1. Sheet1

  A B C D E F G H
1                
2 Cargo Item respective WBS Level Work Package Item Description Date of expected or actual completion Date of expected or actual shipment Float from article completion to transportation leg to MCM Date/Month for Items needed at South Pole (based on assumed 7 year schedule) Time from shipment to 'Needed at the South Pole' date (based on assumed 7 year schedule)
3 1.2 Drill Gen 1 - housed in 20' container 2/6/2020 Delivery to MCM complete Delivery to MCM complete 12/1/2023 Shipping in process (Items awaiting last leg of shipment MCM-NPX)
4 1.2 Drill Gen 2 - housed in 20' container 1/15/2020 1/1/2023
5 1.2 Drill Gen 3 - housed in 20' container 1/15/2020 12/1/2022
6 1.2 Drill 287 Loader 10/15/2019 12/1/2022
7 1.2 Drill Gen hoods Discharge Hoods - currently staged in McMurdo 12/15/2019 1/1/2024
8 1.2 Drill Firn Drill 1/15/2020 12/1/2023
9 1.2 Drill Firn Drill Components - 1 1/15/2020 12/1/2023
10 1.2 Drill Firn Drill Components - 2 1/15/2020 12/1/2023
11 1.2 Drill Weight stack and crates 1/15/2020 12/15/2023
12 1.2 Drill Fuel Tower 1/15/2020 1/1/2023
13 1.2 Drill HPU 1 1/15/2020 1/1/2024
14 Pt. Hueneme:
15 1.2 Drill Container Ski Stack (comprised of 5 sleds) - currently staged in Pt. Hueneme 12/28/2020 1/15/2021 18 12/15/2022 699
16 1.2 Drill Generator Intake Hood - currently staged in Pt. Hueneme 10/8/2020 11/24/2020 47 1/1/2024 1133
17 1.2 Drill Generator Discharge Hoods - currently staged in Pt. Hueneme 10/8/2020 11/24/2020 47 1/1/2024 1133
18 1.2 Drill Drill Hose - currently staged in Pt. Hueneme 7/29/2020 8/15/2020 17 1/1/2024 1234
19 1.2 Drill Drill Hose - currently staged in Pt. Hueneme 11/19/2020 1/15/2021 57 1/1/2024 1081
20 U. Wisconsin:
21 1.2 Drill 8' Refit Container 11/2/2021 11/15/2021 13 11/15/2022 365
22 1.2 Drill 20' Refit Container A 11/13/2021 11/15/2021 2 12/1/2022 381
23 1.2 Drill 20' Refit Container B 11/2/2021 11/15/2021 13 12/15/2022 395
24 1.2 Drill ARA Trailer 11/2/2021 11/15/2021 13 12/15/2022 395
25 1.2 Drill Return Water Cable Reel (RWCR) 10/26/2021 11/15/2021 20 1/1/2023 412
26 1.2 Drill Main Cable Reel (MCR) 11/8/2021 11/15/2021 7 1/1/2023 412
27 1.2 Drill Controls infrastructure - Motor drives, PLCs, electrical hardware, and motor drive mounting kits 4/15/2021 5/1/2022 381 12/1/2022 214
28 1.4 Installation ICL power and timing electronics 7/1/2023 8/1/2023 31 12/1/2023 122
29 1.4 Installation ICL patch cables and patch panels 6/1/2023 8/1/2023 61 12/1/2023 122
30 1.2 Drill ARA Drill System Components - Crate 1 4/15/2021 5/1/2022 381 12/1/2022 214
31 1.2 Drill ARA Drill System Components - Crate 2 4/15/2021 5/1/2022 381 12/1/2022 214
32 1.2 Drill Camp Hose - currently staged at PSL 6/11/2021 11/15/2021 157 12/1/2023 746
33 1.2 Drill Bull wheel 12/1/2021 11/15/2022 349 2/1/2024 443
34 1.2 Drill Load member cable reel 10/15/2022 11/15/2022 31 12/15/2023 395
35 1.2 Installation DOM Handling Facility (DHF) 7/21/2022 11/15/2022 117 12/1/2023 381
36 1.2 Drill Spare Combo cable 10/15/2022 11/15/2022 31 2/12/2024 454
37 1.2 Drill Spare Drill Cable 10/15/2022 11/15/2022 31 2/12/2024 454
38 1.2 Drill Computing/controls components 7/1/2023 8/1/2023 31 11/15/2023 106
39 1.2 Drill Driller resupply/refit components - 8' Container 7/1/2023 8/1/2023 31 11/15/2023 106
40 1.2 Drill Drill refit components 7/1/2023 8/1/2023 31 11/15/2023 106
41 1.2 Drill Drill Heads DNF - X 9/1/2021 11/15/2022 440 2/12/2023 89
42 1.2 Drill Drill Heads DNF - Y 9/1/2021 11/15/2023 805 2/12/2024 89
43 1.2 Drill Drill Heads DNF - R 9/1/2021 11/15/2023 805 2/12/2024 89
44 1.2 Drill Computing/controls components 7/1/2024 8/1/2024 31 11/15/2024 106
45 1.2 Installation Installation Hardware 87-93 7/15/2023 11/15/2023 123 2/15/2024 92
46 1.2 Installation Installation Weights 87-93 7/15/2023 11/15/2023 123 2/15/2024 92
47 1.5 Installation Calibration/Special Devices 87-88 11/30/2022 8/1/2023 244 12/15/2023 136
48 1.3 Installation Special Devices 87-88 1/1/2023 8/1/2023 212 12/15/2023 136
49 1.2 Installation Misc. Science Equipment - FY24 6/1/2023 8/1/2023 61 12/1/2023 122
50 1.3 Installation Special Devices 89-93 1/1/2024 8/1/2024 213 11/25/2024 116
51 1.5 Installation Calibration/Special Devices 89-93 8/15/2023 8/1/2024 352 11/25/2024 116
52 1.2 Installation Misc. Science Equipment - FY25 6/1/2024 8/1/2024 61 12/1/2024 122
53 1.5 Installation Dust logging device 6/1/2024 8/1/2024 61 11/25/2024 116
54 1.5 Installation Dust logging device 6/1/2024 8/1/2024 61 11/25/2024 116
55 1.5 Installation Dust logging device 6/1/2024 8/1/2024 61 11/25/2024 116
56 1.5 Installation Dust logging device 6/1/2024 8/1/2024 61 11/25/2024 116
57 1.5 Installation Logging winch 6/1/2024 8/1/2024 61 11/25/2024 116
58 1.5 Installation Logging winch control box 6/1/2024 8/1/2024 61 11/25/2024 116
59 MSU:
60 1.4 Installation Surface Junction Boxes 11/1/2022 11/15/2022 14 12/10/2023 390
61 1.4 Installation Surface Cable Assemblies 11/30/2021 12/1/2022 366 11/20/2023 354
62 1.4 Installation Breakout cables for strings 87-88 2/28/2023 4/15/2023 46 2/15/2024 306
63 1.4 Installation Breakout cables for strings 89-93 5/22/2023 6/15/2023 24 11/25/2024 529
64 1.4 Installation Main (downhole) load members 87-93 4/1/2023 4/15/2023 14 12/1/2024 596
65 1.4 Installation Main (downhole) cables 87-93 4/1/2023 4/15/2023 14 12/1/2024 596
66 1.3 Installation String Sensors 89-93 8/1/2023 8/1/2024 366 11/25/2024 116
67 1.3 Installation String Sensors 89-93 8/1/2023 8/1/2024 366 11/25/2024 116
68 Other Institutions:
69 1.3 Installation DM-Ice 6/1/2024 8/1/2024 61 11/25/2024 116
70 DESY/Aachen/TUM/Sweden etc :
71 1.3 Installation String Sensors 87-88 4/1/2023 8/1/2023 122 1/15/2024 167
72 1.3 Installation String Sensors 87-88 4/1/2023 8/1/2023 122 1/15/2024 167
73 1.3 Installation Special Devices 87-88 1/1/2023 8/1/2023 212 1/15/2024 167
74 1.5 Installation Calibration Devices 87-88 6/1/2022 8/1/2023 426 1/15/2024 167
75 1.4 Installation FieldHub electronics 8/1/2023 8/15/2023 14 12/1/2023 108
76 1.3 Installation String Sensors 89-93 7/1/2023 8/1/2024 397 11/25/2024 116
77 1.3 Installation Special Devices 89-93 1/1/2024 8/1/2024 213 11/25/2024 116
78 1.5 Installation Calibration Devices 89-93 6/1/2022 8/1/2024 792 11/25/2024 116
79 Chiba:
80 1.3 Installation String Sensors 87 & 88 6/1/2022 8/1/2023 426 1/15/2024 167
81 1.3 Installation String Sensors 87 & 88 6/1/2022 8/1/2023 426 1/15/2024 167
82 1.3 Installation String Sensors 87 & 88 6/1/2022 8/1/2023 426 1/15/2024 167
83 1.3 Installation String Sensors 87 & 88 6/1/2022 8/1/2023 426 1/15/2024 167
84 1.3 Installation String Sensors 89-93 6/1/2023 8/1/2023 61 11/25/2024 482
85 1.3 Installation String Sensors 89-93 6/1/2023 8/1/2023 61 11/25/2024 482
86                
87                
88                
89                
90            