWCR: Integrate & Test (TE) | 8 | |||
| 30 | TE | 8 | |||
| 31 | 1.2.8.5.7.11.1 Winches/Reels: Repair/Retrofit Winches & Reels (EE) | 48 | |||
| 32 | EN | 48 | |||
| 33 | 1.2.8.5.7.11.1 Winches/Reels: Repair/Retrofit Winches & Reels (ME) | 8 | |||
| 34 | EN | 8 | |||
| 35 | 1.2.8.5.7.11.1 Winches/Reels: Repair/Retrofit Winches & Reels (TE) | 48 | |||
| 36 | TE | 48 | |||
| 37 | 1.2.8.5.7.12.1 Hoses/Cables/Etc.: Inventory & Repair | 40 | 40 | ||
| 38 | TE | 40 | 40 | ||
| 39 | 1.2.8.5.7.13.1 IFD: Repair/Refit/Test (EE) | 32 | |||
| 40 | TE | 32 | |||
| 41 | 1.2.8.5.7.13.1 IFD: Repair/Refit/Test (ME) | 32 | |||
| 42 | TE | 32 | |||
| 43 | 1.2.8.5.7.13.1 IFD: Repair/Refit/Test (TE w/ ASC Electrician Support) | 16 | |||
| 44 | TE | 16 | |||
| 45 | 1.2.8.5.7.14.1 ARA Drill: Repair and Upgrade ARA Drill (EE) | 80 | |||
| 46 | EN | 80 | |||
| 47 | 1.2.8.5.7.14.1 ARA Drill: Repair and Upgrade ARA Drill (ME) | 96 | |||
| 48 | EN | 96 | |||
| 49 | 1.2.8.5.7.14.1 ARA Drill: Repair and Upgrade ARA Drill (TE) | 48 | |||
| 50 | TE | 48 | |||
| 51 | 1.2.8.5.7.14.2 ARA Drill: Preliminary Integration (EE) | 8 | |
|---|---|---|---|
| 52 | EN | 8 | |
| 53 | 1.2.8.5.7.14.2 ARA Drill: Preliminary Integration (ME) | 8 | |
| 54 | EN | 8 | |
| 55 | 1.2.8.5.7.14.2 ARA Drill: Preliminary Integration (TE) | 8 | |
| 56 | TE | 8 | |
| 57 | 1.2.8.5.7.14.3 ARA Drill: Winterize & Store ARA Drill | 32 | |
| 58 | EN | 32 | |
| 59 | 1.2.8.5.7.2.1 DCC: Controls Retrofit (EE) | 24 | |
| 60 | EN | 24 | |
| 61 | 1.2.8.5.7.2.1 DCC: Repairs, Electrical Upgrades, Install Racks (EE) | 32 | |
| 62 | TE | 32 | |
| 63 | 1.2.8.5.7.3.1 MHP: Controls Retrofit (EE) | 128 | 128 |
| 64 | EN | 128 | 128 |
| 65 | 1.2.8.5.7.3.1 MHP: Retrofit MHPs | 116 | 116 |
| 66 | EN | 20 | 20 |
| 67 | TE | 96 | 96 |
| 68 | 1.2.8.5.7.3.2 MHP subsystem evaluation | 32 | |
| 69 | EN | 32 | |
| 70 | 1.2.8.5.7.4.1 PHS: Controls Retrofit (EE) | 106 | |
| 71 | EN | 106 | |
| 72 | 1.2.8.5.7.4.1 PHS: Mechanical Retrofit (EN) | 32 | |
| 73 | EN | 32 | |
| 74 | 1.2.8.5.7.4.1 PHS: Mechanical Retrofit (TE) | 40 | |
| 75 | TE | 40 | |
| 76 | 1.2.8.5.7.4.2 PHS: Subsystem Evaluation | 16 | |
| 77 | EN | 16 | |
| 78 | 1.2.8.5.7.4.3 PHS: Install Filtration System | 48 | |
| 79 | EN | 48 | |
| 80 | 1.2.8.5.7.5.1 Water Tanks: Retrofit (Railings, Ladders, Vert pumps, Submersible Pumps, Manifolds, etc.) | 176 | |
| 81 | EN | 40 | |
| 82 | TE | 136 | |
| 83 | 1.2.8.5.7.5.2 Water Tank: Subsystem Evaluation | 16 | |
| 84 | EN | 16 | |
| 85 | 1.2.8.5.7.6.1 HPP: Controls Retrofit (Sensors, Motor Drives, Air Handling, Etc.) | 96 | |
| 86 | EN | 96 | |
| 87 | 1.2.8.5.7.6.1 HPP: Controls Retrofit (Sensors, Motor Drives, Air Handling, Etc.) | 16 | |
| 88 | TE | 16 | |
| 89 | 1.2.8.5.7.6.1 HPP: Mechanical Refit | 120 | |
| 90 | EN | 24 | |
| 91 | TE | 96 | |
| 92 | 1.2.8.5.7.6.2 HPP: Pump Evaluated | 16 | |
| 93 | EN | 16 | |
| 94 | 1.2.8.5.7.7.1 Shops: Repair/Retrofit SHOP | 16 | 16 | 16 |
| 95 | EN | 16 | 16 | 16 |
| 96 | 1.2.8.5.7.7.1 Shops: Repair/Retrofit Shops, MECC | 16 | 16 | 16 |
| 97 | TE | 16 | 16 | 16 |
| 98 | 1.2.8.5.7.7.1 Shops: Repair/Retrofit Shops, OML | 8 | |
| 99 | EN | 8 | |
| 100 | 1.2.8.5.7.7.1 Shops: Repair/Retrofit Shops, SEW | 8 | 8 |
| 101 | EN | 8 | 8 |
|---|---|---|---|
| 102 | 1.2.8.5.7.8.1 TOS/Towers: Inspect/Test Controls (EE) | 8 | 16 |
| 103 | EN | 8 | 16 |
| 104 | 1.2.8.5.7.8.1 TOS/Towers: Inspect/Test Mechanical Systems (ME) | 8 | 8 |
| 105 | EN | 8 | 8 |
| 106 | 1.2.8.5.7.8.1 TOS/Towers: Repair/Retrofit | 64 | 64 |
| 107 | TE | 64 | 64 |
| 108 | 1.2.8.5.7.8.1 TOS/Towers: Repair/Retrofit Controls (EE) | 392 | 392 |
| 109 | EN | 392 | 392 |
| 110 | 1.2.8.5.7.8.1 TOS/Towers: Repair/Retrofit Mechanical (ME) | 32 | 32 |
| 111 | EN | 32 | 32 |
| 112 | 1.2.8.5.7.9.1 MSHR: Repair/Replace Components, Energize & Test (EE) | 48 | |
| 113 | EN | 48 | |
| 114 | 1.2.8.5.7.9.1 MSHR: Repair/Replace Components, Energize & Test (ME) | 24 | |
| 115 | EN | 24 | |
| 116 | 1.2.8.5.7.9.1 MSHR:Repair/Replace Components, Energize & Test | 56 | |
| 117 | TE | 56 | |
| 118 | 1.2.8.5.8.1 Close-out: Document, Photograph Equip & Upgrade Work, Further Req's | 120 | |
| 119 | TE | 120 | |
| 120 | 1.2.8.5.8.2 Winterize/Close/Store all EHWD Equipment | 44 | 40 |
| 121 | TE | 44 | 40 |
| 122 | 1.2.8.5.8.3 Retro all components, crate, pack and deliver to cargo | 32 | |
| 123 | TE | 32 | |
| 124 | 1.2.8.5.9.1 MCM Logistics Rep (driller) | 144 | |
| 125 | TE | 144 | |
| 126 | Grand Total | 468 | 1997 | 1512 | 117 |
| B | C | D | E | |
|---|---|---|---|---|
| 1 | ||||
| 2 | Row Labels | FS2 - November | FS2 - December | FS2 - January |
| 3 | 1.2.8.6.1 START NPX FS2 - Team Arrives [Comm/WTst/FirnDr] | |||
| 4 | EN | |||
| 5 | 1.2.8.6.10.1 Rod Well: Develop & Maintain (Using ARA Drill) | 250 | 150 | |
| 6 | EN | 250 | 150 | |
| 7 | 1.2.8.6.11.1 IFD: Integration and Commissioning | 32 | ||
| 8 | TE | 32 | ||
| 9 | 1.2.8.6.11.2 IFD: Drill 8 Firn Holes | 48 | 48 | |
| 10 | EN | 48 | 48 | |
| 11 | 1.2.8.6.11.4 IFD: Winterize & Store | 48 | ||
| 12 | EN | 48 | ||
| 13 | 1.2.8.6.12.1 Wet Test: Readiness Review, Safety Refresher, Emergency & Safety Systems Tested | 112 | ||
| 14 | EN | 112 | ||
| 15 | 1.2.8.6.12.2 Wet Test: Fire Boilers, Circulate Water or Glycol | 32 | ||
| 16 | EN | 32 | ||
| 17 | 1.2.8.6.12.3 Wet Test: Perform Systems Tests (Wet Test & Comm.) | 672 | ||
| 18 | TE | 672 | ||
| 19 | 1.2.8.6.12.4 Wet Test: Blow Out Systems (need ASC compressor) | 180 | ||
| 20 | TE | 180 | ||
| 21 | 1.2.8.6.13.1 Close-out: Document, Photograph Equip & Upgrade Work, Further Req's | 44 | ||
| 22 | EN | 44 | ||
| 23 | 1.2.8.6.13.2 Close-out: Remove DNF, Computer Equip, Drives, Capacitors, Etc | 144 | ||
| 24 | TE | 144 | ||
| 25 | 1.2.8.6.13.3 Close-out: Winterize/Close/Store all EHWD Equipment | 96 | ||
| 26 | EN | 96 | ||
| 27 | 1.2.8.6.13.4 Close-out: Prepare Retrograde for Shipment | 32 | ||
| 28 | TE | 32 | ||
| 29 | 1.2.8.6.13.5.1 Winterize: Remove & Retro/Store All DNF | 48 | ||
| 30 | TE | 48 | ||
| 31 | 1.2.8.6.13.5.2 Winterize: Winterize SES & TOS, Disconnect all Cables, Hoses, Connections | 144 | ||
| 32 | TE | 144 | ||
| 33 | 1.2.8.6.13.5.3 Winterize: All EHWD Equipment Winterized | |||
| 34 | EN | |||
| 35 | 1.2.8.6.14.1 MCM Logistics Rep (driller) | 144 | ||
| 36 | EN | 144 | ||
| 37 | 1.2.8.6.15 END NPX FS2 Season | |||
| 38 | EN | |||
| 39 | 1.2.8.6.5.1 SES: Fuel Tower: Connect, Test and Make Ready | 32 | ||
| 40 | TE | 32 | ||
| 41 | 1.2.8.6.5.2 SES: Make Ready all SES Modules (DCC, PHS, MHPs, MECC, WTs, All) | 48 | ||
| 42 | TE | 48 | ||
| 43 | 1.2.8.6.5.3 SES: Furnace Checkout & Fire Up (All modules) | 32 | ||
| 44 | EN | 32 | ||
| 45 | 1.2.8.6.5.4 SES: Perform Emergency Incident Drill & Safety Training | 112 | ||
| 46 | EN | 112 | ||
| 47 | 1.2.8.6.5.5 SES: Maintenance Activities | 56 | 56 | |
| 48 | TE | 56 | 56 | |
| 49 | 1.2.8.6.5.6 SES: Site Snow Removal | 96 | ||
| 50 | TE | 96 | ||
| 51 | 1.2.8.6.6.1 Generators/PDM: Charge Generator Batteries | 1 |
|---|---|---|
| 52 | EN | 1 |
| 53 | 1.2.8.6.6.2 Generators/PDM: Prime/Commission Fuel System | 24 |
| 54 | EN | 24 |
| 55 | 1.2.8.6.6.3 Generators/PDM: GEN-1, 2, 3 - Install GEN hoods | 96 |
| 56 | EN | 96 |
| 57 | 1.2.8.6.6.4 GEN-1, 2, 3, PDM - Repairs & Tests w/Contract Tech Support | 96 | 48 |
| 58 | EN | 96 | 48 |
| 59 | 1.2.8.6.6.5 Generator & PDM: Commission & Final Testing | 32 |
| 60 | EN | 32 |
| 61 | 1.2.8.6.6.7 Generators/PDM: Change from Temporary Power to IceCube Grid | 8 |
| 62 | EN | 8 |
| 63 | 1.2.8.6.7.1.1 DCC: Install Racks, Networks, Computers | 32 |
| 64 | TE | 32 |
| 65 | 1.2.8.6.7.10.1 TOS/Tower Equipment - Retrofit & Testing | 128 |
| 66 | TE | 128 |
| 67 | 1.2.8.6.7.11.1 Computing/Control: System Integration, Verification, Test at NPX | 250 | 350 | 360 |
| 68 | TE | 250 | 350 | 360 |
| 69 | 1.2.8.6.7.11.2 Computing/Control: Testing and Reprogramming Motor Drives | 160 | 160 |
| 70 | TE | 160 | 160 |
| 71 | 1.2.8.6.7.11.3 Computing/Controls: Install Retrofit Kits | 48 | 60 | 40 |
| 72 | TE | 48 | 60 | 40 |
| 73 | 1.2.8.6.7.11.4 Computing/Controls: Misc. Controls Tasking (EE) | 8 | 25 | 8 |
| 74 | EN | 8 | 25 | 8 |
| 75 | 1.2.8.6.7.11.4 Computing/Controls: Misc. Controls Tasking (TE) | 48 | 60 | 36 |
| 76 | TE | 48 | 60 | 36 |
| 77 | 1.2.8.6.7.11.5 Computing/Controls: Conduit wiring | 72 | 48 | 48 |
| 78 | TE | 72 | 48 | 48 |
| 79 | 1.2.8.6.7.12.1 ARA Drill: Integrate HPU-2 & Commission | 144 |
| 80 | EN | 96 |
| 81 | TE | 48 |
| 82 | 1.2.8.6.7.12.2 ARA Drill: Decommission & Store ARA Drill | 32 |
| 83 | TE | 32 |
| 84 | 1.2.8.6.7.2.1 MHP: Final Upgrade & Replacement Activities | 64 |
| 85 | EN | 64 |
| 86 | 1.2.8.6.7.2.2 MHP: Final Testing | 32 |
| 87 | TE | 32 |
| 88 | 1.2.8.6.7.3.1 PHS: Install Filters in H2O System | 4 |
| 89 | TE | 4 |
| 90 | 1.2.8.6.7.3.2 PHS: Final Upgrade & Replacement Activities | 32 |
| 91 | TE | 32 |
| 92 | 1.2.8.6.7.3.3 PHS: Final Testing | 32 |
| 93 | EN | 32 |
| 94 | 1.2.8.6.7.4.1 Water Tanks: Install Railings, Ladders, Pumps, Plumbing, Doghouses - Final Upgrades | 176 |
| 95 | EN | 40 |
| 96 | TE | 136 |
| 97 | 1.2.8.6.7.4.2 Water Tanks: Integrate, Verify, Test | 64 |
| 98 | EN | 64 |
| 99 | 1.2.8.6.7.5.1 HPP: Final Upgrade & Replacement Activities | 32 |
| 100 | TE | 32 |
| 101 | 1.2.8.6.7.5.2 HPP: Pump Testing | 32 | |
|---|---|---|---|
| 102 | EN | 32 | |
| 103 | 1.2.8.6.7.6.1 Shops: Final Upgrade/Retrofit Shops, MECC | 8 | |
| 104 | TE | 8 | |
| 105 | 1.2.8.6.7.6.1 Shops: Final Upgrade/Retrofit Shops, OML, TOW, SEW | 16 | |
| 106 | TE | 16 | |
| 107 | 1.2.8.6.7.7.1 MSHR: Install Drill Hose on Reel | 128 | |
| 108 | TE | 128 | |
| 109 | 1.2.8.6.7.7.2 MSHR: Final Upgrades & Testing | 48 | |
| 110 | EN | 48 | |
| 111 | 1.2.8.6.7.7.3 MSHR: Install Blankets, | 54 | |
| 112 | TE | 54 | |
| 113 | 1.2.8.6.7.7.3 MSHR: Install Blankets, Connect to Power, Heating Control and Test | 32 | |
| 114 | EN | 32 | |
| 115 | 1.2.8.6.7.8.1 Winches/Reels: Final Integration & Testing | 192 | |
| 116 | EN | 144 | |
| 117 | TE | 48 | |
| 118 | 1.2.8.6.7.9.1 Fuel Storage/Delivery: Commission Fuel Tower | 32 | 96 |
| 119 | TE | 32 | 96 |
| 120 | 1.2.8.6.8.1 Sensor Handling Facility: Assemble Skis and Deck, Erect Walls, Construct Walls, Construct Roof | 168 | |
| 121 | EN | 168 | |
| 122 | 1.2.8.6.8.2 Sensor Handling Facility: Final Assembly with ASC-provided Crane | 24 | |
| 123 | TE | 24 | |
| 124 | 1.2.8.6.9.1 Condensate Bulb: Drill and Pump | 240 | |
| 125 | EN | 240 | |
| 126 | 1.2.9.5.5 String: On-ice Sensor Handling Training | ||
| 127 | SS | ||
| 128 | TE | ||
| 129 | 1.2.9.5.6.10 String: Install SJB's in Pits (2); Connect cables (ASC & UW) | 8 | |
| 130 | SC | 8 | |
| 131 | 1.2.9.5.6.3 String: Prep/Uncrate Cable Spools; Load onto TU20 (ASC & UW) | 24 | |
| 132 | TE | 24 | |
| 133 | 1.2.9.5.6.4 String: Install 7 Surface Cables into ICL Tower, Across Bridge, into ICL (ASC & UW) | 16 | |
| 134 | SC | 16 | |
| 135 | 1.2.9.5.6.5 String: Prep Cables & Attach to Grounding System in ICL (ASC & UW) | 8 | |
| 136 | SE | 8 | |
| 137 | 1.2.9.5.6.6 String: Connect Surface Cables into ICL Patch Panels (UW) | 8 | |
| 138 | SE | 8 | |
| 139 | 1.2.9.5.6.9 String: Unspool & Lay Surface Cables from Tower to SJB Pits (ASC, UW & MSU) | 32 | |
| 140 | SC | 32 | |
| 141 | Grand Total | 1815 | 2249 | 2616 |
| B | C | D | E | F | |
|---|---|---|---|---|---|
| 1 | |||||
| 2 | Row Labels | FS3 - November | FS3 - December | FS3 - January | FS3 - February |
| 3 | 1.2.8.7.1 START NPX FS3 - Team Arrives [Drilling/Installation] | ||||
| 4 | TE | ||||
| 5 | 1.2.8.7.10.1 Installation: DRILL HOLE # 1 | 522 | |||
| 6 | EN | 522 | |||
| 7 | 1.2.8.7.10.10 Installation: Deployment - String 2 | 72 | |||
| 8 | EN | 72 | |||
| 9 | 1.2.8.7.10.11 Installation: String # 2 Deployed & Complete | 0 | |||
| 10 | EN | 0 | |||
| 11 | 1.2.8.7.10.12 Installation: Closeout & Relocate Tower & TOS to Hole 4 | 32 | |||
| 12 | EN | 32 | |||
| 13 | 1.2.8.7.10.13 Installation: Trench & Install Reel Anchors (Hole 3) | 16 | |||
| 14 | EN | 16 | |||
| 15 | 1.2.8.7.10.14 Installation: Relocate Hose, Cable Reels, Sensor Handling Structure (at end of installation) | 28 | |||
| 16 | TE | 28 | |||
| 17 | 1.2.8.7.10.15 Installation: Prepare SFC-DOM Cable (Mount on TU20, test slip ring) - Prep for String 4 | 8 | |||
| 18 | EN | 8 | |||
| 19 | 1.2.8.7.10.16 Installation: DRILL HOLE # 3 | 522 | |||
| 20 | TE | 522 | |||
| 21 | 1.2.8.7.10.17 Installation: Deployment - String 3 | 72 | |||
| 22 | EN | 72 | |||
| 23 | 1.2.8.7.10.18 Installation: String # 3 Deployed & Complete | ||||
| 24 | TE | ||||
| 25 | 1.2.8.7.10.19 Installation: Closeout & Relocate Tower & TOS for Hole 5 | 32 | |||
| 26 | EN | 32 | |||
| 27 | 1.2.8.7.10.2 Installation: Deployment - String 1 | 72 | |||
| 28 | TE | 72 | |||
| 29 | 1.2.8.7.10.20 Installation: Trench & Install Reel Anchors (Hole 4) | 16 | |||
| 30 | TE | 16 | |||
| 31 | 1.2.8.7.10.21 Installation: Relocate Hose, Cable Reels, Sensor Handling Structure (at end of installation) | 28 | |||
| 32 | EN | 28 | |||
| 33 | 1.2.8.7.10.22 Installation: Hole Excavation, Trench & Install Cable Anchor (Hole 4) | 16 | |||
| 34 | EN | 16 | |||
| 35 | 1.2.8.7.10.23 Installation: Prepare SFC-Sensor Cable (Mount on TU20, test slip ring) - Prep for String 5 | 8 | |||
| 36 | TE | 8 | |||
| 37 | 1.2.8.7.10.24 Installation: DRILL HOLE # 4 | 522 | |||
| 38 | EN | 522 | |||
| 39 | 1.2.8.7.10.25 Installation: Deployment | 72 | |||
| 40 | EN | 72 | |||
| 41 | 1.2.8.7.10.26 Installation: String # 4 Deployed & Complete | ||||
| 42 | TE | ||||
| 43 | 1.2.8.7.10.27 Installation: Closeout & Relocate Tower & TOS for Hole 6 | 32 | |||
| 44 | TE | 32 | |||
| 45 | 1.2.8.7.10.28 Installation: Trench & Install Reel Anchors (Hole 5) | 16 | |||
| 46 | EN | 16 | |||
| 47 | 1.2.8.7.10.29 Installation: Relocate Hose, Cable Reels, Sensor Handling Structure (at end of installation) | 28 | |||
| 48 | EN | 28 | |||
| 49 | 1.2.8.7.10.3 Installation: String # 1 Deployed & Complete | ||||
| 50 | EN | ||||
| 51 | 1.2.8.7.10.30 Installation: Hole Excavation, Trench & Install Cable Anchor (Hole 5) | 16 | ||
|---|---|---|---|---|
| 52 | TE | 16 | ||
| 53 | 1.2.8.7.10.31 Installation: Prepare SFC-Sensor Cable (Mount on TU20, test slip ring) - Prep for String 6 | 8 | ||
| 54 | EN | 8 | ||
| 55 | 1.2.8.7.10.32 Installation: DRILL HOLE # 5 | 522 | ||
| 56 | EN | 522 | ||
| 57 | 1.2.8.7.10.33 Installation: Deployment - String 5 | 72 | ||
| 58 | TE | 72 | ||
| 59 | 1.2.8.7.10.34 Installation: String # 5 Deployed & Complete | |||
| 60 | EN | |||
| 61 | 1.2.8.7.10.35 Installation: Closeout & Relocate Tower & TOS for Hole 7 | 32 | ||
| 62 | EN | 32 | ||
| 63 | 1.2.8.7.10.36 Installation: Trench & Install Reel Anchors (Hole 6) | 16 | ||
| 64 | TE | 16 | ||
| 65 | 1.2.8.7.10.37 Installation: Relocate Hose, Cable Reels, Sensor Handling Structure (at end of installation) | 28 | ||
| 66 | EN | 28 | ||
| 67 | 1.2.8.7.10.38 Installation: Hole Excavation, Trench & Install Cable Anchor (Hole 6) | 16 | ||
| 68 | TE | 16 | ||
| 69 | 1.2.8.7.10.39 Installation: Prepare SFC-Sensor Cable (Mount on TU20, test slip ring) - Prep for String 7 | 8 | ||
| 70 | EN | 8 | ||
| 71 | 1.2.8.7.10.4 Installation: Closeout & Relocate Tower & TOS to Hole 3 | 32 | ||
| 72 | TE | 32 | ||
| 73 | 1.2.8.7.10.40 Installation: DRILL HOLE # 6 | 522 | ||
| 74 | EN | 522 | ||
| 75 | 1.2.8.7.10.41 Installation: Driller Support for Dust Logging Activities | 16 | ||
| 76 | TE | 16 | ||
| 77 | 1.2.8.7.10.42 Installation: Deployment - String 6 | 72 | ||
| 78 | EN | 72 | ||
| 79 | 1.2.8.7.10.43 Installation: String # 6 Deployed & Complete | |||
| 80 | EN | |||
| 81 | 1.2.8.7.10.44 Installation: Closeout & Relocate Tower & TOS to Storage | 32 | ||
| 82 | EN | 32 | ||
| 83 | 1.2.8.7.10.45 Installation: Trench & Install Reel Anchors (Hole 7) | 16 | ||
| 84 | TE | 16 | ||
| 85 | 1.2.8.7.10.46 Installation: Relocate Hose, Cable Reels, Sensor Handling Structure (at end of installation) | 28 | ||
| 86 | EN | 28 | ||
| 87 | 1.2.8.7.10.47 Installation: Hole Excavation, Trench & Install Cable Anchor (Hole 7) | 16 | ||
| 88 | EN | 16 | ||
| 89 | 1.2.8.7.10.48 Installation: DRILL HOLE # 7 | 522 | ||
| 90 | TE | 522 | ||
| 91 | 1.2.8.7.10.49 Installation: Deployment - String 7 | 72 | ||
| 92 | EN | 72 | ||
| 93 | 1.2.8.7.10.5 Installation: Trench & Install Reel Anchors (Hole 2) | 16 | ||
| 94 | TE | 16 | ||
| 95 | 1.2.8.7.10.50 Installation: String # 7 Deployed & Complete | |||
| 96 | TE | |||
| 97 | 1.2.8.7.10.51 Installation: Closeout & Relocate Tower & TOS to Storage Change duration 7 days | 32 | ||
| 98 | EN | 32 | ||
| 99 | 1.2.8.7.10.52 Installation: Drilling & Installation Complete | |||
| 100 | TE | |||
| 101 | 1.2.8.7.10.6 Installation: Relocate Hose, Cable Reels, Sensor Handling Structure (at end of installation) | 28 | ||
|---|---|---|---|---|
| 102 | EN | 28 | ||
| 103 | 1.2.8.7.10.7 Installation: Prepare SFC-DOM Cable (Mount on TU20, test slip ring) Prep for String 3 | 8 | ||
| 104 | EN | 8 | ||
| 105 | 1.2.8.7.10.8 Installation: Operational Debrief | 112 | ||
| 106 | EN | 112 | ||
| 107 | 1.2.8.7.10.9 Installation: DRILL HOLE # 2 | 522 | ||
| 108 | TE | 522 | ||
| 109 | 1.2.8.7.11.1 Decommission and Store: Remove & Retro/Store All DNF | 375 | ||
| 110 | TE | 375 | ||
| 111 | 1.2.8.7.11.2 Decommission and Store:Decommission SES & TOS, Disconnect all cables hoses, connections | 485 | ||
| 112 | EN | 485 | ||
| 113 | 1.2.8.7.11.3 Decommission and Store: Winterize all EHWD equipment | 585 | ||
| 114 | TE | 585 | ||
| 115 | 1.2.8.7.11.4 Decommission and Store: Remove Drill Hose from MSHR, Respool & Ship to ZCM | 217 | ||
| 116 | EN | 217 | ||
| 117 | 1.2.8.7.11.5 Decommission and Store: Shipment of Drill Hose to ZCM | 40 | ||
| 118 | TE | 40 | ||
| 119 | 1.2.8.7.11.6 Decommission and Store: Inventory & Photograph EHWD, Document Repairs needed | 325 | ||
| 120 | EN | 325 | ||
| 121 | 1.2.8.7.11.7 Decommission and Store: UNL Equipment - Deliver to Cargo for Retro or Redistribution | 80 | ||
| 122 | TE | 80 | ||
| 123 | 1.2.8.7.11.8 Decommission and Store: Crate and Deliver EHWD Equipment to Cargo for Retrograde or Redistribution | 225 | ||
| 124 | EN | 225 | ||
| 125 | 1.2.8.7.11.9 Decommission and Store: Cargo Retro FS3 | |||
| 126 | EN | |||
| 127 | 1.2.8.7.5.1 SES: Make Ready all Drill Modules (DCC, PHS, MHPs, TOS 1&2, WTs, Handling Facility) | 244 | ||
| 128 | EN | 244 | ||
| 129 | 1.2.8.7.5.2 SES: Furnace Checkout & Fire Up (All modules) | 32 | ||
| 130 | TE | 32 | ||
| 131 | 1.2.8.7.5.3 SES: Perform Emergency Incident Drill & Safety Training | 672 | ||
| 132 | EN | 672 | ||
| 133 | 1.2.8.7.5.4 SES: Make ARA Drill Ready for Service | 80 | ||
| 134 | EN | 40 | ||
| 135 | TE | 40 | ||
| 136 | 1.2.8.7.5.5 SES: Re-Establish RodWell | 176 | 96 | |
| 137 | EN | 176 | 96 | |
| 138 | 1.2.8.7.5.6 SES: SES and Equipment Maintenance | 60 | 124 | 124 |
| 139 | TE | 60 | 124 | 124 |
| 140 | 1.2.8.7.5.7 SES: Ready for Drilling - (On Ice Final Readiness Assessment) | |||
| 141 | EN | |||
| 142 | 1.2.8.7.5.8 SES: Dig-out | 96 | ||
| 143 | EN | 96 | ||
| 144 | 1.2.8.7.6.1 Generator/PDM: Recommission | 96 | ||
| 145 | TE | 96 | ||
| 146 | 1.2.8.7.6.2 Generator/PDM: Generators Ready | 0 | ||
| 147 | TE | 0 | ||
| 148 | 1.2.8.7.6.3 Generator/PDM: Change from Temp Power to Generators (Stand Alone) | 8 | ||
| 149 | EN | 8 | ||
| 150 | 1.2.8.7.7.1 TOS1/Tower1: Hole Excavation, Trench & Install Cable Anchor (Hole 1) | 16 | ||
| 151 | EN | 16 | ||
|---|---|---|---|---|
| 152 | 1.2.8.7.7.10 TOS1/Tower1: Prepare SFC-DOM Cable (Mount on TU20, test slip ring) | 16 | ||
| 153 | EN | 16 | ||
| 154 | 1.2.8.7.7.11 TOS1/Tower1: Pull Drill Heads from ICL, Final Testing in TOS | 16 | ||
| 155 | TE | 16 | ||
| 156 | 1.2.8.7.7.12 TOS1/Tower1: Site Ready for Drilling | |||
| 157 | EN | |||
| 158 | 1.2.8.7.7.2 TOS1/Tower1: Position & Level TOS1/Tower1 at Hole 1 | 16 | ||
| 159 | EN | 16 | ||
| 160 | 1.2.8.7.7.3 TOS1/Tower1: Position Sensor Handling Structure | 8 | ||
| 161 | TE | 8 | ||
| 162 | 1.2.8.7.7.4 TOS1/Tower1: Hose & Cable Delivery & Layout SES-TOS | 96 | ||
| 163 | EN | 96 | ||
| 164 | 1.2.8.7.7.5 TOS1/Tower1: Trench & Install Reel Anchors (Hole 1) | 8 | ||
| 165 | TE | 8 | ||
| 166 | 1.2.8.7.7.6 TOS1/Tower1: Position Hose & Cable Reels (Hole 1) | 8 | ||
| 167 | EN | 8 | ||
| 168 | 1.2.8.7.7.7 TOS1/Tower1: Make TOS1 Operational, Deliver fuel, fire furnace | 16 | ||
| 169 | TE | 16 | ||
| 170 | 1.2.8.7.7.8 TOS1/Tower1: TOS1 Network/Comms Install | 6 | ||
| 171 | EN | 6 | ||
| 172 | 1.2.8.7.7.9 TOS1/Tower1: Connect Hose Loop, Circulate Water | 48 | ||
| 173 | TE | 48 | ||
| 174 | 1.2.8.7.8.1 TOS2/Tower2: Position & Level TOS2/Tower2 at Hole 2 | 16 | ||
| 175 | EN | 16 | ||
| 176 | 1.2.8.7.8.2 TOS2/Tower2: Cable Layout SES to TOS2 | 16 | ||
| 177 | TE | 16 | ||
| 178 | 1.2.8.7.8.3 TOS2/Tower2:Make TOS2 Operational, Deliver fuel, fire furnace | 16 | ||
| 179 | EN | 16 | ||
| 180 | 1.2.8.7.8.4 TOS2/Tower2: TOS2 Network/Comms Install | 6 | ||
| 181 | EN | 6 | ||
| 182 | 1.2.8.7.8.5 TOS2/Tower2: TOS2/Tower2 in Position & Heated | |||
| 183 | TE | |||
| 184 | 1.2.8.7.9.1 Wet Test: Readiness Review/Safety Refresher | 224 | ||
| 185 | TE | 224 | ||
| 186 | 1.2.8.7.9.1 Wet Test: Training (Direct Hire Drillers -15) | 1200 | ||
| 187 | TE | 1200 | ||
| 188 | 1.2.8.7.9.1 Wet Test: Training (Engineer/Drillers - 3) | 240 | ||
| 189 | EN | 240 | ||
| 190 | 1.2.8.7.9.2 Wet Test: Emergency & Safety Systems Tested | 192 | ||
| 191 | EN | 192 | ||
| 192 | 1.2.8.7.9.3 Wet Test: Fire Boilers, Circulate Water | 160 | ||
| 193 | EN | 160 | ||
| 194 | 1.2.8.7.9.4 Wet Test: Perform Complete Systems Testing (Wet Test & Comm.) | 800 | ||
| 195 | TE | 800 | ||
| 196 | 1.2.9.6.1 String: Plan & Coordinate Installation (FS3) | 80 | 80 | 80 | 80 |
| 197 | SS | 80 | 80 | 80 | 80 |
| 198 | 1.2.9.6.2 String: On Ice Readiness Review for 1st Hole Drill / Deployment | 16 | ||
| 199 | SC | 16 | ||
| 200 | 1.2.9.6.3 String: Erect Sensor Testing Tent - (ASC) | |||
| 201 | TE | |||
|---|---|---|---|---|
| 202 | 1.2.9.6.4.1 String: Excavate Surface Junction Box (SJB #1) Vaults (hole side) (ASC) | |||
| 203 | SC | |||
| 204 | 1.2.9.6.4.10 String: Spool Slack Cable in Pit/Trench, 4 times (UW & MSU) | 16 | ||
| 205 | TE | 16 | ||
| 206 | 1.2.9.6.4.11 String: Connect Cables to SJB #2 x 4 (UW & MSU) | 8 | ||
| 207 | SC | 8 | ||
| 208 | 1.2.9.6.4.12 String: Survey & Backfill Cable Trenches, 4 times (ASC & UW) | 8 | ||
| 209 | SC | 8 | ||
| 210 | 1.2.9.6.4.2 String: Remove SJB #1 Vault Lid & Walls (ASC) | 8 | ||
| 211 | SC | 8 | ||
| 212 | 1.2.9.6.4.3 String: Trench from Holes to SJB #2 Pits, 3 times (ASC) | |||
| 213 | TE | |||
| 214 | 1.2.9.6.4.4 String: Spool Slack Cable in Pit/Trench, 3 times (UW & MSU) | 16 | ||
| 215 | TE | 16 | ||
| 216 | 1.2.9.6.4.5 String: Connect Cables to SJB #1 x 3 (UW) | 112 | ||
| 217 | SE | 112 | ||
| 218 | 1.2.9.6.4.6 String: Survey & Backfill Cable Trenches, 3 times (ASC & UW) | 48 | ||
| 219 | SC | 48 | ||
| 220 | 1.2.9.6.4.7 String: Excavate Surface Junction Box (SJB #2) Vaults (hole side) (ASC & UW) | 8 | ||
| 221 | SC | 8 | ||
| 222 | 1.2.9.6.4.8 String: Remove SJB #2 Vault Lid & Walls (ASC) | 16 | ||
| 223 | SC | 16 | ||
| 224 | 1.2.9.6.4.9 String: Trench from Holes to SJB #2 Pit, 4 times (ASC) | |||
| 225 | SC | |||
| 226 | Grand Total | 1248 | 6002 | 5388 | 80 |